EHP3 for SAP ERP 6.0
December 2009
English
Overhaul Management (886)
SAP AGDietmar-Hopp-Allee 1669190 WalldorfGermany
Building Block Configuration Guide
SAP Best Practices Overhaul Management (886): Configuration Guide
Copyright
© Copyright 2009 SAP AG. All rights reserved.
No part of this publication may be reproduced or transmitted in any form or for any purpose without the express permission of SAP AG. The information contained herein may be changed without prior notice.
Some software products marketed by SAP AG and its distributors contain proprietary software components of other software vendors.
Microsoft, Windows, Excel, Outlook, and PowerPoint are registered trademarks of Microsoft Corporation.
IBM, DB2, DB2 Universal Database, System i, System i5, System p, System p5, System x, System z, System z10, System z9, z10, z9, iSeries, pSeries, xSeries, zSeries, eServer, z/VM, z/OS, i5/OS, S/390, OS/390, OS/400, AS/400, S/390 Parallel Enterprise Server, PowerVM, Power Architecture, POWER6+, POWER6, POWER5+, POWER5, POWER, OpenPower, PowerPC, BatchPipes, BladeCenter, System Storage, GPFS, HACMP, RETAIN, DB2 Connect, RACF, Redbooks, OS/2, Parallel Sysplex, MVS/ESA, AIX, Intelligent Miner, WebSphere, Netfinity, Tivoli and Informix are trademarks or registered trademarks of IBM Corporation.
Linux is the registered trademark of Linus Torvalds in the U.S. and other countries.
Adobe, the Adobe logo, Acrobat, PostScript, and Reader are either trademarks or registered trademarks of Adobe Systems Incorporated in the United States and/or other countries.
Oracle is a registered trademark of Oracle Corporation.
UNIX, X/Open, OSF/1, and Motif are registered trademarks of the Open Group.
Citrix, ICA, Program Neighborhood, MetaFrame, WinFrame, VideoFrame, and MultiWin are trademarks or registered trademarks of Citrix Systems, Inc.
HTML, XML, XHTML and W3C are trademarks or registered trademarks of W3C®, World Wide Web Consortium, Massachusetts Institute of Technology.
Java is a registered trademark of Sun Microsystems, Inc.
JavaScript is a registered trademark of Sun Microsystems, Inc., used under license for technology invented and implemented by Netscape.
SAP, R/3, SAP NetWeaver, Duet, PartnerEdge, ByDesign, SAP Business ByDesign, and other SAP products and services mentioned herein as well as their respective logos are trademarks or registered trademarks of SAP AG in Germany and other countries.
Business Objects and the Business Objects logo, BusinessObjects, Crystal Reports, Crystal Decisions, Web Intelligence, Xcelsius, and other Business Objects products and services mentioned herein as well as their respective logos are trademarks or registered trademarks of Business Objects S.A. in the United States and in other countries. Business Objects is an SAP company.
All other product and service names mentioned are the trademarks of their respective companies. Data contained in this document serves informational purposes only. National product specifications may vary.
These materials are subject to change without notice. These materials are provided by SAP AG and its affiliated companies ("SAP Group") for informational purposes only, without representation or warranty of any kind, and SAP Group shall not be liable for errors or omissions with respect to the materials. The only warranties for SAP Group products and services are those that are set forth in the express warranty statements accompanying such products and services, if any. Nothing herein should be construed as constituting an additional warranty.
© SAP AG Page 2 of 15
SAP Best Practices Overhaul Management (886): Configuration Guide
Icons
Icon Meaning
Caution
Example
Note
Recommendation
Syntax
External Process
Business Process Alternative/Decision Choice
Typographic Conventions
Type Style Description
Example text Words or characters that appear on the screen. These include field names, screen titles, pushbuttons as well as menu names, paths and options.
Cross-references to other documentation.
Example text Emphasized words or phrases in body text, titles of graphics and tables.
EXAMPLE TEXT Names of elements in the system. These include report names, program names, Transaction codes, table names, and individual key words of a programming language, when surrounded by body text, for example, SELECT and INCLUDE.
Example text Screen output. This includes file and directory names and their paths, messages, source code, names of variables and parameters as well as names of installation, upgrade and database tools.
EXAMPLE TEXT Keys on the keyboard, for example, function keys (such as F2) or the ENTER key.
Example text Exact user entry. These are words or characters that you enter in the system exactly as they appear in the documentation.
<Example text> Variable user entry. Pointed brackets indicate that you replace these words and characters with appropriate entries.
© SAP AG Page 3 of 15
SAP Best Practices Overhaul Management (886): Configuration Guide
Contents
Overhaul Management: Configuration Guide..................................................................................5
1 Purpose................................................................................................................................... 5
2 Preparation.............................................................................................................................. 5
2.1 Prerequisites..................................................................................................................5
2.1.1 Building Blocks..........................................................................................................5
3 Configuration........................................................................................................................... 5
3.1 Project Operative Structures..........................................................................................5
3.1.1 Maintaining Network Profile.......................................................................................5
3.1.2 Creating Project Profile.............................................................................................7
3.2 Project Settlement Rule...............................................................................................10
3.2.1 Determining Strategy to Settlement Rule................................................................10
3.2.2 Assigning Strategy to Project Profile.......................................................................11
3.3 Master Date................................................................................................................. 11
3.3.1 Creating Standard Project Definition.......................................................................11
3.3.2 Maintaining WBS Template.....................................................................................12
3.3.3 Creating Standard Network Header........................................................................13
3.3.4 Maintaining Standard Network Activity....................................................................14
© SAP AG Page 4 of 15
SAP Best Practices Overhaul Management (886): Configuration Guide
Overhaul Management: Configuration Guide
1 PurposeThis configuration guide provides the information you need to set up the configuration of this building block manually.
If you do not want to configure manually and prefer an automated installation process using BC Sets and other tools, refer to the installation guide of this building block.
2 Preparation
2.1 Prerequisites
2.1.1 Building BlocksBefore you start installing this building block, you must install prerequisite building blocks. For more information, see the building block prerequisite matrix (Prerequisites_Matrix_[xx]_EN_ZH.xls; the placeholder [xx] depends on the SAP Best Practices version you use, e.g. UTL refers to the SAP Best Practices Utilities Package: Prerequisites_Matrix_UTL_EN_ZH.xls). This document can be found on the SAP Best Practices documentation DVD in the folder ..\BBLibrary\General\:
3 Configuration
3.1 Project Operative Structures
3.1.1 Maintaining Network Profile
UseThe purpose of this activity is to define network profile used for controlling the processing of networks, such as control keys for activities. The data which you enter here in the network profile is copied into the header, activities, and activity elements when you create a network. You can overwrite these values in each new network.
Procedure 1. Access the activity using one of the following navigation options:
Transaction code OPUU
IMG menu Project System Structures Operative Structures Network Settings for Networks Maintain network profile
© SAP AG Page 5 of 15
SAP Best Practices Overhaul Management (886): Configuration Guide
2. On the Change View Network Defaults: Overview screen, choose New Entries.
3. On the New Entries: Details of Added Entries screen, make the following entries:
Field name Description User action and values Comment
Profile YU00004
Description 1000 Overhaul Maintenance Network
Network parameters
Plant 1000
Network type YU02
Planner group YU2
MRP cont.group YU2
Rel. view Relationships view 3
Level of detail 20
Comp. increment 10
Op/act. incrmt Increment for automatic operation/activity numbering
0010
Check WBS act. W
Overview var. Overview variant 000000000002
Procurement YU2
Field key 0000001
Version prof. Version profile 0000001
Graphic
Graphic prfl. Graphic Profile PS / Network
Rel. display 1
Display options 1
Color-Subnetwk. GREEN
Color milestone GREEN
Color for doc.s GREEN
Color for mat. GREEN
Color for elem. GREEN
Prf planning board SAPPS_NW0001
Overall profile ID SAPPS_G007
Internally processed activity
Control key PS05 Network - replaced by subnetwork
© SAP AG Page 6 of 15
SAP Best Practices Overhaul Management (886): Configuration Guide
Field name Description User action and values Comment
Mat.cost elem. 50010101
Unit for work H Hour
Norm. duratn. un. D Day
Calculation key 2 Calculate work
General Costs Activity
Control key PS03 General costs activity
Cost element 56010941
Service
Control key PS04
Cost element 57010203
Material Group YU88888
Purch. Group 001
Unit of measure EA
Externally processed activity
Control key PS02
Cost element 57010202
Currency CNY
Purchasing Org. 1000
Purch. Group 100
Order unit EA
4. Choose Save.
3.1.2 Creating Project Profile
UseThe purpose of this activity is to create project profile which contains default values and other control parameters such as the planning method for dates and costs. The data that you enter in the project profile will be copied into a project in its project definition or in the WBS elements which can later be overwritten.
Procedure 1. Access the activity using one of the following navigation options:
Transaction code OPSA
IMG menu Project System Structures Operative Structures Work Breakdown Structure (WBS) Create Project Profile
© SAP AG Page 7 of 15
SAP Best Practices Overhaul Management (886): Configuration Guide
2. On the Change View Project Profile: Overview screen, choose New Entries.
3. On the New Entries: Details of Added Entries screen, make the following entries:
Field name Description User action and values Comment
Profile YU00004
Description 1000 Overhaul Maintenance Project
Basic Data
Proj. type Y2
Field key 0000001
Version prof. 0000001
Simulation prof 0000001
Display options 1
Level of detai 10
All acct asst elem X
Only one root X
ChangeDocuments X
Proj. summ.MastDa
Project Stock
No stock
non-valuated stk
valuated stock X
Automatic reqmnts grouping
X
Status Management
PD sts. profile YU_PD_02
WBS sts. prof. YU000002
ChangeDocuments X
Graphic
Master data prf. grp PS
Graph.prfl mstr data
HIERARCHY_S
Vertical from level 20
Project summarization
All WBS Elements X
Billing elements
Acct Asst Elements
© SAP AG Page 8 of 15
SAP Best Practices Overhaul Management (886): Configuration Guide
Field name Description User action and values Comment
Organization
Controlling area 1000
Company code 1000
Plant 1000
Project currency CNY
WBS time scheduling
WBS sched. prof 000000000001
Sched. scenario 2
With activities X
Default values
Factory calend. CN
Time unit D
Planning method
Plan.meth/basic 1 Top-down
Plan.meth/fcst 1 Top-down
Calc. with act. 1 taking activity dates into consideration
Network
Network profile YU00004
Network asst 2 For WBS element
Display network hdr
X
Project planning board
Plan.board prf SAPPS_TP0001
Capacity Requirements Planning
Tot.tab.profile SAPPS_G000
Tot.graphic.prf SAPPS_GG00
IndCapTabOvProf SAPPS_GE01
IndCapGrpOvProf SAPPS_GE02
List profile SAPPS_G020
Hierarchy Graphic
Profile group PS
Profile HIERARCHY_T
Time schd. prof 000000000001
Costs/revenues/payments
© SAP AG Page 9 of 15
SAP Best Practices Overhaul Management (886): Configuration Guide
Field name Description User action and values Comment
Object Class INVST
Planning/budgeting
Planning profile YU0002
Budget Profile YU0002
Period-end closing
Costing Sheet PP-PC1
Interest Profile 0000001
Settlement profile YU04
Graphic
Budget profile group
PS
Graph.profile budget
HIERARCHY_B
4. Choose Save.
3.2 Project Settlement Rule
3.2.1 Determining Strategy to Settlement Rule
Use The purpose of this activity is to define the strategy for automatic generation of settlement rules.
Procedure 1. Access the activity using one of the following navigation options:
Transaction code SPRO
IMG menu Project System Costs Automatic and Periodic Allocations Settlement Settlement Rule for Work Breakdown Structure Element Determine Strategy for Settlement Rule
2. On the Change View Strategy: Overview screen, choose New Entries, and then make the following entries:
Field name Description User action and values Comment
Strategy YM
Description Overhaul Maintenance Project
© SAP AG Page 10 of 15
SAP Best Practices Overhaul Management (886): Configuration Guide
3. Confirm the entries.
4. Choose strategy YM, and then double click Settings in the Dialog Structure screen area.
5. On the Change View “Settings”: Overview screen, choose New Entries, and then make the following entries:
Field name Description User action and values Comment
Billing elem.
AA element X
No acct asst
Org. change
Sett.Prof. YU04
AcctAssCat 4
6. Confirm the entries.
7. Choose Save.
3.2.2 Assigning Strategy to Project Profile
Use The purpose of this activity is to assign the strategy for automatic settlement rule generation to a project profile. You can then have the system generate the settlement rule for the WBS element.
Procedure 1. Access the activity using one of the following navigation options:
Transaction code SPRO
IMG menu Project System Costs Automatic and Periodic Allocations Settlement Settlement Rule for Work Breakdown Structure Element Assign Strategy to Project Profile
2. On the Change View Assign Strategy to Project Profile: Overview screen, assign strategy YM to project profiles YU00004.
3. Confirm the entries.
4. Choose Save.
3.3 Master Date
3.3.1 Creating Standard Project Definition
UseThe purpose of this activity is to create standard project definition.
Procedure 1. Access the activity using one of the following navigation options:
SAP ECC menu Accounting Project System Basic Data Templates
© SAP AG Page 11 of 15
SAP Best Practices Overhaul Management (886): Configuration Guide
Standard WBS Create
Transaction code CJ91
2. On the Create Std. WBS: Initial Screen screen, enter the data in the table below:
Field name Description User action and values Comment
Std. project def. 09W2B01-QJ
Project Profile YU000004 1000 Overhaul Maintainance Project
3. Choose Enter.
4. On the Create Std. WBS: Project def. Basic Data screen, make the following entries:
Field name Description User Action and Values Comment
Short description
1发电机组汽轮机大修 Enter into the field to the right of the project definition 09W2B01-QJ
Time unit D
5. Choose the icon WBS element overview (Shift+F12).
6. On the Create Std. WBS: WBS Elements – Descriptions screen, in the Basic data tab make the following sets of entries (an (x) indicates to select the checkmark):
Field name Lev WBS element Description Su PE Acct Bill
Entry 1 1 09W2B01-QJ 1发电机组汽轮机大修 (x) (x)
7. Press Enter.
8. Choose Save to save your standard project.
ResultStandard project definition has been defined.
3.3.2 Maintaining WBS Template
UseThe purpose of this activity is to maintain WBS template.
Procedure 1. Access the activity using one of the following navigation options:
SAP ECC menu Accounting Project System Basic Data Templates Standard WBS Change
Transaction code CJ92
2. On the Change Std. WBS: Initial Screen, enter 09W2B01-QJ in the field Std. project def.
3. Choose the icon WBS element overview (F5).
4. On the Change Std. WBS: WBS Elements – Descriptions screen, in the Basic data tab make the following sets of entries (an (x) indicates to select the checkmark):
© SAP AG Page 12 of 15
SAP Best Practices Overhaul Management (886): Configuration Guide
Field name Lev WBS element Description Su PE Acct Bill
Entry 1 2 09W2B01-QJ/1 高压 西侧切断阀 (x) (x)
Entry 2 2 09W2B01-QJ/2 高压 东侧切断阀 (x) (x)
Entry 3 2 09W2B01-QJ/3 高压 控制阀 1 (x) (x)
Entry 4 2 09W2B01-QJ/4 高压 控制阀 2 (x) (x)
Entry 5 2 09W2B01-QJ/5 高压 控制阀 3 (x) (x)
Entry 6 2 09W2B01-QJ/6 高压 控制阀 4 (x) (x)
Entry 7 2 09W2B01-QJ/7 高压 控制阀 5 (x) (x)
Entry 8 2 09W2B01-QJ/8 高压 控制阀 6 (x) (x)
Entry 9 2 09W2B01-QJ/9 回流阀 (x) (x)
5. Press Enter.
6. Choose Save to save your standard project.
ResultWBS template has been maintained.
3.3.3 Creating Standard Network Header
UseThe purpose of this activity is to create standard network header.
Procedure 1. Access the activity using one of the following navigation options:
SAP ECC menu Accounting Project System Basic Data Templates Standard Network Create
Transaction code CN01
2. On the Standard Network Create: Initial Screen , enter the data in the table below:
Field name Description User action and values Comment
Std network 4000000
Profile YU000002 1000 Overhaul Maintenance Network Profile
3. Choose Enter.
4. On the Standard Network Create: Standard Network Header screen, make the following entries:
Field name Description User Action and Values Comment
Short description
1#发电机组汽轮机大修 Enter into the field to the right of the Std Network 4000000
© SAP AG Page 13 of 15
SAP Best Practices Overhaul Management (886): Configuration Guide
Network usage
3 Universal
Planner group
YU2
Network status
4 Released (general)
5. Press Enter.
6. Choose Save to save your standard network.
ResultStandard network header has been defined.
3.3.4 Maintaining Standard Network Activity
UseThe purpose of this activity is to maintain standard network activity.
Procedure 1. Access the activity using one of the following navigation options:
SAP ECC menu Accounting Project System Basic Data Templates Standard Network Change
Transaction code CN02
2. On the Standard Network Change: Initial Screen, enter 4000000 in the field Std network.
3. Choose the icon Activity Overview (Shift+F1).
4. On the Standard Network Change: Operation Overview screen, in the Int.Processing tab make the following entries:
Activity
Opr.short text Normal duration
Work Percent
Std.WBS element
0010 高压 西侧切断阀 10 240 100 09W2B01/1
0020 高压 东侧切断阀 10 240 100 09W2B01/2
0030 高压 控制阀 1 10 240 100 09W2B01/3
0040 高压 控制阀 2 10 240 100 09W2B01/4
0050 高压 控制阀 3 10 240 100 09W2B01/5
0060 高压 控制阀 4 10 240 100 09W2B01/6
0070 高压 控制阀 5 10 240 100 09W2B01/7
0080 高压 控制阀 6 10 240 100 09W2B01/8
0090 回流阀 10 240 100 09W2B01/9
© SAP AG Page 14 of 15
SAP Best Practices Overhaul Management (886): Configuration Guide
5. Press Enter.
6. On the Standard Network Change: Operation Overview screen, choose Select All (Ctrl + F5), double click activity 0010, in the Standard Network Change: Detailed data dialog box, enter control key: PS05.
7. Choose Next activity (Shift + F11), enter control key: PS05. In this way you maintain the control key for all other activities.
8. Choose Back (Enter).
9. Choose Save to save your standard network.
ResultStandard network activity has been changed.
© SAP AG Page 15 of 15