Page 1: Vala 900 Phase IV Presentation

Vala 900Phase IV

Presentation

Prepared by: Peter GARDENER

& Ekrem CËRVADIKU

Page 2: Vala 900 Phase IV Presentation

Objectives

• Utilize latest Technology• Offer all the existing and latest features• Ability to meet future market needs• Expandable in modular fashion without service

interruption• Offer reliable and quality service• Minimize costs• Seamless integration with other vendors network

equipment and systems

Page 3: Vala 900 Phase IV Presentation

Objectives

• Increase the Network Capacity to support 700.000 customers

• Increase Network Coverage to cover 99% of populated areas

• Improve Network Quality. Achieve Call Blocking and Call Drop rates of 2% “Black Spots”

• Improve existing Products and Services; SMS,VM• Introduce new innovative Product and Services; GPRS,

MMS• Introduce Operational Support Systems to Plan and

manage the GSM Network

Page 4: Vala 900 Phase IV Presentation

Main Factors

• Forthcoming Competition

• Predicted Lack of Capacity

• Lack of GSM Coverage in Populated Areas

• Improvement to Network Quality

• Minimal Product and Services Offering

• Lack of Automated Systems and Tools to manage and optimize the Network

Page 5: Vala 900 Phase IV Presentation

Benefits

• Increasing capacity

• Improving coverage

• Improving quality

• Value Added Services

• Automated Planning and Management Systems

Page 6: Vala 900 Phase IV Presentation

Phase III

• Capacity to support 400.000 customers

• 85% coverage of the population

• 2 MSC-s

• 176 BTS-es

Page 7: Vala 900 Phase IV Presentation

Coverage

Page 8: Vala 900 Phase IV Presentation

Phase IV

• Capacity to support 700.000 customers

• 99% coverage of the population

• 3 MSC-s

• 286 BTS-es

Page 9: Vala 900 Phase IV Presentation

Implementation

• Implementation 12 – 18 months• BTS Civil Works Commenced November 2005• Ease congestion in Prizren late 2005/2006.

Prishtina, Gjakova, Peja - ongoing during project lifecycle

• New Services Commercial Available to market QTR2 2006

• In Parallel enhancements to systems / platforms ongoing during project lifecycle

• Upgrade Network Transmission/Topology/Resilience ongoing during project lifecycle

Page 10: Vala 900 Phase IV Presentation

Health and Safety

• Public shouldn’t be exposed to:

- electric field above 41 Volt/meter

- magnetic field above 11 Amper/meter

• 12/07/1999 European Community

• All European Community regulations Adhered to

Page 11: Vala 900 Phase IV Presentation

• Electromagnetic Compatibility (EMC)

• Acoustic noise

• Safety

• Product Environmental Attributes

• Materials

Health and Safety

Page 12: Vala 900 Phase IV Presentation

Health and Safety

• GSM antenna 4m 10 V/m

• LargPerquesi(400KV) 100m 200 V/m

• Refrigerator 30 cm 90 V/m

• Iron 30 cm 60 V/m

• Hair dryer 10 cm 40 V/m