Value Engineering Summary of Supplementary Findings
Transcript of Value Engineering Summary of Supplementary Findings
Value Engineering Summary of Supplementary Findings
Tunnel Stabilization and Pipeline Replacement ProjectPresentation to SCWD Board of Directors
Special Meeting
February 18, 2016
PARSONS
Agenda1. Introductions2. Background: Findings from Previous VE3. Add. Analyses Performed.
A. Safety and RisksB. Static and Seismic StabilityC. New Alternative
4. Pros and Cons of Alternatives5. Contractual Methods6. Questions and Discussions
1. IntroductionsParsonsJon Kaneshiro (PM/tunnels design)Dave Neil (tunnel constructability)Sangyoon Min (risk specialist)
South Coast Water DistrictWayne Rayfield (President of Board)Rick Erkeneff (VP of Board)Dick Dietmeier (Board Member)Dennis Erdman (Board Member)Bill Green (Board Member)Andy Brunhart (General Manager)Rick Shintaku (Chief Engineer)Karl Francis (Principal Engineer)Joe McDivitt (Chief of Operations)Michelle Collins (Contracts)
2. Background
Portal 2Portal 4
Proposed 4th Ave. Shaft
Adit 12 Adit
16Emergency Repairs Completed
District Easement 32201 Pacific Coast Highway
Visited: 2, 4, 5, 14 & 16 on 1/5/2015
History• Constructed in 1954 with VCP before suburban
development– 10,400 feet long in San Onfre Fm (Breccia, Sandstone,
Siltstone)– Varies in size but generally 5 feet high by 6 feet wide– 19 tunnel access points (Portals & Adits 2 – 25, but many
not accessible)– Mostly unsupported– Intervals supported with timbers– Hydraulics: 50 to 60% full at peak flows
• 2‐foot diameter Techite pipeline installed in 1974• 1999 Inspections• 2007 Emergency Repair• Design for Enlarged Tunnel and Pipeline Replacement• Negotiated Procurement Approx. $80 million• Value Engineering
2. Background
Complex Problem• Efficiency of Access
– Beach Environment– Steep Cliffs– Urban Development– Exclusive Community– Hilly Terrain
• Restricted room in tunnel– Aging– 40 year old Techite Pipe
2. Background
• Mini Charrette• 34 Initial Ideas• 16 shortlisted
• Workshop• 4 New Ideas• 10 Suggestions
• Report• 12 Evaluated• Idea 4i Savings $22 m• E‐2.0 New Pipe $10 m • Net Savings $12 m
VE Workshop Summary and Results2. Background
* Represents potential savings only, which was estimated by factoring “Confidential Construction Estimate by Kiewit” for Types 1 and 2 Ground and Support. Does not consider efficiency’s lost in repairing Type 3, 4 and 5 ground, backfilled areas, construction of 4th Avenue, or pipeline replacement. It is assumed that only areas of poor condition especially at portals are repaired.
Baseline vs. 4iBaseline • 9’ x 9’ enlargement
4i Sealer (in Type 1 & 2 Ground)• 6’ x 5’, limited enlargement• Repair rotten timber, e.g. portals
2. Background
Baseline Project 2. Background
• $78 M• 9 ft Tunnel• Access Shaft on 4th Ave.• Two Pipes• Mechanized Tunneling
Tunnel9’
9’
• Push Cart in tunnel for O&M• Two pipelines• 9 ft diameter size• Shotcrete liner everywhere• Mechanized Excavation (roadheader)• 5 year schedule• Access tunnel (4th Ave Access adit)• New Connections to New Pipe
Baseline Criteria2. Background
4i ProjectSealer in Type 1 and 2 Ground
2. Background
Add Map of 4i
LEM = Labor Equipment Materials Access
Package 1 Package 2
Package 3
Package 4a
E‐2.0/E‐2.24th Ave Shaft for Package 3&4
• $56 M• No enlargement in Types 1 and 2 Ground & Support (5980’)• Portal Areas and Bad Timber Area fixes only• Access Shaft on 4th Ave not necessarily required.• One Pipe• Bucket brigade 5’
6.5’
• No Need for having a Push Cart in the tunnel for O&M• No Two pipelines• No 9 ft diameter size• No Shotcrete liner in Types 1 and 2 Ground & Support• No Mechanized tunneling (hand dig with spaders)• No 5 year schedule• No Long access tunnel (4th Ave Access adit)• No New Connections to existing laterals/Maintain Only
VE and 4i Criteria“Absolutes are not Absolutes”
2. Background
4i• Sodium Silicate sealer• No enlargement of tunnel• No Repair of Timber Areas in Good Condition• Repair poor timber areas only, some shotcrete or slip forming may be required
• Improve Portals Especially• Smaller Access Shaft still possible for access of other repairs
2. Background
Baseline Project Costs $78 m
Idea Savings4i with 4th Ave Access Shaft & Sealer $22m*E‐1.0 Penalty for new pipe ‐$10mNet Savings $12m
Main Questions from BOD from VE Workshop1. What are the relative risks of 4i compared to the baseline?2. Are the alternatives as safe as the baseline project?
2. Background
* Represents potential savings only, which was estimated by factoring “Confidential Construction Estimate by Kiewit” for Types 1 and 2 Ground and Support. Does not consider life cycle costs, efficiency’s lost in repairing Type 3, 4 and 5 ground, backfilled areas, construction of 4th Avenue, or pipeline replacement. It is assumed that only areas of poor condition especially at portals are repaired.
3. Add. Analyses Performed
3.A. Safety and Risks1) Static Stability2) Seismic Stability3) Risk Comparative Risks: Baseline vs. 4i
3.B. New Alternative 4y
Key Parameters Attributing to Stability AnalysisBaseline vs. 4i
3.A.1) Add. Analyses
ItemNo.
Parameter Baseline Design VE Idea 4i Proposal
1 Rock Mass Properties
Massive, moderately hard, strong to friable, weathered to fresh, RMR = 65 to 87% Good to Very Good Rock
Massive, moderately hard, strong to friable, weathered to fresh, RMR = 65 to 87% Good to Very Good Rock
2 Shape Modified Horseshoe-Circular Arch
Cathedral Ceiling/Parabolic Arch
3 Size 9 ft ID/10 ft OD 5 ft wide by 6 ft high4 Litho-static State of
Stress, Ko = horizontal to vertical Stress field
0.5 to 1 0.5 to 1
5 Hydrostatic State of Stress
Allow groundwater inflow seepage
Allow groundwater inflow seepage
6 Type of Liner 8 inch thick shotcrete liner No liner to sealer to thin shotcrete liner
Unsupported Span Standup Time Baseline vs. 4i
3.A.1) Add. Analyses
• Baseline– 7 to 10 ft spans 7 months to > 300 years
• 4i– 3.8 to 5 ft spans 5.7 years to > 1000 years
Estimated Ground Loads in unsupported ground reaches
3.A.1) Add. Analyses
Ground Load Baseline 4i
10% to 20% max of diameter = 1 to 2 ft of ground
10% to 20% max of diameter = 0.5 ft to 1 ft of ground
0 to 10% of vertical load 0 to 10% of vertical load
Baseline vs. 4i
Tunnel
Vertical
Horizon
tal
Static Factor of Safety 3.A.1) Add. Analyses
Baseline vs. 4i
Type 2 Ground and Support
Baseline: 5" shotcrete + W4x13, 9.1' span 6.2 121 13.5
4i: 1.5" shotcrete, 5' span 2.6 110 37
Factor of SafetyType 1 Ground and Support Moment Thrust Shear
Mc/Mn Pc/Pn Vc/VnBaseline: 5” shotcrete, 9.1’ span 2.2 110 7.44i: 1.5" sealer as req’d, 5’span, equivalent rock beam strength, qu, = 100 to 531 psi
2.6 6.9 to 24.2 14.7 to 22.3
Tunnel
-M
-P
-V +M+V
+P
Acceptable F.S = 2.2
2) Seismic Stability (Power et al. 1998) 3.A.2) Add. Analyses
Range of Peak Ground Acceleration 0.4 to 0.5 g for Beach Interceptor
Design Life and Probability of Exceedance
3.A.2) Add. Analyses
Design Life, n
Probability of Exceedance, Pe = 1-[1 – 1/T]n where T =
Return Period
Probability EQ (USGS Haz Maps) with M> 7.0 and 50 km
100 19.0% 25 to 30%30 6.1% 8 to 10%
Exposure risk of 0.4 to 0.5g peak ground acceleration earthquake
Summary: Comparison Static/Dynamic Stability between Baseline and 4I*
• Static Stability– Factor of Safety for M, P, V: 4i compare favorably adequate enough or exceed baseline for Ground and Support Class 1 and 2
• Dynamic Stability (0.4 to 0.5 g)– 4i comparable because of general competency of ground, reduced seismic exposure.
– Damage states similar whether supported or lined
3.A. Add. Analyses
*Does not apply to areas of distress: such as failing timber, noticeable friable or incompetent ground, low ground cover areas, which would be repaired under either scenario
Risk Response Strategies
DG - 001 Design errors/omissions • Design inadequate • Lack of QC and design reviews• Inadequate analysis o f alternative support schemes• A ll new geotechnical data not incorporated
• Design inadequate • Ground failure during construction in tunnel• Redesign• Pro ject delay
T Unlikely 2 M edium 3 3 3 6 T o lerable • Engineers using best practice for design of support schemes• Engineer quality contro l includes senior review o f design documents• PM monitoring fo r early detection and resolution• Ongoing review of new data will be used to adjust design and design contingencies exist
Very Unlikely
1 Low 2 2 2 2 N egligible Engineer Active
DG - 002 Differing site conditions • Insufficient/inadequate geotechnical data• Actual conditions between borings vary from interpreted baseline• Increased quantities o f poorer ground conditions than represented in GBR
• Unexpected delays inpro ject• Dispute and DSC claims• Additional cost• Additional support installed
T Possible 3 M edium 3 3 3 9 T o lerable • Early contracto r involvement during design • Site investigations by Geotechnical ongoing during pro ject• Create contingency plan fo r ground improvement• Engineering conservative design based on documented ground conditions
Unlikely 2 Low 2 2 2 4 N egligible Engineer/District
DG - 003 Conflict and discrepancy between specifications, drawings, GBR
• Lack of QC and design reviews
• Contracto r brings dispute or claims during construction
T Unlikely 2 M edium 3 3 3 6 T o lerable • Engineer quality contro l includes senior review o f contract documents and early contracto r involvement • Contract has claims procedure in it
Very Unlikely
1 Low 2 2 2 2 N egligible Engineer
DG - 004 Late design modifications
• Late design changes • Delay to construction T Likely 4 M edium 3 2 3 12 Undesirable • Early contracto r involvement during design (using constructability review)
Possible 3 Low 2 2 2 6 T o lerable Engineer
DG - 005 Soil rock interface at the shaft -flowable sand and/or groundwater contro l
• Insufficient ground support• Failure o f ground• Bad geologic conditions
• Failure o f ground • Requiring redesign o f support• Instability/ co llapse• Groundwater inflow
T Unlikely 2 M edium 3 3 3 6 T o lerable • Completed explo ration borings at shaft site (LGC Geotechnical)• Contingency plan required
Very Unlikely
1 Low 2 2 2 2 N egligible Engineer
DG - 006 Unknown condition of Laguna Royale caisson foundations
• Caisson foundations close to tunnel• Encountering caisson• No accurate as-built drawings
• Building settlement during excavation • Damage to caisson
T Likely 4 High 4 4 3 16 Into lerable • Pre-construction probe ho le investigation • Design and location adjustments will be included based on findings• Instrumentation and monitoring during
Possible 3 Low 2 2 2 6 T o lerable Engineer
Envi
ronm
ent
Com
mun
ity
Rep
utat
ion
Risk Analysis/ Evaluation - Pre- Mitigation
Initial Risk Score/Class
Risk Identification
Risk IDInitial
ProbabilityInitial
Impact
Com
plia
nce
Risk Scenario Potential Cause Proposed Mitigation MeasuresPotential Consequences
Type
Cos
tTi
me
Hea
lth&
Safe
t
Risk Monitoring and Control
Risk Owner
Risk Status
Risk Re-evaluation - Post-Mitigation
Residual Probability
Residual Impact
Residual Risk Score/ClassC
ost
Tim
eH
ealth
&Sa
fet
Envi
ronm
ent
Com
mun
ity
Rep
utat
ion
Com
plia
nce
Risk Assessment• Risk assessment using semi‐quantitative risk approach• Comparative analysis between Baseline and 4i
3.A.3) Add. Analyses
Risk Identification
Risk M
onitoring/
Control
RISK REGISTER
3.A.3) Add. Analyses
• Risk Scenarios, potential causes and potential consequences• 62 risk scenarios for 6 risk categories
Risk Identification
EN - 055 Community complaints noise issues
• Sound barriers ineffective at nearest residence• Site work continues beyond hourly limitation• Construction equipment not equipped with proper sound attenuation• Trucks idling
• Community complaints • OSHA fines
Risk Identification
Risk ID Risk Scenario Potential Cause Potential Consequences
Risk Identification
Risk M
onitoring/
Control
Risk Identification
• 62 risk scenarios for 6 risk categories
Risk Categories
(8,12.9%)
(9,14.5%)
(26,41.9%)
(11,17.7%)
(5,8.1%)
(3,4.8%)
0%
10%
20%
30%
40%
50%DesignandGeotechnical
Logistics/Access
Construction
Environmental
Safety&Security
OperationandMaintenance
RiskCategories(# ofRisks,Percentages)
3.A.3) Add. Analyses
Risk Analysis & Evaluation
Risk Response Strategies
Possible 3 High 4 2 2 4 12 Undesirable • Instrumentation and monitoring• P lan for alternative approach to attenuate no ise• Contractor to comply with work plan/EIR requirements and PM oversight
Very Unlikely
1 M edium 3 1 1 3 3 N egligible
Com
plia
nce
Rep
utat
ion
Residual Risk Score/Class
Residual Impact C
ost
Tim
eH
ealth
&Sa
fet
Envi
ronm
ent
Com
mun
ity
Com
mun
ityC
ompl
ianc
eR
eput
atio
n
Initial Risk Score/Class
Proposed Mitigation Measures Residual Probability
Initial Probability
Initial Impact C
ost
Tim
eH
ealth
&Sa
fet
Envi
ronm
ent
Risk Analysis/ Evaluation - Pre- Mitigation Risk Re-evaluation - Post-Mitigation
• Likelihood of Occurrence (Probability)• Severity of Impact (Impact) • Risk = Probability x Impact• Initial Risks vs. Residual Risks
3.A.3) Add. Analyses
Risk Identification
Risk M
onitoring/
Control
1 2 3 4 5
Increasing Risk
15 20 25 Intolerable 16-25
Increasing Risk
12 16 20 Undesirable 10-15
Very Likely 5 5 10
9 12 15 Tolerable 5-9
Likely 4 4 8
6 8 10 Negligible 1-5
Possible 3 3 6
Unlikely 2 2 4
4 5 Risk Class
High Very High
Prob
abili
ty
Very Unlikely 1 1 2 3
Impact
Very Low Low Medium
Probability x Impact = Risk
Risk Scoring Matrix3.A.3) Add. Analyses
Risk Response & Mitigation3.A.3) Add. Analyses
Risk Identification
Risk M
onitoring/
Control
• Avoid: Eliminate a threat • Accept: Accept residual risks and take no
action unless the risk occurs• Transfer: A threat still exists, but it is
owned/managed by another party• Mitigate: Reduce probability and/or impact
of risks to acceptable level
Risk Response Strategies
DG - 006 Unknown condition of Laguna Royale caisson foundations
12 Undesirable • Pre-construction probe hole investigation • Design and location adjustments will be included based on findings• Instrumentation and monitoring during construction and contingency plan
4 N egligible
Residual Risk Score/Class
Initial Risk Score/Class
Proposed Mitigation Measures
Risk Identification Pre- Mitigation Post-Mitigation
Risk ID Risk Scenario
Risk Monitoring & Control3.A.3) Add. Analyses
Risk Identification
Risk M
onitoring/
Control
• Risk Status : Current status of the risk element– Active: Risk is being actively monitored and
controlled– Dormant: Risk is not currently a high priority,
but may become active in the future– Retired: Risk is not longer a threat to project
objectives• Risk Owner : Party who owns the risk and is
responsible for implementing the response actions and monitoring risks
Engineer Active
Risk Monitoring and Control
Risk Owner
Risk Status
• Baseline vs. 4i
Negligible 12, 19.4% 60, 96.8% 16, 25.8% 54, 87.1%
Tolerable 35, 56.5% 2, 3.2% 36, 58.1% 6, 9.7%
Undesirable 15, 24.2% 0, 0.0% 9, 14.5% 1, 1.6%
Intolerable 0, 0.0% 0, 0.0% 1, 1.6% 1, 1.6%
RiskClassOption4i
InitialRisks ResidualRisks InitialRisks
Baseline
ResidualRisks
Comparison of Risk Assessment3.A.3) Add. Analyses
• Challenging operation & Maintenance• Inefficiencies associated with laying pipe
RiskID RiskScenarios InitialRiskClass ResidualRiskClass
DG‐005 Soilrockinterfaceattheshaft‐flowablesandand/orgroundwatercontrol Undesirable Negligible
DG‐006 UnknownconditionofLagunaRoyalecaissonfoundations Undesirable Negligible
CO‐010 SlopefailureatAdits23&25 Undesirable Negligible
CO‐011 LagunaLidocondominiums10ftabovetunnelcrown Undesirable Negligible
LA‐015 Accessdifficulties/complaintsat4thAveShaftSite Undesirable Negligible
LA‐016 InabilitytodelivermaterialsorremovewasteatAdit16A/B Undesirable Negligible
CO‐021 Slopeinstabilityatportals2and4andadits16A/B Undesirable Negligible
CO‐022 Unexpectedvoidorsignificantgroundloss(overbreak) Undesirable Tolerable
CO‐031DestabilizationofbluffduringtunnelexcavationinAreasofConcernotherthanlowcove
Undesirable Negligible
CO‐033 Instabilityinlowcoverareatriggersneedtoexcavatefromsurface Undesirable Negligible
EN‐046 Communitycomplaintsnoiseissues Undesirable NegligibleEN‐048 Traffic‐excessivevehiclesworkingatthesite Undesirable NegligibleEN‐052 Beachlandings Undesirable Negligible
SS‐055 Seriousaccident/injurytoworkersduringconstruction Undesirable Negligible
SS‐056 Accident/injuryoccurswithslow/delayresponsetime Undesirable Negligible
Risks with Higher Risk Levels for Baseline3.A.3) Add. Analyses
RiskID RiskScenarios InitialRiskClass ResidualRiskClass
DG‐005 Soilrockinterfaceattheshaft‐flowablesandand/orgroundwatercontrol Undesirable Negligible
CO‐010 SlopefailureatAdits23&25 Undesirable Tolerable
LA‐015 Accessdifficulties/complaintsat4thAveShaftSite Undesirable Negligible
LA‐016 InabilitytodelivermaterialsorremovewasteatAdit16A/B Undesirable Negligible
CO‐021 Slopeinstabilityatportals2and4andadits16A/B Undesirable Tolerable
CO‐043 Inefficienciesassociatedwithlayingpipe Undesirable UndesirableEN‐052 Beachlandings Undesirable Negligible
SS‐055 Seriousaccident/injurytoworkersduringconstruction Undesirable Negligible
SS‐056 Accident/injuryoccurswithslow/delayresponsetime Undesirable Negligible
OM‐060 Challengingoperation&maintenance Intolerable Intolerable
Risks with Higher Risk Levels for Option 4i3.A.3) Add. Analyses
InitialRisks ResidualRisks InitialRisks ResidualRisks
460 181 430 212TotalRiskScores
Baseline Option4i
Risk Scores (Baseline vs. 4i)
62 61
207
87
36
7
46
61
184
71
35 33
0
50
100
150
200
250
DG LA CO EN SS OM
RiskScore
RiskCategory
ComparisonofInitialRiskScoresbyRiskCategory
InitialRisks(Baseline)
InitialRisks(Option4i)
Symbol RiskCategoriesDG DesignandGeotechnicalLA Logistics/AccessCO ConstructionEN EnvironmentalSS Safety&SecurityOM OperationandMaintenance
25 24
79
30
167
21 24
95
2415
33
0
50
100
150
200
250
DG LA CO EN SS OM
RiskScore
RiskCategory
ComparisonofResidualRiskScoresbyRiskCategory
ResidualRisks(Baseline)
ResidualRisks(Option4i)
Symbol RiskCategoriesDG DesignandGeotechnicalLA Logistics/AccessCO ConstructionEN EnvironmentalSS Safety&SecurityOM OperationandMaintenance
• Total Risk Scores
• Risk Scores by Risk Category
3.A.3) Add. Analyses
• Overall risk profiles for both options similar.• Except for risks associated with limited space of tunnel, operation and maintenance issues, and future ability to replace the 24‐inch sanitary sewer pipe, results from risk assessment indicate Option 4i compares favorably to Baseline option.
• Baseline: tunnel excavation and more construction activities (greater initial risks with higher risk scores); it appears that most risks may be mitigated to acceptable risk levels.
• 4i: Minimal additional excavation work; risks associated with limited work space cannot be mitigated
Summary of Comparative Risk Analysis3.A.3) Add. Analyses
Alternative 4y
• Smaller version of Baseline (9 ft by 9 ft) • 7 ft wide by 6.5 ft high• Evaluate
– Cost Savings– Safety and Risks– Constructability
3.B. Add. Analyses
4y Cost Evaluation7 ft wide by 6.5 ft high
•Cost Evaluation based on Kiewit Confidential Estimate•Comparing Volume of Materials (less)•Volume of Support (less)•$6 m savings
3.B. Add. Analyses
3.B. Add. Analyses
Safety and Risk• Similar Favorable Safety Comparison to Baseline Design/4y and 4i
• Similar Favorable Risk Comparison to Baseline Design/4y and 4i
Comparison of Savings and Costs* for Baseline, 4i, 4y
Summary of SavingsBaseline 4i 4yNA $22m $6mNew Pipe ‐$10mNet $12m
Summary of Total CostsBaseline 4i 4y$78m $68 m $74m
*Based on Kiewit’s Confidential Cost Proposal using Negotiated Procurement
3.B. Add. Analyses
Optimum Diameter• Sweet Spot between 7 and 9 ft.• Compromise between Construction vs. O & M• Bucket Brigade vs. Mechanized Tunneling
3.B. Add. Analyses
Tunnel Width (ft) Costs Comment
6 87 HMM (2014)7 64 Parsons (2016) factored Kiewit (2012), no efficiency factors9 78 HMM (2014)9 78.4 Kiewit (2012)
y = 10.033x2 ‐ 153.43x + 646.4R² = 0.9997
0
10
20
30
40
50
60
70
80
90
100
0 1 2 3 4 5 6 7 8 9 10
Cost in
millions of d
ollars
Beach Interceptor Tunnel Width (ft)
Tunnel Width vs. Project CostsSeries1
4. Pros and Cons of AlternativesUn‐weighted/no importance factors
4. Pros & Cons
Alternative/Attribute
O&M spa
ce
Constructability
Perm
itIssues
Muck Issues
Ease of N
ew
Pipe
Install
1 or 2 pipes
(Old Pipe)
OverallRisks
Safety and
Stab
ility
Life of Facility
Suscep
tible
to
Unk
nowns
(Cost con
trol)
CostSavings
Summary
Baseline + + o ‐ + + o o + + ‐ 6+, 3o, 2‐
4i ‐ o ‐ + ‐ ‐ o o o ‐ + 2+, 4o, 5‐
4y + + o + + + o o + + o 7+, 4o, 0‐
Simplified Qualitative Comparative Rating Scale+ Positive/Favorable/Pro ‐ Advantageo Neutral‐ Negative/Unfavorable/Con ‐ Disadvantage
Other Pros and Cons
*Access Permit conditions– 12 months at Portals 2 and 4 are good for fixes up to Adit 10. – Need new shaft to preserve permit conditions
4. Pros & Cons
Attribute Baseline 4i 4y
Muck NA Negligible 800 less truck loads
Ease of New Pipe Construction Best Poor Good
Construction Technique MechanizedTunneling
Bucket Brigade
MechanizedTunneling
Maintenance Ease & Access Best Poor Good
“Absolutes” Design Criteria Preserved Yes No Yes
Existing Permit Conditions* Good Moderate Good
Flexibility for Separate New Pipeline Pkg Good Good Good
Flexibility for Packaging of Repairs Fair to Poor Good Fair to Poor
4th Ave Shaft Required Yes Maybe Yes
5. Alternative Contract TypesA. Negotiated Procurement (Existing Target Price)
– Insurance & Profit Reasonable Cost– OH & Mgmt High Cost
B. Discussion: Other Contract Types 1) Design Build Least Control2) CM at Risk Less Control3) Design Bid Build Most Control
5. Contracts
5.B.1) Design BuildPro: • Suitable for large CIP with small Owner Organization and large complex projects• Single Point of Responsibility• Early construction knowledge avoids pitfalls of over conservatism in Design• Advantage when schedule is concern to eliminate design steps• Designer and Contractor working together on design reducing risk of Change Orders• Fast track• Market place decide on Design Alternatives• Many Risks shed to Contractor
– E.g. No Differing Site ConditionsCon:• Least control• Cost of bidding higher• Procurement different• Contractor mark‐up of Designer• Strong independent QA/QC sometimes warranted (costs borne by Owner)• Spell out in contract where Owner Control is desired• Timely Correction Action Required• Less Review time• Baseline Design is completed• Baseline Design Criteria is set
5.B.1) Contracts
5.B.2) CM at RiskPro:• Suitable for large CIP with small Owner Organization• Early construction knowledge• Fast track• Competition over individual elements of construction• CM acts as agent of Owner• Guaranteed maximum price (+allowances)• Design taken to some percentage (e.g. 60%)
Con:• Less Control: Set clear expectations; deliverables• Preconstruction services (management)• Baseline Design is completed• Baseline Design Criteria is set
5.B.2) Contracts
5.B.3) Design Bid BuildPro:• Most Control• Low bid is awarded Contract• Design Completed to 100%• Baseline Design is completed• Baseline Design Criteria is setCon:• Multiple points of contact for Owner• Designer/Contractor adversity• Designer cannot foresee who will build
5.B.3) Contracts
5.B.3) Design Bid Build (cont)
• Award Project in Pieces/Task Orders by Section– Geographic (access and permit) and Work (mining vs. new pipe)
– Smaller Specialist Tunnel Rehab Contractors– Insurance and Bonding Issues
• Lump sum (Gmax) plus unit cost contract• Unit Price items per Ground Support classes that may vary– Class 1a, Class 2b etc. – Supplemental Ground Support elements
• Steel sets• CY shotcrete
5.B.3) Contracts
Packaging and AccessPackage 1: Portal 2 and tunnel STA 16+14.5 to 20+80 (466 ft)
Package 2: Portal 4 and tunnel STA 27+54 to 47+94 (2040 ft)• Staging area adjacent to P4 is required for a longer period than 12 months.
Package 3: Tunnel STA 70+04 to STA 47+94 (2210 ft):• Construction is from Adit A15 and would require barge access of materials and equipment. • A staging area would need to be permitted at Adit A15.
Package 4a: Tunnel STA 73+45 to STA 103+28 (2983 ft):• Construction is from Adit 16B and would require barge access of materials and equipment. • The use of the staging area adjacent to Adit 16B is required for a longer period than 12 months.
Package 4b: Tunnel STA 103+28 to STA 120+89 (1761 ft):• Construction is from Adit 16B and/or Adit 23 and would require barge access of materials and equipment. • A staging area would need to be permitted at Adit A23 and Adit 16B is likely required for a longer period than
12 months.
5. Contracts
Packaging and Access TBD
LEM = Labor Equipment Materials Access
Package 1 Package 2
Package 3
Package 4a
E‐2.0/E‐2.24th Ave Shaft for Package 3&4
5. Contracts
Estimated CIP Costs 5. Contracts
Alternative Costs Possible Savings
Baseline $78.4 m (N/A)
4iE‐2.0 Net
$56.4 m
$68.4 m
$22 m‐$10 m$12 m
4y $72.4 m $6 m
Factoring Kiewit’s Confidential Cost Estimate: Target Price
6. Pros and Cons of AlternativesUn‐weighted/no importance factors
6. Pros & Cons
Alternative/Attribute
O&M spa
ce
Constructability
Perm
itIssues
Muck Issues
Ease of N
ew
Pipe
Install
1 or 2 pipes
(Old Pipe)
OverallRisks
Safety and
Stab
ility
Life of Facility
Suscep
tible
to
Unk
nowns
(Cost con
trol)
CostSavings
Summary
Baseline + + o ‐ + + o o + + ‐ 6+, 3o, 2‐
4i ‐ o ‐ + ‐ ‐ o o o ‐ + 2+, 4o, 5‐
4y + + o + + + o o + + o 7+, 4o, 0‐
Simplified Qualitative Comparative Rating Scale+ Positive/Favorable/Pro ‐ Advantageo Neutral‐ Negative/Unfavorable/Con ‐ Disadvantage
6. Pros and Cons of AlternativesImportance Factor /Weighting of Attributes
6. Discussions
Attribute
O&M spa
ce
Constructability
Perm
itIssues
Muck Issues
Ease of N
ew
Pipe
Install
1 or 2 pipes
(Old Pipe)
OverallRisks
Safety and
Stab
ility
Life of Facility
Suscep
tible
to
Unk
nowns
(Cost con
trol)
CostSavings
Summary
6. Other Pros and Cons
*Access Permit conditions– 12 months at Portals 2 and 4 are good for fixes up to Adit 10. – Need new shaft to preserve permit conditions
Attribute Baseline 4i 4y
Muck Negligible 800 less cy
Ease of New Pipe Construction Best Poor Good
Construction Technique MechanizedTunneling
Bucket Brigade
MechanizedTunneling
Maintenance Ease & Access Best Poor Good
“Absolutes” Design Criteria Preserved Yes No Yes
Existing Permit Conditions* Good Moderate Good
Flexibility for Separate New Pipeline Pkg Good Good Good
Flexibility for Packaging of Repairs Fair to Poor Good Fair to Poor
4th Ave Shaft Yes Maybe Yes
6. Discussions
DG - 001 Design errors/omissions 6 T o lerable 2 N egligible 4 N egligible 1 N egligible B aseline B aseline
DG - 003 Conflict and discrepancy between specifications, drawings, GBR
6 T o lerable 2 N egligible 4 N egligible 1 N egligible B aseline B aseline
DG - 004 Late design modifications 9 T o lerable 6 T o lerable 6 T o lerable 4 N egligible B aseline B aseline
DG - 006 Unknown condition of Laguna Royale caisson foundations
12 Undesirable 4 N egligible 6 T o lerable 4 N egligible B aseline Same
DG - 008 Insufficient engineering support during construction 6 T o lerable 2 N egligible 3 N egligible 2 N egligible B aseline Same
CO - 009 Utility conflict/delay 9 T o lerable 2 N egligible 6 T o lerable 2 N egligible B aseline Same
CO - 011 Laguna Lido condominiums 10 ft above tunnel crown 12 Undesirable 2 N egligible 9 T o lerable 2 N egligible B aseline Same
CO - 022 Unexpected void or significant ground loss (overbreak)
12 Undesirable 6 T o lerable 8 T o lerable 6 T o lerable B aseline Same
CO - 024 SDG&E electrical power delayed 9 T o lerable 4 N egligible 6 T o lerable 2 N egligible B aseline B aseline
CO - 027 M ore boulders during excavation 9 T o lerable 4 N egligible 4 N egligible 2 N egligible B aseline B aseline
CO - 029 Excessive ground movements 9 T o lerable 2 N egligible 6 T o lerable 2 N egligible B aseline Same
CO - 030 Vibrations in excess of allowable (EIR) 9 T o lerable 4 N egligible 4 N egligible 2 N egligible B aseline B aseline
CO - 031 Destabilization of bluff during tunnel excavation in Areas of Concern other than low cover
12 Undesirable 3 N egligible 8 T o lerable 3 N egligible B aseline Same
CO - 033 Instability in low cover area triggers need to excavate from surface
12 Undesirable 3 N egligible 8 T o lerable 3 N egligible B aseline Same
CO - 036 Portal 2 increased risk o f exposure to unstable face 9 T o lerable 2 N egligible 6 T o lerable 2 N egligible B aseline Same
CO - 037 Undocumented foundations that impact tunnel rehabilitation
6 T o lerable 2 N egligible 4 N egligible 1 N egligible B aseline B aseline
CO - 042 M aterials/equipment shortages & delayed procurements
9 T o lerable 2 N egligible 4 N egligible 1 N egligible B aseline B aseline
EN - 045 Negative visual impacts to residences 6 T o lerable 3 N egligible 6 T o lerable 2 N egligible Same B aseline
EN - 046 Community complaints noise issues 12 Undesirable 3 N egligible 9 T o lerable 2 N egligible B aseline B aseline
EN - 047 Beach activities interfere with recreation 9 T o lerable 2 N egligible 6 T o lerable 2 N egligible B aseline Same
EN - 048 Traffic-excessive vehicles working at the site 12 Undesirable 3 N egligible 6 T o lerable 2 N egligible B aseline B aseline
EN - 049 Truck traffic-neighborhood impacts 6 T o lerable 4 N egligible 4 N egligible 2 N egligible B aseline B aseline
EN - 050 Air quality issues 8 T o lerable 3 N egligible 6 T o lerable 2 N egligible B aseline B aseline
SS - 059 Public injury 5 T o lerable 4 N egligible 4 N egligible 3 N egligible B aseline B aseline
Option 4iResidual
RisksInitial RisksResidual Risk
Score/ClassInitial Risk
Score/ClassResidual Risk Score/Class
Initial Risk Score/Class
BASELINE
Risk ID Risk Scenario
Baseline: Risks with Higher Risk Scores compared to 4i
6. Discussions
CO - 010 Slope failure at Adits 23 & 25 12 Undesirable 4 N egligible 12 Undesirable 6 T o lerable Same Optio n 4i
CO - 021 Slope instability at portals 2 and 4 and adits 16A/B 12 Undesirable 4 N egligible 12 Undesirable 6 T o lerable Same Optio n 4i
CO - 025 Excessive groundwater ingress 4 N egligible 2 N egligible 9 T o lerable 4 N egligible Optio n 4i Opt io n 4i
CO - 034 Damage to existing pipe after encasement (overload) 4 N egligible 2 N egligible 8 T o lerable 6 T o lerable Optio n 4i Opt io n 4i
CO - 043 Inefficiencies associated with laying pipe 1 N egligible 1 N egligible 15 Undesirable 15 Undesirable Optio n 4i Opt io n 4i
OM - 060 Challenging operation 2 N egligible 2 N egligible 16 Into lerable 16 Into lerable Optio n 4i Opt io n 4i
OM - 061 Long term maintenance 1 N egligible 1 N egligible 9 T o lerable 9 T o lerable Optio n 4i Opt io n 4i
OM - 062 Hazard for workers and sewer line 4 N egligible 4 N egligible 8 T o lerable 8 T o lerable Optio n 4i Opt io n 4i
Residual Risk Score/Class
Initial Risk Score/Class
Residual Risk Score/Class
Initial Risk Score/Class
Risk ID Risk Scenario
BASELINE Option 4iInitial Risks
Residual Risks
4i: Risks with Higher Risk Scores compared to Baseline
6. Discussions