VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

152
VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) TOLL ROAD PROJECTS: A REAL OPTIONS APPROACH by FRANK HARLEY BComm., The University of British Columbia, 1994 A THESIS SUBMITTED IN PARTIAL FULFILLMENT OF THE REQUIREMENTS FOR THE DEGREE OF MASTER OF SCIENCE (BUSINESS ADMINISTRATION) in THE FACULTY OF GRADUATE STUDIES Department of Transportation and Logistics We accept this thesis ^ig^nf^niiQg to the required standard THE UNIVERSITY OF BRITISH COLUMBIA April 1998 © Frank Harley, 1998

Transcript of VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

Page 1: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) TOLL ROAD

PROJECTS:

A REAL OPTIONS APPROACH

by

FRANK HARLEY

BComm., The University of British Columbia, 1994

A THESIS SUBMITTED IN PARTIAL FULFILLMENT OF THE REQUIREMENTS

FOR THE DEGREE OF MASTER OF SCIENCE (BUSINESS ADMINISTRATION)

in

THE FACULTY OF GRADUATE STUDIES

Department of Transportation and Logistics

We accept this thesis ̂ ig^nf^niiQg to the required standard

THE UNIVERSITY OF BRITISH COLUMBIA

April 1998

© Frank Harley, 1998

Page 2: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

In presenting this thesis in partial fulfilment of the requirements for an advanced

degree at the University of British Columbia, I agree that the Library shall make it

freely available for reference and study. I further agree that permission for extensive

copying of this thesis for scholarly purposes may be granted by the head of my

department or by his or her representatives. It is understood that copying or

publication of this thesis for financial gain shall not be allowed without my written

permission.

The University of British Columbia Vancouver, Canada

Department

DE-6 (2/88)

Page 3: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

A B S T R A C T

The goal of this thesis is to show how option valuation techniques can be used to

value managerial flexibility in Build-Operate-Transfer (BOT) toll road projects. It begins

by discussing the dramatic shift towards public-private partnerships and BOTs in the

infrastructure industry. It then looks at how traditional capital budgeting techniques often

fail to capture important sources of value created by flexibility. It discusses real options

and introduces Contingent Claims Analysis (CCA) as a means of valuing flexibility

which takes into account the opportunity to construct replicating portfolios in the market.

It applies CCA to the real options present in each phase of a BOT toll road project.

During the build phase, it looks at the option to abandon, the option to change

scale/technology, and time-to-build flexibility. During the operate phase, it analyzes toll-

setting flexibility, development gain options, and project financing flexibility. At the

transfer phase it considers arrangements with option-like features. In conclusion, this

thesis emphasizes the relevance of real option valuation techniques to BOT toll road

projects and points the way to further research fusing the fields of transport economics

and financial economics.

Page 4: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

TABLE OF CONTENTS

Abstract ii Table of Contents iii List of Figures vi Acknowledgements vii

1. Introduction 1

2. The infrastructure revolution 5 2.1. Introduction 6 2.2. The changing nature of infrastructure 6 2.3. The spectrum of public-private partnerships 8 2.4. Build-Operate-Transfer 11

Host government Sponsors Lenders Consumers

2.5. BOT toll roads 15

3. The real options revolution 17 Introduction 18 3.1 Traditional capital budgeting 19

3.1.1. Introduction 19 3.1.2.Why is net present value the best investment decision criteria? 19

The financial objective of the firm Time-preference utility curves Capital markets Productive opportunities Investing in both productive opportunities and capital markets Internal Rate of Return (IRR) Payback period Average return on book value Profitability index

3.1.3. Evaluating investment opportunities under uncertainty 27 Risk-adjusted discount rate approach (RADR) Certainty equivalent approach Sensitivity analysis Monte Carlo simulation Decision-Tree analysis

3.1.4. Problems with traditional capital budgeting 40 3.2 Real Options 41 3.2.1. Introduction 41

What is a real option? The real options revolution

iii

Page 5: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

Financial options versus real options Call options Put options The analogy between financial options and real options

3.2.2. The basics of real option valuation 49 An example of real options Contingent claims analysis (CCA) Using CCA to value real options The option to defer investment The option to default during construction The option to expand The option to contract The option to temporarily shut down The option to abandon for salvage value or switch to best alternative use The option for corporate growth

3.2.3. Summary 63

4. Real options in BOT toll roads 65 Introduction 66 4.1. Build phase 68 4.1.1. Introduction 68 4.1.2. The option to abandon midstream 68 4.1.3. The option to change scale or technology 75 4.1.4. Time to build option 77 4.1.5. Summary 78 4.2. Operate phase: toll-setting flexibility 79 4.2.1. Introduction 79 4.2.2. Deriving the toll demand curve 80 4.2.3. Stochastic demand curves and the value of fixed tolls 93 4.2.4. The value of complete flexibility 96 4.2.5. The value of partial flexibility 103 4.2.6. Trigger adjustments 104 4.2.7. Profit-maximization versus economic efficiency 106 4.2.8. Summary 112 4.3. Operate/transfer phase: other real options 113 4.3.1. Introduction 113 4.3.2. Development gain options 113 4.3.3. Financial flexibility 115 4.3.4. Transfer options 118 4.3.5. Summary 119

5. Conclusion 121

6. Bibliography 124

Page 6: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

7. Appendices 128 6.1. BOT toll road survey 129 6.2. Value of Travel Time Savings (VTTS) 132 6.3. Traffic congestion functions 136 6.4. Mathcad derivation of toll demand curve 138

V

Page 7: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

LIST OF FIGURES

2.1 Structure of a BOT project 12 3.1 Time-preference utility curves 20 3.2 Market opportunity line 21 3.3 Productive opportunities curve 22 3.4 Optimal and suboptimal investments exploiting market opportunities 23 3.5 Diversification eliminates unique risk, but leaves market risk 28 3.6 Efficient Portfolio frontier with borrowing and lending 29 3.7 The CAPM security market line (SML) 31 3.8 Sensitivity analysis: A simplified toll-bridge spider graph 34 3.9 NPV probability distribution 36 3.10 Decision tree of whether or not to invest in AVI technology 38 3.11 Managerial flexibility introduces payoff asymmetry 42 3.12 Asymmetric payoffs from options 45 3.13 Value of a call (C) before its expiration date, . . 46 3.14 Value of a put (P) before its expiration date 47 3.15 Possible price movements over one year 51 3.16 A portfolio replicating the value of the investment opportunity 51 3.17 Possible price movements over one time period 54 3.18 Salvage value or best alternative use (A) 62 4.1 The life cycle of a BOT toll road project from the concessionaire's perspective 66 4.2 Stochastic movement of project value 70 4.3 A twist to traditional Social Cost-Benefit Analysis 81 4.4 Deriving the toll demand curve assuming everyone has the same VTTS 83 4.5 Demand for travel to D for groups with different values of travel time savings 85 4.6 Dynamic process to derive the toll demand curve for two groups with different VTTS 86 4.7 Toll demand curve derived by Mathcad for groups H and L 91 4.8 Dynamic process for four VTTS groups 92 4.9 Binomial movements of BH over time 94 4.10 Profit-maximizing toll at time zero BH =100 94 4.11. Present value of opportunity to receive uncertain cash flows at time one 98 4.12 Sensitivity of complete flexibility option value to (3 estimates (from 0 to 2) 101 4.13 Sensitivity of partial flexibility option value to beta estimates (from 0 to 2) 104 4.14. Trigger adjustment option payoff diagram 105 4.15. The marginal time cost toll demand curve 109 4.16. Average time cost toll demand curve 110 4.17 Movements in shopping mall value 115 III. 1. A congestion function for a highway and a central business district street 137

Page 8: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

ACKNOWLEDGEMENTS

I would like to thank Dr. Bill Waters for his guidance and encouragement

throughout the preparation of this thesis. My gratitude also goes to Dr. Burton Hollifield

for his valuable insights into financial economics and to Dr. Tae Oum for his teachings

on transport demand analysis. Finally, I would like to thank my parents for all their

support.

Page 9: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

CHAPTER ONE

INTRODUCTION

Page 10: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

1. INTRODUCTION

The goal of this thesis is to show how real option valuation techniques can be

used to quantify the value of flexibility in Build-Operate-Transfer (BOT) toll road and

bridge projects. A BOT is a complex public-private partnership in which the host

government grants a private-sector consortium a concession to build an infrastructure

facility, operate it long enough to pay back project debt and equity, and then transfer

ownership to the host government.

Traditionally, infrastructure projects have been supported through public sector

agencies. These projects often do not recover their costs but are justified on social

grounds or because of their broader economic benefits. However changes in technology,

demand, and economic philosophy have led to a surge in the popularity of BOT as an

efficient approach to providing infrastructure. Within the rapidly changing infrastructure

environment, policy-makers and investors are struggling to understand the key factors to

a successful BOT project. However, many of their analytical tools are coarse and fail to

reveal the opportunities for profit or loss created by complex contractual arrangements in

BOT projects. Fortunately, innovations in financial economics have a created a new tool

— real option valuation — which can provide insight into the dynamics of value in BOT

toll road projects.

This thesis begins by discussing the revolution which is taking place in the

provision of infrastructure around the world. Chapter Two looks at how severe fiscal

constraints and growing demand for infrastructure have stimulated governments in both

developed and lesser developed countries to explore public-private partnerships (P3s) as a

2

Page 11: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

means of coping with infrastructure bottlenecks in transportation, power, and

telecommunications. The chapter introduces the BOT concept and its many variations

reflecting different degrees of risk sharing between the public and private sector. It

discusses the key ingredients of a BOT project and the pros (additionality, acceleration,

efficiency, externalities) and cons (complexity) of the BOT approach. Chapter Two

concludes by looking at the role of BOTs in the area of toll roads and points out that

while BOTs have the potential to improve a nation's transportation system, they can be

overwhelmingly complex to value with traditional capital budgeting techniques.

Chapter Three looks at how the "real options revolution" in financial economics

has provided investors and policy-makers with a set of powerful new valuation tools. The

chapter begins with an overview of traditional capital budgeting techniques such as risk-

adjusted discounting, simulation, and decision-tree-analysis and points out their inability

to correctly value managerial flexibility. It then introduces option valuation as means of

quantifying the value of risky cash flows which have asymmetric payoffs. It draws a

comparison between financial options which involve the right, but not the obligation, to

buy (call) or sell (put) financial assets and real options which involve claims on real

assets (a factory, an oil field, revenues from a toll road). It shows how Contingent Claims

Analysis (CCA) and the concept of arbitrage-free replicating portfolios can be used to

price real option premiums. Finally, it works through a generic oil field example to

illustrate the mechanics of real option pricing.

Chapter Four focuses on the application of real option valuation techniques to

BOT toll road projects. Real options in a BOT toll road project include the flexibility to

3

Page 12: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

abandon or postpone the project during construction, change the scale or technology of

the project, set tolls, develop ancillary facilities, alter the pattern of equity injection and

debt repayment, and transfer the facility. By using real option valuation techniques to

value these different types of flexibility, the parties to a BOT project can gain a better

understanding of the tradeoffs they are making when they negotiate a BOT contract. This

should facilitate the development of economically sound BOT projects.

Chapter Five concludes by summarizing the major points of this thesis. It argues

that the timely convergence of two revolutions — one in transportation economics and

one in financial economics — has profound implications for both the suppliers and the

consumers of infrastructure around the world. The real options approach to capital

budgeting has provided policy makers and investors with valuable analytical tools. By

applying these tools in an innovative and theoretically sound manner, the government

and private sector should be able to improve the chances of success for a BOT project.

This in turn should help societies around the world cope with the tremendous pressures

mounting on their road infrastructure.

4

Page 13: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

CHAPTER TWO

THE INFRASTRUCTURE REVOLUTION

Page 14: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

2.1. Introduction

Unprecedented economic growth in the twentieth century has created severe

infrastructure bottlenecks around the globe. Rapid population growth and urbanization

have placed tremendous strains on basic infrastructure such as water and sewage systems,

power, telecommunications and transportation networks in both the developed and the

developing world. Furthermore, mismanagement of infrastructure has damaged the

environment, hurt people's quality of life, and undermined the economic competitiveness

of many nations. Cashed-strapped governments realize the need for change, but are hard-

pressed to come up with the necessary resources.

Faced with intense pressure to improve infrastructure services, the public and

private sectors have begun to explore various types of partnerships. This chapter focuses

on one of these partnerships: Build-Operate-Transfer (BOT). It begins by discussing how

and why the infrastructure market is changing. It then looks at several types of public-

private partnerships which have emerged as alternatives to traditional public sector

infrastructure provision. Next, it examines the dynamics of BOT projects and discusses

their pros and cons. The final section provides a brief introduction to the BOT toll road

market and sets the stage for the application of real option valuation techniques to BOT

toll roads.

2.2. The changing nature of infrastructure

Traditionally, infrastructure has been thought of as a "public good" which should

be provided by the government. The argument for government control is based on two

6

Page 15: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

observations. First, infrastructure tends to be a natural monopoly because it involves

large fixed costs and economies of scale. Government control is therefore necessary to

prevent abuse of monopoly power. In addition, the government must keep the price low

to encourage the utilization of sunk facilities, even though this may not lead to cost

recovery. Second, infrastructure is the backbone of many economic activities and

involves significant positive externalities and network effects. Government control is

thus necessary to ensure a stable and sufficient supply of vital infrastructure services.

This philosophy has been the driving force behind infrastructure policy since the turn of

the century. However, since the 1980s, developments in the public and private sector

have been challenging the traditional approach to infrastructure. The main forces behind

this change are:

• Disenchantment with publicly provided infrastructure: In many cases, public

monopolies and state agencies have been largely ineffective in meeting the growing

demand for infrastructure. Voters and politicians want change.

• Fiscal constraints: Accumulated debts, aging populations, and increasing pressures

on health and education systems have left many governments with fewer resources to

spend on infrastructure.

• Construction firms looking for work1: The aftershocks of the end of the Middle

East construction boom in the early 1980s are still being felt as construction firms

scour the globe in search of new infrastructure projects to take up the slack.

1 Augenblick M. and Scott-Custer B. The BOT approach to infrastructure projects in developing countries. World Bank Working Paper, August 1990

7

Page 16: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

• Financial innovations and the globalization of financial markets: The rapid

growth in limited recourse project financing, improvements in risk management

techniques, and greater access to global capital markets have stimulated governments

and financiers to look for innovative ways to finance infrastructure.

• Technological developments: New technologies such as IPP (Independent Power

Producers), cellular phones, port containerization, and AVI (Automatic Vehicle

Identification) systems are radically changing the nature of infrastructure provision.

These technologies have reduced natural monopoly characteristics, facilitated

unbundling, encouraged private entry, and stimulated competition in many

infrastructure services.

These forces have converged to make "privatization" the buzzword of the 1990s.

Governments around the world are promoting "privatization" strategies as a means of

tapping into private sector efficiencies while improving government finances.

Unfortunately, the word privatization is often used rather crudely and fails to reflect the

wide range of possible partnerships between the public and private sector.

2.3. The spectrum of public-private partnerships (P s)

Public-private partnerships exist along a continuum between complete public

sector ownership and operation and complete private sector ownership and operation.

The goal of P s is to promote economic efficiency in infrastructure services by allocating

project risks to those parties best able to mitigate the risks and by tapping into private

8

Page 17: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

sector managerial efficiency and discipline. The following is a list of the major P types

which are being used to inject life and efficiency into moribund infrastructure services .

• Service contracting: the public sector provider sets performance criteria, evaluates

bids, supervises the contract, and pays lump-sum fees. A common example is road

maintenance.

• Management contracting: like service contracting, except the contractor has more

autonomy in day-to-day management and shares some of the commercial risk of the

enterprise.

• Design-Build (DB or turnkey): the private sector designs and builds a facility to

meet public-sector performance specifications. The private sector often bears the risk

of cost overruns.

• Design-Build-Maintain: the public sector operates the DB facility, but the private

sector still has certain maintenance responsibilities.

• Design-Build-Operate (DBO or "super turnkey"): the private sector builds and

operates the facility, but ownership remains with the public sector

• Lease-Develop-Operate (LDO): the public sector leases an existing facility to a

private operator who expands, and operates the facility. The facility remains publicly

owned and is transferred back to the public sector at the end of the lease.

• Build-Lease-Operate-Transfer (BLOT): a private operator leases land from the

public sector to build and operate a new facility. The facility is transferred to the

public sector at the end of the lease term.

2 British Columbia. Task Force on Public-Private Partnerships. Building Partnerships: report of the Task Force on Public-Private Partnerships. Crown Publications, Oct. 1996

9

Page 18: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

• Build-Transfer-Operate (BTO): a private developer designs, finances and

constructs a facility which is transferred to the public sector upon completion. The

public sector then leases the facility back to the private developer. BTO enables the

developer to get a reasonable return on investment while avoiding the liability

complications of private ownership.

• Build-Operate-Transfer (BOT): a private developer receives a concession to

finance, design, build and operate an entirely new facility for a specified period. The

facility is transferred to the public sector at the end of the concession period.

• Build-Own-Operate (BOO): a private developer finances, builds, owns, and

operates a facility in perpetuity subject to public sector intervention as stipulated in

the concession contract.

• Transfer to Quasi-public Authority: a quasi-public authority takes control of a

public sector asset under contract that it will perform public services using private

procedures and financing.

This is an incomplete list of the evolving terminology in the infrastructure

market. Other points on the P 3 spectrum include BOOT (Build-Own-Operate-Transfer),

BOOST (Build-Own-Operate-Subsidize-Transfer), BROT (Build-Rent-Operate-

Transfer), ROT (Refurbish-Operate-Transfer), RTO (Refurbish-Transfer-Operate). In

Britain, P s are referred to as PFI (Private Finance Initiative). All of these terms reflect

different degrees of risk and responsibility sharing between the public and private sector.

Amidst this explosion of acronyms, BOT has gained the most notoriety and is often used

10

Page 19: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

casually to refer to many of the forgoing P3s. We will use BOT in a stricter sense

described in the following section.

2.4. Build-Operate-Transfer

In a BOT project, the government grants a concession to a private consortium to

build an infrastructure facility, operate it for a specified period (usually 20 to 30 years) to

earn a reasonable return on investment, and then transfer the facility to the government at

the end of the concession period. The roots of BOT can be traced back to the concessions

of the eighteenth and nineteenth centuries. One of the earliest BOT prototypes was a

concession granted to the Perrier brothers in 1782 to supply water to Paris. Egypt is

home to perhaps the most famous early BOT fossil — the Suez Canal. Opened in 1869,

this canal was built and financed by a British-French consortium under a concession

granted by the Egyptian government.

The properly-structured modern BOT has evolved considerably from its primitive

ancestors. While earlier concessions gave the private sector free reign over the facility,

today's BOT strives to achieve an optimal sharing of risk and responsibility between the

public and private sector. As shown in figure 2.1, the key ingredients to a BOT are:

Host government:

Support from the host government is crucial to the success of a BOT project.

There are several reasons why the host government may prefer the BOT approach:

11

Page 20: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

Figure 2.1. Structure of a BOT project

Host government

Multilateral agencies Project agreement

Government Special agencies agreements

Lenders Loan agreements

Insurers Insurance policies Insurance policies

Shareholders' agreement

Technical, financial and legal advisors

Supply contract

Sponsors

Consumers of infrastructure service

Construction contract

Contractors Construction contract

Suppliers

Operation and Maintenance contract

Operator Operation and Maintenance contract

Operator Operation and Maintenance contract

• Additionality: projects are realized which otherwise would not get built due to

constraints on public spending. Commercial banks may be reluctant to lend to certain

countries, but willing to lend to specific projects within those countries.

• Acceleration: projects can be accelerated which otherwise would have to wait for

scarce funds.

0 Efficiency: private sector capital, initiative, and know-how may reduce construction

costs and time while improving operating efficiency.

• Credibility: the scrutiny of private sector investors may weed out any "white

elephants".

12

Page 21: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

° Positive externalities: society can benefit from technology transfer and training, the

strengthening of local capital markets, and an improved investment climate.

• Strategic control: the government maintains a certain degree of control over

important infrastructure networks.

The major disadvantage of BOTs is that they are extremely complex to negotiate

and manage. If the host government decides that the advantages of the BOT approach

outweigh the costs of its complexity, then the host government must decide what kind of

role to play in order to ensure the project's success. This role can take a variety of forms

such as providing direct loans, standby loan agreements, revenue guarantees, loan

guarantees, or tax breaks. The host government must decide how to regulate rate-of-

return, tariffs, and safety. A controversial issue is whether or not the host government

should take an equity position in the project. While a government equity position

improves the project's transparency and could prevent the consortium from being

exploited by any one sponsor (for example, the lead construction company may favour

subcontracting to its own subsidiaries whereas other sponsors with smaller equity stakes

may want to look for cheaper external subcontractors), such an arrangement may also

result in the loss of private sector efficiencies due to the interference of inexperienced

government officials.

Sponsors

Construction companies have typically taken the lead in forming BOT project

companies. The inclusion of independent non-construction-related investors is

recognized as an important means of imposing discipline on the project company. The

13

Page 22: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

consortium should be well balanced: David and Goliath do not mix well. Project

companies tend to be international consortiums. This has two main advantages. First, it

improves the political acceptability of the project because the concession is not seen as

benefiting any one country. Second, it spreads the risks and gives the project company

access to funds from a number of different export credit agencies. A project company

should also include well-connected local contractors as sponsors.

Sponsors typically take equity stakes in a BOT project ranging from 10 to 30

percent. Their stake can take a variety of forms such as common shares, preference

shares (guaranteed dividend), or convertible preference shares. The size of the equity

stake is important because it is often interpreted by the host government as an indication

of the sponsors' degree of commitment to the project. A large equity stake lessens the

interest burden. However, a large equity stake also increases the pressure on the project

company to impose high tariffs in order to maximize dividends. This may go against the

government's desire to keep tariffs at a politically acceptable level (i.e., a level which

maximizes social welfare).

Lenders

Project financing is the foundation of any BOT project. In project financing,

lenders look to the project's assets and revenue stream for repayment. Lenders have

limited or no recourse to the project sponsors' other assets. Project financing relies on

financial engineering to allocate project risks optimally among lenders and equityholders.

Financial engineering uses debt of varying seniority, convertible bonds, and derivatives

14

Page 23: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

(foreign exchange and interest rate options and futures) to construct complex mezzanine

financing arrangements which are tailored to the risk structure of the project.

Lenders tend to be large international and domestic banks. Host governments can

also play significant roles as lenders. Multilateral agencies such as the International

Finance Corporation and the Asian Development Bank have begun to raise their profile

as BOT lenders. Infrastructure funds such Global Power Investments ($2.5 billion joint

venture between GE Capital, Soros Fund Management, and the IFC) and AIG Asian

Infrastructure Fund ($1.2 billion) have also entered the BOT market.

Consumers

The direct consumer of the output from a BOT project can be the government

(off-take agreements for electric power plants), large corporations (airlines using a BOT

airport) or the general public (toll roads). The uncertainty of demand varies dramatically

depending on the type of customer. This should be reflected in the financial structuring

of the project.

The general public may support the BOT approach because it does not involve the

raising of taxes. Furthermore, the "user-pay" approach may appeal to those who rarely

use the facility.

2.5. BOT toll roads

Toll roads and bridges have become one of the hottest areas in the BOT market.

Developed and developing countries alike are rushing to introduce BOT projects into

their transportation networks. Appendix I lists some of the major BOT toll road and

15

Page 24: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

bridge projects around the world. However, BOT toll roads should not be viewed as a

panacea for a nation's transportation problems. Poorly managed BOT toll roads can

exacerbate traffic congestion and damage a country's overall investment environment

(witness the Bangkok Second Stage Expressway fiasco). Nevertheless, the efficiencies of

a prudently planned BOT toll road project can benefit society immensely by releasing

resources (government finances, travellers' time) which can be put to productive use in

other sectors of the economy.

The success of a BOT toll road hinges on identifying and correctly pricing

important sources of project value. This enables all parties involved to gain a better

understanding of what they are getting into. Chapter Three shows how traditional capital

budgeting fails to recognize the value of managerial flexibility. Managerial flexibility in

a BOT toll road is created both by the inherent nature of large infrastructure projects and

by negotiated contractual arrangements between the public and private sector. Chapter

Three introduces the option valuation technique of Contingent Claims Analysis as a

means of valuing managerial flexibility. This discussion sets the stage for the main focus

of this thesis: How to use real option valuation techniques to value flexibility in BOT toll

road projects.

16

Page 25: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

CHAPTER THREE

THE REAL OPTIONS REVOLUTION

Page 26: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

INTRODUCTION

To understand the far-reaching implications of the real options "revolution", it is

necessary to review the basics of traditional capital budgeting. This chapter begins by

reviewing the economic rationale behind net present value (NPV) analysis, first under

certainty, and then under uncertainty. It looks at how traditional approaches such as risk-

adjusted discounting, Monte Carlo simulation, and decision-tree-analysis fail to capture

the value of managerial flexibility in many situations. It then introduces the concept of

real options as a means of valuing managerial flexibility and gives a brief overview of

their academic evolution. Finally, it works through a generic oil field example to show

how Contingent Claims Analysis (CCA) can be used to value real options.

18

Page 27: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

3.1. TRADITIONAL CAPITAL BUDGETING

3.1.1. Introduction

This section looks at traditional approaches to capital budgeting and project risk

evaluation. It begins by discussing the economic theory behind the fundamental rule of

investment: maximize net present value (NPV). It shows how NPV is superior to other

investment criteria such as internal rate of return (IRR), payback period, average return

on book value, and profitability index. It then looks at how risk is handled by the

traditional tools of capital budgeting: the risk-adjusted discount rate and the Capital Asset

Pricing Model (CAPM), the certainty equivalent approach, sensitivity analysis,

traditional simulation (Monte Carlo), and decision-tree analysis. It concludes by pointing

out the shortcomings of traditional capital budgeting tools and the need for an approach

which systematically captures the value of managerial flexibility under uncertainty.

3.1.2. Why is net presient value the best investment decision criteria?

The financial objective of the firm

The financial goal of a firm should be to maximize the utility of its stockholders.

Stockholders have different utility curves reflecting their desires:3

• to maximize wealth

• to transform that wealth into preferred consumption patterns over time

• to choose the risk characteristics of those consumption patterns

3 Brealey, R., and S.C. Myers. Principles of Corporate Finance, fourth edition. McGraw-Hill. 1991. p. 23

19

Page 28: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

The firm does not need to know the individual utility curves of all its

shareholders in order to maximize their utility. If the firm maximizes shareholders'

wealth by undertaking all projects with a positive net present value, then in competitive

capital markets, shareholders will be able to maximize their utility through their own

actions. They can achieve the desired intertemporal pattern of consumption by borrowing

and lending. They can also adjust the riskiness of their consumption pattern by investing

in assets with different degrees of risk. Thus, within capitalist economies where the

separation of ownership and management is a practical necessity, managers of firms

should follow one simple instruction: maximize net present value. The logic behind this

fundamental rule can be illustrated graphically as follows. For simplicity, we will

consider a riskless, two-period world.

Time-preference utility curves

Individuals must choose between current and future consumption. In figure 3.1,

time-preference utility curves represent combinations of current and future consumption

which leave an individual equally satisfied. These curves are convex to the origin

Figure 3.1 Time-preference utility curves

C

U-

c,

20

Page 29: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

indicating that individuals prefer current consumption (C0) to future consumption (Q).

An individual's objective is to achieve the highest utility possible.

Capital markets

Capital markets facilitate the transfer of wealth across time; dollars today are

traded for dollars in the future at an exchange rate known as the interest rate (r) which is

represented by the slope of the market-opportunity line in figure 3.2. The relationship of

a dollar today (C0) to a dollar in the future (d) is:

C - C l

1 + r

Figure 3.2 Market-opportunity line

prefers to lend Q | j for future

consumption

prefers to borrow for current consumption

C 0

Borrowing and lending through the capital market removes the obligation to

match consumption and cash flow. Individuals will invest where their indifference curves

are tangential to the market-opportunity line.

Productive opportunities

Individuals can also invest in real assets such as plants and machinery. The

returns from investing in productive opportunities are depicted in figure 3.3. Starting

from P, the initial investment lj may yield returns higher than those in the capital market.

21

Page 30: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

However, this curve exhibits diminishing returns because "unless the individual is a

bottomless pit of inspiration, the line will become progressively flatter"4. The slope of

this curve is the marginal rate of return on productive investments which is identical to

the internal rate of return (IRR). In the absence of capital markets, individuals will invest

at the point of tangency between their utility curves and the productive opportunities

curve.

Figure 3.3 Productive-opportunities curve

Diminishing returns: investment Ij yields return of Rj Equivalent amount I2 only yields R 2

Investing in both productive opportunities and capital markets

We will now see how an individual's utility can be maximized by investing in

both productive opportunities and capital markets. Looking at figure 3.4, if people could

only invest in capital markets, then they would have to choose a point along DH.

Likewise, if they could only invest in productive opportunities, then they would have to

choose a point along DL. However, by investing amount JD in productive opportunities

4 Brealey and Myers p. 17

22

Page 31: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

and lending OJ in capital markets, they could increase their future income by GM. By

borrowing against OG, they could increase their current income by JK. By investing an

optimal amount JD in productive opportunities and then borrowing or lending in capital

markets, individuals have increased their utility to any point along KM.

Figure 3.4 Optimal and suboptimal investments exploiting market opportunities

Q

M With an optimal

M S. / investment, utility is N. / maximized to any

\ / point along line KM

L H \ \ ^ " " " O ^ Optimal

>w / investment G

\ ^ i / Yv Suboptimal N . • \ \ / investment M )

>. 'V/\ yields only DQ

0 J N D Q K C o

Why is JD the optimal amount to invest? This can be explained by the Net

Present Value Rule. JK is the present value of OG. JD is the cost of the investment and

the net present value of the investment is JK-JD-DK. JD is the amount which

maximizes this difference DK. If we only invested ND, then the NPV would be A©-

NQ=DQ which is less than DK and thus suboptimal.

The preceding discussion has shown how maximizing NPV will lead to an

optimum level of investment from a shareholder's perspective. However, while NPV is

widely considered to be the superior investment rule, there are several other investment

23

Page 32: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

criteria available to managers: internal rate of return (IRR), payback, average return on

book value, and profitability index.

Internal Rate of return (IRR)

The Internal Rate of Return is the discount rate that makes the NPV of a project

equal zero. The IRR investment rule states simply "Accept investment opportunities

offering rates of return in excess of their opportunity costs of capital."5 IRR, which is a

profitability measure determined by the amount and timing of project cash flows, should

not be confused with the opportunity cost of capital which is a standard of profitability

determined in the market by the expected rate of return on assets with similar risk

profiles.

In figure 3.4, the optimality of JD in a two-period certain world can be explained

using IRR. Moving along the productive-opportunity curve from P, we invest in

productive opportunities as long as the marginal return on investment is greater than the

slope of the market-opportunity line. In other words, we invest as long as the internal rate

of return (IRR) is greater than the opportunity cost of capital.

Although NPV and IRR criteria often lead to the same results, the IRR rule

contains several pitfalls:

• Lending or borrowing: In some projects, we pay out money now and receive money

later which is equivalent to lending. In other projects, we receive money now and pay

out money later which is equivalent to borrowing. Some projects are hybrids which

exhibit features of both borrowing and lending over time. Depending on the timing of

5 Brealey and Myers p. 83

24

Page 33: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

cash inflows and outflows, all such projects could end up having the same IRR

leaving us at a loss as to which was the best investment. NPV would clearly indicate

the optimal investment.

• Multiple Internal Rates of Return: In some cases, there are several discount rates

which make NPV equal zero. According to Descartes "rules of signs", "there can be

as many different internal rates of return for a project as there are changes in the sign

of the cash flows."6

• Mutually exclusive projects: IRRs do not add up so that if you combine a bad project

with a good project, you may end up with a higher IRR than the good project on its

own. In addition, IRR can be misleading when you try to rank projects of different

scale and with different patterns of cash flow over time. However, these difficulties

can be overcome if you look at the IRR on incremental investment.

• Curved interest-rate term structures: The short-term opportunity cost of capital often

differs from the long term rate. The IRR rule tells us to invest if IRR is greater than

the cost of capital, but how do we compare the IRR to several different rates? We are

now faced with the difficult task of trying to come up with a weighted average of

these rates.

Despite these problems, IRR can be finessed to produce the same results as NPV

analysis. However, NPV is a simpler method less prone to pitfalls.

Payback Period

6 Brealey and Myers p. 87

25

Page 34: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

Firms arbitrarily choose a payback period — the time it takes before cumulative

forecasted cash flows equal the initial investment — and then accept any projects which

make this cutoff. Payback is inferior to NPV analysis because it ignores all cash flows

after the cutoff point.

Average return on book value

Projects are judged on their book rate of return — the average forecasted profits of

a project after depreciation and taxes divided by the value of the investment. This method

has several serious defects. First, it doesn't consider the time value of cash flows.

Second, it uses accounting definitions of capital investment and depreciation rather than

real cash flows. Finally, the choice of a cutoff average book rate of return is completely

arbitrary.

Profitability index

The profitability index, also known as the benefit-cost ratio, divides the present

value of future cash flows by the initial investment. The rule is to accept all projects with

an index greater than one. Profitability index closely resembles NPV, but suffers from

the same pitfalls as IRR when comparing mutually exclusive projects.

In conclusion, within the framework of traditional capital budgeting, the NPV

investment rule is the most reliable approach to maximizing shareholder utility.

However, as will be emphasized throughout this paper, straight discounted cash-flow

NPV analysis does not fully capture the dynamics of project value under uncertainty. We

now look at how traditional capital budgeting has dealt with the problem of evaluating

investment opportunities under uncertainty.

26

Page 35: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

3.1.3. Evaluating investment opportunities under uncertainty

The preceding discussion assumed away risk. However, risk is present in any

investment decision. Sources of risk include uncertainty over costs, demand, competition,

and government policy. Under uncertainty, NPV input variables are characterized by a

probability distribution rather than a specific value. Given an NPV function, the

distribution of primary input variables can be used to generate a probability distribution

of NPVs. Rational individuals are risk-adverse and will require higher returns for taking

on projects which have greater NPV variability. Evaluation of risk is an integral part of

capital budgeting and has traditionally been dealt with using a variety of approaches:

• risk-adjusted discount rate approach

• certainty equivalent approach

• sensitivity analysis

• Monte Carlo simulation

• decision tree analysis

Risk-adjusted discount rate approach (RADR)

RADR adjusts the discount rate (r) to factor in both the time value of money and

a risk premium for the project. Future expected cash flows E(c) are discounted at this

adjusted rate (r) to calculate the NPV:

NPV = ± ^ T - I £k (l + r)r

27

Page 36: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

where / is the initial investment. According to the rules outlined above, firms should take

on positive NPV projects to maximize shareholder utility.

Some firms use discount rates based on a rather ad-hoc set of investment risk

categories; 30% discount rate for speculative ventures, 20% for new products, 15% for

the expansion of existing business (current cost of capital), and 10% for cost

improvements using known technologies7. However, this is a coarse approach which

often fails to recognize the risk characteristics of specific projects.

The Capital Asset Pricing Model (CAPM) is a more systematic approach which

relates the return of a project to its relevant nondiversifiable (systematic) risk. The logic

behind the CAPM can be summarized as follows.

As shown in figure 3.5, overall risk can be reduced by holding a portfolio of

assets which are not perfectly correlated. Losses in one position tend to be offset by gains

in another. The variance of returns for a well-constructed portfolio will be less than the

sum of the individual variances. Unique or firm-specific risk (eg. the health of a CEO)

can be diversified away leaving only nondiversifiable risk (also called market or

Figure 3.5 Diversification eliminates unique risk, but leaves market risk.

Portfolio o unique risk

market risk

number of assets

1 5 10 15

7 Brealey and Myers p. 201

28

Page 37: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

systematic risk) which is driven by general economic forces (eg. inflation).

By combining different assets, investors seek to create a portfolio which

maximizes return for a given level of risk. In figure 3.6, the crosses represent inefficient

mixtures of assets because a higher return could be attained for the same level of risk.

The thick curve represents the frontier of efficient portfolios. This curve can be

calculated using a variant of linear programming known as quadratic programming

which requires estimates of the expected return and standard deviation of each asset and

the correlations between each pair of assets as inputs.

Figure 3.6 Efficient Portfolio frontier with borrowing and lending

Expected return _ borrowing

lending /

x x

[ X x

Standard deviation

We can extend the range of investment possibilities through borrowing and

lending. By investing some money in asset portfolio 5 and some in riskless treasury bills

(i.e., lending), we can achieve any risk-return combination along line RtS. If we can

borrow at the risk-free rate, by investing the proceeds in S, we can achieve risk-return

combinations beyond S.

29

Page 38: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

With opportunities for diversification, an investor should only require a risk

premium to compensate for a new asset's marginal contribution to the total risk of the

market portfolio. The CAPM determines this risk premium using "betas" (|3) which are a

function of the covariance of an asset's return to the return of the securities market as a

whole:

£ ( r ) = r + 6 [E(rm)-rf]

where E(r) is the required return from the asset, E(rJ is the expected return from the

market portfolio, rf is the risk-free interest rate and

= cov(r,rm) var(rm)

is the asset's volatility relative to the market. Betas are estimated by regressing an asset's

returns against the returns of the entire market (a stock index like the TSE 300):

r = a + (3xr m +8

where r is the return on the asset, rm is the return on the market and a and e are

parameters characteristic of the asset. Beta is estimated using ordinary least-squares

(OLS) regression. There are a number of brokerage and advisory services which

regularly publish beta estimates.

The CAPM formula relating the expected return on an investment to its beta can

be represented graphically with the security market line. A riskless investment has a beta

of zero while the market portfolio has a beta of one. As depicted in figure 3.7, the CAPM

postulates a linear relationship between these two benchmarks with the risk premium of

an investment varying in direct proportion to its beta.

30

Page 39: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

Figure 3.7 The CAPM security market line (SML)

Expected return on investment

I SML=E(r)=rf+(3[E(rm)-rf]

The CAPM provides a sound theoretical basis for deriving an appropriate

discount rate. It assumes there is a set of efficient asset portfolios which provide the

highest expected return for a given standard deviation. The market portfolio is the point

of tangency between the frontier of efficient portfolios and the borrowing-lending line

extended from the risk-free rate of return. Investors are interested in the marginal impact

of an asset on the risk of a portfolio. This impact depends on the stock's sensitivity to

changes in portfolio value. This sensitivity is measured by betas. The appropriate

discount rate (i.e., the opportunity cost of capital) for a given project is calculated using

the project's beta, the risk-free rate, and the risk premium (expected market portfolio

return minus risk-free rate) as inputs. This discount rate is then used for NPV analysis.

Let's look at how RADR could be used to evaluate a toll road project. First the

betas for similar toll road projects would be estimated by regressing the returns on toll

roads to the returns on a market index. Although what constitutes a similar project is

often subject to debate, we will assume that these toll roads are exposed to basically the

Page 40: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

same economic, political, and operational risks and have similar debt-equity structures.

Given an average beta estimate of 0.80 (perhaps reflecting stable demand and a

monopolistic position for the toll roads), a risk premium on the market of 7.4% , and a

risk free rate of 5%, we would use the CAPM as follows:

E(r)=rf+$x[E(rm)-rf]

Eir) =0.05 + 0.8(0.074)

Eir) =0.1092

to calculate an opportunity cost of capital for this project of 10.92 %. We would then use

this rate to discount the expected cashflows, assuming the beta doesn't change

dramatically over the lifetime of the project (a questionable assumption). Summing up

the present value of future cashflows,

NPV = ±-^L-I

we should invest in the project if the NPV is positive.

Certainty equivalent approach

While RADR incorporates adjustments for risk and time into the discount rate r,

the CEQ makes separate adjustments for risk and time. The certainty equivalent (CEQ) is

the smallest certain payoff we would accept in exchange for a risky cash flow C t . In

other words; we have two identical expressions for present value (PV):

C, CEQ PV =

1 + r l + rf

where rf is the risk-free rate.

Brealey and Myers p. 177

32

Page 41: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

We can use the CAPM to derive certainty equivalents. The CAPM tells us that the

return on an asset with present value PV should be:

C l + r = — - = l + rf +6 (r - A > )

py f ' m J

To calculate beta,

f C ^ cov(r,rJ KPV j

0 CT m m

Since is known and thus does not "covary", we can rewrite the expression as,

1 cov(C l t rJ

Plugging this into the CAPM return-on-asset equation,

C\ cov^.r^,) rM - r 7

= 1 + r, + J — ^ - x - y f PV oi

The expression is known as the market price of risk and is written as "k. It

indicates the risk premium per unit of variance. With some simple manipulation, the PV

equation can be written as,

C1-'kco\(C1,rm) PV = -l + rf

The deduction we make from a risky cash flow to calculate the CEQ thus depends on the

market price of risk and the co variance of the risky cashflow with the market.

The CEQ and RADR approaches are equivalent under the assumption that

cumulative risk increases at a constant rate over time (i.e., the risk borne per period is

33

Page 42: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

constant). However in practice, the risk-per-period is usually not constant and the market

risk premium is difficult to determine.

Sensitivity analysis

NPV is a function of a number of variables. Sensitivity analysis assesses how

changes in each variable affect NPV. A base-case scenario is developed using the most-

likely variable forecasts. Each variable is then changed by a certain percentage above and

below its base-case and the impact of this change on NPV is measured. This process

forces managers to identify the crucial variables which contribute most to the riskiness of

the project's NPV. In addition, it indicates where additional information would be useful

and helps to expose inappropriate forecasts.

Sensitivity analysis can be represented on spider graphs as in figure 3.8 which

evaluates a simplified version of a toll bridge project. Assume that NPV is a function of

Figure 3.8 Sensitivity analysis: A simplified toll-bridge spider graph

% change in NPV

construction costs \ toll levels

operating costs

construction time traffic

% change in variable

34

Page 43: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

the following primary variables: construction costs, construction time, operating costs,

traffic, and toll levels.

Looking at this graph, we see that increases in toll levels and traffic have a

positive impact on NPV whereas increases in construction time, construction costs, and

operating costs have a negative impact. Furthermore, we see that changes in construction

costs and toll levels have a strong impact on NPV whereas operating costs have a small

effect on NPV.

Sensitivity analysis has its limitations. Because we are looking at the effect of

variables in isolation, we may be overlooking important interactions between variables.

In the toll-bridge example, there is probably a strong correlation between the level of

tolls and bridge traffic. Construction time could be decreased through fast-tracking at the

expense of increased construction costs. Another drawback is that we cannot easily

capture the impact on NPV of simultaneous changes in combinations of variables.

Monte Carlo simulation

Sensitivity analysis looks at the effect of a limited number of likely variable

combinations. Monte Carlo simulation is a method of evaluating all possible

combinations. A probability distribution of NPV is generated through repeated random

sampling from probability distributions of the crucial NPV input variables. The steps for

a Monte Carlo simulation are as follows:

1. Model the project: Express NPV as a mathematical function of relevant variables.

Include interdependencies between variables and across time. Models can be

developed in a discrete or continuous-time framework.

3 5

Page 44: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

2. Specify the probabilities of relevant variables: Use sensitivity analysis to determine

which variables are important so that special care can be taken in obtaining their

precise probability distributions. Probabilities can be derived from past empirical data

or elicited subjectively.

3. Simulate cash flows: Use a computer random number generator to draw random

samples from each of the probability distributions for the relevant variables. Input

these numbers into the NPV formula to calculate NPV. Repeat the process many

times to generate a probability distribution for the project's NPV as shown in figure

3.9.

Figure 3.9 NPV probability distribution

NPV probability

0 Expected NPV

Although Monte Carlo simulation can be useful in evaluating expected cash flows

and risk, it has a number of limitations. First, it is very difficult to correctly model all the

interdependencies and functional forms of the project variables. Second, it may be

difficult to obtain unbiased estimates of probability distributions for the variables. Third,

it is difficult to interpret the information provided by a distribution of NPVs. Cashflows

for each iteration of the model are discounted at the risk-free rate rather than the cost of

capital. Using a risk-adjusted rate in the simulation would amount to double counting.

Risk is reflected in the dispersion of the NPV distribution. However, our traditional

36

Page 45: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

interpretation of NPV — the price at which an asset would sell in a competitive market —

is meaningless when we are faced with a number of possible NPVs. Management "has no

rule for translating that profile into a clear-cut decision for action." Furthermore,

simulation ignores the investor's opportunity to diversify and fails to capture the

interaction between the distribution of returns on a project and the distributions of returns

on other assets.

Decision-Tree Analysis

Decision-tree analysis (DTA) is useful in analyzing sequential investment

decisions when uncertainty is resolved at discrete points in time. The mechanics of

decision-tree analysis can be illustrated using a simple example. Let's look at a toll road

operator considering whether or not to invest in the development of AVI (automatic

vehicle identification) technology. There is a 30% chance that the $0.5 million R&D

investment will lead to the successful development of a technically feasible AVI

technology. The operator can then implement this new technology for $3 million. The

marketing department has forecast there is a 60% chance that this new technology will be

well-received by the marketplace resulting in cash flows with an NPV at year two of $20

million and a 40% chance that it will be poorly received resulting in cash flows with an

NPV at year two of $6.5 million. If the firm doesn't go ahead with the R&D investment,

then it will continue to receive cash flows with an NPV at year zero of $8 million. If it

doesn't implement the new technology (i.e. the R&D fails or management decides the

new technology is too risky), it will receive cash flows with an NPV at year one of $8.8

9 Trigeorgis, Lenos. Real Options MIT Press 1997. p.56

37

Page 46: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

million. Assume the cost of capital is 10%. Figure 3.10 depicts this scenario using a

decision-tree chart where squares represent decision nodes and circles represent outcomes

determined by fate.

Figure 3.10 Decision tree of whether or not to invest in AVI technology

The optimal initial decision of whether or not to invest in the new technology is

determined by starting at the end of the tree and working backward to the beginning. The

dynamic programming approach works as follows:

First, we calculate the expected NPV assuming the R&D investment in AVI is

successful and the new technology is implemented.

M(2W+04teS 1.10

38

Page 47: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

Because the expected value of implementing the new technology ($10.27m) is greater

than the value of maintaining the status quo ($8.8 m), the optimal decision at year one

would be to implement the new technology. However, this decision is contingent upon

the success of the initial R&D investment. Working backwards to time zero, the expected

NPV of the R&D investment is:

N p 0.4(10.27) + 0.6(8.8)_ 0^ 8 03 0 1.10

Since the expected NPV from investing in the AVI project is greater than that from

maintaining the status quo ($8.0m), the NPV rule tells us to go ahead with the initial

R&D investment.

While decision tree analysis can be a useful tool in analyzing the value of events

which are contingent upon the outcome of other events, it suffers from several

drawbacks. One problem is practicality. When trying to model complex sequential

investment opportunities, decision trees quickly become unwieldy decision "bushes".

Another problem lies in DTA's treatment of the discount rate. In the presence of

operational flexibility, the risk structure of the project changes and the appropriate

opportunity cost of capital becomes unclear. In the above example, if the company could

invest in the $0.5 million R&D through installments (e.g., $250,000 immediately and

$250,000 six months from now), then it could abandon the R&D at an early stage if the

investment didn't look promising. This option to pull out before making the full $0.5

million commitment makes the R&D project less risky than if the company had to make

the full commitment upfront. We must somehow adjust the 10% discount rate to reflect

39

Page 48: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

the change in the riskiness of the R&D cash outflows. Traditional DTA, while on the

right track to valuing complex sequential decisions, unfortunately offers little insight into

the discount rate problem.

3.1.4. Problems with traditional capital budgeting

Managers have long realized that DCF methods such as NPV analysis are ill-

equipped to value projects rich in flexibility and strategic importance. How can one value

the role of active management? What is it worth now to be able to adapt to the arrival of

new information in the future? How do we quantify the portion of a project's value

created by its interdependence with other projects? Rigid NPV analysis based on the

assumption of passive investment gives little insight into these questions. Sensitivity

analysis, Monte Carlo simulation and decision tree analysis shed some light on the

importance of flexibility, yet they also lack the ability to fully model the dynamics of

project flexibility. The dissatisfaction with traditional capital budgeting techniques,

combined with breakthroughs in financial economics, gave rise to the subject of the next

section: "the real options revolution."

40

Page 49: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

3.2. REAL OPTIONS

3.2.1. Introduction

What is a real option?

In the parlance of finance, an option is the right, but not the obligation, to buy or

sell an asset at a predetermined price within a specified time period. Whereas financial

options are written on financial assets (stocks, bonds, derivative instruments), real

options are on "real" assets (a factory, a patent, a technology, a line of business). Real

options can be broadly divided into two categories: operating options and strategic

options. Operating options include the flexibility to defer, expand, contract, or abandon

projects. Strategic options are created by a project's interdependence with future and

follow-up investments.

The real options approach to capital budgeting attempts to quantify the value of

managerial flexibility in capital investment projects. Managers are able to react to

changes in the marketplace and respond to the arrival of new information. This ability to

adapt to future market conditions has value because it expands an investment

opportunity's upside potential while limiting its downside losses. This asymmetrical

payoff pattern is at the heart of an option's value. Figure 3.11 shows how this asymmetry

skews the probability distribution of a project's NPV. This skewed probability

distribution is also known as expanded NPV because it includes both static NPV and the

value of active management. A project in which a manager can defer investment,

contract or expand operations, abandon the project for a salvage value, switch inputs or

Page 50: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

outputs, or expand into other projects has more value than a project in which the manager

can do nothing but passively watch the project unfold after making the initial investment.

Figure 3.11 Managerial flexibility introduces payoff asymmetry

expected static NPV expected expanded NPV

: 0 ^ * NPV

\ option premium

The real options revolution

The real options revolution arose as managers and academics became dissatisfied

with traditional investment decision-making techniques. After the second World War,

two schools of thought on corporate resource allocation emerged: capital budgeting and

strategic planning. Capital budgeting focused on measurable cash flows and valued them

using discounted cash flow (DCF) techniques such as Net Present Value (NPV) analysis.

NPV had originally been developed to value passive investments such as bonds and was

ill-suited to analyze the value of managerial flexibility present in complex capital

investment projects. Strategic planning recognized the limitations of capital budgeting

and used a qualitative approach focusing on intangibles such as competitive advantage,

market leadership, and industry structure. The Boston Consulting Group's growth matrix

(1970s) and Porter's diamond are examples of strategic planning techniques.

Page 51: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

By the 1980s, the shortcomings of traditional passive DCF analysis had become

glaringly apparent. Academic critics such as Robert Hayes and William Abernathy

argued that such techniques were systematically undervaluing projects by ignoring

strategic concerns.10 James Hodder and Henry Riggs argued that DCF was frequently

being misused and that the incorrect treatment of inflation and risk adjustments was

leading to poor investment decisions.11 Myers concluded that while part of the problem

lay in the misapplication of the underlying theory, DCF methods were inherently limited

in their ability to value investments with significant operating and strategic options. He

12 proposed option pricing as a means of valuing such investments.

The pioneering work of Black and Scholes13, Merton14, and Cox, Ross, and

Rubinstein15 has given investment analysts the basic tools to begin quantitatively valuing

real options. However, the application of option pricing techniques to investment analysis

has encountered some resistance. First, many professional managers are intimidated by

the high-powered math of option pricing and fear that a mysterious "black-box" approach

to project evaluation will further complicate investment decision-making. Second, many

decision scientists argue that decision tree analysis is already sufficient to capture the

value of managerial flexibility.

R. Hayes and W. Abernathy, "Managing Our Way to Economic Decline," Harvard Business Review. July-August 1980 1 1 J. Hodder and H. Riggs, "Pitfalls in Evaluating Risky Projects," Harvard Business Review. January-February 1985. pp. 128-135 1 2 S.C. Myers, "Finance Theory and Financial Strategy," Midland Corporate Finance Journal, Spring 1987, pp. 6-13 1 3 F. Black and M. Scholes, "The Pricing of Options and Corporate Liabilities," Journal of Political Economy May/June 1973, pp. 637-659 1 4 R.C. Merton, "Theory of Rational Option Pricing," Bell Journal of Economics and Management Science Spring 1973, pp. 141-183 1 5 J. Cox, S. Ross, and M. Rubinstein, "Option Pricing: A Simplified Approach," Journal of Financial Economics, September 1979, pp. 229-263

43

Page 52: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

Lenos Trigeorgis and Scott P. Mason counter these arguments in their 1987 paper

"Valuing Managerial Flexibility"16, which shows the workability of option pricing

techniques and presents option pricing as a special economically-corrected version of

decision tree analysis that recognizes market opportunities to trade and borrow. Our

introduction to the mechanics of discrete-time real option valuation is based largely on

this article and other works of Lenos Trigeorgis. However, before we look at the

dynamics of real option value, it is useful to review the basics of financial options and

draw an analogy between financial options and real options.

Financial options versus real options

A call option is the right to buy a specified financial asset (stock, bond, future,

other option) at a specified exercise or strike price on or before a specified expiration or

maturity date. A put option is the right to sell a specified financial asset at a specified

exercise price on or before a specified expiration date. If the option can only be exercised

at maturity, it's called a. European option; if it can be exercised before maturity, it's

called an American option. As emphasized earlier, the value of an option lies in its

asymmetrical payoff. Figure 3.12 contrasts the symmetrical payoff position from buying

the underlying asset (a long position) with the asymmetrical payoff positions from

buying a call or put on the underlying asset.

What is the price or premium we should pay or expect to receive in order to enter

an option position? There are many mathematically sophisticated approaches to option

L. Trigeorgis and S.P. Mason, "Valuing Managerial Flexibility," Midland Corporate Finance Journal, Spring 1987, pp. 14-21

44

Page 53: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

pricing. At this point however, we will only point out the main factors influencing the

value of an option.

Figure 3.12 Asymmetric payoffs from options

Buy asset Buy call on asset Buy put on asset

+ Position value X=exercise X X

price

Call options

The price or premium (C)of a call option depends on the following variables:

• stock price (S): an increase in S causes an increase in C. Upon exercise, the payoff

max(S-X,0) becomes greater with a larger S.

• exercise price (X): an increase in X causes a decrease in C. Upon exercise, the payoff

max^-XO) becomes less with a smaller X

• interest rate (ry): an increase in r causes an increase in C. Options enable investors to

buy an asset on installment credit; they pay a premium today, but don't pay the full

purchase price until a time in the future. The value of being able to delay payment

increases with higher interest rates.

• time to expiration (t): an increase in t causes an increase in C. There is more time for

the stock price to move upwards. Also, the value of the installment credit feature of a

call option increases with longer maturity.

45

Page 54: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

variance of returns on stock (a ): an increase in volatility causes an increase in C.

There is a higher probability of the stock price making large upward movements.

As long as the stock price isn't zero, a call option will always exceed its

minimum value; i.e. the payoff to immediate exercise of max(S-X,0). This provides the

lower bound for the option's value. The share price provides the upper bound for the

option's value. This is because the payoff from the call option of max(S-X,0) is less than

S by amount X if exercised and is zero which is less than S if unexercised. As depicted in

figure 3.13, the value of a call option lies along a curve between these two bounds. The

shape of this curve is determined by r, t, and a .

A n American call option on a non-dividend paying stock should never be

exercised early and should have the same value as a European call option. This is because

if the option is kept alive, there is always a probability that S will move up to increase the

payoff from exercising the call.

Put options

The price of a put option (P) depends on the following variables:

Figure 3.13 Value of a call (C) before its expiration date

Share price S X

46

Page 55: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

• stock price (S): an increase in S causes a decrease in P. Upon exercising, the payoff

ma.x(X-S,0) becomes less with a larger S.

• exercise price (X): an increase in X causes an increase in P. Upon exercising, the

payoff max(X-S,0) becomes greater with a larger X.

• interest rate (jy): an increase in r causes a decrease in P. Upon exercising the put, the

holder receives amount X A higher interest rate means a lower present value of X

and hence the value of P decreases.

• time to expiration (t): an increase in t causes an increase in C. There is more time for

the stock price to move downwards.

• variance of returns on stock (a ): an increase in volatility causes an increase in C.

There is a higher probability of the stock price making large downward movements.

Unlike a call option, it may be optimal to exercise a put option before its

maturity. This is because for low values of S, it is highly likely that the put will be

exercised to receive X. However, waiting will bring at most X, but at a later time and

with a lower present value. Thus there is a critical point (S*) where the value of waiting

for a potential further drop in S is outweighed by the loss in present value of X from

Figure 3.14 Value of a put (P) before its expiration date

Option value

S* X priceS

47

Page 56: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

waiting. At this point, the option value curve joins the lower bound which is the payoff

from immediate exercise; maxC -̂S'.O). Figure 3.14 shows the shape of the put option

value curve which is also determined by r, t, and a .

The analogy between financial options and real options

An opportunity to invest in a corporate project resembles a call option to invest in

a corporation's stock. We can map project characteristics onto the variables which

determine a call option's value as follows

Project Variable Call option Expenditures required to acquire X Exercise price the asset Value of the operating assets to S Stock price be acquired Length of time decision may be t Time to expiration deferred Riskiness of underlying a2 Variance of returns on stock operating assets Time value of money rf Risk-free rate of return

Investment opportunities can also exhibit features similar to a put option. For

example, a government loan guarantee is essentially a put option on loan payments

written by the government to the party taking out the loan. The ability to scale back

operations during a market downturn can also be thought of as put with the exercise price

being the part of planned expenditures which can be scaled back.

Given the similarities between financial options and many investment

opportunities, the pricing tools developed to value financial options can also be used to

Luehrman, Timothy A. Capital Projects as Real Options: An Introduction. Harvard Business School

48

Page 57: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

analyze the value of complex investment opportunities. The next section will work

through a simple example to illustrate the principles behind real option valuation.

3.2.2. The basics of real option valuation

An example of real options

18

We will use Trigeorgis' example of an oil extraction and refinery project to

explore the nature of real options. An oil company has a one-year lease to develop an

untapped oil reserve. Operation can begin only after the development stage (exploration,

construction) is completed. Once the refinery is operating, the company can adjust to

market conditions by either contracting, expanding, or temporarily shutting down

operations. At any time during operations, the company can switch its equipment to an

alternative use or salvage it for a salvage value. The options present in this example are:

• the option to defer investment

• the option to default during construction

• the option to expand

• the option to contract

• the option to temporarily shut down

• the option to abandon for salvage value or switch inputs and outputs

• the option for corporate growth

Trigeorgis, Lenos. "Real options and interactions with financial flexibility." Financial Management 22 1993, no.3. 202-224

49

Page 58: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

Before exploring each of these options in more detail, it is necessary to provide a

brief introduction to an option-pricing technique know as Contingent Claims Analysis

(CCA).

Contingent claims analysis (CCA)

Contingent Claims Analysis is used when the value of a claim on an asset is

contingent upon the outcome of a probabilistic event. CCA is operationally similar to

decision tree analysis. However, CCA uses risk-neutral probabilities rather than actual

probabilities to calculate expected values and it discounts these expected values at the

risk-free rate rather than a risk-adjusted rate.

The basic idea behind CCA is as follows. First, through market transactions we

create a portfolio which exactly replicates the payoffs from the investment opportunity

under all possible future states. From this portfolio, we calculate risk-neutral probabilities

and use these probabilities to calculate certainty-equivalent (CEQ) cash flows. We

discount the CEQ cash flows using the risk-free rate to determine the current value of the

investment opportunity.

CCA assumes there is a "twin security" which has the same risk characteristics as

the project and is traded in financial markets. In the oil field example, a "twin security"

could be the stock price of a similar operating unlevered oil company. The value of the

project (i.e. V; the present value of expected cash flows) and the value of the twin

security (S) are expected to move up with probabilityp and down with probability (1-p).

The value of the opportunity to invest in the oil field {E) should not be confused with the

gross value of the fully developed oil field (V). Movements in the value of the

50

Page 59: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

opportunity to invest in the oil field are perfectly correlated with movements in V and S.

Figure 3.15 shows the possible movements in value over one year.

Figure 3.15 Possible price movements oyer one year

Value of completed project Value of twin security Value of investment opportunity

P /

Through open market transactions, we follow a standard option pricing hedging

strategy to create a replicating portfolio. By carefully combining n units of S and B units

of a riskless investment, we can create a portfolio which exactly replicates the payoff

from investment opportunity E. The mechanics of the replicating portfolio involve

borrowing amount B and using the proceeds to finance a portion of the purchase price of

n units of S. The difference between the price of n units of stock and the amount

borrowed is the cost of the replicating portfolio. Figure 3.16 shows this graphically.

Figure 3.16 A portfolio replicating the value of the investment opportunity

E+=nS*-(l+rf)B

E=nS-B

Borrow B and put the proceeds towards buying amount n of S.

E=nS'-(l+rf)B

51

Page 60: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

We now invoke the principle of "no arbitrage" which states that investments with

equivalent payoffs and risk characteristics must have the same present value. If the future

payoffs from our replicating portfolio and our investment opportunity are the same under

all possible future states, then their current prices must also be the same. If the prices

diverged, we could make infinite riskless profits through arbitrage by continuously

buying low and selling high. The market doesn't allow such "free lunches" and astute

market players are quick to force prices to a no-arbitrage equilibrium. Under the

assumption of no arbitrage, we can use a replicating portfolio of traded assets to price a

non-traded asset such as an investment opportunity.

From figure 3.16, treating the conditions of equal payoffs as two equations, we

can solve for the unknowns n and B:

Plugging n and B into the equation E=nS-B, we can calculate the current value of the

investment opportunity

n —

B =

(E+-E-) (S+-S~) (E+S~ -E~S+) (S+-S-)(l + rf)

E = (E+-E-)s (E+S~-ES + ) (S+-S~) (S+-S-)(l + rf)

Rearranging,

(S(l + rf)-S-) (S+-S~)

(S(l + rf)-S-)

( s + - s - ) E++\l- E

E = J

1 + r, /

52

Page 61: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

(S(X + rf)-S~) and making p' — , we can express the value of the investment as,

(S+-S~)

E^p'E+ + (l-p')E-

1 + r,

where p' is called the risk neutral probability. Another way of looking at p' is to ask

what probabilities would make the expected return on asset 5 equal to the risk-free rate.

Expressed mathematically,

s f

Solve for p',

(l + rf)S-S~ p' -

F s + - s ~

Note the difference between the risk-neutral probability p' and the actual

probability p. Instead of using actual probabilities to calculate expected future values and

then discounting these values at a risk-adjusted rate, we use risk-neutral probabilities to

calculate CEQ values which allows us to discount at the riskless rate.

So far, our approach to CCA risk-neutral option valuation has been based on the

ability to use a traded underlying security and riskless borrowing to create a portfolio

which replicates the payoff of the option. For real options however, the underlying asset

is often not traded. Despite this obstacle, contingent claims on an asset can be priced in a

world with systematic risk by replacing the expected cash flow with a CEQ calculated

using the market price of risk A, (recall CEQ approach in capital budgeting).

Using CCA to value real options

5 3

Page 62: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

We will now work through a simple one-period numerical example of the oil field

investment opportunity to compare traditional discounted cash flow decision tree analysis

(DCF/DTA) with contingent claims analysis. Assume that the expected price movements

of the project value and the twin security value are as shown in figure 3.17 with the

actual probability of an up movementp-0.5, the risk-free interest rate ry=8%, the risk-

adjusted interest rate r=20%, and the required investment outlay at time zero 70=$104.

Figure 3.17 Possible price movements over one time period

Value of completed project Value of twin security

0.5 . ̂ V + = 1 8 0 0.5 , 'y S+=36

V=?? <Q S=20 < ^

0.5 \ V"=60 0.5 \ S"=12

First, we find V, the value of this investment opportunity, assuming there are no

options. Traditional DCF/DTA analysis using expected values calculated with actual

probabilities yields a result of,

r = pV+ + (l-p)V-1 + r

05(180) +0.5(60) 1.2

7 = 100

CCA uses risk-neutral probabilities calculated from a perfectly correlated twin

security S (in our case, the traded oil company),

54

Page 63: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

, = {S(l + r)-S~) P (S+-S~)

, 20(1.08)-12 p =

36-12 p' = 0A

The certainty equivalent values are then discounted at the risk free rate,

p'V+ + (l-p)y-l + rf

0.4(180)+ 0.6(60) 1.08

V = 100

In the absence of options, traditional DCF/DTA and CCA yield the same result,

7=100. Given the initial required investment of $104, the NPV rule tells us to reject this

project because it has a negative NPV (100-104=-4).

In the presence of options however, DCF/DTA and CCA yield different results.

Managerial flexibility creates asymmetrical payoffs which DCF/DTA is ill-equipped to

value. The following examples explore the options present in the oil field case and show

how CCA succeeds in valuing these options.

The option to defer investment

Assume the company has a one-year lease on the oil field. Although undertaking

the project immediately has a negative NPV, the company can wait one year to see what

happens to oil prices. If prices go up, the project may become profitable. If prices go

down, the company has no obligation to invest and will end up losing only the cost of the

lease. This position is analogous to a call option on project value V with an exercise price

equal to the required outlay ̂ =112.32 (104x1.08).

55

Page 64: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

E+ = max(F+ -/ 1,0) = max(180-112.32,0) = 67.68

E~ =max(V~ -Ilt0) = max(60-112.32,0) = 0

Using the risk-neutral probabilities derived earlier to calculate expected value and

then discounting back at the risk-free rate,

v = p'V+ + (l-p')V-1 + r,

0.4(67.68)+ 0.6(0) 1.08

V = 25.07

we find that the value of this opportunity to invest E is $25.07. An NPV which includes

both the value of passive investment and the value of active management is often called

expanded NPV. The expanded NPV of this investment opportunity is derived from two

sources: traditional static NPV (-4) and the option to defer (29.07).

Expanded NPV = option to defer + static NPV

The value of the option to defer can thus be expressed as,

Option to defer = expanded NPV - static NPV

It is interesting to compare CCA valuation of this option with DCF/DTA

valuation. Using actual probabilities and a risk-adjusted discount rate, DCF/DTA may

value the option to defer differently to CCA. In this example,

E = PE+ + (X-p)E-l + rf

„ 05(67.68) + 0.5(0) E =

1.20 E = 28.20

Why is the CCA value of $25.07 correct and the DCF/DTA value of $28.20

incorrect? Recalling the principle of no arbitrage, clearly nobody would pay $28.20 for a

56

Page 65: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

future payoff which can be replicated in the market for $25.07. In this case, the

replicating portfolio would be,

(E+-E~) 67.68-0 n = = = 2.82

(S+-S~) 36-12 _ (E+S~-E~S+) = (67.68x12)-(Ox36) = 3 J 3 3

" (S+-S-)(l+rf) ~ (36-12)(1.08)

By buying 2.82 shares at $20 each for a total of $56.40 and borrowing $31.33 at the

riskless rate, next year our portfolio would be worth

E+ =nS+ -(1 + ^)5 = 2.82x36-1.08x31.33 = 67.68

E~ =nS~ -(1 + ^)5 = 2.82x12-1.08x31.33=0

which is exactly the same as the payoffs from our investment in the oil field.

The current cash outflow required to create this portfolio is the price of the stock

purchase ($56.40) less the amount borrowed ($31.33) which is $25.07, the value of the

investment opportunity calculated using CCA. This example shows how DCF/DTA fails

to take into account market opportunities to buy or sell and borrow or lend. CCA corrects

for this by creating a replicating portfolio and using it to determine the expanded NPV of

the investment opportunity.

The option to default during construction

If the investment is made in stages, management can abandon the project during

construction if further outlays are expected to exceed the value of continuing the project.

Suppose the $104 investment consists of two stages: construction of basic infrastructure

costing $44 and then construction of the oil refinery costing $60. First, 70=44 would be

paid upfront and the remaining $60 would be placed in an escrow account earning the

57

Page 66: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

risk-free rate (8%) to be paid as 7Z=64.8 (1.08x60) at year one. At the end of the first

year, management has the option to decide whether or not to proceed with construction

of the plant. If the value of the plant goes up, management should continue with the

project for a payoff of,

E+ = max(7+ -7 l f0) = max(180- 64.8,0) = 115.2

If the value of the plant decreases, management should default on the payment and

abandon the project for a payoff of,

E~ = max(V~ -1, ,0) = max(60 - 64.8,0) = 0

The expanded NPV of this investment opportunity with the option to default on future

outlays is,

h rr y° „ 0.4x115.2 + 0.6x0 A A

E = 44 1.08

E = -1.33

The value of the option to abandon by defaulting is,

Option to abandon by defaulting = expanded NPV - static NPV = -1.33-(-4)=2.67

While the option to default during construction has value, the expanded NPV is

still negative so we shouldn't undertake this project.

The option to expand

If market conditions turn out to be favourable after one year, management may

want the flexibility to expand operations. Suppose that after one year, a follow-on investment of I[ =$80 would double the scale and value of the plant. At year one,

58

Page 67: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

management has the option to either expand operations and receive a payoff of 27 + - 1 \

or maintain the current scale and receive V. This investment opportunity can be thought

of as a call option on a future opportunity to expand. The payoffs from this investment

opportunity are,

E+ = max(V+,2V+ -/*) = (180,360-80) = 280

E~ = max(7-,2F- - J,e) = (60,120-80) = 60

The expanded NPV of this investment opportunity with the flexibility to expand

operations is,

p'E+ + (l-p)E-h - r~ 7<>

l + rf

„ 0.4x280 + 0.6x60 . . . E = 104

1.08 E = 33.04

The value of the option to expand is,

Option to expand = expanded NPV - static NPV =33.04-(-4)=37.04

The option to contract

The option to contract is similar to the option of abandoning by default during

construction. However, instead of completely abandoning the project, management

merely scales down the operations. Suppose that an initial investment of IQ=50 would

enable the refinery to run at half the planned scale, 0.5V. An investment of I± =$58.32

(the future value of $54) at year one would bring the plant up to full capacity. If market

conditions next year turn out to be unfavourable, management may want to exercise its

option to halve the scale of operations by not investing IX. This option to contract is

analogous to a put option on the part of the project which can be contracted with an

59

Page 68: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

exercise price equal to the planned expenditures which can be canceled. The payoffs

from this investment opportunity are,

E+ = max(F+ -1, ,0.5V+) = (180 - 58.32,90) = 121.68

E~ = max(V~ -1, ,0.57') = (60 - 58.32,30) = 30

The expanded NPV of this investment opportunity with the option to contract is,

„ 0.4x121.68+0.6x30 c n

E = 50 1.08

£ = 11.73

The value of the option to halve operations is,

Option to contract = expanded NPV - static NPV=11.73-(-4)=15.73

The option to temporarily shut down

If cash revenues are insufficient to cover variable costs in a given year,

management may have the flexibility to temporarily shut down operations until they

become profitable again. Each year can be viewed as a call option on that year's cash

revenue with the exercise price equal to the variable cost of operating.

We can breakdown the components of project value into certainty equivalent

amounts (CEQ) of revenue (R), variable costs (VO and fixed costs (FC). Assuming a

lifespan of T years, the value at year n=l of the project is given by:

„ ^CEQ(R-VC-FC)

" . -E q + r / r

For simplicity we will treat R, VC, and FC as riskless after year one and will

ignore the value of any options after year one. If the value of the project goes up to 180

in year one, assume that the cash flows for year one are ̂ =100, 76̂ =35 and FCi=5.

Under good market conditions, year one thus contributes 60 to the project's total value of

60

Page 69: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

180. The remaining cash flows from year two to year T contribute 120 to the project's

total value at year one. If the value of the project goes down to 60, assume that the cash

flows for year one are ^=20, FC1=35, and FCj=5. Under poor market conditions,

operating in year one results in a loss of 20 (20-35-5=-20) implying that the remaining

cash flows after year one contribute 80 to the project's total year-one value of 60 (80-

20=60). What is the value of being able to avoid this 20 loss by temporarily shutting

down? If we operate, we pay VCX and FCX to get Rv If we temporarily shut down, we

pay FClt avoid paying VCX and forego receiving Rx. The payoff from this option to

temporarily shut down is,

E = max(/?1 - VCX - FC, ,-FC^) + Vr

where Vr is the value of the cash flows after year one.

£ + = max(100 - 35 - 5,-5) +120 = max(60,-5) +120 = 180

E~ = max(20 - 35 - 5,-5) + 80 = max (-20,-5) + 80 = 75

The expanded NPV of an investment opportunity which allows management to

avoid any losses in year one due to poor market conditions, but still continue the project

by paying fixed costs is

_ 0.4x180 + 0.6 x 75 1.08

E = 4.33

The value of this option to temporarily shutdown is

Option to temporarily shut down = expanded NPV - static NPV=4.33-(-4)=8.33

The option to abandon for salvage value or switch to best alternative use

61

Page 70: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

If market conditions become unfavourable, management may have the option to

abandon the project and receive its salvage value or switch the refinery's facilities to

their best alternative use (i.e. convert the crude oil into a variety of products). Assume

that the project's salvage value or its best alternative use value (A) moves over time as in

Currently, .4=90 is less than the 7=100 so management would not want to switch

or abandon. However, if prices go down in year one, management would want to switch

or abandon for a value of A' =72 which is greater than V =60. The payoffs from this

investment opportunity with the option to abandon or switch are:

E+ = max {V+ ,A + ) = max (180,144) = 180

E~ =max(7",iO = max(60,72) = 72

The expanded NPV of this investment opportunity is,

„ 0.4x180 + 0.6x72 E = 104

1.08 E = 2.67

The value of this option to abandon for salvage value or switch to the best alternative use

is,

Value of option to abandon or switch = expanded NPV-static NPV=2.67-(-4)=6.67

figure 3.18.

Figure 3.18 Salvage value or best alternative use (A)

A+=144

62

Page 71: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

The option for corporate growth

Corporate growth options are similar to the option to expand operations, but have

much deeper strategic implications. Some projects are unattractive in isolation, but play a

crucial role as a link in a chain of interrelated projects. The value of such projects "may

derive not so much from their expected directly measurable cash flows, but rather from

unlocking future growth opportunities."19 For example, suppose the proposed oil refinery

is a pilot project to develop a new technology. The infrastructure and experience gained

from undertaking this project could act as springboard to further process improvements

and to applications in new areas. Real option techniques attempt to quantify the value of

such strategic growth options.

3.2.3. Summary

The preceding discussion has provided an introduction to the basics of real option

valuation. In reality, Contingent Claims Analysis is complicated by the effects of

multiple interacting options. For example, the option to change the scale of the project

during construction affects the value of the option to temporarily shut down. If a project

is a collection of calls and puts which interact, their combined value may differ from the

sum of the separate option values. However, with some adjustments, the risk-neutral

backward valuation procedure outlined above can be extended into a multiperiod

interacting options setting. As the number of periods increases, the discrete solution

approaches the continuous time Black-Scholes solution if it exists. However, for

19 Trigeorgis, Lenos. "Real Options and Interactions With Financial Flexibility" Financial Management

Autumn 1993 p. 202-224

63

Page 72: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

simplicity, this thesis will work within a discrete time framework. In the next chapter, we

look at how real option valuation techniques can be used to understand the dynamics of

value in BOT toll road projects.

64

Page 73: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

CHAPTER FOUR

R E A L O P T I O N S I N B O T T O L L R O A D S

Page 74: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

I N T R O D U C T I O N

The value of a BOT toll road project is affected by a variety of real options. Some

of these real options arise from the inherent nature of large-scale infrastructure projects

involving sequential investments. Others are created by contractual arrangements

negotiated by the parties to a BOT. This chapter looks at how contingent claims analysis

can be used to value BOT real options. Figure 4.1 depicts the typical life cycle of a BOT

20 toll road project from the concessionaire's perspective.

Figure 4.1 The life cycle of a BOT toll road project from the concessionaire's perspective

money

BUILD OPERATE

: loan drawdown '•

pre-design

design

Tendering/design field

commisioning

mgmt of design/construction

Revenue

operation and maintenance

debt servicing

mgmnt of operat ion and maintenance

TRANSFER -><> .-7

time

During the build phase, important real options include the option to abandon

midstream, the option to change scale or technology, and "time-to-build" options. During

Wahdan, Mohamed Y., Russell, A.D., and Ferguson, D. "Public Private Partnerships and Transportation Infrastructure" paper presented at 1995 Annual Conference of the Transportation Association of Canada, Victoria, British Columbia.

66

Page 75: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

the operating phase, significant real options include the flexibility to set tolls, the option

for development gain, and financial flexibility created by project financing. At the

transfer stage, there are number of possible arrangements between the public and private

sector which exhibit option-like features. Analyzing the value of these options is

important to understanding the tradeoffs involved in negotiating a BOT toll road. This

understanding is crucial to the successful development and management of a BOT toll

road.

67

Page 76: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

4.1. BUILD PHASE

4.1.1. Introduction

Important real options during the build phase of a BOT project include the option

to abandon midstream, the option to change scale or technology, and "time-to-build"

options. Because BOT projects are negotiated between the public and private sector,

there are likely to be many contractual arrangements which affect the value of flexibility

during the build phase. For example, a BOT contract may stipulate certain penalties for

abandoning a project during the build phase. This would affect the value of the option to

abandon midstream. This section outlines how contingent claims analysis can be used to

value various types of flexibility during the build phase.

4.1.2. The option to abandon midstream:

If the value from continuing the project is less than cost of the investment

required to continue, then management may wish to abandon the project. To analyze this

option within the context of a BOT toll road, we develop a two-factor model which

captures the stochastic nature of project value and construction costs at each stage of the

project. Kensinger's21 analysis of the option to exchange one asset for another is a useful

starting point. We adapt his model which looks at the option to transform an input

commodity into an output commodity (for example, soybeans into soybean meal or crude

oil into gasoline). In our case, we move up the value chain and consider construction

costs (labour, materials) as the input and a completed construction stage as the output.

2 1 Kensinger, John W. "Adding the Value of Active Management into the Capital Budgeting Equation." Midland Corporate Finance Journal. Spring 1987 p. 31-42

68

Page 77: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

Project value is the present value of future operating profits plus any operating options

upon completion of the project. We assume there is no correlation between project value

and construction costs and that there is no correlation between the construction costs of

different stages. This is to simplify the explanation, although such correlations could be

factored into the model.

Consider a BOT toll road build phase consisting of three one-year stages. The

first stage involves detailed design work and the costs are certain at $3 million. The

second stage involves preliminary ground preparation and the costs are uncertain with an

expected value of $11.25 million and a standard deviation of $5.44 million. The third

stage involves major construction and the costs are also uncertain with an expected value

of $105 million and a standard deviation of $15 million. These expected values and

standard deviations are derived from the following distributions:

Construction costs (C) $ Probability of C Stage one 3 1.00 Stage two 20 0.25

10 0.5 5 0.25

Stage three 130 0.25 100 0.5 90 0.25

These distributions are based on past data and expert opinion from engineers. We assume

the variance of construction costs is largely driven by the probability of technical

problems rather than the price volatility of inputs (concrete, labour). In other words,

construction costs are not correlated with the market.

69

Page 78: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

To find the value of the option to abandon midstream, we begin at the final stage

of construction and work backwards. We are interested in the spread between

construction costs and expected value upon completion. We model the project's value

which is derived from the stream of expected toll revenues over the concession period

and includes the value of any options during the operating period. We treat movements in

project value as binomial and assume these movements are highly correlated to the

movements of a traded asset (perhaps an index of toll road companies). In our example,

we assume that both our project's value and the value of the twin security have an actual

probability of 50% of moving up by a factor 1.2 and a 50% probability of moving down

by a factor of 1/1.2. These movements are shown in figure 4.2.

Figure 4.2 Stochastic movement of project value

rf = 5% u = 1.2

Value of project

P* 120

100

144

100

1-p** 83

69

d=l/u

Value of twin security: toll index

288

p* 240'

200 ^

1-p* 167

200

139

We use this twin security to calculate the risk-neutral probability of an up

movement:

(l + r)-d (1.05)-0.833 u-d 1.2 - 0.833

= 0.59

70

Page 79: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

If we complete stage three, we have the following risk-neutral probabilities for

the values (V):

V P*(V) 144 0.349174 100 0.483471

69.44444 0.167355

where p*(144)=(p*)2, p(100)=2xp*x(l-p*), and p*(69.44)=(l-p*)2.

To receive these values, we must pay construction costs at stage three. For

simplicity, assume that we receive the project value instantaneously upon payment of the

construction costs. If construction costs were found to be correlated with the market, we

could work with risk-neutral probabilities. However, because most construction projects

are highly idiosyncratic and cost overruns are not likely to be related to general market

movements, we choose to use true probabilities. These true probabilities may be elicited

subjectively or based on past data from similar projects. As stated above, for our project,

engineers consider the following costs and probabilities as appropriate for stage three:

c P*(C) 130 0.25 100 0.5 90 0.25

We are interested in the expected spread between project value and costs. With

the option, the project will be abandoned if the spread is negative. The spread V - C , the

associated joint probability for each spread (using risk-neutral probabilities for V and

true probabilities for C), and the expected value at stage three both with the option to

abandon (i.e., max(V-C,0))and without (V-C) are as follows:

71

Page 80: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

V C prob(V,C) no opt V-C option V-C E(opt V-C) E(no opt) 144 130 0.087293 14 14 1.2221074 1.222107 144 100 0.174587 44 44 7.6818182 7.681818 144 90 0.087293 54 54 4.713843 4.713843 100 130 0.120868 -30 0 0 -3.62603 100 100 0.241736 0 0 0 0 100 90 0.120868 10 10 1.2086777 1.208678

69.44444 130 0.041839 -60.55556 0 0 -2.53357 69.44444 100 0.083678 -30.55556 0 0 -2.55682 69.44444 90 0.041839 -20.55556 0 0 -0.86002

14.826446 5.25

At stage two, the value of the investment opportunity with the option is the

expected spread with the option discounted back at the risk-free rate:

2 1.05

To receive this value, we must pay construction costs to complete stage two.

Given the following distribution of stage two construction costs:

C P(C) 20 0.25 10 0.5 5 0.25

The spread between the value of 14.12 and C, the associated joint probabilities,

and the expected stage two value with and without the option to abandon are:

V C P(V,C) no opt V-C option V-C E(opt V-C) E(no opt) 14.12043 20 0.25 -5.879575 0 0 -1.46989 14.12043 10 0.5 4.120425 4.120425 2.0602125 2.060213 14.12043 5 0.25 9.120425 9.120425 2.2801063 2.280106

4.3403188 2.870425

The value of the investment opportunity with the option to abandon at stage one

is:

4 34 V, =—— = 4.133

1 1.05

72

Page 81: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

To receive this value, we must pay known costs of $3 million at stage one. The

value of the investment opportunity with the option to abandon at any stage during the

project is thus worth,

4.133-3 = 1.33

How does this compare with the value of an investment opportunity which has no

option to abandon? The stage three expected value without the option to abandon is

$5.25 million. Discounting this amount back to stage two at the riskless rate yields $5

million. At stage two, the expected value is:

V C p(V,C) no opt V-C option V-C E(opt V-C) E(no opt) 5 20 0.25 -15 0 0 -3.75 5 10 0.5 -5 0 0 -2.5 5 5 0.25 0 0 0 0

0 -6.25

Assuming that we cannot abandon at stage two, we discount the no option expected value

of -$6.25 million back to stage one,

0 1.05

and subtract the stage one construction costs. This yields a negative value of:

-5.95-3 =-8.95

The value of the option to abandon at any stage is the difference between the

expanded NPV of the investment and the static NPV:

1.33-(-8.95) = 10.28

In other words, if the BOT agreement was structured so that the project company

could walk away at any time when the costs of proceeding exceeded the value of

Page 82: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

proceeding, this would add $10.28 million to the value of the BOT investment

opportunity.

Of course, due to the highly political nature of BOT projects, it may be very

difficult for a concessionaire to disentangle itself from a project which becomes

unprofitable during the build phase. The government may try to discourage the

concessionaire from exercising its option to abandon by explicitly stipulating penalties

for abandonment in the BOT contract. For example, suppose the BOT contract stated that

if the concessionaire abandons the project at stage three, it must pay the government $65

million. Under this condition, the concessionaire would never abandon the project

because the expected payoff from continuing is higher under all possible states at stage

three; i.e., the greatest expected loss of $60.56 million (for V=69.44, C=130) is less than

$65 million. However, if the penalty for abandoning at stage three was only $25 million,

then the option to abandon would still have some value because $25 million is less than

the V-C spreads of -60.56 (for V=69.44, C=130), -30.56 (for V=69.44, C=100), and -30

(forV=100, C=130).

The government could also use the value of the option to abandon as a bargaining

chip. For example, the government could consider asking for an upfront payment of

$10.28 in exchange for granting the concessionaire the right to abandon the project. In

essence, the government has sold the concessionaire a call option on the value of the

project at stage three and a call option on the stage three call option. The premiums for

these calls could be paid by the concessionaire in the form of higher taxes or lower tolls -

- whichever the government feels is socially optimal.

74

Page 83: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

The option to abandon may interact with the option for strategic growth.

Abandoning a project midstream would undoubtedly have negative a impact on the

concessionaire's relationship with the government and the public. This in turn could hurt

the concessionaire's chances of procuring future BOT projects and expanding further into

a nation's infrastructure market.

4.1.3. The option to change scale or technology

The option to expand or contract the scale of the project in response to the arrival

of new market information has value. For example, the concessionaire may wish to

expand the scale of the project if expected demand increases during the build phase. The

ability to adapt technologies to changing demand conditions also has value. For example,

a toll road company may have the option to install a more expensive but more efficient

high tech AVI (automatic vehicle identification) toll collection system if demand

conditions justified the increased cost.

The option to change scale or technology can be valued using a method similar to

the technique outlined in the previous section. In the following analysis, we will consider

a situation where the concessionaire has both the option to abandon and the option to

change scale or technology. Assume C, is the base-case construction cost which has a

distinct distribution with an expected value of E(Cj). By paying Ck — where Ck has a

distinct distribution and E(Ck)>E(Cj) — to increase the scale or install a more efficient

technology, management could increase the value of the project by 50%. Likewise, by

paying Q where Q has a distinct distribution and E(Ci)<E(Cj), management could

decrease the scale of the operations or use less efficient technology, but avoid paying C,-

75

Page 84: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

Ci. At year three, the payoff from this investment opportunity {W) with the option to

abandon and the option to change scale or technology is,

E(W3) = max

£ £ m a x ^ -CJ,0)xp*{Vi)xp{CJ) V ' = 1 J=l

£ £ max(1.5V, - Ck ,0) x p * ) x p{Ck)

m q

£ £ max(.75F;. - C, ,0) x * iy.) x /»(C,) \i=i 1=1

where m is the number of possible values, p* is the risk neutral probability associated

with each of these values, n is the number of possible base case construction costs with

probabilityp(C), x is the number of possible increased-scale/improved technology

construction costs with probabilitypfC/J, andg is the number of possible decreased-

scale/cheaper technology construction costs with probability p(C).

The present value of this investment opportunity is found through the reiterative

process:

E{W2) = max

^max E(W3) 1 + r,

•CJt0 xp{Ct)

^ max k=l

1.5 E(W3) 1 + r,

Ck,0 f

xp{Ck)

max /=i

. 7 5 ^ > - C „ 0 1 + r, /

xp(C,)

yielding an expanded net present value of,

E (W) Expanded_ NPV = ^ 2 - Cx

76

Page 85: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

This approach assumes that we can expand/contract or change the technology of

the project by the same amount each year. This is perhaps unrealistic because there may

only be certain times during construction when the scale or technology of the project can

be changed. There may also be upper and lower limits to the size of these changes. The

model can be tailored to factor in these characteristics.

It should be noted that the option to change scale or technology involves multiple

interacting options. Changes in scale may affect the value of options present during the

operating period. For example, toll-setting options depend on the number of possible

users which in turn depends on the scale of the operation. The option to change

technology could also be an important strategic option. For example, by developing high­

tech toll collection technology, a company could establish itself as a leader in the

growing toll technology industry.

4.1.4. Time-to-build option

This option is a variation of the option to abandon midstream, but rather than

completely abandoning the project, management can alter the timing of the project's

completion. If the market moves favourably, management can bring the project into

operation earlier by fast-tracking (overlapping different phases of the project),

accelerating (shortening the length of a phase), or some combination of fast-tracking and

accelerating. However, fast-tracking/accelerating comes with a higher cost than a

regularly paced project. If the market moves unfavourably, management may wish to

wait and see if the situation improves before making further investments.

77

Page 86: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

Saman Majd and Robert Pindyck have written an instructive article on this topic

22

called "Time to build, option value, and investment decisions" . In their article, they

show how "optimal investment rules can be determined for projects with sequential

investment outlays and maximum construction rates". They model the value of a

completed factory using a Weiner process and then use contingent claims analysis to

analyze the "market value of the entire investment program" given that sequential

investment outlays can be adjusted between zero and some maximum level depending on

the arrival of new information. Their analysis shows "how simple NPV can lead to gross

errors."

4.1.5. Summary

Real options during the build phase can contribute significantly to the value of a

BOT project. When negotiating a BOT contract, it is important for the public and private

sector to understand how different contractual arrangements affect the value of BOT

build real options. Due to the public nature of BOT projects, they are likely to have less

flexibility than similar scale projects developed purely in the private sector. However,

straight NPV analysis is likely to overlook important sources of value arising from the

option to abandon, the option to change scale or technology, and time-to-build flexibility.

Contingent Claims Analysis can successfully value these real options.

Majd, Saman and Pindyck, Robert S., "Time to build, option value, and investment decisions." Journal of Financial Economics 18 (March) 1987: 7-27

78

Page 87: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

4.2. OPERATE PHASE: TOLL-SETTING FLEXIBILITY

4.2.1. Introduction

The setting of tolls is a highly contentious issue in BOT toll road projects. The

concessionaire wants the freedom to set profit-maximizing tolls. The public wants an

equitable and predictable toll structure. The government wants to ensure toll rates are

economically efficient and satisfy both the concessionaire and the public. Within this

framework of competing demands, the government and the concessionaire can choose

from a variety of toll-setting arrangements;

• Complete flexibility: the concessionaire is free to react to changes in market

conditions and set profit-maximizing tolls.

• Partial flexibility: the concessionaire is free to set prices within specified bounds.

• Trigger adjustments: adjustments are allowed to ensure a specified rate of return

• Fixed: the toll structure is fixed over the life of the project

Each of these options entails varying degrees of flexibility. This flexibility can be

valued using real option valuation techniques. We will develop a generic toll road BOT

project to show how these techniques can be applied. First, we model a demand curve

which relates toll prices to traffic levels. The derivation of this demand curve is an

iterative process which reflects how groups of consumers with different willingness-to-

pay to get to a certain destination and with different values of travel time savings (VTTS)

respond to varying levels of congestion. Next, we determine the stochastic nature of the

socioeconomic variables which shape the demand curve. Given the stochastic

characteristics of the demand curve, we then look at profit-maximizing price-setting

79

Page 88: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

strategies under the constraints of each of the price-setting arrangements. Finally, we use

the real option technique of contingent claims analysis to value projects with varying

degrees of price-setting flexibility in an environment of uncertain future demand

conditions.

4.2.2. Deriving the toll demand curve

We begin by deriving a toll demand function for travel to destination D through

the BOT toll road . This toll demand curve relates toll levels (p) to traffic quantity (q)

where quantity measures the number of vehicles which pass through the system per unit

of time (hour, day, year). Our demand curve analysis in figure 4.3 puts a slight twist on

23

the traditional transport economic analysis of pricing congested roads . Unlike

traditional congestion pricing which factors in congestion externalities to determine the

socially optimal price and quantity, we are interested in the toll road operator's profit-

maximizing toll.

In figure 4.3, the vertical axis measures both the driver's willingness-to-pay in

terms of money and the financial value of lost time and the supplier's costs to provide the

service. The demand curve reflects consumers' willingness to pay (WTP) out-of-pocket

expenses (tolls) and willingness to sacrifice time to get to destination D. The average

total social cost curve (ATSC) is the vertical sum of fixed and variable infrastructure

operating costs (we treat road operator average variable costs, AVC, as equal to road

operator marginal costs, MC; i.e., the costs of serving one additional vehicle does not

change significantly with quantity) divided by q and the user's own time costs and

Mohring, Herbert. Transportation Economics. Ballinger Publishing Company 1976, Ch. 3

80

Page 89: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

vehicle operating costs24. The user marginal social cost (MSC) curve reflects congestion 0

externalities and reveals how much an additional driver increases the travel time of all

drivers. -

Figure 4.3 A twist to traditional Social Cost-Benefit Analysis

User AC(average costs): average time and operating costs of each driver User MSC(marginal social costs): the time and operating costs an additional driver imposes on all other drivers Road operator MC(marginal Costs): the costs of servicing one additional vehicle. Equivalent to average variable costs in our case. ATSC (Average total social costs): the vertical sum of user AC, operator MC, and operator fixed costs divided by q Demand: consumer's willingness-to-pay in time and money to get to destination D

Consumers are willing to use the facility and suppliers are willing to supply the

service up to point q where average total social costs equal WTP. However, this point is

not optimal from society's perspective because drivers are not considering the congestion

externalities they impose on others. The socially optimal toll would restrict traffic to

quantity q* at a generalized price of p*. This is where user MSC intersect the demand

Throughout our discussion, we will only model the effects of congestion on driver time and not consider its effect on vehicle operating costs. This is because the full costs of congestion perceived by road users is dominated by their value of time spent rather than their vehicle operating costs. In other words, vehicle operating costs are assumed constant regardless of congestion.

81

Page 90: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

curve. In other words, the cost of an additional driver equals the willingness to pay of the

marginal driver.

However, in BOT projects, we must also consider the toll-setting decision from

the operator's perspective. The operator wants to maximize profits by restricting quantity

to the point where the operator's marginal costs equal marginal revenue. This is shown

in figure 4.3 at pointpt, q{. The toll operator can exploit its monopoly power to maximize

profits by charging the operator optimal toll.

To analyze a toll operator's profit maximizing behaviour under stochastic

conditions, we require a demand curve solely in terms of WTP cash; i.e., demand net of

the value of time contributed by motorists using the toll road. We achieve this by

deriving a toll demand curve which relates traffic quantity exclusively to toll levels. This

is in contrast to traditional congestion pricing which relates general willingness to pay in

both time and money to traffic quantity. If we assume that consumers all have the same

VTTS, deriving this demand curve is a straight-forward procedure in which we simply

subtract average time costs at quantity q from the general WTP at q to determine the toll

which generates traffic q. Taking the derivative of this toll demand function yields the

toll marginal revenue curve. The profit-maximizing toll and quantity is where the toll

marginal revenue curve intersects the toll road operator's marginal cost curve. For

simplicity, we assume the marginal costs for providing toll road services are fixed,

although in reality maintenance expenses may increase for every additional car allowed

on the system if the traffic level far exceeds the facility's design capacity. The derivation

of this demand curve is shown in figure 4.4.

82

Page 91: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

Fig. 4.4 Deriving the toll demand curve assuming everyone has the same VTTS

General demand curve Toll demand curve Profit-maximizingj9* and q*

P WTP average user time costs

MR

L firm's MC

However, the assumption that all consumers have the same VTTS is questionable.

There is evidence that people with higher incomes tend to have higher VTTS. See

appendix II for a more thorough discussion of VTTS. Our model allows for groups of

consumers to have different VTTS. It generates a toll demand curve through an iterative

process in which given a toll price, consumers adjust to different levels of congestion

according to their VTTS. These adjustments oscillate towards an equilibrium quantity for

each toll level. If we assume that consumers all have the same VTTS, then our model

will lead to the same results as the previously mentioned process of simply subtracting

average consumer borne (time and operating) costs from consumer WTP. However, the

above-mentioned approach breaks down when we introduce different VTTS because it

fails to reveal which points on each group's time cost curves should be subtracted from

which points on each group's WTP curves. Our model is capable of determining an

equilibrium toll demand curve which captures congestion effects in an environment

where consumers value time differently. The mechanics of this model are as follows.

83

Page 92: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

We divide potential consumers into groups based on their value of travel time

savings (VTTS). For simplicity, consider two groups of potential road users who want to

get to destination D:

• Hgroup: high-income potential road users who are willing to pay $5 to reduce their

travel time by one hour

• L group: low-income potential road users who are willing to pay $1 to reduce their

travel time by one hour

Once we have segmented potential consumers based on their VTTS, we derive a demand

curve for each group. The demand curve reveals how much consumers in each group are

willing to pay to get to destination D.

We are making an important distinction between consumers' willingness to pay

out-of-pocket expenses (i.e., a toll) to get to D and their willingness to sacrifice travel

time. For arguments sake, assume there is no congestion and a person from group L can

always get to D at the free flow travel rate (the optimal car speed and hence travel time

which is determined by the design capacity of the system). Assume that free flow travel

time converts to a monetary value of $1 for people from L. Under this condition, there

may be one person from the L group willing to pay a toll of up to $9 on top of the $1

travel cost for a total price of $10 to use the road. Thus a $9 toll would induce one person

from L to use the road. At a toll of $4 (for a total price of $5), there may be fifty people

from L who would use the road. When deriving the WTP curves for H and L, it is

important to bear in mind that these curves are made up of two components: the WTP a

84

Page 93: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

toll and the WTP time costs. For simplicity, we assume these demand curves are linear as

shown in figure 4.5.

Fig. 4.5 Demand for travel to D for groups with different values of travel time savings

Generalized price (toll and time)

Now we introduce the effects of congestion on the quantity demanded for a given

toll price. As shown in figure 4.6, the derivation of the demand curve with congestion

costs is an iterative process which reveals how groups with different willingness-to-pay

for travel to destination D and different VTTS respond to different levels of congestion

over time. At time zero, a toll pricep is set. We assume that at time zero, users expect to

pay time costs based on the free flow rate of traffic in addition to the toll. At time zero,

the total number of users is q^o + qH>0.

However, at total quantity qL0 + qH0, there is likely to be some unexpected

congestion. The level of congestion is determined by a travel time-traffic flow function

which is based on empirical results from traffic engineering studies. Our model uses the

Kimber and Hollis25 function:

Bureau of transport and communications economics. Traffic congestion and road user charges in Australian capital cities. Australian Government Publishing Service, 1996

85

Page 94: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

Figure 4.6 Dynamic process to derive the toll demand curve for two groups with different VTTS

Time Zero

E(TCU0)-TCU0

E(TCLi0)

WTP toll and time to get to D

E(TCn0 )-TCHi0

E(TCHi0)

<1L

Time cost function

L

\ E(TCLi0)-TCLt0

E(TCU)-TCU >, E(TCU

free flow yw -I

Time one

E(TCU0)-TCU0

E (TCH0 )-TCH0

E(TCHJ )-TCHJ

_ E(TCH>0)= free flow

+ qui

— E(TCH0 )-TCH0

Time two

E(TCLJ )-TCLJ

qui + qm

_ E(TCHJ)-TCHJ

qui + qn2

K = K[l + ((* - 1) + a V ( * - D 2 + f o t ) ]

where ta is average travel time per kilometre, t0 is free speed travel time per kilometre, x

is the volume-capacity ratio, and a and b are parameters which change depending on the

86

Page 95: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

type of road. See appendix III for more details on traffic flow functions. We multiply ta

by each group's VTTS to find their time costs, TC.

After actually using the road at time zero, drivers from L find they are paying

more than they had expected to pay because TCh0>E{TCu0), where £(• ) is an

expectations operator. At time zero, EiTC^o) is equal to the free flow rate. Those people

who had paid E{TCLi0)-TCLi0 more than they would have been willing to pay if they had

known the costs of congestion beforehand will not use the road again at time one. The

same reasoning applies to drivers from H. Thus, the number of drivers from L and H at

time one will be less than at time zero.

However, because the total number of drivers on the road at time one is less than

at time zero, travelers from L and H who actually use the road at time one will find the

congestion costs lower than they had expected. At time one, the expected time costs for

drivers from L would be, EiTC^) which is equal to the actual time costs from the

previous period TCL0. The actual amount drivers end up paying, TCU1 is lower than the

price drivers expected to pay, TCL0 and thus more drivers would have used the road if

they had known this beforehand. The same reasoning applies to drivers from H. Hence

the number of drivers from H and L at time two will be greater than at time one, but less

than at time zero.

This process will converge to equilibrium points qL and qH which are unique to

the pricep, as long as each group's WTP curve is greater than its average time cost

(ATC) curve. We repeat this process for all relevantp's to derive the equilibrium demand

curve. We impose the conditions that qL cannot exceed the quantity at which ATCL equals

87

Page 96: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

WTPL and qH cannot exceed the quantity at which ATCH equals WTPH. Otherwise the

process will become unstable.

This dynamic process can be modelled using a computer program such as

Mathcad (see appendix IV). We will work through a simple example using Mathcad to

show the mechanics of this dynamic process. First we define the variables for the two

groups mentioned above; H and L.

Variable Description Value AL

generalized price which would force everyone from L off the road under free 5 flow conditions

AH generalized price which would force everyone from H off the road under free 10 flow conditions

BL, number of drivers from L who would use the road if it were free 120 BH

number of drivers from H who would use the road if it were free 100 P toll price varies qL,t number of drivers per time unit from L who would use the road at time t varies qL,t

expecting to pay total costs experienced at t-1. iHt number of drivers per time unit from H who would use the road at time t varies iHt

expecting to pay total costs experienced at t-1 TCUt time costs for L at a given level of congestion at time t varies TCH,t

time costs for H at a given level of congestion at time t varies VTTSL value of travel time savings per hour for L 1 VTTSH value of travel time savings per hour for H 5 D length of the road 20 k capacity of the road beyond which significant congestion arises 400 a estimated congestion parameter depending on the type of road 25 b estimated congestion parameter depending on the type of road 0.00089 f free speed kilometer per hour 60

We assume that the relevant time unit is one day. This means that a driver decides

whether or not to use the road on a particular day based on the traffic conditions of the

previous day. This assumes that information regarding traffic conditions disseminates to

all potential users. The model works as follows:

1. We start from the highest generalized price anyone is willing to pay in terms of both

tolls and free flow time costs to get to B. If we charged a toll of $10, nobody from H

88

Page 97: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

OTL would use the road. Assume that we can only charge tolls in multiples of $0.25.

We start therefore with a toll of $9.75.

2. At time zero, we use the demand curves to determine the number of drivers from H

and L who would use the road at a toll of $9.75. Assuming that drivers make their

decision expecting to complete the journey at the free-flow time, their expected time

costs are:

E(TCrn)= — xDxVTTS, = — x 20x1 = 0.333 • f 60

E (TCH „) = — x D x VTTS „ = — x 20 x 5 = 1.666 H,0> j " 6 0

At a toll of $9.75 under free flow conditions, the number of drivers from L and H

would be:

qL=UL -P-E(7U£>0))x^- = (5-9.75-0.333) x — = -122 AL 5

<1H = (AH ~P~E(TCHO» x — = ( 1 0 - 9 - 7 5 - L 6 6 6 ) x — = -14 AH 10

We cannot have a negative number of drivers so throughout the model we impose the

condition q=max(q,0). At $9.75, no drivers would use the road.

3. We repeat the process with descending tolls until we have a positive quantity. At a

toll of 8.25, we have,

B 120 qL=(AL -p-E(TCL0)) x— -̂ = (5-8.25-0.333) x = -86

AL 5

qH=(AH-p-E(TCH0))x^=(10-8.25 -1.666) x ̂ = 1 AH 10

However, there is virtually no congestion at this level of traffic so we will move

89

Page 98: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

down to a lower price to illustrate how qL , q H ,qi+qH> VTTSL, and VTTSH interact to

converge towards an equilibrium point.

4. Consider the price $2. Atp=$2, we would have the following number of users given

that users were expecting to pay the free flow time costs.

qL = (AL -p-E(TCL0)) x ^ = (5-2-0.333) X — = 64 AL 5

qH = (AH-p-E(TCH0))x^=(10-2-1.666)x^ = 63 AH 10

However, at a total quantity of 127, there is some congestion and we use Kimber and

Hollis' function to determine the congestion costs forZ, and//:

TCLO= — ' f

l + a + . J

+ b 9L +QH

J xDxVTTS,

TCL0 = 0.339

TC"fi ~ f l + a <1L +4H + . + b <1L +1H xDx VTTS H

TCH0 =1.698

In this first iteration, drivers from L were expecting to pay 0.333 in time costs, but

ended up paying 0.339. Likewise, drivers from H were expecting to pay 1.666, but

ended up paying 1.698. This will affect their decision to use the road again at time

one.

5. In the second iteration (i.e., at time one), the number of L and H drivers will decrease

by the amount:

90

Page 99: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

AqL, = ̂ x (E(TCL,)- TCLl (0.333- 0.339) = -0.144 AL 5

AqH, =^-x(E {TCHA ) - TCHX )= ^ x (1.666 -1.669) = -0.3 AH 1 U

The number of L and H drivers for the second iteration will be

= <IL,« + = 64 - 0.144 « 64

1H,I =<1H,O+ ^H.I = 63 - 0.3 - 63

In this case, the congestion effects are extremely small and we don't need many

iterations to converge to an equilibrium point. However, when there are significant

congestion effects, it may take several iterations to reach equilibrium. The number of

users will contract and expand with each change being smaller than the previous

change. In figure 4.7, Mathcad has calculated a set of equilibrium total quantities for

each price given the group demand and congestion conditions stated above. Note that

the zero toll quantity is less than the horizontal sum of BL+BH due to congestion and

time cost effects.

Figure 4.7 Toll demand curve derived by Mathcad for j 'roups H and L

10 10 1 1 1 9

g -

7 - \ -

6 P

5 \

4

3

2

1

1 1 1 0 50 100 150 200

q (drivers/day)

91

Page 100: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

This method of generating demand curves can be extended to more than two

VTTS groups. Figure 4.8 illustrates how the dynamic process would look for four groups

with different VTTS: commercial truck drivers, high-income wage earners, low-income

wage earners, and pensioners. The different VTTS are reflected in the size of each

group's response to levels of congestion for each iteration. For simplicity, this diagram

assumes that a stable equilibrium of qcr+lH is reached at toll p (qL and qP are zero) after

three iterations/

Figure 4.8 Dynamic process for four VTTS groups

commercial / truckers (CT)

' toll

, high income (H)

ICT / / ' 7

pensioners (P)

* low income (L)

For toll p, the total quantity will be qCT + qH

after three iterations

The derivation of toll demand curves can be summarized as follows. First

determine the generalized price-traffic quantity relationship for all significant VTTS

groups assuming that travellers expect to make the journey at the free flow rate. Use the

iterative process outlined above to determine the equilibrium quantity at each toll price

given the congestion function and the different VTTS and demand curves for each group.

Page 101: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

We are now ready to model the stochastic nature of the toll demand curve. This

will enable us to determine the profit maximizing toll within a stochastic environment for

each of the toll-setting-arrangements. With this information, we will be able to value

varying degrees of toll-setting flexibility using Contingent Claims Analysis.

4.2.3. Stochastic demand curves and the value of fixed tolls

In our simple model, the shape of each VTTS group's demand curve is

determined by two parameters, y-intercept (generalized price) A and x-intercept

(quantity) B. By ascribing stochastic properties to these parameters, we can model the

random nature of the demand curve. An increase in the WTP to get to destination D

among current users would result in an increase in 4. This may be due to a change in the

industrial structure of D. A general increase in the population would lead to an increase

in B. Predicting the nature of these parameter changes over time is the work of

demographers, urban planners, and transport economists. By modelling the volatility of

these parameters, we can determine the probability distribution of future demand curve

shapes.

Continuing with our two VTTS group example, imagine that next time period (in

26

this case next year ), BH will either move up by a factor of 2 to 200 or down by a factor

of 1/2 to 50. The probabilities of an up move and a down move are both equal to 0.5.

Figure 4.9 shows these scenarios.

2 6 Note we are dealing with different time periods here than in the iterative process to equilibrium. Here, we are modelling probabalistic demographic shifts over a long time period (one or more years). The dynamic process works through iterations over short time periods (one day) and assumes fixed parameters.

93

Page 102: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

Figure 4.9 Binomial movements of BH over time

Time zero Time one

10

Pu = 0.5

AH = \Q u

\ Pd = 0.5

BH = 200

BH =100 ^v. d

10

BH = 50

What toll will maximize the net present value of profits from time zero and time

one under this scenario given the condition that the toll set at time zero can not be

changed at time one? Assume tolls can be set at increments of $0.10. In figure 4.10,

Mathcad is used to calculate the profits (jr.) for each toll level (p). The nomenclature for

profits is J t p ^ wherep is the toll, t is the time period, ands is the state at time period t

Figure 4.10 Profit-maximizing toll 2 0 0

at time zero BH =100 Profit

p*= 3.10 %.i,o - 133.62 0

200

- /

1

1 0 p* 5 10

P

94

Page 103: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

which will either be up (w) or down (d). The profit formula is:

Xpt =PXa ~ (FC + VCxq)

where fixed costs (FC) are 100 and variable costs (VC) are $0.5 per car. Figure 4.10

shows the profit curve at time zero with £#=100.

The tolls and associated profits for time zero and the up and down states at time

one are as follows:

Toll Time zero % BH =100 Time one ot1|U £#=200 Time one jt l i d BH =50 3.6 125.904 272.215 52.648 3.5 128.806 273.377 56.418 3.4 131.029 273.66 59.609 3.3 132.572 273.064 62.22 3.2 133.436 271.589 64.252 3.1 133.62 269.235 65.704 3.0 133.125 266.003 66.576 2.9 131.95 261.892 66.868 2.8 130.096 256.903 66.581

At a toll of $3.10, the present value of the fixed toll investment opportunity (i.e.

the net present value of profits from time zero and time one) would be:

^ 3.1,1 ^ A7 37(jt 3 1)=at 3 1 | 0+-

AW(jt 3 1 ) =133.62 +

1 + r 05x269.235 + 05x65.704

NPV {% 3,)) =133.62 +

1+r 167.47 1 + r

The question of what risk-adjusted discount rate (r) to use will be addressed later.

At this point, it is sufficient to note that/?=3.10 yields the greatest net present value as

long as r is less than 144% Althoughp= 3.2 has a greater expected time one value of

167.9205 (0.5x271.589+0.5x64.252), p=3.2 has a smaller time zero value of 133.436. It

95

Page 104: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

would only make sense to choosep=3.2 if the present value of the difference between

E(x311) and E(x32>i) was greater than the difference between o t 3 1 0 and Jt3.2,o- This

condition is only met when r is greater than 144% which is highly unlikely to occur.

Therefore, given the stochastic properties of BH outlined earlier, if we were forced to set

an unadjustable toll at time zero,/?=3.10 would be the toll which maximizes profits from

time zero and the expected profits from time one and hence maximizes the value of the

investment opportunity.

To price other toll-setting arrangements with varying degrees of flexibility, we

act as though there is a market for the time-one profits from the fixed-toll position. In

other words, we treat the time-one cash flows as though they were a tradable commodity.

We can price this theoretical commodity based on its risk profile and the market's

attitude toward risk. The price we would pay for this theoretical commodity if it were

traded can be calculated using an equilibrium model such as the CAPM. We will discuss

the application of the CAPM in more detail in the next section. For now, it is important

to accept that even if an asset (in this case claims to future annual toll profits) is not

actually traded, it can still be priced in a world with systematic risk.

4.2.4. The value of complete flexibility

Imagine that the concessionaire has complete freedom to set profit-maximizing

tolls under any state at time one. At time zero, the operator would set the toll at $3.10 for

a profit of $133.62. At time one, if BH increased by a factor of 2 the operator would set

the toll at $3.40 for a profit of $273.66 (versus $269,235 at a toll of $3.10). This reflects

Page 105: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

the increase in the number of people with a high WTP to use the road. If BH decreased by

a factor of 1/2 the operator would set the toll at $2.90 for a profit of $66,868 versus

$65,704 for a toll of $3.10).27

This flexibility to adapt toll levels to changes in the demand curve can be valued

using Contingent Claims Analysis. By combining the present value of the expected fixed-

toll profits at time one with a riskless asset, we can create a portfolio which exactly

replicates the payoffs of the flexible toll investment opportunity under all possible states

at time one. The cost of this portfolio at time zero must equal the value of the flexible toll

investment opportunity. The replicating portfolio is created as follows.

First, we recognize that the net present value of the fixed toll investment

opportunity has two components: a certain time zero cash flow and an uncertain time one

cash flow. We are only interested in the present value of the expected time-one cash

flows:

At time zero, we are willing to pay PV(E(it3u)) to receive an uncertain profit at time

one. We create a portfolio by combining PV(E(%31>1)) with a riskless investment to

replicate the payoffs to a flexible toll-setting investment opportunity at time one. Figure

4.11 shows the payoffs for the two investment opportunities. Given these payoffs, we

solve the following system of equations to determine the replicating portfolio:

It is interesting to note that if BL increased by a factor of 2 rather than BH„ the optimal pricing strategy would be to decrease the toll to $2.90 for a profit of $233,456. With a decrease in BL by a factor of 1/2, the optimal toll would be $3.4 for a profit of $87,019.

PV(E(z3X1)) = Pu X 3 t 3.1,1,* +Pd x j t

1 + r 167.47 1 + r

97

Page 106: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

Figure 4.11. Present value of opportunity to receive uncertain cash flows at time one

Fixed toll (/) Complete flexibility (cflex)

/ ^ 3 . 1 , l , u ~

269.235 ^ 3 . 4 , 1 ^ -

273.66

1 + r cflex.O' ,=

^ . l . l . d -

65.704 ^ 2 . 9 , 1 4 " "

66.868

n xot -B = %

nx% -B = % 2.9,14

where n is the size of the position in the asset which pays off at time one and B is the

amount of borrowing or lending. Solving the equations for n and B, we get:

« x 269.235-5 = 273.66 nx 65.704-5 = 66.868 n = 1.016 5 = -0.111

By buying 1.016 of the time-one fixed-toll payoff position and buying 0.111 bonds (i.e.

lending money) at the risk free rate, we have a portfolio with exactly the same time-one

payoffs as the complete flexibility (cflex) position. Conceptually, we run into a problem

here because the replicating portfolio involves buying a stake in the fixed-toll year-one

profits which is greater than the whole. While it is impossible to own more than 100% of

something, it is important to remember that with the CCA approach, we are treating the

fixed-toll year-one profit position as though it were a traded asset in unlimited supply.

98

Page 107: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

We assume such an asset is priced in the market based on its systematic risk and the

market's price of risk. While mentally difficult to digest, this idea is crucial to the use of

real options pricing techniques.

The cost of this replicating portfolio (RP) to us today is:

n n 167.47 0.111 RPa=lM6x- +

0 . 1 + r l + rf

Under the principle of no-arbitrage, RP0 must equal the time-zero value of the time-one

flexible payoff position; RP0 = Vc(lexfi. The exact value of RPQ at time zero depends on

the risk-adjusted discount rate r and the riskless lending rate r f. For arguments sake,

assume that r f =5% and r =15%.

o=RP0= 1.016 x + M l = 148.06 c f l e x 0 0 1.15 1.05

This is greater than the time-zero value of the time-one fixed-toll payoff position:

E 167.47 V, o = 3 1 4 = =^^- = 145.62

f'° 1 + r 1.15

The difference,

J'cfiex.o - F f ,0 =148.06-145.62 = 2.44

is the value of having complete flexibility to set toll levels. The value of flexibility makes

up almost 1% of the total value of the complete flexibility alternative. This difference

will always be positive as long as r is less than 25xrf (this is found by solving the

inequality Vcnex,0<Vf 0). The exact value of complete flexibility is determined by the risk-

adjusted discount rate (r). If the CAPM holds, then r is estimated using the familiar

formula:

99

Page 108: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

r = r, + 6 (r -rf) where (3 = ' - j n -a

m

Beta could be estimated by regressing percentage changes in fixed-toll profits to

market returns. Whereas betas are usually estimated on assets such as company stocks,

here we are treating the toll profits from each time period as an asset. For example,

consider the Eastern Harbour Tunnel crossing BOT project in Hong Kong. Figures from

1992-1996 on profits, percentage changes in profits, and annual Hong Kong stock market

(Hang Seng index) returns are:

Year Profit̂ 8 % change in profit Hang Seng return^ 1992 77,744,879 1993 131,083,266 0.686069 0.11567 1994 143,734,462 0.096513 -0.311 1995 119,500,526 -0.1686 -0.22981 1996 131,997,006 0.104573 0.33534

The statistics from regressing percentage change in profit on the annual Hang Seng

return are:

(3 Op a a a R 2 Residual a # of obs. 0.5 0.76 0.19 0.20 0.181 0.399 4

The beta of 0.5 indicates that toll profits are less sensitive to general economic

forces than the market. The alpha is the average percentage change in toll profits when

the market return is zero. R 2 reveals that 18% of the changes in toll profits can be

explained by market movements. In other words, 18% of the risk is market risk and 82%

2 8 from company Eastern Harbour Tunnel Crossing website: www.easternharbourtunnel.com 29

courtesy of Rod Morreau at CIBC Wood Gundy

100

Page 109: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

of the risk is unique risk. Residual a measures the amount of unique risk as a standard

deviation.

The high standard deviations for beta and alpha mean these estimates have a high

probability of being wrong. There is usually a large margin of error when estimating

betas for individual stocks. The above estimates could probably be improved if we

regressed the profits from several similar toll road companies (i.e., came up with a Hong

Kong toll road industry profit index) on the Hang Seng returns. Furthermore, the above

example has only four observations; exceedingly few for a reliable regression. Despite

the shortcomings of the crude regression above, the technique could be fine-tuned to

produce workable risk-adjusted discount rate estimates. These estimates could then be

used to value the flexibility in different toll-setting arrangements. Figure 4.12 shows how

sensitive the value of complete flexibility in our example is to different estimates of beta.

The value of complete flexibility appears quite robust to errors in the estimate of beta.

Figure 4.12 Sensitivity of complete flexibility option value to |3 estimates (from 0 to 2)

j 1 1

v Our estimate 2.5 |3=0.5

Option(r f , r m , p , E V f , n , B )

2

: i i 1.5 0 1 2 3

P

At this point, you may ask why not just discount the time-one flexible profits at

the project's risk-adjusted discount rate:

101

Page 110: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

Pu X j t 3 . 4 , i , « +Pd xx2.9,14 0.5x273.66 + 0.5x66.868 1 / ) O A C C

Vcflex = = = 148.055 c f l e x 1 + r 1.15

This method will yield a different answer to CCA, although in this case the difference is

slight (148.06 for CCA versus 148.055 for straight CAPM r discounting). CCA is the

correct approach because it recognizes that flexible price-setting arrangements change the

riskiness of future cash flows. The same risk-adjusted discount rate cannot be applied to

cashflows with different risk profiles. Recall the arbitrage argument from chapter three.

Astute investors would not allow someone to pay $148,055 to enter a position which the

market valued at $148.06. The price would be bid up to the CCA value.

Using risk-neutral probabilities

The preceding discussion has shown how a replicating portfolio can be used to

price the value of toll-setting flexibility. The same results can be achieved using risk-

neutral probabilities. Recall the formula for risk neutral probabilities from chapter three:

(\ + rf)S-S~ p' —

s + - s ~

In this case, the twin security S is the fixed toll investment opportunity where,

= 167.47 _ 6 2 5 6 5

1.15 S + = 269.235

5" =65.704

The risk neutral probability of an up movement is,

, (1.05) x 145.62565-65.704 n „ O A r

p' =- = 0.42845 269.235-65.704

102

Page 111: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

We use the risk neutral probabilities to calculate the certainty-equivalent expected cash

flows at time one for the completely flexible toll-setting investment opportunity. We then

discount this value back to time zero using the risk-free rate:

P'*X34iM + G-/>')xjt 2 9 W 0.42845x273.66+(1-0.42845) x66.868 1 A O n

cftex l + rf 1.05 The risk-neutral probability approach yields the same answer as the replicating

portfolio approach. This is because they are different ways of saying the same thing.

Both methods depend on the market price of risk and the correlation between toll

revenues and the market. These relationships are expressed through beta calculated using

the CAPM. While the use of risk-neutral probabilities is perhaps more elegant, working

through the mechanics of replication instills a deeper understanding of the underlying

logic behind real options.

4.2.5. The value of partial flexibility

Suppose the government allowed the concessionaire to increase tolls by no more

than $0.10 a year. At year one, if BH shifted up, the concessionaire would want to

increase the toll from $3.10 to $3.40 for a profit of $273.66, but would be limited by the

ceiling and would be forced to settle for an increase to $3.20 for a profit of $271,589. If

BH shifted down, the concessionaire would decrease the toll to $2.90 for a profit of

66.728,. Using the same contingent claims approach as above, we could replicate the

year-one payoffs from the partial flexibility position above by buying a stake n in the

fixed-toll year-one profit payoffs and lending money at the risk-free rate.

103

Page 112: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

rax 269.235-5 = 271589 rax 65.704-5 = 66.868 ra = 1.00585 5 = -0.7798

Working with the figures from the complete flexibility example (r =15% and

rf=5%), we calculate the present value of the replicating portfolio and hence the partial

flexibility (Fp f l e x) as:

^ f i e x o = R P o =

L 0 ° 5 8 5 x + — = 147.22 p f l e x'° 0 1.15 1.05

The value of partial flexibility is $1.59 (147.22-145.62). The partial flexibility

position (147.22) is more valuable than the fixed position (145.62), but less valuable than

the complete flexibility position (148.06). Figure 4.13 shows the sensitivity of partial

flexibility option value to estimates of beta. Again, it is quite robust.

Figure 4.13 Sensitivity of partial flexibility option value to beta estimates (from 0 to 2)

1.8 I

O p t i o n ( r f , r m , P , E V f , n , B ) L 6

T T

4.2.6. Trigger adjustments

The objective of trigger adjustments is to ensure that the concessionaire receives a

rate of return acceptable to both the public and private sectors. Downside risks are

limited so as to encourage private sector participation in the project. If there is a return

104

Page 113: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

shortfall below a specified threshold (X) the government allows the concessionaire to

increase tolls. The government has written the concessionaire a put. Upside potential is

bounded to prevent excessive exploitation of monopoly power. If the return exceeds a

specified value (Y), the concessionaire is compelled to reduce tolls. The concessionaire

has written a call to toll-road users. The upside and downside potential is thus limited

between the bounds shown in Figure 4.14.

Figure 4.14. Trigger adjustment option payoff diagram.

The value of this position can treated as the sum of a put with strike price X and a

call with strike price Y. As with financial options, the values of the put and call depend

on their strike price, the current value of the toll profits (the underlying asset), the

volatility of the toll profits, and the maturity of the guarantees. However, unlike financial

options which are valued under the assumption that traded assets can be used to create a

replicating portfolio, these toll-road real options are valued using theoretical assets. The

105

Page 114: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

value of these theoretical assets is determined through equilibrium models such as the

CAPM.

Trigger adjustment toll-setting arrangements may seem similar to partial

flexibility arrangements which cap the size of toll increases. However, the two are

fundamentally different. Partial flexibility sets no limit on the size of the return. Under

partial flexibility, although the concessionaire may not be able to set the profit-

maximizing price, by lowering costs it may still end up achieving high rates of return —

perhaps too high for the government's and public's liking. If the government is

concerned with regulating the concessionaire's rate of return, then trigger adjustment

arrangements are clearly the more effective alternative.

However, by regulating rates of return, the government is damaging the

concessionaire's motivation to innovate and improve operations. If the government is

worried that the public will perceive the concessionaire as a monopolistic price-gouger,

yet does not want to dampen the concessionaire's incentives to strive for lower costs and

better service, then the partial flexibility alternative has some advantages. It prevents the

concessionaire from jacking up tolls dramatically, yet also encourages the concessionaire

to push for efficiency so as to maximize its rate of return.

4.2.7. Profit-maximization versus economic efficiency

The discussion so far has focused on the toll operator's profit-maximizing

behaviour. A toll demand curve was generated under the assumption that consumers

decided whether or not to use the road based only on their own time costs (i.e., average

106

Page 115: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

time costs) and the level of tolls. The operator then maximized profits by setting the toll

at the point of intersection between the marginal operating cost curve and the marginal

revenue curve derived from the toll demand curve.

How does the profit maximizing toll compare to the socially optimal toll? The

socially optimal toll occurs where price equals social marginal costs. The social marginal

cost curve consists of both consumer-borne marginal time costs created by congestion

and the supplier's marginal operating costs. Our earlier toll demand curve model

assumed that marginal time costs did not factor into a driver's decision. Drivers were

only concerned with their own time costs and did not think about how much they would

increase the travel time of other drivers if they joined the traffic stream. To find the

socially optimal toll, we must force drivers to internalize such congestion externalities.

This requires adjustments to our multi-VTTS model.

First, we force drivers to bear the marginal congestion costs they impose on

others. To do this, we calculate the derivative of total travel time30. Total travel time (7)

is T = qTxta where ta is the Kimber and Hollis congestion function and qT is the total

number of users. The derivative of ta with respect to qT is:

The marginal travel time function has the form:

Bureau of transport and communications economics. Traffic congestion and road user charges in Australian capital cities. Australian Government Publishing Service, 1996.p. 81

107

Page 116: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

dt.

For qT, we enter the quantity qL+ qH to determine the marginal increase in total traffic

time for one additional driver at the total traffic level. To determine the monetary

marginal time costs (MTC) for each group, we multiply the components of tm as follows:

M T C l A ? r X « ' * ^ + ? « x V T T S " xVTTSL

dqT qL +qH

M T C h = £ V x t r x ' ' X W T O ^ * ' x m 5 » + t . XVTTS„ dqT qL +qH

We multiply —— by the weighted average — — — — because this term dqT q L

+ q H

shows how much an additional driver increases the time costs to everyone in the traffic

stream. Therefore, we should use a weighted average VTTS to reflect the fact that

different components of the traffic stream have different VTTS and that the breakdown

of these components changes with the overall level of traffic.

The problem of how a driver could know the weighted average VTTS at a

specific traffic level is irrelevant to our analysis. We want to derive a toll demand curve

under the assumption that drivers behave in a socially optimal manner considering both

their own average time costs and marginal time costs. By equating the marginal

operating cost to this marginal cost toll demand curve, we can find the socially optimal

price and quantity.

In the adjusted multi-VTTS model, for each iteration, drivers decide whether or

not to use the road in the next time period based on the difference between the sum of

expected average and marginal costs (i.e., the actual average and marginal costs in the

108

Page 117: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

previous time period) and the sum of actual average and marginal costs in the current

time period. As in the calculation of the toll demand curve, these differences oscillate

towards an equilibrium total traffic quantity for each toll level. In figure 4.15, Mathcad

has calculated the marginal time cost toll demand curve using the numbers from our

earlier example.

Figure 4.15. The marginal time cost toll demand curve

10 1 1 1 9 g

7 —

6 - Socially optimal -

P _ 5 - quantity =108 v

4

3 Operator marginal \

2

1 costs = 0.5 — \ ^ \ ^ ^ \

0 0 30 60 90 „, 120 q*

q ( A l , B l , A 2 , B 2 , a , b , k , T V l , T V 2 , f , D , n )

The socially optimal quantity occurs at point q*= 108 where the operator's

marginal cost ($0.50) intersects the marginal time cost toll demand curve. At this point,

consumers have reached an equilibrium through a decision process in which they

consider both their own time costs and the time costs they impose on others.

In reality however, drivers do not consider the costs they impose on others and

are only concerned with their own time costs. This is the toll demand curve shown in

figure 4.16 which was derived earlier based only on average time costs. Assuming the

operator behaves in a socially optimal manner and charges a toll equal to its marginal

109

Page 118: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

<

operating costs, drivers will use the road up to point q. However, this is an excessive

amount from society's point of view. To a reach a socially optimal quantity, we must

force drivers to internalize time cost congestion externalities by charging a toll 71*.

In our example, the operator's marginal cost curve is constant at $0.5 and

intersects the average time cost toll demand curve at q - 176. From society's perspective,

this is an excessive amount with the optimal amount at g*=108. Assuming that people

behave based only on their own average time costs, the government should force the

operator to charge a toll of />*=2.55 to reach the socially optimal output.

However, a toll of $2.55 will result in profits of only $122,489. This is

significantly less than the profits of $133.62 at the profit maximizing toll of $3.10. The

government and concessionaire should negotiate a BOT toll-setting arrangement between

these two bounds. To tap into private sector efficiencies, the government should maintain

attractive profit incentives for the private sector. At the same time, the government wants

to prevent the concessionaire from abusing its monopoly power. For example, the

Figure 4.16. Average time cost toll demand curve

10

200

q ( A l , B l , A 2 , B 2 , a , b , k , T V l ,TV2, f ,D ,n )

110

Page 119: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

government may grant the concessionaire a certain degree of pricing flexibility in

exchange for the concessionaire setting the price closer to the socially optimal level. This

could keep the public happy while still motivating the private sector with the possibility

for future profits.

Real options can be used to value varying degrees of flexibility. This will enable

BOT participants to better understand the nature of the tradeoffs they are making. For

example, consider a concessionaire operating under a fixed toll regime at the profit-

maximizing price p=$3.10. The government makes the following proposal: "Drop your

toll this year to $2.90 and we will give you complete toll-setting flexibility next year."

The concessionaire would lose $1.67 in current profits (^31-3t2.9=133.62-131.95 =1.67),

but would gain $2.44 in option value. The concessionaire should accept the government's

offer. However, if the government asked the concessionaire to drop its toll to $2.90 in

exchange for partial flexibility (i.e., increases limited to $0.10), the concessionaire

should decline because it would lose $1.67 in current profits, but only gain $1.59 in

option value.

In our scenario, the toll road happens to be profitable at the socially optimal

output. However, if the toll road had large,fixed costs relative to demand, it may lose

money at the socially optimal output. In such cases, the government traditionally tries to

make up for this shortfall by subsidizing the loss or by regulating the firm to charge a toll

covering average total operating costs. It may be difficult to attract the private sector to

manage an unprofitable infrastructure facility on a BOT basis. However, the possibility

of future toll-setting flexibility may entice the private sector to take on a facility which is

i l l

Page 120: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

currently unprofitable. The government may force the concessionaire to operate close to

the money-losing socially optimal output level for a certain period of time in the hope

that during this period, the efficiencies of the private sector concessionaire will transform

the toll road from a money-losing natural monopoly to a profitable economic activity.

The concessionaire may be willing to operate at an unprofitable output level for a period

of time in the hopes of being able to charge profit-maximizing tolls in the future By

dangling the "carrot" of toll-setting flexibility in front of the concessionaire, the

government may be able to inject BOT efficiencies and discipline into certain types of

infrastructure services while at the same time maintaining output close to the socially

optimal level. Real options can be used to value such "carrots".

4.2.8. Summary

The setting of tolls is often a source of friction in BOT projects. While

governments and concessionaires realize intuitively that flexibility in toll-setting has

value, there are few tools available to systematically quantify this value. In combination

with sophisticated transport demand modelling techniques, the real options method of

contingent claims analysis is well-equipped to tackle this problem. By identifying and

attempting to quantify elusive sources of value such as toll-setting flexibility, real options

valuation techniques provide important insight into the complex dynamics of value in

public-private partnerships.

112

Page 121: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

4.3. OPERATE/TRANSFER PHASE: OTHER BOT REAL OPTIONS

4.3.1. Introduction

In addition to toll-setting options, there are other real options during the operate

phase of a BOT toll road such as development gain options and options arising from

limited recourse project financing. Project financing also creates real options during the

build phase. At the transfer stage of a BOT project, real options can be used to analyze

the value of different transfer arrangements between the concessionaire, the government,

and third parties. This section presents a brief look at these types of BOT real options.

4.3.2. Development gain options

An important source of value in BOT projects is often the potential for

"development gain". Development gain refers to an arrangement in which a

concessionaire is given the exclusive right to develop ancillary facilities in return for

providing much needed, but perhaps unprofitable, infrastructure services. The giant

construction and real estate development company Hopewell Holdings of Hong Kong is

famous for taking this approach. The company has constructed toll roads in China on

condition that it have the right to develop real estate running alongside the roads. The

company has also worked on a $3.2 billion mass transit project in Bangkok (Bangkok

31

Elevated Rail and Transport System — BERTS) which involved the development of

real estate nearby stations. Another famous example involving development gain is the

Channel Tunnel. The tunnel operator Eurotunnel was granted first option on a concession

3 1 Cancelled by the Thai cabinet in September 1997 due to the Asian currency crisis. "Thai Cabinet Derails Hopewell transit project" Globe and Mail. October 1, 1997

113

Page 122: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

to operate a parallel road link and was also given the right to propose expansions to the

existing rail routes.32

BOT projects with the potential for development gain have option-like features. If

the government grants a concessionaire the exclusive right, but not the obligation, to

develop an ancillary facility, then the government has written a call option to the

concessionaire on the value of the ancillary facility. The flexibility inherent in such

arrangements can profoundly affect the value of BOT projects. For example, imagine

that the government makes the following offer: "If you build and operate toll road X, we

will give you the exclusive right to develop a shopping mall alongside toll road X next

year." For simplicity assume the toll road can be built and brought into operation in one

year. After calculating all the build and operate options, the expanded NPV of the toll

road project turns out to be a paltry $5 million. On an investment of $100 million, this

return of 5% is not very attractive. However, we must also include the value of the option

to develop a shopping mall. Suppose the value of the shopping mall next year moves as

shown in figure 4.16. The risk-free interest rate is 5%, w=1.5 and d=l/l.5. The risk-

neutral probabilitiesp* are also shown in figure 4.17. The cost of developing the

shopping mall next is 100. For simplicity, assume we pay 100 and receive the value of

33 the project instantly .

The expanded NPV of this investment opportunity is:

"Second Channel tunnel proposed: Road link would parallel rail route." Globe and Mail. December 30, 1997 3 3 In reality, there is of course a delay between when we exercise this real option and when we receive the value from exercising the option.

114

Page 123: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

Figure 4.17 Movements in shopping mall value

p*= 0.46 150 max(150-100,0)=50

100

p*= 0.54 67 max(67-100,0)=0

shopping_ exp_ NPV — (0.46) x 50+(1-0.46) xO

1.05 = 21.9

Adding our shopping mall expanded NPV of 21.9 on to our toll road without

development gain expanded NPV of 5 substantially increases the expanded NPV and the

expected net return for our overall involvement in the project.

Note that if we were obligated to develop the shopping mall under money losing

conditions (67-100=-33), our static shopping mall investment opportunity would only

be,

The option not to develop the shopping mall is worth 16.97 (21.9-4.933) and contributes

significantly to the overall value of our toll road project with development gain.

4.3.3. Financial flexibility

shopping _static _NPV = (0.46) x 50+(1-0.46) x (-33)

1.05 = 4.933

115

Page 124: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

Project finance is the backbone of BOT projects. Limited recourse project

financing was originally developed in the oil industry, but is now common in many other

industries. Project financing can be defined as:

"A financing of a particular economic unit in which a lender is satisfied to look

initially to the cash flows and earnings of that particular economic unit as the source of

funds from which a loan will be repaid and to the assets of the economic unit as

collateral for the loan"34

BOT projects are typically financed by mezzanine capital which is a mixture of

equity and limited recourse debt of varying seniority. Projects such as toll roads which

are exposed to market risks tend not to exceed 60-65% debt leverage35. The introduction

of debt financing gives the concessionaire the option to default on debt payments. This

option has value as illustrated by the following example.

Consider a BOT toll road which involves a cash outlay of 100 million at time

zero to receive cash flows at year one. The project which currently has a value of 100

million will have a value of either 170 million or 59 million (w=1.7,/>*=0.415) at year

one. Under complete equity financing, the NPV of this project is zero. However, if 60

million of the time-zero 100 million outlay is project financed with debt at an interest

rate of 12%, then the equity holders must put up 40 million of their own at time zero and

pay the debtholders 67.2 (60x1.12) million at year one. The expanded NPV of the project

with the option to default becomes:

NevittK.P. Project Financing. Euromoney Publications, London, 1989 (reprint), p. 13 United Nations Industrial Development Organization. UNIDO BOT Guidelines 1996. p. 185

116

Page 125: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

ENPV_def = (0.415) x max(170 - 67.2,0) + (1 - 0.415) x max(59 - 67.2,0)

1.05 _ 40 = 0.63

The right under limited liability to default and surrender the projects assets to debtholders

has given this project a positive NPV.

Financial flexibility may interact with operating flexibility. Take the previous

example and imagine that construction expenditures are made in two installments. We

pay $60 million in year zero and then $40 million in year one to receive the year one

value of the firm (either 170 or 59). Equityholders now have the financing option to

default on the loan payment and the operating option not to make the required $40

million year-one expenditure to complete the project. The expanded NPV with these two

options is,

In this case, the value of the investment opportunity with both operating and financial

flexibility is substantially greater than the investment opportunity with only financial

flexibility.

BOT financing arrangements are often extremely complex as governments,

export credit agencies, international agencies such as the World Bank and the IMF,

construction companies, contractors, banks, and investment funds can all end up having

both debt and equity stakes in a project. Ideally, BOT financing arrangements should be

able to change during the life cycle of the project so as to reflect its changing risk profile.

ENPV_op_def = (0.415) x max(170 - 67.2 - 40,0) + (0.585) x max(59 - 67.2 - 40,0)

1.05 = 24.8

117

Page 126: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

Creating financial flexibility through project finance plays a crucial role in achieving this

goal. In the words of Lenos Trigeorgis:

"...the flexibility to actively revalue the terms of a financing deal to better match

the evolution of operating project risks, whether increasing or decreasing, as the project

moves into its various stages creates value..."36

4.3.4. Transfer options

The transfer phase of BOT projects is still largely uncharted territory. This is

because most BOT projects are relatively young and no one is sure what will happen at

the end of a twenty or thirty year concession period. There are several possible transfer

arrangements:

1. concessionaire turns over the facility to the government for free and the government

manages the facility

2. concessionaire must bid on equal footing against other potential operators if it wants

to continue operating the facility

3. concessionaire turns over the facility to the government for a predetermined price

4. concessionaire turns over the facility to the government for its market value at the

time of transfer

5. concessionaire has the option to pay a specified value to continue operating the

facility

Most BOT transfer stages are type 1 or 2 arrangements which don't have any

option-like features. In type 3 arrangements the government has essentially sold the

3 6 Trigeorgis, Lenos. "Real options and interactions with financial flexibility." Financial Management 22 1993p.219

118

Page 127: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

concessionaire a bullet bond (i.e., one payment at maturity). The price of this "bond" is

the present value of the termination payment discounted at the government borrowing

rate. The concessionaire could pay for this "bond" through higher taxes or lower tolls,

whichever the government feels is socially optimal. -

Type 4 transfer arrangements have no option-like features and the concessionaire

should be willing to pay the expected residual value discounted at the appropriate risk-

adjusted rate. Again, there are various ways the concessionaire could pay for this

arrangement, some of which may improve social welfare more than others.

A type 5 transfer arrangement involves the government writing a call to the

concessionaire on the residual value of the facility with the predetermined price as the

exercise price. At the time of transfer, the government owns the facility, but must sell the

facility back to the concessionaire if the concessionaire wishes to exercise its option (i.e.,

if the residual value exceeds the strike price). The premium of this call could be

determined using option pricing techniques, although long maturities and difficulties in

modelling the stochastic nature of the underlying asset (toll profits) may pose some

problems. It is interesting to consider the implications of allowing trading in this option

before its maturity date. Could an option market emerge for residual values of BOT toll

roads?

4.3.5. Summary

While this section has provided a cursory treatment of development gain options,

financial flexibility, and transfer options, the brevity of the discussion by no means

119

Page 128: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

indicates that these options are unimportant. A large part of a BOT project's value may

be derived from these options, especially development gain options and financial

flexibility. By valuing these different types of flexibility, governments, financiers, and

concessionaires will be better equipped to create BOT projects which effectively meet the

needs of the public and private sector.

120

Page 129: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

CHAPTER F I V E

CONCLUSION

Page 130: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

CONCLUSION

The goal of this thesis was to show how real option valuation techniques can

provide insight into the complex dynamics of value in BOT toll road projects. BOT toll

roads are a promising part of the infrastructure revolution, yet they are fraught with new

uncertainties and risks. As policy-makers and investors struggle to understand the nature

of BOT risk-reward tradeoffs, they are finding that traditional methods of capital

budgeting are ill-equipped to analyze many important sources of value in a BOT project

such as the option to alter construction plans, the option to change tolls, the option to

develop ancillary facilities, the flexibility created by project financing, and the options

involved in transferring the facility. The real options approach promises to give policy­

makers and investors a deeper understanding of the nature of value in BOT toll road

projects.

This thesis has a presented a simplified discussion of the mechanics of real option

valuation in a discrete time framework. In the field of financial economics, there are

many sophisticated continuous-time mathematical models which can be used to price real

options. Such models were beyond the scope of this thesis, yet an understanding of them

is crucial to the actual implementation of real option pricing. It is hoped that financial

economists will turn their attention to the emerging BOT market as an area in which they

can test and fine-tune their valuation techniques. Furthermore, it is hoped that they will

continue to proselytize the real options revolution in a manner which is accessible to

politicians, bureaucrats, investment bankers, and engineers alike.

Page 131: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

On the transport side, it is hoped that transport economists will begin to analyze

infrastructure projects within a real options framework. Such an approach will enhance

their understanding of the economic tradeoffs created by public-private partnerships.

While real options may seem rather esoteric to many currently involved in BOTs,

they have the potential to make significant contributions to the understanding of BOTs

and P3s. It is hoped that this thesis points the way to further research fusing the fields of

transport economics and financial economics. The synergies from the convergence of

these two academic disciplines will undoubtedly pave the way to exciting new

developments in the world of transportation infrastructure.

123

Page 132: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

6. BIBLIOGRAPHY

Public-Private Partnerships and Build-Operate-Transfer

• "A pioneer on hold." Asiamoney. Dec. 1994/Jan. 1995 p.58

• "A long and winding road." Asiamoney. Sep. 1993 p. 65

• "Are Asian Projects all that enticing?" Euromoney. Jan. 1994. p. 92-92

• Augenblick, M. and Scott-Custer, B. The BOT approach to infrastructure projects in developing countries. World Bank Working Paper, August 1990

• Bond, Gary and Carter, Laurence. Financing Private Infrastructure Projects-Emerging Trends for IFC's Experience. IFC Discussion Paper 23, The World Bank. 1994

• British Columbia. Task Force on Public-Private Partnerships. Building Partnerships: report of the Task Force on Public-Private Partnerships. Crown Publications, Oct. 1996

• "For whom the road tolls." Asiamoney. Mar 1994. p. 53

• Fox, William F. Strategic options for urban infrastructure management. Urban management programme UNDP/UNCHS/World Bank. Washington D.C. 1994

• HM Treasury. Private opportunity, public benefit: progressing the private finance initiative. 1995

• Israel, Arturo. Issues for infrastructure management in the 1990s. World Bank discussion papers; 171. Washington D.C 1992

• Kessides, Christine. Institutional options for the provision of infrastructure. World Bank discussion papers; 212. Washington D.C. 1993

• Lall, Ashish and Tay, Richard. "Private Provision and Financing of Infrastructure in ASEAN." Logistics and Transportation Review. March 1996

• Levy, Sidney M. Build, operate, transfer: paving the way for tomorrow's infrastructure. J. Wiley & Sons. 1996

• Nevitt, K.P. Project Financing. Euromoney Publications, London, 1989 (reprint)

• OECD. Infrastructure Policies for the 1990s. Paris. 1993

124

Page 133: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

• Scurfield, R.G. The private provision of transport infrastructure. World Bank, 1992

• "Second Channel tunnel proposed." Globe and Mail. Dec. 30, 1997

• "Thai cabinet derails Hopewell transit project." Globe and Mail. Oct. 1, 1997

• Tiong, R. "Impact of Financial Package Versus Technical Solution in a BOT Tender." Journal of Construction engineering and management. Sept. 1995, p.304-310

• Tiong, R. "Comparative Study of BOT Projects." Journal of Management in Engineering. Vol. 6 No.l Jan. 1990, p.107

• Tiong, R. "Critical Success Factors in Winning BOT Contracts." Journal of Construction Engineering and Management. Vol. 118, No. 2, June 1992, p. 217-228

• Tiong R. The structuring of BOT construction projects. (Construction Management?) (technological monograph, Nanyang Technological University, Singapore, 1992)

• Tiong, R. "BOT projects: risks and securities." Construction management and economics. E. & FN. Spoon. 1990. 8. 315-328.

• United Nations Industrial Development Organization. UNIDO BOT Guidelines

• Walker, C. and Smith, A.J. editors. Privatized infrastructure: the BOT approach. Thomas Telford Publication. 1995

• Wahdan, Mohamed Y., Russell, A.D., and Ferguson, D. "Public Private Partnerships and Transportation Infrastructure" paper presented at 1995 Annual Conference of the Transportation Association of Canada, Victoria, British Columbia.

• World Bank, Infrastructure for Development. Oxford University Press, New York, World Development Report 1994

Real Options

• Berk, Jonathan, Green, Richard C , and Naik Vasant. "Valuation and Return Dynamics of R&D Ventures", working paper 1997

• Black, F. and Scholes, M., "The Pricing of Options and Corporate Liabilities," Journal of Political Economy May/June 1973, pp. 637-659

125

Page 134: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

• Brealey, R., and Myers S.C. Principles of Corporate Finance, fourth edition. McGraw-Hill. 1991

• Cox J., Ross S., and Rubinstein M., "Option Pricing: A Simplified Approach," Journal of Financial Economics, September 1979, pp. 229-263

• Dixit, Avinash K. and Pindyck, Robert S., Investment Under Uncertainty. Princeton University Press 1994

• Grenadier, Steven R. and Weiss, Allen M., "Investment in technological innovations: An option pricing approach." Journal of Financial Economics 1997

• Hayes and Abernathy,W. "Managing Our Way to Economic Decline," Harvard Business Review. July-August 1980

• Hodder and Riggs, H. "Pitfalls in Evaluating Risky Projects," Harvard Business Review. January-February 1985. pp. 128-135

• Kensinger, John W. "Adding the value of active management into the capital budgeting equation." . Midland Corporate Finance Journal 5, 1987 Spring 31-42

• Kolb, Robert W., Futures, Options and Swaps. Blackwell Publishers 1997

• Luehrman, Timothy A. "Capital Projects as Real Options: An Introduction" Harvard Business School class note. 1994

• Majd, Saman and Pindyck, Robert S., "Time to build, option value, and investment decisions." Journal of Financial Economics 18 (March) 1987: 7-27

• Merton, "Theory of Rational Option Pricing," Bell Journal of Economics and Management Science Spring 1973, pp. 141-183

• Morck, Randall, Schwartz E., and Stangeland D. "The Valuation of Forestry Resources under Stochastic Prices and Inventories. " Journal of Financial and Quantitative Analysis 24 (December) 1989: 473-487

• Myers, "Finance Theory and Financial Strategy," Midland Corporate Finance Journal, Spring 1987, pp. 6-13

• Neftci, Salih N., An Introduction to the Mathematics of Financial Derivatives. Academic Press 1996

• Siegel, Daniel R., Smith, James L. and Paddock, James L. "Valuing offshore oil properties with option pricing models." Midland Corporate Finance Journal 5, 1987

126

Page 135: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

Spring 22-30

• Trigeorgis, Lenos. Real Options MIT Press 1997

• Trigeorgis, Lenos. "Real options and interactions with financial flexibility." Financial Management 22 1993, no.3. 202-224

• Trigeorgis, Lenos and Mason, S.P. "Valuing managerial flexibility." Midland Corporate Finance Journal 5, 1987 Spring. 14-21

• Wilmott, Paul. et. al. The Mathematics of Financial Derivatives: A Student Introduction. Cambridge University Press 1997

Transportation Economics

• Bureau of transport and communications economics. Traffic congestion and road user charges in Australian capital cities. Australian Government Publishing Service, 1996.

• Gujarati, D.N. Basic Econometrics. Second Edition. McGraw-Hill Publishing Company. 1988

• Mohring, Herbert. Transportation Economics. Ballinger Publishing Company 1976

• Oum, Tae Hoon, et. al. Transport Economics: Selected Readings. Korea Research Foundation For the 21st Century.

• Waters, W.G., "The Value of Time Savings for the Economic Evaluation of Highway Investments in British Columbia" Centre for Transportation Studies, University of British Columbia. 1992

• Varian, Hal R. Intermediate Microeconomics. Second Edition. W.W. Norton & Company. 1990.

127

Page 136: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

APPENDICES

128

Page 137: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

APPENDIX I P 3 T O L L ROADS AND BRIDGES AROUND THE WORLD

3 '

The following is a sampling of the P and BOT projects being developed around

the world:

CANADA:

• Highway 407: A 35-year concession granted by the Ontario government to Canadian

Highways International Corporation (a consortium led by Monenco AGRA Inc) in

1994 to design, build, operate and maintain a new C$1.7 billion, 69 km toll highway

project north of Toronto. Financing largely arranged by the Ontario Financing

Authority.

• Highway 104: C$120 million toll highway in Nova Scotia. Concession period tied to

the length of time needed to repay money borrowed. Funding from federal-provincial

highway program and Newcourt Credit Group.

• Northumberland Strait Bridge: An C$840 million, 35-year BOT fixed-link to

replace ferry service between Prince Edward Island and New Brunswick.

• Lion's Gate Bridge: negotiations for a new P3 tunnel or bridge to replace the aging

Lion's Gate Bridge are underway.

UNITED KINGDOM

• Birmingham North Relief Road: England's first toll road built by a joint-venture

between Trafalgar House and Iretecria.

• Queen Elizabeth II Bridge (also known as the Dartford Crossing): a toll bridge

spanning the Thames river east of London. Built and financed by Dartford River

Crossing Ltd. (DRC) a joint venture between Trafalgar House and Bank of America.

129

Page 138: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

• Skye Bridge: a toll fixed link to the Isle of Skye in Scotland.

• Second Severn Crossing: A U.S. $549 million toll bridge linking England and

Wales.

• Channel Tunnel Crossing: U.S. $12 billion dollar tunnel between England and

France. Concession granted to Euromnnel (10 U.K. and French contractors and

banks) for 55 years.

ASIA:

• North-South Highway (Malaysia) : U.S. $1.8 billion, 30-year concession led by

United Engineers. Noted for government guarantees against revenue short falls due to

adverse exchange rate and interest rate movements.

• Sydney Harbour Tunnel (Australia) : U.S. $540 million, 35-year BOT toll tunnel

concession granted to joint venture between Transf ield Pty Ltd. and Kumagai Gumi.

• Second Stage Expressway (Thailand) : U.S. $880 million, 30-year toll road

concession in Bangkok initially granted to Bangkok Expressway Company Limited

(BECL) consortium led by Kumagai Gumi. Notorious for controversy over how to

share tolls between BECL and the government. Ambiguities over whether the project

was BOT or BTO also caused many headaches.

• Eastern Harbour Crossing (Hong Kong) : U.S. $442 million BOT toll tunnel by

Japanese construction giant Kumagai Gumi.

• Western Harbour Tunnel (Hong Kong) : U.S. $790 million toll tunnel built by

Kumagai Gumi-Nishimatsu Construction Co. Ltd. joint venture.

130

Page 139: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

• Guangzhou Superhighway (Hong Kong-China) : U.S. $1.5 billion 304 km toll

road connecting Hong Kong and Guangzhou built by Hong Kong's construction giant

Hopewell Holdings.

• Indonesian toll roads: many BOT toll roads controlled by Suharto's family.

LATIN AMERICA

• Autopista del Sol (Mexico): U.S. $1.3 billion BOT Cuernavaca-Acapulco toll road

joint venture between Mexican construction firms Grupo Mexicano de Dessarrollo

(GMD), ICA, and Tribasa. Dubbed "headache highway" due to construction cost

overruns and lower than expected demand. Initial concession period of 14 years

extended to 30 years.

• Mexico City-Toluca toll road (Mexico): U.S. $313 million, 10-year concession to

Tribasa. Financing arranged by Lehman Brothers.

• Argentina, Brazil, Chile, and Columbia: actively promoting P3s and BOTs in their

transport sector.

UNITED STATES

• Dulles Greenway: part of a road privatization program in Virginia

• Caltrans (California Department of Transportation): experimenting with the

BTO approach for toll roads.

I

131

Page 140: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

APPENDIX II. VALUE OF TRAVEL TIME SAVINGS (VTTS)

The importance of VTTS to transport economics

Travellers must sacrifice their time to consume a transportation service. The

monetary value of a traveller's time is the subject of much research and debate in the

field of transport economics. Unlike other economic activities, transportation requires

that consumers also act as suppliers because they must provide a substantial amount of

their own time to consume a transportation service. In transport economics, the

characteristics of consumers are reflected in both the demand curve and the supply curve.

The demand curve shows how much a traveller is willing to pay in out-of-pocket'

expenses and value of time to get to a certain destination. The supply curve shows the

operating costs of the supplier plus the time costs of the users. An understanding of how

people value their travel time is thus crucial to any transport demand-supply analysis.

Evaluating VTTS

There are theoretical reasons to expect the value of travel time to be related to

wage rates. For people with high wages, the opportunity costs of being stuck in traffic are

higher and they may be willing to pay more to travel faster. There are a number of

empirical approaches which can be used to estimate people's value of travel time savings.

These approaches can be broadly categorized as "revealed preference" and "stated

preference".

Revealed preference (RP)

Revealed preference looks at how people make time-money tradeoffs. There are

three major markets in which time-money tradeoffs can be indirectly observed: j

132

Page 141: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

• Choice of speed market: By driving faster, travellers can reduce their travel time.

However, driving faster also raises operating costs and increases the chances of

receiving a speeding ticket or getting into an accident. By looking at how drivers

choose their speed given this speed-cost tradeoff, we can impute their implied value

of travel time. Of course, this approach is undermined by the questionable

assumption that drivers fully understand the nature of the speed-cost tradeoff.

• Choice of location market: Homeowners face a tradeoff between property values and

accessibility to the central business district (CBD). By examining the relationship

between property values and distance to the CBD, we can get an idea of how people

value travel time. However, there are many other factors which influence the location

decision and these tend to cloud the analysis.

• Choice of mode and route choice: A majority of RP studies are of this type. We

impute people's value of travel time by looking at how they choose between modes

with different travel times and different costs (i.e., a fifteen minutes bus trip which

costs $1.50 versus a five minute car trip which costs $3.00 in gas and parking).

However, it is often difficult to separate travel time from other factors which

influence, choice such as comfort and convenience.

Stated Preference (SP)

Stated preference asks people directly how they value travel time. Carefully

designed surveys with built-in cross-checks for accuracy are used to elicit people's value

of travel time. While there is a danger of bias in questionnaires, they have an advantage

in that they can distinguish the effects of time from other factors such as comfort and

133

Page 142: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

convenience. Improvements in the design of questionnaires have led to a greater reliance

on SP methods in recent times.

Empirical results

Looking at the results from these empirical methods, there appears to be several

factors which influence how people value travel time:

• Trip purpose: Work trips are generally valued at an employee's full wage rates. This ^

makes sense because an hour less travel on the job translates into an hour more

productive work. Non-work trips such as commuter and leisure trips tend to be

valued below the wage rate. There are substantial differences among the estimates of

appropriate wage rate percentages, although most estimates range between 25-40%37.

• Personal characteristics of the traveller: Personal attributes such as age, sex, family

structure, cultural background, and income can affect VTTS. Of these, the effects of

income level appear to be the most compelling. There is some evidence which backs

the following relationship between income (Y) and VTTS 3 8 :

VTTSr =l^xVTTSavg

where Yavg is the mean income level and VTTSavg is the VTTS for the average

income. In other words, VTTS rises with income, though not proportionally.

• The size of time savings: People are unable to do much with a few seconds saved.

Therefore, people should value small blocks of time saving proportionally less than

37 I

Waters, W.G., "The Value of Time Savings for the Economic Evaluation of Highway Investments in British Columbia" Centre for Transportation Studies, University of British Columbia. 1992. p. xii 38 Ibid. p. xiii

134

Page 143: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

large blocks. In other words, one second saved by one thousand people should be

valued differently to one hundred seconds saved by ten people. The evidence on this

issue is conflicting and it is still the subject of much debate.

While the above methods are far from an exact science, they nevertheless play an

important role in the evaluation of transport projects. For simplicity, many transport

projects are evaluated using a homogeneous VTTS or a weighted average VTTS 3 9 .

However, this thesis proposes that such a simplification glosses over important

characteristics of the process which determines transport demand. Our multi-VTTS

model attempts to rectify this problem.

Mohring, Herbert. Transportation Economics. Ballinger Publishing Company 1976. Ch. 4

135

Page 144: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

APPENDIX III TRAFFIC CONGESTION FUNCTIONS

Congestion functions attempt to describe the relationship between traffic volume

and speed. Roads are designed with a capacity to handle a certain level of traffic at a free

flow rate. As traffic volume approaches road capacity, drivers must slow down to avoid

accidents. However, the manner in which drivers decrease their speed as traffic volume

increases is by no means clear and depends on the type of road, the road conditions, and

the nature of the drivers themselves. Engineers have long struggled to establish empirical

relationships between traffic flow and traffic speed. However, the results have been

weak. .

For our study, we follow the approach of the Australian Bureau of Transport and

Communications Economics (BCTE) and adopt the Kimber and Hollis (1979) model.

This function handles "random fluctuations in traffic flow below capacity, the effect of

overcapacity traffic flows of finite duration, and provides a smooth transition between

the two regimes."40 The function has the form:

K =t„x l + a((jc-l)+V(x-l)2 +&c)J where,

ta = average travel time per kilometre

t0 = free speed travel time per kilometre

x = volume-capacity ratio

a and b are parameters which describe the type of road

40 Bureau of transport and communications economics. Traffic congestion and road.user charges in

Australian capital cities. Australian Government Publishing Service, 1996 p.79

136

Page 145: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

The parameters a and b are estimated empirically and can be adjusted to reflect

different road types. In figure III.l, we use BCTE estimates to show how different types

of roads have different congestion characteristics. The jc-axis shows the volume-capacity

ratio while the_y-axis shows how many minutes it takes to travel one kilometre at each

level of traffic. The congestion curve for a highway with a free speed of 100 km/hr uses

a=31.26 and Z?=0.0004. The congestion curve for a central business district street with a

free speed of 30 km/hr uses a=9.26 and &=0.0350. The CBD congestion function is

smoother indicating that drivers make less dramatic adjustments to increasing traffic

density. This is because they are already driving at a low speed and less likely to panic at

a sudden increase in volume.

Figure III.l. A congestion function for a highway and a central business district street

I I 1 27 -24 / / 21

if H i g h w a y _ t a ( t o h , a h , b h , x ) 18 — t i ­

ll 15 - y r -

C B D - t a ( t o c . a c - b c x ) 1 2 _ / /

J I

9 ~~ ' / 6 J j 3 — ' /

——4-̂ —W 1 0 0 0.5 1 1.5 2

X

While a number of traffic flow functions (Davidson 1978, Akcelik 1978, Taylor

1984, Tisato 1991) have been developed, we choose Kimber and Hollis's model for its

robustness and proven track record.

137

Page 146: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

APPENDIX IV

MATHCAD PROGRAM TO CALCULATE MULTI-VTTS TOLL DEMAND CURVE

138

Page 147: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

VARIABLES

Congestion function

a =25 b=.00089 k =400 D =20 f =60 y =50

1 -ha- k / A \k 1 ^•D-TV

Group 1: High income

Al=10 Bl=100 TV1 =5 freeflowTC1 Tfl(TVl) = y - D T V l

Group 2: Low income

A2=5 B2=120 TV2=1 freeflow TC2 Tf2(TV2) = y-D-TV2

Solving for maximum values of q1 and q2. The quantity from any group cannot exceed the point where the group's demand curve equals its average time costs. Beyond this point (WTP<ATC), the model becomes unstable.

High income quantity limit

H(Al ,Bl ,a ,b ,k ,TVl , f ,D,y) 1 -ha- : - l + 1 +b- j - D - T V l A l - ^ - y

solHCAl.Bl.a.b.k.TVl.f.D.y) :=root(H(Al,Bl,a,b,k,TVl,f,D,y),y)

solH(Al,Bl,a,b,k,TVl,f ,D,y) =83.287

Hlimit ^solHCAl.Bl.a.b.k.TVl.f .D.y)

Low income quantity limit

L(A2,B2,a,b,k,TV2,f,D,y) 1 + a- 1 + 1 +b- •D-TV2 A 2 - B 2 - y

solL(A2,B2,a,b,k,TV2,f,D,y) :=root(L(A2,B2,a,b,k,TV2,f,D,y),y)

solL(A2 )B2 )a,b,k JTV2,f,D,y) =111.969

Llimit =solL(A2,B2,a, b,k,TV2,f,D,y)

139

Page 148: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

THE MULTI-VTTS DYNAMIC PROCESS

Determine equilibrium total traffic quantities for the following toll prices

p 10,9.9..0

Number of iterations n=10

qT=

i^O

qTi ;-if^

qT2.<-if

(Al - p - Tfl(TVD)

(A2 - p - Tf2(TV2))

Bl

A l

B2

A2

>0,

>0,

(Al - p - Tfl(TVD)

(A2 - p - Tf2(TV2))

Bl

A l

B2"

A2

i ^ i + 1

q T l . ^ if(qTl. <HlimitqTl.,Hlimit)

qT2.<- if(qT2. <LlimitqT2., Llimit)

q T . ^ q T l 0 + q T 2 0

ETC 1. _ x <- Tf 1 (TV 1)

ETC2_1*-Tf2(TV2)

TCI i - 1

TC2. i - 1

l + a-

l + a-

^____

[ k

^ i - i

1 +

1 +

D-TV1

D-TV2

diffl. ,^ETC1. - T C I . , l - l i - l i - l

diff2 , ^ E T C 2 - TC2. , i - l i - l i - l

qTl.^if (qTl. , + diffl. • — ] >0, qTl. 1 + diffl. •—1,0 . - 1 ' - l A l 1 - 1 1 - 1 A l '

qTl.^if^qTl.<HlimitqTl.,Hlimitj, .

qT2^iff (qTZ_ t + diff2_ 1 J | ) >0, (qT2;_ x + difK_ ,0

qT2.<- if ̂ qT2. <Llimit qT2., Llimit)

qT.^-qTl. + qT2.

for ie 2..n

E T C l . _ j . - T C l . _ 2

ETC2 ,^TC2. , i - l 1 - 2

Page 149: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

TCI i - 1

TCZ. i - 1

1 + a-

1-j-a-

( q T i - i

\ k

If,-,

1 -t- b •D-TV1

•D-TV2

diff 1. ,<- E T C ! , - TCI. , l—l i — i i - i

diff2 _ l <- ETC2 _ j - TC2. _ x

R1\ / R1 q T l r if] (qTL_ t + d i f f l , >0, qTl._ 1 + d i f f L , , — J.0

qTl.^Hlimit if qTl >Hlimit

qT2.«-ifj R2\ / R? qT2. 1 + diff2 • — >0, • qT2. , + diff 2 , ),0

i - i ' - i A 2 A2> qT2.^- Llimit if qT2.>Llimit

qT.̂ -qTl.-t-qT2.

Page 150: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

Toll demand curve and profits for B1 =100

50 100 150

q ( A l , B l , A 2 , B 2 , a , b , k , T V l , T V 2 , f , D , n )

200

P

4 J3 3JS 3J_ 3^ 35 JA 33 32

H T J3 2J8

2 7

2L6

25

Profits(Al,Bl,A2,B2,a,b,k,TVl,TV2;f,D,n )FC,VO

107.5 113.12 118.061 122.3221

125.904 128.80(4 131.029" 132.57i 133.4361

133.62 133.125 131.95 130.096 127.5631

124.35 120.45.

200

P ro f i t s (A l ,B l ,A2 ,B2 ,a ,b , k ,TV l , T V 2 , f , D , n , F C , V C ) o h

-200'

142

Page 151: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

Toil demand curve and profits for B1 =200

10

p s h

50 100 150 200 250

q ( A l , B l , A 2 , B 2 , a , b , k , T V l ,TV2, f ,D ,n)

300

P

4 3̂ 9 3̂ 8 3.7 3̂ 6 35 3A 33 32 3A 3_

2~9 2]8 27 2̂ 6 25

Profits( A l , B l , A2, B2, a, b, k, TV1, TV2, f, D, n, FC, V O

258.779* 263.457 267.253 270.174 272.21$ 273.377 273.66 273.064 271.589* 269.23$ 266.00J 261.892* 256.903̂ 251.035 244.289̂ 236.66$

500

'P ro f i t s (A l ,B l ,A2 ,B2 ,a ,b , k ,TV l , T V 2 , f , D , n , F C , V C ) 0 h

-500'

143

Page 152: VALUING FLEXIBILITY IN BUILD-OPERATE-TRANSFER (BOT) …

Toll demand curve and profits for B1 =50

50 ' , 1 0 0 150

q ( A l , B l , A 2 , B 2 , a , b , k , T V l ,TV2, f ,D ,n)

200

P 4

J3 3^ 37 3̂ 6 3̂ 5

M 33 32

T 2$ 2& 2.7 2~6 2.5

Profits( A l , B l , A2, B2, a, b, k, TV1, TV 2, f, D, n, FC, V O

31.76? 37.8571

4336? 48.29? 52.6481

56.418 59.609 62.22 64.252 65.7041

66.5761

66.8681

66.581 65.714* 64.2671

62.2411

ioo

Pro f i t s (A l ,B l ,A2 ,B2 ,a ,b , k ,TV l , T V 2 , f , D , n , F C , V C )

-200'

144