OVERCOMING BARRIERS FOR PEOPLE WITH CRIMINAL RECORDS LEGAL ACTION CENTER 2014 1.
VCHP Energy Efficiency Measure Development Roadmap Barriers Action Items Resources TI Research...
-
Upload
jacey-dome -
Category
Documents
-
view
218 -
download
0
Transcript of VCHP Energy Efficiency Measure Development Roadmap Barriers Action Items Resources TI Research...
VCHP Energy Efficiency Measure Development Roadmap
Barriers
Action Items
Resources
TI Research Needed
Resource Available
Proposed Action Item
E3T Assessment NeededIdentified Barrier
Difficult to Develop Measures and Incentive
Programs
Uncertain Savings, Costs and Cost effectiveness
Owner Unfamiliarity with VCHP
Designer Unfamiliarity with
VCHP
Contractor Unfamiliarity with
VCHP
Codes and Standards
Lack of Information to prioritize measures
Develop contractor qualifications and
training
Develop commissioning requirements
Document operation and
energy useDevelop best
practices to ensure energy saving
Develop designer training and
outreach
Develop screening tool for cost
effective opportunities
Develop owner training on utility incentives and VCHP benefits
Select and define highest priority
measures
Develop high consensus M&V
protocols
Quantify savings and costs over a specific baseline
Develop measures
Develop program
Deliver program
Follow developing codes and standards
Action Plan for Variable Capacity Heat Pump Technology
Lessons learned from previous projects
Manufacturer training
Lab and field testing resources
Existing owner training channels
VCHP research and resources
Industry, professional and utility research and
resources
Codes and standards research and
resources
Others Barriers
Define value proposition for utilities,
building owners and contractors
1
p.2 p.3 p.4 p.5 p.6,7 p.8,9 p.10 p.11
VCHP Energy Efficiency Measure Development Roadmap
Barriers
Action Items
Resources
TI Research Needed
Resource Available
Proposed Action Item
E3T Assessment NeededIdentified Barrier
Manufacturer training is difficult to access (nearest training
center is in Southern California)
Contractor Unfamiliarity with VCHP
Lack of contractor knowledge/experience
Poor installation even by the trained contractors
Develop contractor qualifications and
training
Develop commissioning requirements
VRF contractor training in Irvine, California
Mark Jerome
Get early copies of ASHRAE 90.1 2010 VRF mechanical tables
Daikin provides online classes (http://www.daikinac.com/comm
ercial/trainingOverview.asp?sec=training)
Develop best practices to ensure energy
savings
Get early copies of ASHRAE VRF Handbook Chapter, which is
scheduled to be available Spring of 2012
Investigate Cascade Energy Engineering VRF system; they have been monitoring system
energy use for 5 yearsMike Cundiff
Lessons learned from ASHRAE Headquarters VRF demonstration project
Investigate lessons learned from Oakridge residential
DHP field testing
Investigate lessons learned from Energy Trust New Buildings program has provided incentives for new community college buildings in Southern
Oregon, installing Mitsubishi VRFs. M&V-completion date is Fall 2011Erin Rowe
Investigate savings and lessons learned from Corvallis Wild Life
Preserve VRF system with HRV and economizers
Mark Jerome
Investigate lessons learned from Ecotope single-head DHP report (residential),
including both field and lab testing. Contact Bob Davis or David Baylon at Ecotope
Collaborate with "Center for Built Environment" for post occupancy evaluation of comfort and behavior
Paul Delaney
Investigate new products and features, including US-centric controls, heat pump boilers, data center rack cooling, etc.
Mike Cundiff
Technology misapplication can affect deployment
2
VCHP Energy Efficiency Measure Development Roadmap
Barriers
Action Items
Resources
TI Research Needed
Resource Available
Proposed Action Item
E3T Assessment NeededIdentified Barrier
Designer Unfamiliarity with VCHP
Proprietary equipment makes it hard to understand or
commission
Develop commissioning requirements
Document operation in lab tests
Lack of education in design and construction
fields on technology
VCHP does not fit into standard design
process
Unfamiliar with
controls
Get early copies of ASHRAE 90.1
2010 VRF mechanical tables
Engineers are designing systems around the technologies that they are
more comfortable with
Develop best practices to ensure energy
savings
Develop designer training and outreach
Get early copies of ASHRAE VRF Handbook Chapter, which is
scheduled to be available Spring of 2012
Investigate Cascade Energy Engineering VRF system; they have been monitoring system
energy use for 5 yearsMike Cundiff
Lessons learned from ASHRAE Headquarters
VRF demonstration project
Investigate lessons learned from Oakridge
residential DHP field testing
Investigate lessons learned from Energy Trust New Buildings program has provided incentives for new community college buildings in Southern
Oregon, installing Mitsubishi VRFs. M&V-completion date is Fall 2011Erin Rowe
Investigate savings and lessons learned from Corvallis Wild Life
Preserve VRF system with HRV and economizers
Mark Jerome
Investigate lessons learned from Ecotope single-head DHP report (residential),
including both field and lab testing. Contact Bob Davis or David Baylon at Ecotope
NREL may be a resource for lab testing VRF systems
Bruce Baccei
TI Project 216 EPRI Lab Testing
Codes and standards were not available until
recently
Collaborate with "Center for Built Environment" for post occupancy
evaluation of comfort and behaviorPaul Delaney
Investigate new products and features, including US-centric controls, heat pump boilers, data center rack cooling, etc.
Mike Cundiff
EWEB commissioning
case study
AHRI 1230Mike Cundiff
Daikin provides online classes (http://www.daikinac.com/comme
rcial/trainingOverview.asp?sec=training)
Get early copies of ASHRAE VRF Handbook Chapter, which is scheduled to be available Spring
of 2012
Technology misapplication can affect deployment
Questionable cost effectiveness of economizers and ground coupled
applications
Develop screening tool for cost effective opportunities
Lack of performance data to validate
manufacturer claims
Lack of robust design and
modeling tools
Not all applications of VCHP systems with simultaneous heating and cooling
capability are cost effective
Some applications are not appropriate for VRV e.g. large OSA with not many zones
Technology misapplication
3
VCHP Energy Efficiency Measure Development Roadmap
Barriers
Action Items
Resources
TI Research Needed
Resource Available
Proposed Action Item
E3T Assessment NeededIdentified Barrier
Uncertainty in the market about the benefits of the system over the other systems
Unsure of system operation
Owner Unfamiliarity with VCHP
Develop owner training on utility incentives and VCHP
benefits
Owners are not familiar with the
systems
Get early copies of ASHRAE 90.1
2010 VRF mechanical tables
Develop best practices to ensure energy savings
Get early copies of ASHRAE VRF Handbook Chapter, which is scheduled to be available
Spring of 2012
Investigate Cascade Energy Engineering VRF system; they have been monitoring
system energy use for 5 yearsMike Cundiff
Lessons learned from ASHRAE Headquarters
VRF demonstration project
Investigate lessons learned from Oakridge
residential DHP field testing
Investigate lessons learned from Energy Trust New Buildings program has provided incentives for new community college buildings in Southern
Oregon, installing Mitsubishi VRFs. M&V-completion date is Fall 2011Erin Rowe
Investigate savings and lessons learned from Corvallis Wild Life
Preserve VRF system with HRV and economizers
Mark Jerome
Investigate lessons learned from Ecotope single-head DHP report (residential),
including both field and lab testing. Contact Bob Davis or David Baylon at Ecotope
There are a lot of HVAC options in the market so this may not be perceived as the
best option for a given application
Lack of data and market knowledge to promote
technology
Perception of risk, uncertain owner and user, occupant
acceptance
Collaborate with "Center for Built Environment" for
post occupancy evaluation of comfort and behavior
Paul Delaney
Investigate new products and features, including US-centric controls, heat pump boilers, data center rack cooling, etc.
Mike Cundiff
NEEA and BOMA owner training
4
VCHP Energy Efficiency Measure Development Roadmap
Barriers
Action Items
Resources
TI Research Needed
Resource Available
Proposed Action Item
E3T Assessment NeededIdentified Barrier
Lack of Information to Prioritize Measures
Select and define highest priority measures
Identify when and where designers include electric resistance heat
with VRF systems
Screen for where VRF HR systems are
cost-effective
Quantify savings for replacing electric
heat
Understand engineering, Installation, ownership,
utility barriers
Hard to define baselines to make comparisons
Evaluate whether the amount of VCHP
refrigerant is an issue
Preliminary screening of cost effectiveness of measures
Identify installations where savings can be verified
Verify the significance of duct losses and
feasibility of M&V
Investigate savings for baselines that do
not have cooling
Distribute and post EPRI VRF market studies,
commissioned by BPA, when they
are availableMira Vowles
Develop cost database
Mitsubishi VRF analysis based on EnergyPro model
Nick Fernandez
ASHRAE 90.1 2010 Appendix
G
Uncertain cost effectiveness for some
applications
VCHP measure potential
research and studies (Power
plan)
Evaluate top identified
applications
5
VCHP Energy Efficiency Measure Development Roadmap
Barriers
Action Items
Resources
TI Research Needed
Resource Available
Proposed Action Item
E3T Assessment NeededIdentified Barrier
Uncertain Energy Savings, Costs and Cost Effectiveness
Quantify savings and costs over a specific baseline
Select baseline
Quantify annual energy savings, benefits, costs
Develop models to quantify savings for top
priority measures
Quantify energy savings for night setback
Quantify non-energy benefits (O&M, gas savings, productivity due to improved comfort, etc.) to fully account for additional cost
effective measures
Uncertain savings
Establish measure life
Investigate lessons learned from BC Hydro
VRF office building retrofit in Vancouver; combination
of modeled/measures savings. Presented at
Emerging Tech Conference in Sacramento
in Nov 2010Ron Domitrovic
Mitsubishi VRF analysis based on EnergyPro model
Nick Fernandez
Document savings
trade-off for VRF HR without
economizers, Paul DopplerJim Benville
Investigate savings and
lessons learned from Corvallis
Wild Life Preserve VRF system with
HRV and economizersMark Jerome
Use AHRI 1230 equipment performance ratings (EER, COP, IEER) to estimate savings, including water cooled VRF system savings over air cooled VRF systems
Mike Cundiff
Skepticism about savings and real cost/benefit ratio
Investigate lessons learned from
PNNL/NEEA work to disaggregate
electrical loads, and use to determine
actual VRF system energy use
Nick Fernandez
Uncertain cost
Unknown equipment life
Distribute and post EPRI VRF market studies, commissioned by BPA, when they are available
Mira Vowles
Investigate new products and
features, including US-centric
controls, heat pump boilers,
data center rack cooling, etc.Mike Cundiff
Condensate piping and pumps are a costly oversight
Incremental costs of VRF systems could be higher or
lower than baseline systems
Utilities can not incent if incremental cost is
negative
Investigate life of Asian systems
TI Project 216 EPRI VRF HR Lab Testing
6
VCHP Energy Efficiency Measure Development Roadmap
Barriers
Action Items
Resources
TI Research Needed
Resource Available
Proposed Action Item
E3T Assessment NeededIdentified Barrier
Identify installations where savings can be
verified
Existing M&V approaches like energy modeling and deemed savings are not proven for VRF
systems
Complex systems-hard to accurately measure and quantify savings
Develop high consensus M&V
protocols
Share results from EPRI VRF&DHP EE Demo's
Mira Vowles
RTF VCHP Sub committee
IPMVP
Document M&V protocols from field tests
Possible opportunity for field testing in a set of test bed commercial buildings that are being constructed in Richland, WA at PNNL's
headquarters.Nick Fernandez
Challenges metering commercial VCHP
systems
M&V for Uncertain Energy Savings
7
VCHP Energy Efficiency Measure Development Roadmap
Barriers
Action Items
Resources
TI Research Needed
Resource Available
Proposed Action Item
E3T Assessment NeededIdentified Barrier
Product/Service Area :
Difficult to Develop Measures
Uncertain savings
Document magnitude and longevity of the incremental
electric energy savings.
Develop simple savings calculators based on documented performance to be nimble,
reduce reliance on energy models and lower program delivery cost
Evaluate cost effectiveness of measures
Develop whole building savings estimation and M&V using billing data
Verify tenant billing system
for M&V
Determine sample size to quantify statistically significant
savings
Develop equipment based measures
Uncertain cost
Field test M&V protocols
Summarize lessons learned based on
evaluation of SCE's upstream VRF
incentive programPaul Delaney
ASHRAE 90.1 2010 VRF mechanical tables
Unknown equipment life
Describe energy savings time-of-occurrence and duration: Load
Shape, Lifetime
Use AHRI 1230 equipment performance ratings (EER, COP, IEER) to estimate savings, including water cooled VRF system savings over air cooled
VRF systemsMike Cundiff
Develop performance
based measures
Consider upstream program ($/ton), similar to SCE, based
on energy models
Quantify baseline EUIs for building types
Higher first cost
VRF may add cooling to uncooled baselines
Design program to minimize free ridership
Develop simple system start-up requirements for
incentives
Develop measure specific M&V
protocols
Share results from EPRI VRF&DHP EE Demo's
Mira Vowles
RTF VCHP Sub committee IPMVP
Possible opportunity for field testing in a set of test bed commercial buildings that are being
constructed in Richland, WA at PNNL's headquarters.
Nick Fernandez
VRF Pilot to verify measure savings
Investigate incorporating VRF systems into office of
the future pilot projects which have 30-50%
savings goals. Contact Amy Cortese, with New
Building Institute, [email protected]
Bruce Baccei
Complicated utility incentive process
Define the value proposition for the utilities, building owners
and contractors
8
VCHP Energy Efficiency Measure Development Roadmap
Barriers
Action Items
Resources
TI Research Needed
Resource Available
Proposed Action Item
E3T Assessment NeededIdentified Barrier
Difficult to Develop Incentive Programs
Quantify savings for baselines that do not have
cooling
Develop VRF measures, possibly whole building/pay for performance incentives
Quantify baseline EUIs for building types
Develop best practices to prevent electric resistance
heat operation
Develop best practices and specifications for ERV design
and operation
Evaluate unoccupied temperature set-back/set-up, DOAS control, electric resistance heat lock-out, low-ambient
performance and optimal start capabilities -develop best practices and pay for performance
Higher initial costUsually adds cooling to a space that did not have
cooling before
Summarize lessons learned based on evaluation of SCE's upstream VRF incentive program
Paul Delaney
Determine free ridership. Design program to minimize
free ridership
Develop simple system start-up requirements for incentives
Develop equipment based measures
Develop performance
based measures
Consider upstream program ($/ton), similar to SCE, based
on energy models
Develop VCHP Incentives
9
VCHP Energy Efficiency Measure Development Roadmap
Barriers
Action Items
Resources
TI Research Needed
Resource Available
Proposed Action Item
E3T Assessment NeededIdentified Barrier
Codes and Standards
Costly to meet ventilation codes with VCHP systems
Follow developing IECC and other economizer code exceptions
Evaluate whether the amount of VCHP refrigerant is an issue
Safety concerns over refrigerant leaks
ASHRAE refrigerant standard
Codes and standards are still being developed
IECC 2012Get early copies of ASHRAE 90.1
2010 VRF mechanical tables
Get early copies of ASHRAE VRF Handbook Chapter, which is scheduled to be available Spring
of 2012
Follow developing codes and standards
Document savings trade-off for VRF HR without economizers, Paul Doppler
Jim Benville
IECC 2012
Difficult to meet net zero
Follow developing IECC net zero requirements
Follow developing IECC and other economizer code exceptions
Evaluate whether the amount of VCHP refrigerant is an issue
Follow developing IECC net zero requirements
10
VCHP Energy Efficiency Measure Development Roadmap
Barriers
Action Items
Resources
TI Research Needed
Resource Available
Proposed Action Item
E3T Assessment NeededIdentified Barrier
Other Barriers
Inertia of traditional (US) HVAC manufacturing design and
contracting system
Define the value proposition for the utilities, building owners
and contractors
Cheaper install equals less commission for sales man
Negative experiences e.g. ASHRAE HQ Issues
Lessons learned from ASHRAE Headquarters VRF demonstration project
Investigate lessons learned from Oakridge residential DHP field testing
Investigate lessons learned from Energy Trust New Buildings program has provided incentives for new community college buildings in Southern Oregon, installing
Mitsubishi VRFs. M&V-completion date is Fall 2011Erin Rowe
Investigate savings and lessons learned from Corvallis Wild Life Preserve VRF
system with HRV and economizersMark Jerome
Investigate lessons learned from Ecotope single-head DHP report (residential), including both field
and lab testing. Contact Bob Davis or David Baylon at Ecotope.Bob Davis
Investigate lessons learned from BC Hydro VRF office building retrofit in Vancouver; combination of modeled/measures savings. Presented
at Emerging Tech Conference in Sacramento in Nov 2010Ron Domitrovic
Share EPRI VRF & DHP EE Demo results
and Market StudiesMira Vowles
Get early copies of ASHRAE VRF Handbook Chapter, which is scheduled to be available Spring
of 2012
11
VCHP Energy Efficiency Measure Development Roadmap
Barriers
Action Items
Resources
TI Research Needed
Resource Available
Proposed Action Item
E3T Assessment NeededIdentified Barrier
Non Energy Benefits of VCHP Systems
Non Energy Benefit (Adoption Driver)
Non Energy Benefits
Aesthetics
Aesthetically more pleasing than a PTAC or PTHP
Design and Installation
Flexibility-large array of applications and models-can fit many different needs
Allows for the application of a heat pump to larger buildings where traditional HP systems
aren't feasible
Adds A/C to older buildings with less disruption
Good for renovations "older buildings"
More space in ceilings and walls
Less ductwork or no duct work
needed
Adaptability for retrofit applications
Modular components may help simplify design and flexibility for tenant changes
Ease of installation in retrofit applications
Smaller footprint than RTU
No wasted space costing-smaller shafts, mechanical rooms etc.
Straight forward retrofit for many existing systems
Full integrated controls ensures system
performs as intended
Multi splits can prevent zones from
fighting
Interface
Individualized control-billing for tenants in an office building
Energy use monitoringFDD capabilities and
remote displays
Packaged controls
Improved Comfort
Low noiseNon heat recovery mechanical
ventilation can be a comfort and an energy waster
Zonal control can be more precise-minimal simultaneous heating and cooling
Improved comfort with multiple thermostats to allow individual office personal to control their own
environment
12
13
Gannt Chart: Action Items in High Level
VCHP Energy Efficiency Measure Development Roadmap
14
Gannt Chart: Action Items in Detail (1 of 2)
VCHP Energy Efficiency Measure Development Roadmap
15
Gannt Chart: Action Items in Detail (2 of 2)
VCHP Energy Efficiency Measure Development Roadmap
Application Existing System New System
Commercial application in a converted house Electric resistance DHP mini split 2 head, 1 outdoor unit
Small and medium office Multiple single speed ASHP-AC with electric heat VRF multi split-VRF heat recovery
Small and medium office Old rooftop HP VRF with separate rooftop HP ERV
Small and medium office Single speed ASHP or A/C with electric heat VRF multi split
Small Retail Split system heat pump with fans/zonal electric without AC DHP mini split or with multiple heads
Building with data center or other heat source Any electric heat VRF heat recovery and DOAS
SchoolHydronic heat pumps with electric boiler-closed cooling tower-economizers for each zone
VRF with heat recovery
Small and medium office VAV with electric perimeter heat VRF with heat recovery
Small and medium office WSHP VRF with heat recovery
Assisted Living PTAC DHP 1 head-1 comp per room
Lodging PTAC/PTHP DHP mini split
Multi family/Multi family small-rise Zonal electric or electric FAF/Electric resistance Single or two head DHP/DHP split
Multi family-Apartments Base board heat-electric VRF multi split
Multi family-Apartments low rise PTHP with electric resistance DHP mini split
Assisted Living 4 pipe FC VAV with reheat
Lodging-Hotel Chiller-Boiler with fan coils Water cooled VRV
Assisted Living Boiler & Cooling Tower with 180 WSHPs DHP-Fujitsu 3 ton 3 head DHP 60 outdoor units 180 indoor units
Dorm FCU WSHP
Large office 4 pipe FCU VAV with reheat
Small and Medium Office-Small office up to 5000 sf RTUS(gas pack or heat pump) VRF multi split
Small or medium office-4 to 5 stories PSZ heat pumps-multiple sercing each floor VRF with heat recovery
Small and medium officeRooftop air cooled DX VAV with series or parallel fan box with ECM, 100% OA economizer-no heat recovery
VRF with heat recovery
School Chilled water fan coil units-radiators VRF with heat recovery
School Ceiling heat VRF with heat recovery
School FCU VAV with reheat
Assisted Living Base board heat-Window AC VRF with heat recovery
Large Office (>60000, > 150 tons) Packaged VAV HP VRV heat pump
Lodging-Hotel PTAC with electric heat VRF with heat recovery
Retail building approximately 40000 sq ft concrete block slightly pitched roof (flat)
Multiple roof top units (6) 10 ton with 3 ph strip heat with concentric diffusers
Daikin VRV or Mitsubishi City Multi R2: 20- 2x2 casettes for T bar ceiling & 3-wall mount units
Large Office (>60000, > 150 tons) VAV with reheat-chilled & hot water loop VRF with heat recovery
School Central boiler-Window AC VRF multi split16
Application Existing System New System
Commercial application in a converted house
Electric resistanceDHP mini split 2 head, 1 outdoor
unit
Small and medium officeMultiple single speed ASHP-
AC with electric heatVRF multi split-VRF heat
recovery
Small and medium office Old rooftop HPVRF with separate rooftop HP
ERV
Small and medium officeSingle speed ASHP or A/C
with electric heatVRF multi split
Small RetailSplit system heat pump with
fans/zonal electric without AC
DHP mini split or with multiple heads
17
Survey for Prioritization of Potential Measures
VCHP Energy Efficiency Measure Development Roadmap
18
Objective of this survey is to prioritize potential measures identified in the VCHP roadmapping effort.
Please use the following link to reach the survey
Link: http://www.surveymonkey.com/s/RM58D75
Please complete the survey by 5:00 pm on May 27th