Solutions Guide: Flexible Storage Systems with Intel SSR212MC2 and Open-E Data Storage Server
Valuing Energy Storage as a Flexible Resource...Valuing Energy Storage as a Flexible Resource –...
Transcript of Valuing Energy Storage as a Flexible Resource...Valuing Energy Storage as a Flexible Resource –...
Valuing Energy Storage as a Flexible Resource
Final Phase 1 Report for Consideration in CPUC A. 14-02-006 June 19, 2014
© 2010 Copyright. All Rights Reserved.
Energy and Environmental Economics, Inc.
101 Montgomery Street, Suite 1600
San Francisco, CA 94104
415.391.5100
www.ethree.com
Valuing Energy Storage as a Flexible Resource Final Phase 1 Report for Consideration in CPUC A. 14-02-006 June 19, 2014
Table of Contents
1 Introduction ............................................................................................ 1
2 Overgeneration is a key challenge ..................................................... 3
2.1 Flexibility challenges............................................................................. 3
2.2 How soon will overgeneration occur? ............................................... 5
2.3 Magnitude of overgeneration .............................................................. 7
2.4 Increase in overgeneration under high RPS scenarios ................. 9
2.5 Frequency of overgeneration (under 40% RPS) .......................... 10
2.6 Duration of overgeneration................................................................ 12
3 Renewable Curtailment........................................................................ 13
3.1 Managing overgeneration has significant value ............................ 14
3.2 Energy storage can reduce renewable curtailment ...................... 16
4 Overgeneration requires long-duration solutions ........................... 17
5 System level cost-benefit analysis is crucial ................................... 19
5.1 Comparing value of short- and long-duration ................................ 19
5.2 Small market for frequency regulation ............................................ 20
5.3 Serial dispatch of short-duration ...................................................... 22
5.4 Production simulation understates flexibility need and value ..... 22
6 Benefits of a diverse portfolio ............................................................ 24
7 Conclusions .......................................................................................... 25
Appendix A: Cost of Renewable Curtailment .......................................... 27
7.1 Avoided RPS Costs ............................................................................ 27
Interim Report
P a g e | 1 |
Introduction
© 2010 Energy and Environmental Economics, Inc.
1 Introduction
Energy and Environmental Economics (E3) produced this report to briefly summarize key
issues that are critical to consider when analyzing the potential benefits of energy
storage. E3 is pleased to provide this report for parties to consider in the California
Public Utilities Commission (CPUC) preceding considering the applications of PG&E, SCE
and SDG&E (A. 14-04-006) for approval their respective energy storage procurement
framework and programs as required by D. 13-10-040. This document, dated June 19,
2014, contains some revisions and added material to the interim report filed on June
12th. The overall conclusions remain unchanged.
The impetus for this report grew out of discussions between E3 and several parties to
the CPUC proceeding after the June 2, 2014 Workshop on IOU Energy Storage
Procurement Applications and during the 2014 Annual Energy Storage Association
Conference in Washington D.C. June 3-6, 2014. We discussed the methods described for
utility evaluation of energy storage project proposals and for the Common Evaluation
Protocols. Throughout the week we shared our thoughts about how those methods may
not fully capture the value of energy storage with the higher penetrations of renewable
generation anticipated and planned for in California.
In January 2014 E3 published the report “Investigating a Higher Renewables Portfolio
Standard in California” on behalf of PG&E, SCE, SDG&E, SMUD and LADWP (Utility High
RPS Report).1 Using E3’s stochastic production simulation model REFLEX, E3 quantified
the flexibility needs of the California grid under 40 and 50% RPS scenarios.2 REFLEX is
specifically designed to investigate flexible capacity needs and value with variable
renewable resources (VER). REFLEX performs random draws of weather-correlated
1 “Investigating a Higher Renewables Portfolio Standard in California”, Energy and Environmental Economics, January 2014. https://ethree.com/documents/E3_Final_RPS_Report_2014_01_06_with_appendices.pdf 2 See https://ethree.com/public_projects/reflex.php
Valuing Energy Storage as a Flexible Resource – Interim Report for Consideration in CPUC A. 14-02-006
P a g e | 2 |
load, wind, solar and hydro conditions taken from a very large sample of historical and
simulated data. It characterizes the need for system ramping capability through
stochastic treatment of load, wind and solar generation, hydropower conditions,
dispatchable generator outages and other random variables on multiple time scales:
annual, monthly, diurnal, hourly and sub-hourly. The model uses optimal unit
commitment and economic dispatch to model the ability of the system’s dispatchable
resources to respond to a full range of conditions. Flexibility violations such as
shortages in upward or downward ramping capability are characterized according to
their likelihood, duration and depth, using metrics that are analogous to conventional
reliability metrics such as LOLP, Loss of Load Probability Expectation (LOLE), and
Expected Unserved Energy (EUE).
REFLEX employs an economic framework to evaluate the costs and benefits of
investments in flexible resources. In order to determine whether investments in new
flexible resources are cost-effective, flexibility violations are assigned cost penalties
based on their economic value. New resources are then tested for their ability to
prevent flexibility violations and avoid the associated cost penalties. The capital and
operating costs of new flexible resources are compared to the value of flexibility
violations they avoid, ultimately identifying a least-cost portfolio of new resources. This
framework can be used to evaluate flexible resources such as combustion turbines,
reciprocating engines, energy storage, or demand response, as well as changes in
operating procedures such as improved forecasting, participation in a regional market,
or renewable curtailment.
The Utility High RPS Report and subsequent work using the REFLEX model have
produced results demonstrating how specific costs, benefits and input assumptions can
dramatically impact the valuation of energy storage as a flexible resource. This report
presents several of the more important findings for your consideration as the CPUC
Interim Report
P a g e | 3 |
Overgeneration is a key challenge
© 2010 Energy and Environmental Economics, Inc.
reviews the IOU energy storage applications in A.14-04-006. The overarching themes of
this report are that a cost-effectiveness framework for energy storage must:
Include not just existing markets and avoided costs, but also the future benefits
of reducing renewable curtailment under higher RPS levels.
Describe how the relative costs, benefits and tradeoffs of short- vs. long-
duration solutions will be quantified and evaluated.
Include system level and portfolio costs and benefits.
2 Overgeneration is a key challenge
2.1 Flexibility challenges
The Utility High RPS Report models CAISO system flexibility needs under 33%, 40% and
50% RPS levels The report describes five distinct types of flexibility challenges that the
system will face under high renewable penetration and shows a sample operating day in
January that illustrates these five challenges:
1. Downward ramp: as solar generation increases in the morning, flexible resources will be needed to ramp generation down (or ramp load up).
2. Minimum generation: to accommodate solar generation during the day, fossil generation will need to turn off, or operate at minimum levels, but still be ready to increase generation in the late afternoon and early evening.
3. Upward Ramp: in the evening, as solar generation declines, other generating resources will need to ramp up (or load ramp down).
4. Peaking Capacity: sufficient resources will be needed to meet peak loads with sufficient reserve margins.
5. Sub-hourly Flexibility: flexible resources will be required to provide both existing and new types of ancillary services including frequency regulation, flexi-ramp and load following.
Valuing Energy Storage as a Flexible Resource – Interim Report for Consideration in CPUC A. 14-02-006
P a g e | 4 |
Figure 1: Renewable Integration Challenges
The Utility High RPS study models flexibility needs in high RPS scenarios in 2022 and
finds that the largest renewable integration challenge is “overgeneration”.
Overgeneration occurs when “must-run” generation—non-dispatchable renewables,
combined-heat-and-power (CHP), nuclear generation, run-of-river hydro and thermal
generation that is needed for grid stability—is greater than loads plus exports.
Overgeneration can occur even in a highly flexible power system if there is simply not
enough load to absorb the available quantity of renewable energy during a given hour.
However, additional overgeneration or curtailment of renewable output may occur due
to lack of power system flexibility. As an example of this, consider a situation where
limited upward ramping capability would prevent the system operator from meeting the
steep upward ramp that occurs after sundown on the day depicted above. One strategy
for addressing this situation is to curtail renewable resource output during the middle of
the day, thus reducing the magnitude of the upward ramp to a manageable level and
avoiding firm load curtailment.
Interim Report
P a g e | 5 |
Overgeneration is a key challenge
© 2010 Energy and Environmental Economics, Inc.
2.2 How soon will overgeneration occur?
While there is currently no legislated RPS requirement above 33%, there are several
reasons overgeneration is likely to occur at significant levels before 2020:
Renewable procurement is on a trajectory to hit 40% levels: Even absent a
legislative requirement, procurement is on track to exceed 33% in 2020. Project
failure in recent solicitations has been much lower than anticipated based on
prior experience. Large declines in PV prices have also accelerated procurement
outside of IOU RPS solicitations.
Statewide model without transmission constraints: The production simulation
case modeled in REFLEX did not include transmission and associated constraints
that would increase overgeneration challenges.
Solar development is concentrated in Southern California: Solar project
development is heavily weighted to Southern California. The South of Path 15
(SP15) zone will reach 40% RPS generation levels and experience overgeneration
much sooner than the state as a whole.
Investment Tax Credit: Most of the solar projects planned are endeavoring to
begin operation before the end of 2016 to ensure their eligibility for the Federal
Investment Tax Credit.
Production simulation tends to overstate system flexibility: The specific ways
in which flexibility can be overstated are described below. E3 took steps to
constrain hydro generation and imports to realistic levels. However, the model
does assume all fossil generation can be dispatched by the CAISO within
operating constraints. In reality, self-scheduled generation may not be readily
available for flexible dispatch by the CAISO.
Indeed, negative prices due to overgeneration have already occurred in California, in
advance of even 33% RPS. Figures 2-4 show total generation, renewable generation and
SP-15 prices for March 6, 2014. Figure 2 shows that the thermal units are ramped down
Valuing Energy Storage as a Flexible Resource – Interim Report for Consideration in CPUC A. 14-02-006
P a g e | 6 |
in the middle of the day to accommodate ~3,000 MW of solar generation (Figure 3). This
leads to several intervals with negative prices between HE 11 and HE 17 (Figure 4).
Figure 2: CAISO March 6, 2014 – Generation by resource type
Figure 3: CAISO March 6, 2014 – Renewable generation
Interim Report
P a g e | 7 |
Overgeneration is a key challenge
© 2010 Energy and Environmental Economics, Inc.
Figure 4: CAISO March 6, 2014 – SP-15 locational marginal price (LMP)
2.3 Magnitude of overgeneration
E3’s Higher RPS Study finds that overgeneration is pervasive at RPS levels above 33%,
particularly when the renewable portfolio is dominated by solar resources. This occurs
even after thermal generation is reduced to the minimum levels necessary to maintain
reliable operations. Overgeneration is most pronounced in the spring, when loads are
relatively low, hydro generation is peaking and solar generation is substantial.
Figure 5 shows an April day in 2030 under the 33% RPS, 40% RPS, and the 50% RPS Large
Solar Scenarios on which the system experiences both low load conditions and high
solar output. A very small amount of overgeneration is observed at 33% RPS. The 40%
RPS Scenario experiences over 5,000 MW of overgeneration, while the 50% RPS Large
Solar Scenario experiences over 20,000 MW of overgeneration.
Valuing Energy Storage as a Flexible Resource – Interim Report for Consideration in CPUC A. 14-02-006
P a g e | 8 |
Figure 5: Generation mix calculated for an April day in 2030 with the (a) 33% RPS, (b) 40% RPS, and (c) 50% RPS Large Solar portfolios showing overgeneration
Interim Report
P a g e | 9 |
Overgeneration is a key challenge
© 2010 Energy and Environmental Economics, Inc.
2.4 Increase in overgeneration under high RPS scenarios
Table 1 and Figure 6 show overgeneration statistics for the 33%, 40% and 50% RPS Large
Solar Scenarios. In the 33% RPS scenario, overgeneration occurs during 1.6% of all
hours, amounting to 0.2% of available RPS energy.3 In the 50% RPS Large Solar case,
overgeneration must be mitigated in over 20% of all hours, amounting to 9% of available
RPS energy, and reaches 25,000 MW in the highest hour.
Table 1: 2030 Overgeneration statistics for the 33%, 40% and 50% RPS Large Solar Scenarios
Overgeneration Statistics 33% RPS 40% RPS 50% RPS
Large Solar
Total Overgeneration
GWh/yr. 190 2,000 12,000
% of available RPS energy 0.2% 1.8% 8.9%
Overgeneration frequency
Hours/yr. 140 750 2,000
Percent of hours 1.6% 8.6% 23%
Extreme Overgeneration Events
99th Percentile (MW) 610 5,600 15,000
Maximum Observed (MW) 6,300 14,000 25,000
3 Curtailment as a percentage of available RPS energy is calculated as: overgeneration divided by the amount of renewable energy that is needed to meet a given RPS target.
Valuing Energy Storage as a Flexible Resource – Interim Report for Consideration in CPUC A. 14-02-006
P a g e | 10 |
Figure 6: Increase in overgeneration with increasing renewables penetration
2.5 Frequency of overgeneration (under 40% RPS)
E3 analysis performed since the Utility High RPS Report was published shows that
overgeneration is persistent throughout the year under 40% RPS scenarios. Figure 7
shows an illustrative dispatch of resources, including ~1,500 MWs of storage, on a
flexibility constrained spring day in the REFLEX model. The model dispatches all available
resources within their defined operating parameters to meet load at the lowest possible
cost. In this example day, the storage is charging to reduce overgeneration during the
day and discharging in the early evening to reduce the dispatch of a combustion turbine
or demand response (DR) to meet peak needs. Fossil resources (Steam Turbine (ST), Gas
Turbine (GT) and combined cycle gas turbines (CCGT)) are reduced to minimum load
during the day, but must be online to meet the evening ramp and peak net load.4 Other
resources, including hydro and imports are also reduced to minimum loads during the
day. Combined heat and power (CHP) and nuclear are assumed to be non-dispatchable
base load resources.
4 Net load is the total system load minus the non-dispatchable variable energy resources, including wind and solar generation.
Interim Report
P a g e | 11 |
Overgeneration is a key challenge
© 2010 Energy and Environmental Economics, Inc.
Figure 7: Illustrative dispatch energy storage on flexibility constrained day
Figure 8 shows that overgeneration occurs throughout the year. As described above,
overgeneration is most prevalent in the spring, with average overgeneration of over
4,000 MW near solar noon in March. Overgeneration occurs in significant quantities in
the fall and winter as well. Only when loads peak in the summer is overgeneration
minimal. Peak net loads occur in the evening and either DR or combustion turbines (CTs)
are dispatched during peak net load hours in the early evening. These resources are
dispatched not to meet peak loads, but to respond to the substantial ramp in net load
that occurs between HE 15 and HE 17.
Valuing Energy Storage as a Flexible Resource – Interim Report for Consideration in CPUC A. 14-02-006
P a g e | 12 |
Figure 8: Average renewable curtailment and demand response/CT dispatch throughout the year
2.6 Duration of overgeneration
Many prior studies have focused on the hourly and sub-hourly variability in renewable
generation to quantify operational renewable integration needs. The Utility High RPS
Study examines the integration challenge from both a long-term planning and short-
term operational perspective. With this approach, overgeneration emerges as a primary
challenge requiring longer-duration solutions. Referring back to Figure 5, on the
particular spring day presented, overgeneration occurs from hour ending (HE) 09 to 17
under 40% RPS and HE 08 to 18 under 50% RPS – durations of 8 and 10 hours
respectively.
Figure 8 shows that significant quantities of overgeneration occur from hour ending (HE)
9 to 16 throughout the spring, a duration of 7 hours.
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
1 9
2 13
3 0
4
5
6
7
8 24 76 161 106 5 8
9 6 518 801 823 354 69 6 157 74 32
10 52 305 1,963 1,860 1,489 805 151 30 252 546 395 174
11 514 928 3,272 2,846 2,154 1,238 211 48 332 1,068 897 807
12 1,124 1,471 4,168 3,493 2,618 1,439 220 79 342 1,264 1,358 1,521
13 1,465 1,750 4,298 3,533 2,667 1,421 191 59 237 1,050 1,395 1,885
14 1,333 1,567 3,914 3,035 2,245 1,142 90 11 138 654 892 1,552
15 641 847 2,726 2,074 1,578 655 49 33 259 259 593
16 27 120 1,129 902 785 271 0 20
17 2 16 54 90 47 3 42 7
18 479 68 6 26 4 21 62 58 710 725
19 267 194 347 139 67 44 46 20 219 435
20 17 61 55 11 34 27 8 91
21
22
23
24Avg. Dispatched Demand Response (MW)
Avg. Renewable Curtailment (MW)
Interim Report
P a g e | 13 |
Renewable Curtailment
© 2010 Energy and Environmental Economics, Inc.
If curtailment of renewable generation at such high levels is to be avoided, new
strategies, resources and market designs must be developed to provide flexibility and
absorb overgeneration. These potential solutions must be available for periods lasting
up to 10 hours, during large portions of the year and must comprise a large total
capacity.
3 Renewable Curtailment
One solution to overgeneration is to curtail renewable generation. However,
curtailment may be an expensive strategy. The immediate cost of curtailment is that the
utility cannot use zero emission and marginal cost generation that has already been
contracted and paid for. Curtailing renewable generation can also make it more difficult
for utilities to achieve RPS and GHG emission reduction goals, which can impose
additional costs on the utility.
If utilities have procured resources to meet the RPS with the expectation that a certain
level of renewable energy will be delivered from these resources, frequent renewable
curtailment may increase the risk of being out of compliance in a given year. There are
two strategies for minimizing this risk: 1) the utility can procure additional renewable
resources to comply meet RPS targets; or 2) the utility can procure resources that
provide enough flexibility to ensure that energy from their renewable resources can be
delivered (such as energy storage). For a utility, the choice between these two options
will depend on the cost of procuring additional renewables versus the cost of procuring
flexible resources, as well as the incremental fuel and operating costs associated with
each option.
E3 has developed a low and high avoided curtailment value scenario to illustrate the
impact of curtailment on system costs and flexible resource value (using methods
further described in Appendix A). The low case reflects a scenario where utilities have
Valuing Energy Storage as a Flexible Resource – Interim Report for Consideration in CPUC A. 14-02-006
P a g e | 14 |
procured sufficient renewable generation to meet RPS targets even with anticipated
curtailment levels and do not need to procure additional renewables. Hence there is no
cost to the utility for replacement renewable generation. The high case presumes that
utilities must procure additional renewables to meet required RPS targets when
curtailment occurs. In the high case, the replacement cost for renewable generation is
$125/MWh, reflecting a higher levelized cost for PV that has a lower capacity factor due
to its being curtailed on a regular basis. A high cost of curtailment leads to negative
values for energy when overgeneration occurs (Figure 9). We refer here to energy value
rather than prices because the wholesale market prices for energy will not necessarily
reflect the cost of curtailment to the utility.
Figure 9: Average hourly energy value in April under 40% RPS scenario with low and high cost of curtailment
3.1 Managing overgeneration has significant value
Avoiding curtailment of renewable generation with flexible resources can provide
significant system value. Here we consider the same 40% RPS scenario as above.
Without any additional flexible resources the default strategy to prevent overgeneration
is curtailing renewable generation. Recall that the REFLEX model dispatches available
resources to meet system load with the minimal cost of energy production. Figure 10
Interim Report
P a g e | 15 |
Renewable Curtailment
© 2010 Energy and Environmental Economics, Inc.
shows the relative cost of two specific strategies to meet system needs - renewable
curtailment to avoid overgeneration and dispatching flexible resources such as DR or
CTs to meet peak net loads in the evening. Reducing peak load is often considered one
of the highest potential values for energy storage. In this case the total annual value of
DR or CT capacity costs that could be avoided with a flexible resource such as energy
storage is just under $100 million.5 In comparison, the cost of curtailment that can be
avoided with flexible resources is over $300 million, more than three times the capacity
value. This illustrates that avoiding renewable curtailment is a potentially large and
quantifiable value that should be included in the cost-effectiveness evaluation of flexible
resources.
Figure 10: Relative value of avoided curtailment, avoided DR/CT dispatch with high curtailment value for a 40% RPS scenario
5 With the assumptions used in this analysis, using DR or CT’s to meet peak net loads resulted in similar total annual costs.
Valuing Energy Storage as a Flexible Resource – Interim Report for Consideration in CPUC A. 14-02-006
P a g e | 16 |
3.2 Energy storage can reduce renewable curtailment
The market value for energy storage in capacity, energy and ancillary service markets
increases on a $/kW basis with an increase in duration (Figure 11). These values are
calculated using production simulation values from REFLEX model in the EPRI Energy
Storage Valuation Tool (ESVT) developed by E3. We used the ESVT to co-optimize the
dispatch of energy storage across capacity, energy and ancillary service markets and
calculate the total value provided, on a $/kW-Yr. basis, by each respective system
configuration.
With high curtailment value there are negative values for energy when overgeneration
occurs (Figure 9). Thus the energy used to charge storage doesn’t represent a cost (e.g.
the marginal cost of generating electricity), but actually provides a positive value to grid
in reducing curtailment. This increases the value by the amount shown in the avoided
curtailment bars on the right.
Figure 11: Illustrative annual revenues for energy storage of increasing duration with low and high values for avoided curtailment for a 40% RPS scenario
In this example, the hourly values from production simulation runs are used in ESVT to
calculate annual revenues with co-optimized dispatch of energy storage. However,
Interim Report
P a g e | 17 |
Overgeneration requires long-duration solutions
© 2010 Energy and Environmental Economics, Inc.
evaluating each storage project individually as a price taker using production simulation
results provides an incomplete evaluation of cost-effectiveness. This approach alone
does not provide a full and accurate comparison of the system level benefits that energy
storage of different durations can provide - an issue we explore further in Section 5.
Reducing renewable curtailment provides measureable value, but is not incorporated in
current market prices. Neither is curtailment value (yet) included in the Distributed
Energy Resources (DER) Avoided Cost Framework developed by E3 and adopted by the
CPUC for cost-effectiveness evaluation. The value of reducing curtailment can be
reflected in production simulation results, but only when explicitly incorporated in the
input assumptions and modeling approach.
4 Overgeneration requires long-duration solutions
Here we consider the relative ability of short-duration (2 hour) and long-duration (4
hour) storage to avoid renewable curtailment on the same flexibility constrained day
shown above. This example, for the sake of illustration, presumes that energy storage is
cost-effective when compared to alternative strategies that can reduce curtailment.
In the first example, 4,000 MW of 2-hour storage (8,000 MWh) is shown to reduce
overgeneration and DR/CT dispatch from the top down for the peak solar generation
and net load hours respectively (Figure 12). The storage is charged at full capacity in HE
12 and at partial capacity in HE 11 and HE 13. The storage is discharged during the
evening peak to eliminate DR/CT dispatch for peak net loads, and reduce some of the
fossil generation that is online to meet the evening ramp. The 2 hour duration is not
able to address the “shoulders” of the overgeneration in the morning and late
afternoon. On this spring day, 4,000 MWs of 2-hour storage can absorb ~47% of the
excess renewable generation.
Valuing Energy Storage as a Flexible Resource – Interim Report for Consideration in CPUC A. 14-02-006
P a g e | 18 |
With longer duration, a much larger portion of the overgeneration can be absorbed with
energy storage. Here 4,000 MW of 4-hour storage (16,000 MWh) is shown addressing
the challenge from the bottom up (Figure 13). The long-duration storage absorbs
overgeneration from HE 09 to HE 15, charging over 6 hours, but at the full 4,000 MW
nameplate capacity for only 3 hours. The storage discharges and displaces fossil
generation over from HE 17 to HE 22 in the evening. The 4-hour storage is able to
absorb ~90% of the excess renewable generation. With the longer duration, the storage
is also able to displace more of the fossil generation that is needed to provide upward
ramping capacity and meet peak net loads in the evening.
Figure 12: Illustrative short-duration storage dispatch
2 Hr Storage
Interim Report
P a g e | 19 |
System level cost-benefit analysis is crucial
© 2010 Energy and Environmental Economics, Inc.
Figure 13: Illustrative long-duration storage dispatch
5 System level cost-benefit analysis is crucial
5.1 Comparing value of short- and long-duration
Figure 8 and Figure 13 suggest that long-duration solutions will be needed to address
the majority of the overgeneration that occurs under 40% RPS levels. A portfolio level
cost-effectiveness framework will describe how the metrics and methods can be used to
evaluate the relative costs, benefits and trade-offs between short- and long-duration
storage.
While short-duration storage does have value under this scenario, our work finds that
the dominant flexibility need is for long-duration. Moreover, long-duration storage can
provide short-duration services but not vice versa. The flexible resources procured to
meet long-duration needs might also fully satisfy the short-term needs at little or no
4 Hr Storage
Valuing Energy Storage as a Flexible Resource – Interim Report for Consideration in CPUC A. 14-02-006
P a g e | 20 |
extra cost. Thus, the quantitative work that has been done to date on this topic
provides a strong value proposition for long-duration storage.
There is an additional question with respect to the impact duration will have on GHG
emissions. Flexible resources can enable reliable operation of the grid with fewer fossil
plants required to remain online at minimum load to meet evening ramps. Reducing the
number of start-ups and minimum load hours of fossil generation helps to reduce GHG
emissions from the residual fossil fleet. It is reasonable to hypothesize that longer-
duration solutions will avoid a larger number of start-ups and minimum fossil generation
hours throughout the year (as shown for the example spring day in Figure 13). On days
when fossil generation is required over periods of 4-5 hours in the evening to meet peak
net loads, it can only be avoided with longer duration storage. The magnitude of this
benefit, however, is not yet determined. The benefits of reduced fossil start-ups and
minimum operating hours is a crucial factor in evaluating the relative costs and benefits
of short- and long-duration solutions.
A cost-effectiveness framework for energy storage should specify how it will enable a
robust, portfolio level evaluation of the relative benefits and trade-offs between short-
and long-duration flexibility solutions.
5.2 Small market for frequency regulation
Frequency regulation is currently one of the most remunerative services that energy
storage can provide, but is a relatively small market. The CAISO procures on average
roughly 350 MW of regulation down and 330 MW of regulation up services.6 Even if the
frequency regulation market doubles in size with increased renewables, a modest
amount of energy storage (or flexible loads) would be sufficient to cause market clearing
prices to decline. Figure 7 above shows that the size of a 600 MW regulation up and
6 CAISO 2012 Annual Report on Market Issues and Performance, p. 118
Interim Report
P a g e | 21 |
System level cost-benefit analysis is crucial
© 2010 Energy and Environmental Economics, Inc.
regulation down market is small relative to overgeneration on a flexibility constrained
spring day. Furthermore, if, as the Utility High RPS Report suggests, significant quantities
of fossil generation will be operating at minimum load throughout the day to provide
ramping in the afternoon, those units could provide frequency regulation with no
opportunity cost of lost revenue in the energy market. This would depress frequency
regulation prices in the future. This finding runs counter to popular notions that the
increased demand for short-duration services such as frequency regulation will lead to
significant economic opportunity for storage resources. However, such narratives
ignore the supply side of the equation. E3’s (admittedly early) work in this area suggests
that there will be plenty of resources available to meet this increased demand, even
before considering long-duration storage procured to meet the needs of a diurnal
energy cycle.
Evaluating projects individually, without accounting for saturation effects, will overvalue
the frequency regulation benefits that can be realized with energy storage. The
potential for this result is illustrated by the EPRI “Cost-Effectiveness of Energy Storage in
California” Report (EPRI 3002001162). The study evaluated 31 energy storage use cases
and found most use cases (with several caveats) cost-effective with the storage costs
and assumptions used. Of those use-cases, 20 relied on frequency regulation for 40% or
more of their total revenue. Attributing frequency regulation benefits to each storage
project individually will overstate the total value for the system as a whole. Given the
small market size and the potential for competition to reduce market prices, the value
that can be realized for the system as a whole will, in this case, be less than the sum of
each project evaluated individually. It is therefore important to include a system level
quantification of both costs and benefits in the cost-effectiveness analysis of energy
storage to account for the effect of market saturation, which begins to significantly
affect value at relatively low levels of penetration. A system level approach would
either, a) limit the quantity of storage that is assumed to provide frequency regulation,
or b) model the impact on market prices of all storage participating.
Valuing Energy Storage as a Flexible Resource – Interim Report for Consideration in CPUC A. 14-02-006
P a g e | 22 |
5.3 Serial dispatch of short-duration
It is feasible for three 1 MW, 2-hour batteries be dispatched in serial to effectively
provide the same duration as a single 1 MW, 6-hour battery. However, this is unlikely to
be the least-cost solution. Storage systems include costs for MW of power delivery (e.g.
inverters, power electronics) and for MWh of energy storage capacity (e.g. cells,
electrolytes). The three 2-hour systems have 3 MW of power deliver costs as compared
to 1 MW for the 6-hour system.
An assessment of how the portfolio of energy storage will be dispatched for the system
as a whole is therefore crucial. If short-duration batteries are dispatched in series to
manage longer duration overgeneration, only 1 MW of power delivery is used in any
given hour, while 2 MW sit idle. There will also be associated costs, potentially borne by
the utilities and CAISO rather than the storage project developer, to interconnect,
integrate and manage the dispatch of multiple systems. This would result in a higher
system level cost that is not reflected when evaluating storage projects individually.
5.4 Production simulation understates flexibility need and value
When quantifying system level costs and benefits, it is important to bear in mind the
limitations of production simulation, which tends to overstate the flexibility of the grid
and therefore understate the need for and value of new flexible resources such as
energy storage. System level cost and benefit calculations should account for how such
limitations will impact the valuation of flexible resources and employ techniques to
counteract these biases.
WECC wide dispatch: production simulation of the WECC will optimally dispatch
all resources to minimize costs for the region as a whole. In reality, the 20+
balancing authorities in the WECC are operated independently, reducing
Interim Report
P a g e | 23 |
System level cost-benefit analysis is crucial
© 2010 Energy and Environmental Economics, Inc.
operational flexibility and efficiency relative to the production simulation
model.
Unrealistic hourly variations in imports: Production simulation will tend to rely
on imports and exports for flexibility to a much greater degree than is typically
observed in practice.
Unrealistic dispatch of hydro: Similarly, hydro resourced tend to be dispatched
with much greater variation that is allowed in practice, given constraints for
recreation, environmental and water supply objectives. In addition, production
simulation will count the full upward capability of hydro for operating reserves
with actual upward ramping capabilities are constrained by other factors. When
analyzing the benefits of the Imbalance Energy Market for PacifiCorp, E3 limited
hydro contributions to flexibility reserves to 12 – 25% of nameplate capacity.
Full ISO dispatch: Production simulation assumes ISO dispatch of all fossil units.
In reality the majority of fossil units are self-scheduled and not fully available or
visible to the ISO operators.
Single “snapshot” year of market conditions. Due to data processing and run-
time limitations, conventional production simulation models such as GridView
and PLEXOS only consider a single year of load and resource conditions. Most
analyses of California and the Western Interconnection use 2005 conditions as
the test year, since 2005 represents relatively average load and hydro
conditions. However, modeling a single, average year does not consider
combinations of load and hydro conditions that can result in the highest market
prices for energy and capacity (low hydro, high load) or the largest amount of
renewable curtailment (high hydro, low load).
Taken together, these issues can significantly understate the value of adding flexible
resources such as energy storage to the resource portfolio modeled in production
simulation.
Valuing Energy Storage as a Flexible Resource – Interim Report for Consideration in CPUC A. 14-02-006
P a g e | 24 |
6 Benefits of a diverse portfolio
The Utility High RPS Study provides results for a large solar case and a diverse renewable
portfolio. The large solar case has the highest levels of renewable curtailment – the
marginal PV generation will have more than half of its generation curtailed at the 50%
RPS level. With a more diverse mix of renewable resources, marginal curtailment levels
are reduced (Figure 12).
Table 2: Marginal overgeneration of different RPS scenarios
Technology 33% RPS 40% RPS 50% RPS Large Solar
50% RPS Diverse
Geothermal 2% 9% 23% 15%
Wind 2% 10% 22% 15%
Solar PV 5% 26% 65% 42%
Figure 13: Average overgeneration under 50% RPS scenarios
Interim Report
P a g e | 25 |
Conclusions
© 2010 Energy and Environmental Economics, Inc.
This finding illustrates how a diverse portfolio provides system level benefits relative to
one that is dominated by a single technology. This diversity benefit is also illustrated by
the history of renewable procurement. In the early years of RPS procurement, wind was
the least cost resource. In subsequent years solar thermal was thought to have the
technological cost advantage. Finally, in recent years, the precipitous drop in panel
prices has led PV to lead the pack. Procuring all three technologies throughout the
procurement process helped spur competition and innovation and positioned California
to more quickly pivot to lower cost renewable technologies. In energy efficiency too we
have seen the perils of becoming over reliant on a dominant technology, CFLs, for the
majority of efficiency program savings. When building codes and legislation phased out
incandescent bulbs, energy efficiency program managers had to scramble to find new
strategies and technologies to meet efficiency goals.
The magnitude of the potential overgeneration under the 40% RPS scenario (5,600 MW
at the 99th percentile) suggests no single strategy or resource type will fully address the
challenge. Furthermore, if renewables penetration is to increase to support long-term
GHG reductions, even larger quantities and longer durations of curtailment will need to
be managed. This suggests that we should cast a wide net in our search for flexibility
and energy storage solutions.
7 Conclusions
In this report we have summarized the results of prior work, including the Utility High
RPS Study to illustrate why it is important to perform a system level evaluation of costs
and benefits when analyzing the cost-effectiveness of energy storage as a flexible
resource. The primary conclusions of the paper are:
Overgeneration will be a significant challenge under expected levels of RPS
before 2020.
Valuing Energy Storage as a Flexible Resource – Interim Report for Consideration in CPUC A. 14-02-006
P a g e | 26 |
Overgeneration will require flexibility solutions with durations of 7-10 hours.
Managing overgeneration with flexible resources reduces expected levels of
renewable curtailment, providing a significant and quantifiable value to utilities
and ratepayers.
Long-duration flexibility solutions provide quantifiable benefits that are not
reflected in existing markets and DER Avoided Costs. Evaluation protocols that
rely predominately on these benefits alone will understate the value of long-
duration storage.
Future and system level costs and benefits, such as reduced renewable
curtailment, are essential to fully quantify value storage and to evaluate the
relative benefits of both short- and long-duration storage.
Evaluating storage projects in an individual basis will, at a system level,
overstate the value of short-duration storage and understate the value of longer
durations. This holds true even if prices from system-wide production
simulation are used.
Our experience in RPS procurement and energy efficiency illustrates the
importance of procuring a diverse portfolio of resources. Ensuring that the cost-
effectiveness and procurement frameworks support diverse strategies is crucial
to achieve ambitious GHG reduction goals provides a long-term benefit to
ratepayers.
Interim Report
P a g e | 27 |
Appendix A: Cost of Renewable Curtailment
© 2010 Energy and Environmental Economics, Inc.
Appendix A: Cost of Renewable Curtailment
In the recent E3 study, “Investigating a Higher Renewables Portfolio Standard in
California,” it was determined that a significant challenge to integrating renewables
under a 40% or 50% RPS in California is the avoidance of renewable curtailment.
Renewable curtailment was identified as an operational solution to avoid
overgeneration events, which are marked by high frequency conditions and negative
prices to incentivize generators to shut down. While renewable curtailment may be a
valuable tool in maintaining reliability and avoiding volatility in the system under a
higher RPS, this renewable curtailment does not come without a cost. If utilities have
procured resources to meet the RPS with the expectation that a certain level of
renewable energy will be delivered from these resources, frequent renewable
curtailment may increase the risk of being out of compliance in a given year. There are
two strategies for minimizing this risk: 1) the utility can over procure renewable
resources; or 2) the utility can procure resources that provide enough flexibility to
ensure that energy from their renewable resources can be delivered. For a utility, the
choice between these two options will depend on the cost of procuring additional
renewables versus the cost of procuring flexible resources and the cost savings
associated with avoided renewable procurement that is afforded by these resources.
7.1 Avoided RPS Costs
The incremental cost of RPS compliance for a utility that is anticipated to be short due
to curtailment will depend on a number of factors. First and most intuitively, it will
depend on technology and installation costs, which are rolled into renewable PPA price
forecasts. In addition, the RPS costs will depend on whether utilities are in under-
procurement over over-procurement positions with respect to the RPS targets.
Consider the following scenarios:
Valuing Energy Storage as a Flexible Resource – Interim Report for Consideration in CPUC A. 14-02-006
P a g e | 28 |
Utilities are generally long on renewables – this scenario reflects the situation
in California today. When the utilities are long on renewable resource
procurement with respect to the RPS, renewable energy in excess of RPS
targets. In this scenario, there is no immediate cost for renewable curtailment.
A utility is short on renewables – in this scenario the utility must procure
additional renewable resources. If utilities are generally short on renewables,
then curtailed renewable energy must be replaced at or near the cost of new
construction for renewable generation.
Marginal Curtailment Adjustment
When renewable curtailment forces utilities to procure additional resources to ensure
RPS compliance, utilities must also account for curtailment of these incremental
renewable resources in assessing RPS compliance costs. Consider for example, that a
utility requires an additional 5,000GWh/yr. of renewables to meet its RPS requirements.
Based on operational simulations, the utility expects that 5% of the energy produced by
incremental renewable resources might be curtailed. The utility therefore sets its
procurement target at 5,000/(1-0.05) = 5,263MWh. At $70/MWh, the utility must pay
$368,000 per year to deliver the 5,000GWh for RPS compliance. The effective new build
cost is therefore $73.68/MWh. This logic leads to a PPA price multiplier that depends
on the expected curtailment of incremental renewable resources, which will be referred
to as the marginal curtailment rate for the remainder of this document. The PPA price
multiplier is equal to 1/(1-[marginal curtailment rate]).
Renewable-Based Fuel Savings Adjustment
There is an additional fuel savings adjustment that must be made when using
production simulations to quantify the net costs of new flexible resources. Production
cost simulations are typically run with portfolios of renewable resources designed to
meet RPS requirements assuming that no renewable curtailment occurs. In scenarios
Interim Report
P a g e | 29 |
Appendix A: Cost of Renewable Curtailment
© 2010 Energy and Environmental Economics, Inc.
when renewable curtailment occurs we assume that the utilities meet their RPS
requirements either through additional renewable procurement or through
procurement of flexible resources to ensure the delivery of their renewable resources.
This additional renewable generation offsets an equal amount of thermal production to
account for the energy value of the additional renewable resources. The cost impact of
avoided renewable curtailment therefore includes both the cost of new build and the
cost savings of avoided thermal generation.
Returning to the example described above, the utility that determined that it would be
5,000MWh short due to expected curtailment in the operational year, could expect to
see 5,000MWh of fuel savings if it were to procure the 5,263MWh of renewables to
meet its RPS requirements. If these resources offset thermal resources at $30/MWh,
then the net cost of meeting its RPS requirements with incremental resources is $73.68-
$30 = 43.68/MWh. The full build-up of this cost is shown schematically below for two
scenarios. In Scenario 1, utilities have generally over procured renewable resources,
leading to low net costs for any incremental purchases or REC’s needed by a utility to
meet its RPS requirements. With the purchase of additional renewable generation,
there is an associated reduction in fuel costs. In Scenario 2, utilities are generally short,
so the incremental compliance net costs reflect the full costs of new renewable build.
Valuing Energy Storage as a Flexible Resource – Interim Report for Consideration in CPUC A. 14-02-006
P a g e | 30 |
Figure 13: Value of avoided curtailment under scenarios when the utilities are long vs. short on renewables