Utility Management of Distributed Energy Resources -P …energypa.org/assets/files/2017/Sept...

22
Utility Management of Distributed Energy Resources PPL’s Vision for Tomorrow’s Grid Paul Toub Jr Operations Engineering Manager Distribution Control Center

Transcript of Utility Management of Distributed Energy Resources -P …energypa.org/assets/files/2017/Sept...

Utility Management of Distributed Energy ResourcesPPL’s Vision for Tomorrow’s Grid

Paul Toub JrOperations Engineering ManagerDistribution Control Center

2016 PPL Electric Utilities

2

Agenda

• Tomorrow’s Grid• PPL and our Smart Grid• PPL’s Vision• Keystone Solar Future Project• Project Challenges• Questions

2016 PPL Electric Utilities

3

Tomorrow’s Grid

2016 PPL Electric Utilities

4

Tomorrow’s Grid

2016 PPL Electric Utilities

5

About PPL Electric Utilities

• Headquartered in Allentown, PA

• 400 distribution substations

• Facilities: 4kV to 500kV  

• 1.4 million customers , load peaked at 7844 MW

• Serves 29 counties and 6 cities in eastern PA

• Deployed Centralized DMS in 2014

• Completed FISR Deployment May 2016

2016 PPL Electric Utilities

6

Smart Grid Rollout

Timeline2009 – 2010 U.S. D.O.E. Federal Stimulus Grant

2011 Smart Grid Pilot 150 Devices, 50 Feeders2012 – 2013 Phase 1: 374 Devices, 52 Feeders

Distribution SCADA2014 - 2016 Phase 2: ~4000 Devices, ~1200 Feeders

Core DMS with FISR Implemented

2016 PPL Electric Utilities

7

Centralized Device Control

DMS Implementation:

• Layered on top of the existing SCADA• Allowed operators to make all of the decisions and switching• Model developed & advanced applications were fully vetted 

Key Benefits: No additional system programing required as feeder configurations 

change. Once a new controllable device is installed it is available to the 

software. Updates to software can be done on a global level one time.

2016 PPL Electric Utilities

8

DA Device Information & Control

• Recloser Configurations (~3700) Recloser Sectionalizer Switch Reconfigurable Remotely

• Capacitors (~780) Open / Close  Neutral Amps Indication 

• MOABS (~1000) Open / Close Volts Amps Fault Indication

2016 PPL Electric Utilities

9

Challenges Presented by DER

High Penetration of DER creates:• Bi-directional power flows• Hidden Loads• Affects Voltage Quality• Not all DER is a reliable 

source, i.e. Solar

Increasing penetration of Distributed Energy Resource (DER) is calling forchanges in planning, design, standard, protection and operation of traditionaldistribution system.

These changes reside in many areas such as technical, industry standard, market,customer engagement, training and regulation.

2016 PPL Electric Utilities

10

Challenge: Bi – Directional Power Flow 

2016 PPL Electric Utilities

11

Challenge: Hidden Loads

2016 PPL Electric Utilities

12

Challenge: Voltage Quality

2016 PPL Electric Utilities

13

PPL’s Vision

• Enhance existing DMS• Load and PV Forecasting• Operator of the Future• Operations Planner of the Future

• PPL’s Vision of Operating in Tomorrow’s Grid

2016 PPL Electric Utilities

14

Our Opportunity

Utilize PPL’s current Smart Grid and technologies as a foundation to build Tomorrow’s Grid.

Department of Energy ENERGISE , PPL’s Keystone Solar Future Project (KSFP)

• Utilize Customer and Utility Devices, i.e. Solar Inverters 

• Leverage existing grid utility innovation as a stepping stone

• Demonstrate how to share value with customers by supporting an integrated grid

2016 PPL Electric Utilities

15

KSFP and ENERGISE Goals

PPL’s KSFPLeverage Solar and other Distributed Energy Resources (DER) as assets to enhance the reliability of our distribution grid as penetration levels continue to rise.

DOE ENERGISEEncourage the power delivery industry to develop economical solutions that allow high penetrations of Solar resources while maintaining a reliable grid. 

2016 PPL Electric Utilities

16

Project Objectives

• Build on our Foundational Technologies • Distribution Management System (DMS)• Distributed Automation• AMI RF Network

• Create a Distributed Energy Resource Management System (DERMS) Platform (expansion of DMS)• Proof of Concept through Pilot in Lancaster Region

• Create a Automated process for DER Applications, reducing the time for approval.

2016 PPL Electric Utilities

17

Solution: DERMS 

• Enhance DMS Applications• Fault Isolations, System Restoration (FISR)• Volt / VAr Optimization (VVO)• Advanced Feeder Reconfiguration (AFR)

• Load and Forecasting Engine• Provide Load and Generation Data at Customer Level• Utilized meter, weather, and other data• Forecast up to 10 days out• Real-Time Estimation

2016 PPL Electric Utilities

18

Solution: DERMS 

2016 PPL Electric Utilities

19

Timeline

Grant Concept Paper: June 2016Submitted Grant Application: August 2016Proposal Selected: January 2017Project Start: October 2017

Design & Develop

Build & Integrate

Deploy (Pilot)

Budget Period 1 Budget Period 2 Budget Period 3

One Year One Year One Year

Keystone Solar Future Project

2018 2019 2020 2017

2016 PPL Electric Utilities

20

Vendor Partners

Build DERMS, Enhance DMS

Build Communication Pathway between Inverters and DERMS & DMS

Provide Guidance for Inverter Standards, Industry Knowledge Share

Industry Knowledge Share, Facilitate Conversations in Solar Industry

Simulation Setup and Run

Cyber Security Strategy and Implementation

2016 PPL Electric Utilities

21

Project Challenges

• DMS to AMI Interface• OT v. IT - Gateway vs. Interface, IEEE 2030.5, CIM Compliant

• Pilot Customer Enrollment • 500 Customer totaling  20MW

• Modelling of Inverters• SCADA v. Not SCADA

• Communication Bandwidth Issues

• Ensuring Scalability for Enterprise Solution

2016 PPL Electric Utilities

22

Questions