Utilty Scale Solar PV Project Experience final - Electric … · 2014-10-15 · Example Reactive...

33
Utility Scale Solar PV Project Experience William Peter System Engineer, Grid Integration ERCOT Emerging Technologies Working Group Solar Workshop © 2011 SunPower Corporation ERCOT Emerging Technologies Working Group Solar Workshop April 25 th 2011

Transcript of Utilty Scale Solar PV Project Experience final - Electric … · 2014-10-15 · Example Reactive...

Page 1: Utilty Scale Solar PV Project Experience final - Electric … · 2014-10-15 · Example Reactive Power Testing Procedures Test Condition Test Req i ementRequirement Maintain voltage

Utility Scale Solar PV Project ExperienceWilliam Peter

System Engineer, Grid IntegrationERCOT Emerging Technologies Working Group Solar Workshop

© 2011 SunPower Corporation

ERCOT Emerging Technologies Working Group Solar WorkshopApril 25th 2011

Page 2: Utilty Scale Solar PV Project Experience final - Electric … · 2014-10-15 · Example Reactive Power Testing Procedures Test Condition Test Req i ementRequirement Maintain voltage

Safe Harbor StatementThis presentation contains forward looking statements within the meaning of the Private SecuritiesThis presentation contains forward-looking statements within the meaning of the Private Securities Litigation Reform Act of 1995. Forward-looking statements are statements that do not represent historical facts and may be based on underlying assumptions. SunPower uses words and phrases such as "expects," “believes,” “plans,” “anticipates,” "continue," "growing," "will," to identify forward-looking statements in this presentation, including forward-looking statements regarding: (a) plans and expectations regarding the company’s cost reduction roadmap, (b) cell manufacturing ramp plan, (c) financial forecasts, (d) future government award funding, (e) future solar and traditional electricity rates, and (f) trends and growth in the solar industry. Such forward-looking statements are based on information available to the company as of the date of this release and involve a number of risks and uncertainties, some beyond the company's control that could cause actual results to differ materially from those anticipated by thesecompany s control, that could cause actual results to differ materially from those anticipated by these forward-looking statements, including risks and uncertainties such as: (i) the company's ability to obtain and maintain an adequate supply of raw materials and components, as well as the price it pays for such; (ii) general business and economic conditions, including seasonality of the industry; (iii) growth trends in the solar power industry; (iv) the continuation of governmental and related economic incentives promoting the use of solar power; (v) the improved availability of third-party financing arrangements for the company's customers; (vi) construction difficulties or potential delays, including permitting and transmission access and upgrades; (vii) the company's ability to ramp new production lines and realize expected manufacturing efficiencies; (viii) manufacturing difficulties that could arise; (ix) the success of the company's ongoing research and development efforts to compete with other companies and competingcompany s ongoing research and development efforts to compete with other companies and competing technologies; and (x) other risks described in the company's Annual Report on Form 10-K for the year ended January 3, 2010, and other filings with the Securities and Exchange Commission. These forward-looking statements should not be relied upon as representing the company's views as of any subsequent date, and the company is under no obligation to, and expressly disclaims any responsibility to, update or alter its for ard looking statements hether as a res lt of ne information f t re e ents or other ise

© 2011 SunPower Corporation

2

alter its forward-looking statements, whether as a result of new information, future events or otherwise.

Page 3: Utilty Scale Solar PV Project Experience final - Electric … · 2014-10-15 · Example Reactive Power Testing Procedures Test Condition Test Req i ementRequirement Maintain voltage

Outline Utility Scale Solar PV

– Introduction to SunPower

S P P j t E l– SunPower Project Examples

– OASIS: Tracking Solar PV Power Plant Blocks

Grid Integration of Solar PV

– Voltage Support

– Fault Ride Through

– Active Power Management

– Frequency Support

– System Impact Studies

© 2011 SunPower Corporation

3

Page 4: Utilty Scale Solar PV Project Experience final - Electric … · 2014-10-15 · Example Reactive Power Testing Procedures Test Condition Test Req i ementRequirement Maintain voltage

SunPower 2011 – The World’s Standard for Solar2010: Revenue $2.15-$2.25B5,500+ Employees550+ MW 2010 production

World-leading solar conversion efficiencyDiversified portfolio: roofs to power550+ MW 2010 production

>1.5 GW solar PV deployed5 GW power plant pipeline

Diversified portfolio: roofs to power plants1,500 dealer partners, #1 R&C USA

Commercial Power PlantsResidential

© 2011 SunPower Corporation

4

Page 5: Utilty Scale Solar PV Project Experience final - Electric … · 2014-10-15 · Example Reactive Power Testing Procedures Test Condition Test Req i ementRequirement Maintain voltage

SunPower To Open Operations Center in Austin, TX

SunPower is expanding into Texas with a new operations center in Austin

SunPower will create 450 jobs in the region by 2015 beginning withthe region by 2015, beginning with 115 jobs created in 2011

The new Austin facility will house operations including marketing, legal, and finance functions

© 2011 SunPower Corporation

5

Page 6: Utilty Scale Solar PV Project Experience final - Electric … · 2014-10-15 · Example Reactive Power Testing Procedures Test Condition Test Req i ementRequirement Maintain voltage

Over 250 MW of power plants installed in Europe

Olivenza, SPAINSerpa, PORTUGAL Isla Mayor, SPAIN Jumilla, SPAIN Montalto, ITALY Muehlhausen, © 2011 SunPower Corporation

,18 MW

Se pa, O UG11 MW

y ,8 MW

,23 MW

6

,72 MW

,GERMANY, 6 MW

Page 7: Utilty Scale Solar PV Project Experience final - Electric … · 2014-10-15 · Example Reactive Power Testing Procedures Test Condition Test Req i ementRequirement Maintain voltage

SunPower Utility Solar PV Power Plants Examples of Project Experience

YEAR MARKET MW NAME

2004 Germany 10 Solar Bavaria2004 Germany 10 Solar Bavaria

2006 Portugal 11 Serpa

2007 U.S. - Nevada 14 Nellis Air Force Base

2008 Spain 18 Olivenza

2009 U.S. - Florida 35 DeSoto (FPL)

2010 Italy 72 Montalto di Castro

2010 U.S. - Colorado 19 Greater Sandhill (Xcel)

2011 U.S.- California 250 CVSR (PG&E)

© 2011 SunPower Corporation

7

Page 8: Utilty Scale Solar PV Project Experience final - Electric … · 2014-10-15 · Example Reactive Power Testing Procedures Test Condition Test Req i ementRequirement Maintain voltage

M t lt 72 MWMontalto 72 MWLazio, Italy

© 2011 SunPower Corporation

8

Page 9: Utilty Scale Solar PV Project Experience final - Electric … · 2014-10-15 · Example Reactive Power Testing Procedures Test Condition Test Req i ementRequirement Maintain voltage

N lli AFB 14 MW NVNellis AFB 14 MW: NV energyLas Vegas, NV, U.S.

© 2011 SunPower Corporation

9

Page 10: Utilty Scale Solar PV Project Experience final - Electric … · 2014-10-15 · Example Reactive Power Testing Procedures Test Condition Test Req i ementRequirement Maintain voltage

G t S dhill 19 MW X lGreater Sandhill 19 MW: XcelAlamosa County, Colorado, U.S.

© 2011 SunPower Corporation

10

Page 11: Utilty Scale Solar PV Project Experience final - Electric … · 2014-10-15 · Example Reactive Power Testing Procedures Test Condition Test Req i ementRequirement Maintain voltage

California Valley Solar Ranch (CVSR)

250 MW PPA with PG&E

Target Schedule– Q3/Q4 2011 – Start of Construction– Q4 2011/Q1 2012 – Phase I

Complete/First 25MW on-line– Q4/2013 – Project Completionj p

Permit recently approved by San Luis Obispo county supervisors 5-0Luis Obispo county supervisors 5 0

© 2011 SunPower Corporation

11

Page 12: Utilty Scale Solar PV Project Experience final - Electric … · 2014-10-15 · Example Reactive Power Testing Procedures Test Condition Test Req i ementRequirement Maintain voltage

SunPower Oasis Power Plant

The SunPower Oasis power plant is a modular utility solar platform consisting of configurable 1.5 MW PV power blocks

coupled with a sophisticated plant operating system© 2011 SunPower Corporation

12

p p p p g y

Page 13: Utilty Scale Solar PV Project Experience final - Electric … · 2014-10-15 · Example Reactive Power Testing Procedures Test Condition Test Req i ementRequirement Maintain voltage

The SunPower Oasis Tracker & 425 W Panel

S P T0 T kSunPower T0 Tracker

Most installed solar tracker in the world – 400MW over 10 years

Increases capacity factor by up to 25%

Simple control system = lowest O&M of any PV power plant fixed or tracking Jeonju Korea

SunPower 425W panel has today’s highest efficiency

Jeonju, Korea2 MW

© 2011 SunPower Corporation

13

Page 14: Utilty Scale Solar PV Project Experience final - Electric … · 2014-10-15 · Example Reactive Power Testing Procedures Test Condition Test Req i ementRequirement Maintain voltage

Oasis Power Block Enhances Production

Fixed TiltSunPower Oasis

nt O

utpu

t

Up to 25% moreenergy delivery

ratio

n of

Pla

Illus

tr

1:00 AM 6:00 AM Noon 6:00 PM Midnight

© 2011 SunPower Corporation

14

Page 15: Utilty Scale Solar PV Project Experience final - Electric … · 2014-10-15 · Example Reactive Power Testing Procedures Test Condition Test Req i ementRequirement Maintain voltage

Outline Utility Scale Solar PV

– Introduction to SunPower

S P P j t E l– SunPower Project Examples

– OASIS: Tracking Solar PV Power Plant Blocks

Grid Integration of Solar PV

– Voltage Support

– Fault Ride Through

– Active Power Management

– Frequency Support

– System Impact Studies

© 2011 SunPower Corporation

15

Page 16: Utilty Scale Solar PV Project Experience final - Electric … · 2014-10-15 · Example Reactive Power Testing Procedures Test Condition Test Req i ementRequirement Maintain voltage

Progress in Solar PV Integration

Solar PV’s initial application was residential and commercial– Standards (UL1741, IEEE 1547) intended for distribution networks

I t f di t ib ti t k i iti ll d i d ith t– Inverters for use on distribution networks initially designed without LVRT, voltage control, etc. to meet these requirements

SunPower Utility Scale PV plants have the technical capabilities to provide features similar to modern wind plants:

– Ride Through (Voltage and Frequency) – Real Power Curtailmentg ( g q y)– Over Frequency Droop Response – Reactive Power Support

Grid integration products in the market are evolving Grid integration products in the market are evolving

© 2011 SunPower Corporation

16

Page 17: Utilty Scale Solar PV Project Experience final - Electric … · 2014-10-15 · Example Reactive Power Testing Procedures Test Condition Test Req i ementRequirement Maintain voltage

OASIS Grid Integration Options Reactive Power

– +/- 0.95 PF at POI

– Voltage Power Factor orVoltage, Power Factor, orReactive Power Control

Fault Ride-ThroughFault Ride Through– Configurable Voltage and

Frequency Ride though Windows

Over Frequency Droop Response

Active Power Curtailmentfrom 0 to 100%

© 2011 SunPower Corporation

17

Page 18: Utilty Scale Solar PV Project Experience final - Electric … · 2014-10-15 · Example Reactive Power Testing Procedures Test Condition Test Req i ementRequirement Maintain voltage

Reactive Power RequirementsIllustration of ExampleReactive Power Requirement at POI

0.4

Illustration of Example Reactive Power Requirement at POI

Leading Lagging

BShaded Area 1 BShaded Area 1

0.2

0.3

pu]

20% P

max

max= 1p

u

20% P

max

max= 1p

u

0

0.1

0 0.2 0.4 0.6 0.8 1 1.2ve Pow

er (Q

) [p

P < 2 P m

A

P < 2 P m

A

‐0.2

‐0.1

Reactiv

‐0.4

‐0.3

Real Power (P) [pu]

© 2011 SunPower Corporation

18

Page 19: Utilty Scale Solar PV Project Experience final - Electric … · 2014-10-15 · Example Reactive Power Testing Procedures Test Condition Test Req i ementRequirement Maintain voltage

Reactive Power as Function of Voltage at POIIll t ti f R ti P F ti f POI V lt

0.3

0.4

Illustration of  Reactive Power as Function of POI Voltage

PF=0.95 B

0.1

0.2

(Q) [pu

]

‐0.1

0

active Pow

er (

A

‐0.3

‐0.2Rea

‐0.4

0.85 0.9 0.95 1 1.05 1.1 1.15

Voltage at POI [pu]

© 2011 SunPower Corporation

19

Page 20: Utilty Scale Solar PV Project Experience final - Electric … · 2014-10-15 · Example Reactive Power Testing Procedures Test Condition Test Req i ementRequirement Maintain voltage

Example Reactive Power Testing ProceduresTest Condition Test Req i ement Test Condition Test Requirement

Maintain voltage setpoint

P = 25% to >92.5% of Available Capacity

Set voltage setpoint to 1.02 pu

Voltage held within +/- 1%, subject to p.f. limits and Available Capacity. New voltage setpoint(s) may be selected. p y

Compensate for changing transmission conditions

Q = ~0 MVAR output after LTC is adjusted several steps

Set voltage setpoint as necessary

Q <=0 MVAR at POI

Lead/Lag 0.95 limits

P = 25%, 50%, 75% and >92.5% of Available Capacity,

Set voltage to demonstrate 0.95 p.f. Lead

Meter shop test equipment indicates 0.95 or less

Set voltage to d t t

Meter shop test equipment indicates 0 95 l

p y,limited to 9.4 MVAR at POI.

demonstrate 0.95 p.f. Lag

0.95 or less

Raise/lower setpoint

P > 50% of Available Capacity

Series selected at time of test (ex:

Voltage at POI is consistent with change in setpoint, subject to p.f. limits and within the ability of the

Available Capacity = Total plant power output correcting for environmental variables (e.g.

Capacity (ex: Raise/Lower voltage 0.005pu)

limits and within the ability of the plant to influence the voltage

© 2011 SunPower Corporation

p y p p p g ( girradiance, temperature).

20

Page 21: Utilty Scale Solar PV Project Experience final - Electric … · 2014-10-15 · Example Reactive Power Testing Procedures Test Condition Test Req i ementRequirement Maintain voltage

Example of Test DemonstrationS f l t t f Successful test of reactive power tests for SunPower UtilityS S

1.045

1.051.5

Demonstration of Reactive Power

Reactive Power (pu) Real Power (pu) Voltage at POI (pu)

Scale Solar PV Plant

Demonstrated at 1.03

1.035

1.04

1.045

0.5

1

 (pu)

Power (p

u)

Demonstrated atrange of Poweroutputs during the morning 1.015

1.02

1.025

‐0.5

0

Volta

ge at PO

I

eal and

 Reactive P

morning

Reaches Full Reactive Power 1

1.005

1.01

‐1.5

‐1

Re

Requirements (+/-0.95 pf)

7:30 7:40 7:50 8:00 8:10 8:20 8:30 8:40 8:50 9:00 9:10 9:20 9:30

© 2011 SunPower Corporation

21

Page 22: Utilty Scale Solar PV Project Experience final - Electric … · 2014-10-15 · Example Reactive Power Testing Procedures Test Condition Test Req i ementRequirement Maintain voltage

Voltage Control(1) Rise in

transmission system voltage

(1) Rise in transmission

system voltage

(2) SunPower PV Plant(2) SunPower PV Plant

(3) Transmission voltage returns to

setpoint

(3) Transmission voltage returns to

setpoint(2) SunPower PV Plant absorbs reactive power to reduce transmission

voltage

(2) SunPower PV Plant absorbs reactive power to reduce transmission

voltage

setpointsetpoint

SunPower PV Plant operational in North America with automated voltage control on the transmission system

SunPower PV Plant operational in North America with automated voltage control on the transmission system

© 2011 SunPower Corporation

22

Page 23: Utilty Scale Solar PV Project Experience final - Electric … · 2014-10-15 · Example Reactive Power Testing Procedures Test Condition Test Req i ementRequirement Maintain voltage

Summary of Reactive Power Requirements

SunPower Utility Scale PV Plants have demonstrated bilit t id ti t d h lability to provide reactive power support and help

maintain voltage

Shared goal of grid reliability and stability

R i t th t d i d t t id t bilit– Requirements that are designed to promote grid stability and reliability while avoiding market barriers

– Utility Testing and Operational Requirements– Utility Testing and Operational Requirements

© 2011 SunPower Corporation

23

Page 24: Utilty Scale Solar PV Project Experience final - Electric … · 2014-10-15 · Example Reactive Power Testing Procedures Test Condition Test Req i ementRequirement Maintain voltage

Regulatory Ride Through Requirements Rules on Ride through still evolving in U S and elsewhere Rules on Ride through still evolving in U.S. and elsewhere

– OASIS has configurable Voltage and Frequency Ride though Windows– Ex: FERC Order 661-A, NERC PRC-024 (Draft), WECC ONF, MV BDEW

Example of LVRT Requirement: Ride through three phase faults on transmission grid with normal clearing times (4-9 cycles)

 Under‐frequency Limit   Over‐frequency Limit  WECC Minimum Time > 59.4 Hz 60 Hz to < 60.6 Hz N/A (continuous operation)

WECC Off‐Nominal Frequency (ONF) Tolerance

   59.4 Hz 60 Hz to   60.6 Hz N/A (continuous operation) ≤ 59.4 Hz    ≥60.6 Hz    3 minutes   ≤ 58.4 Hz   ≥61.6 Hz    30 seconds  ≤57.8 Hz 7.5 seconds ≤57.8 Hz    7.5 seconds   ≤57.3 Hz  45 cycles≤57 Hz    >61.7 Hz   Instantaneous trip  

© 2011 SunPower Corporation

24

Page 25: Utilty Scale Solar PV Project Experience final - Electric … · 2014-10-15 · Example Reactive Power Testing Procedures Test Condition Test Req i ementRequirement Maintain voltage

Ride Through

Example of operationalSunPower Solar PV Plantriding through a disturbanceriding through a disturbance

Voltage and FrequencyRide Through

Plant remains online andPlant remains online and continues providing poweras the grid recovers

See: “METHODS OF INTEGRATING A HIGH PENETRATION PHOTOVOLTAIC POWER PLANT INTO A MICRO GRID”, Lars Johnson, 35thIEEE

© 2011 SunPower Corporation

25

, ,PVSC, Honolulu, Hawaii, June 2010.

Page 26: Utilty Scale Solar PV Project Experience final - Electric … · 2014-10-15 · Example Reactive Power Testing Procedures Test Condition Test Req i ementRequirement Maintain voltage

Lanai (Hawaii) 1.2 MW ProjectL i k t l d Lanai peak net load:4.7 MW

Operational since:D b 2008December, 2008

Lanai City & Koele Lodge

PV Plant

Miko Basin Power Plant

Manele Hotel

© 2011 SunPower Corporation

26

Page 27: Utilty Scale Solar PV Project Experience final - Electric … · 2014-10-15 · Example Reactive Power Testing Procedures Test Condition Test Req i ementRequirement Maintain voltage

Example of Active Power CurtailmentA ti P C t il t

250Active Power Curtailment

Curtailment Set Point

Plant Output

150

200

kW)

Ramp rate is 4.3 kW/s

100

150

lant Outpu

t (

Utility sets plant output from 150kW to 200kW

kW/s

Setpoint

50

P Setpoint reduced to 50kW to 200kW

0

13:52 13:58 14:04 14:10 14:16 14:22 14:28 14:34 14:40 14:46

© 2011 SunPower CorporationSee: “METHODS OF INTEGRATING A HIGH PENETRATION PHOTOVOLTAIC POWER PLANT INTO A MICRO GRID”, Johnson R, Johnson L, Nelson L, Lenox C, Stein J.

27

Page 28: Utilty Scale Solar PV Project Experience final - Electric … · 2014-10-15 · Example Reactive Power Testing Procedures Test Condition Test Req i ementRequirement Maintain voltage

Over Frequency Droop OASIS has the option of a configurable droop response

Example: Project currently in late stage developmentExample: Project currently in late stage development– Project expected to start construction this year– Specific voltage and frequency issues for local grid

Utilit i t t d i ti f O F D R– Utility interested in option of Over-Frequency Droop Response

Not aware of any requirements for over frequency droop for a currently operational Solar PV Plant in U Soperational Solar PV Plant in U.S.

© 2011 SunPower Corporation

28

Page 29: Utilty Scale Solar PV Project Experience final - Electric … · 2014-10-15 · Example Reactive Power Testing Procedures Test Condition Test Req i ementRequirement Maintain voltage

Example Simulation: Over Frequency Droop

63

64

1.0

1.1

Example Simulation of Over Frequency Droop Response

60

61

62

0.7

0.8

0.9

Hz)

utpu

t (pu)

58

59

60

0.4

0.5

0.6

Freq

uency (H

Real Pow

er Ou

55

56

57

0.1

0.2

0.3

Total R

540.00 3 6 9 12 15 18 21

Time (s)

© 2011 SunPower Corporation

29

Page 30: Utilty Scale Solar PV Project Experience final - Electric … · 2014-10-15 · Example Reactive Power Testing Procedures Test Condition Test Req i ementRequirement Maintain voltage

System Impact Studies for Solar PV Plants

Assess impacts on system reliability and stability

California ISO Cluster Process California ISO Cluster Process– Over 16,000 MWs of Solar PV in Interconnection Queue– Power flow, dynamic stability, and short circuit studies

SunPower has provided Plant Level Equivalent Models for System Impact Studies

– Proprietary positive sequence models (PSSE/PSLF) exist today for Solar PV inverters

– WECC Renewable Energy Modeling Task Force (REMTF)

© 2011 SunPower Corporation

30

Page 31: Utilty Scale Solar PV Project Experience final - Electric … · 2014-10-15 · Example Reactive Power Testing Procedures Test Condition Test Req i ementRequirement Maintain voltage

Summary of Grid Support SunPower Utility Scale PV plants have demonstrated ability to provide:

– Voltage Support– Ride through disturbances on the grid– Ride through disturbances on the grid– Active power management– Over frequency droop response

Models of Solar PV Plants available for System Impact Studies

Shared goal of requirements that promote grid reliability and stabilitywhile avoiding market barriers

© 2011 SunPower Corporation

31

Page 32: Utilty Scale Solar PV Project Experience final - Electric … · 2014-10-15 · Example Reactive Power Testing Procedures Test Condition Test Req i ementRequirement Maintain voltage

Summary

Thank you for the opportunity to present our experiences! SunPower has over 1.5 GW of solar PV deployed worldwide The OASIS Power Plant with grid integration options:

– Ride Through (Voltage and Frequency) – Real Power Curtailment– Over Frequency Droop Response – Reactive Power Support q y p p pp

A thank you for all the helpful support to: Kari Smith, Alan Comnes, Carl Lenox, Chris Barker, Robert Johnson, Lars Johnson, and many others from the SunPower team

Contact Information:– William Peter: [email protected]

J h Pitt j h itt @– John Pitts: [email protected]

© 2011 SunPower Corporation

32

Page 33: Utilty Scale Solar PV Project Experience final - Electric … · 2014-10-15 · Example Reactive Power Testing Procedures Test Condition Test Req i ementRequirement Maintain voltage

© 2011 SunPower Corporation