Using case studies - Renewable heat · Using case studies to understand the integration of ground...
Transcript of Using case studies - Renewable heat · Using case studies to understand the integration of ground...
![Page 1: Using case studies - Renewable heat · Using case studies to understand the integration of ground storage of energy intoground storage of energy into building and underground structures](https://reader031.fdocuments.in/reader031/viewer/2022011817/5e7ac4aaa23ae3029a48fa08/html5/thumbnails/1.jpg)
18/04/2011
1
Using case studies Using case studies to understand the integration of to understand the integration of ground storage of energy intoground storage of energy intoground storage of energy into ground storage of energy into
building and underground structuresbuilding and underground structures
Göran HellströmGöran HellströmGöran HellströmGöran HellströmLund University, SwedenLund University, SwedenNeoEnergyNeoEnergy Sweden LtdSweden Ltd
Energy StorageEnergy Storage
Underground Underground energyenergy storagestorage unitunit (0,6 kWh/(m(0,6 kWh/(m33,K)),K))
![Page 2: Using case studies - Renewable heat · Using case studies to understand the integration of ground storage of energy intoground storage of energy into building and underground structures](https://reader031.fdocuments.in/reader031/viewer/2022011817/5e7ac4aaa23ae3029a48fa08/html5/thumbnails/2.jpg)
18/04/2011
2
UnbalancedUnbalanced energyenergy loadload
D t t h t t ti t !Due to net heat extraction rate!
5 10 15
Time (years)
Heat carrier fluid temperature variation during 15 years for a large installationOnly extraction of heat
BalancedBalanced energyenergy loadload
Net heat extraction reduced by recharge!
ENDAST VÄRMEUTTAG
H t t ti b h t d h b td i
Extraction in balance with recharge!
Heat carrier fluid temperature variation for system with heat pump and extraction and recharge by outdoor air
Heat extraction by heat pump and recharge by outdoor air
5 10 15
Time (years)
![Page 3: Using case studies - Renewable heat · Using case studies to understand the integration of ground storage of energy intoground storage of energy into building and underground structures](https://reader031.fdocuments.in/reader031/viewer/2022011817/5e7ac4aaa23ae3029a48fa08/html5/thumbnails/3.jpg)
18/04/2011
3
Heat pump efficiencyHeat pump efficiencyNominal heat pump capacity 10 kW
13
14Heat pump output
2
3
4
5
6
7
8
9
10
11
12
13
Po
wer
(kW
)
Compressor electric power
0
1
2
-5 -4 -3 -2 -1 0 1 2 3 4 5 6 7 8 9 10
Entering heat carrier fluid temperature (C)
Heat pump capacity vs. source temperature1 degree lower temperature causes a 3-4 % reduction of heating output
Heat pump efficiencyHeat pump efficiencyNominal heat pump capacity 10 kW
13
14Heat pump output
2
3
4
5
6
7
8
9
10
11
12
13
Po
wer
(kW
)
Compressor electric power
0
1
2
-5 -4 -3 -2 -1 0 1 2 3 4 5 6 7 8 9 10
Entering heat carrier fluid temperature (C)
Heat pump capacity vs. source temperature1 degree lower source temperature causes a 3-4 % reduction of heat pump output
![Page 4: Using case studies - Renewable heat · Using case studies to understand the integration of ground storage of energy intoground storage of energy into building and underground structures](https://reader031.fdocuments.in/reader031/viewer/2022011817/5e7ac4aaa23ae3029a48fa08/html5/thumbnails/4.jpg)
18/04/2011
4
Energy balance?Energy balance?
HEAT COLDHEAT COLD
Energy balance for the ground determines choice of system design of ground source
Imbalance may cause undesirable long-term temperature changes
Hybrid GSHPHybrid GSHP
GroundGround sourcesource ExhaustExhaust air air sourcesource OutdoorOutdoor air air sourcesource Water Water sourcesource (lake, river)(lake, river) Solar Solar sourcesource Waste heatWaste heat
![Page 5: Using case studies - Renewable heat · Using case studies to understand the integration of ground storage of energy intoground storage of energy into building and underground structures](https://reader031.fdocuments.in/reader031/viewer/2022011817/5e7ac4aaa23ae3029a48fa08/html5/thumbnails/5.jpg)
18/04/2011
5
Project Lulevärme
Summer: Storage of waste heat from steel plant
Stored heat: ca 2000 MWh (maximum temp 82 °C)
Seasonal storage of waste heat
Stored heat: ca 2000 MWh (maximum temp 82 C)
Winter: University building heated with/without heat pump
Extracted heat: 1000-1200 MWh
Project Lulevärme, LuleåProject Lulevärme, Luleå
Estimated ground temperature after charging
![Page 6: Using case studies - Renewable heat · Using case studies to understand the integration of ground storage of energy intoground storage of energy into building and underground structures](https://reader031.fdocuments.in/reader031/viewer/2022011817/5e7ac4aaa23ae3029a48fa08/html5/thumbnails/6.jpg)
18/04/2011
6
Project Lulevärme, LuleåProject Lulevärme, Luleå
3000
3500
4000
4500
Simulated heat injection
Measured heat injection
Simulated heat extraction
Measured heat extraction
0
500
1000
1500
2000
2500
3000
En
erg
y (
MW
h)
Measured and simulated energy balance 1983-1988
-1500
-1000
-500
1983-84 1985-861984-85 1987-881986-87
Glazed solar collectorsGlazed solar collectors
Glazed solar collectors absorb about 850 kWh/m2/year of which 500 kWh/m2/year for hot water and 350 kWh/m2/year deliveredconnected to evaporator side of GSHP (heat source and recharge)
![Page 7: Using case studies - Renewable heat · Using case studies to understand the integration of ground storage of energy intoground storage of energy into building and underground structures](https://reader031.fdocuments.in/reader031/viewer/2022011817/5e7ac4aaa23ae3029a48fa08/html5/thumbnails/7.jpg)
18/04/2011
7
COOLING
HEATING• Hot water
• Space heatingGlazed solar
GSHP/Solar hybridGSHP/Solar hybrid
COOLING
HP
• Increasing HP evaporator temperature
• Recharging of ground loop
collectors
HighHigh--temperature seasonal energy storagetemperature seasonal energy storage
Seasonal storage of solar heatSeasonal storage of solar heatExamples: Neckarsulm, Germany, and Anneberg, SwedenExamples: Neckarsulm, Germany, and Anneberg, Sweden
![Page 8: Using case studies - Renewable heat · Using case studies to understand the integration of ground storage of energy intoground storage of energy into building and underground structures](https://reader031.fdocuments.in/reader031/viewer/2022011817/5e7ac4aaa23ae3029a48fa08/html5/thumbnails/8.jpg)
18/04/2011
8
Project Anneberg, Danderyd
• 70 single-family houses
• Summer: Storage of excess solar heat in ground store
• Winter: Heating without heat pump using under-floor heatingg p p g g
• 100 borehole to 65 meters depth
• In operation: March 2002
• Solar fraction estimated to 70 % of total energy demandStorage pe r form ance
200
250
60
75
0
50
100
150
200
J F M A M J J A S O N D
He
at
[MW
h/m
on
th]
0
15
30
45
60
Te
mp
. [°
C]
Coll. Gain Storage losses
To coll. Temp. Storage temp.
Project Anneberg, DanderydProject Anneberg, Danderyd
Max temp:p
+30 C, 2003
+40 C, 2005
Temperatures in solar collectors and borehole heat store.Temperatures in solar collectors and borehole heat store.
System in full operation in summer of 2006.System in full operation in summer of 2006.
![Page 9: Using case studies - Renewable heat · Using case studies to understand the integration of ground storage of energy intoground storage of energy into building and underground structures](https://reader031.fdocuments.in/reader031/viewer/2022011817/5e7ac4aaa23ae3029a48fa08/html5/thumbnails/9.jpg)
18/04/2011
9
Project Anneberg, DanderydProject Anneberg, DanderydSummer 2003: Leakage in main distribution system between energy plant room and houses. Replacement of manifolds.
Autumn 2004: Poor quality of U-pipes and bottom weight design resulted in leakage in 5 of 100 boreholes. Probably caused by elongation of pipes during heating.
Replacement of UReplacement of U--pipes (summer 2005)pipes (summer 2005)Old New
SolarSolar--assisted GSHP hybridassisted GSHP hybrid
19 boreholes to 300 m with 125 m2 glazed solar collectors
![Page 10: Using case studies - Renewable heat · Using case studies to understand the integration of ground storage of energy intoground storage of energy into building and underground structures](https://reader031.fdocuments.in/reader031/viewer/2022011817/5e7ac4aaa23ae3029a48fa08/html5/thumbnails/10.jpg)
18/04/2011
10
Unglazed Unglazed solarsolar collectorscollectors
Unglazed solar collectors absorb about 850 kWh/m2/year connected to evaporator side of GSHP as heat source and for recharge
COOLING
HEATING• Solar recharge of
ground loop Unglazed
GSHP/Solar hybridGSHP/Solar hybrid
COOLING
HP
• Increasing HP evaporator temperature
solar collectors
Alternative
![Page 11: Using case studies - Renewable heat · Using case studies to understand the integration of ground storage of energy intoground storage of energy into building and underground structures](https://reader031.fdocuments.in/reader031/viewer/2022011817/5e7ac4aaa23ae3029a48fa08/html5/thumbnails/11.jpg)
18/04/2011
11
QQ--MED, UppsalaMED, Uppsala
New facilities for New facilities for manufacturing of manufacturing of medicinemedicine
Building consists of four Building consists of four storeys incl. basementstoreys incl. basement
Total area ca 7020 mTotal area ca 7020 m22
Energy service rooms Energy service rooms prepared for future prepared for future storage space of ca storage space of ca 2000 m2000 m22
Design load & criteria Design load & criteria Design loadsDesign loads
CapacityCapacity Annual energy loadAnnual energy loadHeat load Heat load winterwinter
410 kW410 kW 925 MWh925 MWh
Heat load Heat load summersummer
160 kW160 kW 50 MWh50 MWh
Cool load Cool load winterwinter
90 kW90 kW 190 MWh190 MWhwinterwinterCool load Cool load summersummer
330 kW330 kW 305 MWh305 MWh
Criteria for system design:
Boreholes designed for max entering fluid temp +14°C
All air cooling coils designed for 14-17 °C
All air heating coils designed for 50-35 °C
![Page 12: Using case studies - Renewable heat · Using case studies to understand the integration of ground storage of energy intoground storage of energy into building and underground structures](https://reader031.fdocuments.in/reader031/viewer/2022011817/5e7ac4aaa23ae3029a48fa08/html5/thumbnails/12.jpg)
18/04/2011
12
Ground loopGround loopGround water level
4 t b l 00--25 meter soft clay25 meter soft clay 2525--30 meter silt / sand30 meter silt / sand
3030--200 meter granite200 meter granite
ca 4 meter below ground surface
38 boreholes38 boreholes200 m deep
Energy service roomEnergy service room
6 heat pumps with 41 kW capacity6 heat pumps with 41 kW capacity
Three of the heat pumps fitted Three of the heat pumps fitted with desuperheaters forwith desuperheaters forheating of tap waterheating of tap water
Refrigerant R407CRefrigerant R407C
Electric heater 255 kWElectric heater 255 kW
Heat pumps (IVT Greenline F40H) in the service room
![Page 13: Using case studies - Renewable heat · Using case studies to understand the integration of ground storage of energy intoground storage of energy into building and underground structures](https://reader031.fdocuments.in/reader031/viewer/2022011817/5e7ac4aaa23ae3029a48fa08/html5/thumbnails/13.jpg)
18/04/2011
13
Profitability Profitability –– investment costinvestment cost
Alternative 1Alternative 1Conventional system with Conventional system with district heating and cooling district heating and cooling machinemachineDistrict heating District heating connectionconnection
700 kSEK700 kSEK
District heating centralDistrict heating central 400 kSEK400 kSEK
C li lC li l 1650 kSEK1650 kSEK
Alternative 2Alternative 2GroundGround--coupled heat pump and coupled heat pump and direct coolingdirect coolingAdditional connection cost for Additional connection cost for extended electric power extended electric power installationinstallation
200 kSEK200 kSEK
Boreholes, manifolds, etcBoreholes, manifolds, etc 2600 kSEK2600 kSEK
Heat pumps / cooling centralHeat pumps / cooling central 850 kSEK850 kSEKCooling centralCooling central 1650 kSEK1650 kSEK
2750 kSEK2750 kSEK
Heat pumps / cooling centralHeat pumps / cooling central 850 kSEK850 kSEK
3650 kSEK3650 kSEK
Additional investment cost 900.000 SEK Additional investment cost 900.000 SEK (excl. VAT)(excl. VAT)300.000 EUR 400.000 EUR
100.000 EUR
$125.000
Profitability Profitability –– annual operating costannual operating costAlternative 1Alternative 1Conventional system with district heating and cooling machineConventional system with district heating and cooling machine
Heat load winterHeat load winter 925 MWh x 530 SEK/MWh925 MWh x 530 SEK/MWh 490 kSEK490 kSEKHeat load winterHeat load winter 925 MWh x 530 SEK/MWh925 MWh x 530 SEK/MWh 490 kSEK490 kSEK
Heat load summerHeat load summer 50 MWh x 400 SEK/MWh50 MWh x 400 SEK/MWh 20 kSEK20 kSEK
Cool load winterCool load winter 190 MWh x 820 SEK/MWh / 3,0 (COP)190 MWh x 820 SEK/MWh / 3,0 (COP) 52 kSEK52 kSEK
Cool load summerCool load summer 305 MWh x 820 SEK/MWh / 3,0 (COP)305 MWh x 820 SEK/MWh / 3,0 (COP) 83 kSEK83 kSEK
645 kSEK645 kSEK
Alternative 2Alternative 2GroundGround--coupled heat pump and direct coolingcoupled heat pump and direct cooling
Heat load winterHeat load winter 925 MWh x 820 SEK/MWh / 3 0 (COP)925 MWh x 820 SEK/MWh / 3 0 (COP) 253 kSEK253 kSEK
70.000 EUR
Reduced operating
cost
Annual savings 360 kSEK Annual savings 360 kSEK (excl. VAT)(excl. VAT)
Heat load winterHeat load winter 925 MWh x 820 SEK/MWh / 3,0 (COP)925 MWh x 820 SEK/MWh / 3,0 (COP) 253 kSEK253 kSEK
Heat load Heat load summersummer
50 MWh x 820 SEK/MWh / 3,0 (COP)50 MWh x 820 SEK/MWh / 3,0 (COP) 14 kSEK14 kSEK
Cool load winterCool load winter 11 MWh x 820 SEK/MWh (circ.pump)11 MWh x 820 SEK/MWh (circ.pump) 9 kSEK9 kSEK
Cool load summerCool load summer 11 MWh x 820 SEK/MWh (circ.pump)11 MWh x 820 SEK/MWh (circ.pump) 9 kSEK9 kSEK
285 kSEK285 kSEK 30.000 EUR
40.000 EUR
$37.500
![Page 14: Using case studies - Renewable heat · Using case studies to understand the integration of ground storage of energy intoground storage of energy into building and underground structures](https://reader031.fdocuments.in/reader031/viewer/2022011817/5e7ac4aaa23ae3029a48fa08/html5/thumbnails/14.jpg)
18/04/2011
14
ProfitabilityProfitability
Additional investment cost:Additional investment cost: 900.000 900.000 SEKSEK100.000 100.000 EUREUR
Reduced operating cost:Reduced operating cost: 360.000 360.000 SEK/yearSEK/year40.000 40.000 EUR/yearEUR/year
Straight payStraight pay--back timeback time 2,5 2,5 yearsyears
Astronomy Department, LundAstronomy Department, Lund
BTES heating and free cooling combined with district heatingBTES heating and free cooling combined with district heating
Office space 4.900 mOffice space 4.900 m22
![Page 15: Using case studies - Renewable heat · Using case studies to understand the integration of ground storage of energy intoground storage of energy into building and underground structures](https://reader031.fdocuments.in/reader031/viewer/2022011817/5e7ac4aaa23ae3029a48fa08/html5/thumbnails/15.jpg)
18/04/2011
15
Energy loadEnergy load
Energy supplyEnergy supply
![Page 16: Using case studies - Renewable heat · Using case studies to understand the integration of ground storage of energy intoground storage of energy into building and underground structures](https://reader031.fdocuments.in/reader031/viewer/2022011817/5e7ac4aaa23ae3029a48fa08/html5/thumbnails/16.jpg)
18/04/2011
16
BoreholesBoreholes
Borehole
20 boreholes, depth 200 m
Energy balanceEnergy balanceEnergy balance Normal year (adjusted)Energy balance Normal year (adjusted)
Heat from heat pumpHeat from heat pump 475 MWh475 MWh
Cold from ground source (free cooling)Cold from ground source (free cooling) 155 MWh155 MWh
El t i it t h tEl t i it t h t 104 MWh104 MWh
Key factors Normal year (adjusted)Key factors Normal year (adjusted)
Seasonal performance factor Seasonal performance factor -- heat pump (incl. circulation)heat pump (incl. circulation) 4,54,5
Seasonal performance factor Seasonal performance factor -- free coolingfree cooling 4747
Electricity to heat pump compressorElectricity to heat pump compressor 104 MWh104 MWh
District heating (hot water + peak load)District heating (hot water + peak load) 40 MWh40 MWh
Electricity to circulationspumps (ground and condensor side)Electricity to circulationspumps (ground and condensor side) 7 MWh7 MWh
pp gg
Heating and cooling demandHeating and cooling demand 126 kWh/m126 kWh/m22,yr,yr
Bought energyBought energy 28 kWh/m28 kWh/m22,yr,yr
Seasonal performance factor Seasonal performance factor –– ground source (heat pump + free cooling)ground source (heat pump + free cooling) 5,75,7Seasonal performance factorSeasonal performance factor–– total (ground source + district heating)total (ground source + district heating) 4,44,4
![Page 17: Using case studies - Renewable heat · Using case studies to understand the integration of ground storage of energy intoground storage of energy into building and underground structures](https://reader031.fdocuments.in/reader031/viewer/2022011817/5e7ac4aaa23ae3029a48fa08/html5/thumbnails/17.jpg)
18/04/2011
17
ProfitabilityProfitability
Additional investment:Additional investment: 180.000 EUR180.000 EURReduced operating cost:Reduced operating cost: 18.000 EUR/yr18.000 EUR/yrStraight payStraight pay--back time: 10 yearsback time: 10 years
Grants: 80 000 EURGrants: 80 000 EURGrants: 80.000 EURGrants: 80.000 EURStraight payStraight pay--back time (with grants): 6 yearsback time (with grants): 6 years
Sea WaterSea Water
Boreholes
Water intake
Hybrid system Hybrid system -- Boreholes with summer recharge from lakeBoreholes with summer recharge from lake
Water outlet
![Page 18: Using case studies - Renewable heat · Using case studies to understand the integration of ground storage of energy intoground storage of energy into building and underground structures](https://reader031.fdocuments.in/reader031/viewer/2022011817/5e7ac4aaa23ae3029a48fa08/html5/thumbnails/18.jpg)
18/04/2011
18
GSHP with recharge from sea waterGSHP with recharge from sea waterNäsby park slott, SwedenNäsby park slott, Sweden
HP48 boreholes
Cost of borehole B h l t ith t
Lake
storage
230,000 EUR
Borehole storage without lake recharge:80 boreholes400,000 EURCost of recharge
system
40,000 EURInitial cost reduction with recharge about 30 %
ProfitabilityProfitabilityEstimated based on three years of operation Estimated based on three years of operation
Alternative 1. Oil Alternative 1. Oil Alternative 2. GroundAlternative 2. Ground--source heat pump and oil (peak)source heat pump and oil (peak)
Additional investment cost:Additional investment cost: 750.000 EUR750.000 EURReduced operational cost:Reduced operational cost: 225.000 EUR/year225.000 EUR/year
Straight payStraight pay--back time:back time: 3,3 years3,3 years
Reduced oil consumption 79 %Reduced oil consumption 79 %Reduced bought energy (oil & electricity) 57 %Reduced bought energy (oil & electricity) 57 %
![Page 19: Using case studies - Renewable heat · Using case studies to understand the integration of ground storage of energy intoground storage of energy into building and underground structures](https://reader031.fdocuments.in/reader031/viewer/2022011817/5e7ac4aaa23ae3029a48fa08/html5/thumbnails/19.jpg)
18/04/2011
19
Combining groundCombining ground--source for source for buildings with different load buildings with different load
Community clustersCommunity clusters
RESIDENTIAL OFFICE
Common ground sourceCommon ground source
CombiningCombining groundground--sourcesource for for buildingsbuildings with different with different loadload
AvantorAvantor--NydalenNydalen, Oslo, Norway, Oslo, Norway
Hotel
University
OfficesFlats
Area : 180,000 m2
Energy store : 90 boreholes, depth 200 m
+ 70 borehole, depth 260 m
![Page 20: Using case studies - Renewable heat · Using case studies to understand the integration of ground storage of energy intoground storage of energy into building and underground structures](https://reader031.fdocuments.in/reader031/viewer/2022011817/5e7ac4aaa23ae3029a48fa08/html5/thumbnails/20.jpg)
18/04/2011
20
Chemistry Department, LundChemistry Department, Lund
Chemistry
IKDC
Architecture
Energy store 153 boreholes
Energy balance by combining buildings with different load profiles
Heating loadHeating load
ChemistryChemistryIKDC
Heating loadHeating loadTotal heat demand 8,5 MW
Heat pump capacity 1,8 MW
- From ground loop 1,2 MW
![Page 21: Using case studies - Renewable heat · Using case studies to understand the integration of ground storage of energy intoground storage of energy into building and underground structures](https://reader031.fdocuments.in/reader031/viewer/2022011817/5e7ac4aaa23ae3029a48fa08/html5/thumbnails/21.jpg)
18/04/2011
21
Cooling loadCooling load
ChemistryArchitecture
ChemistryIKDC
Cooling loadTotal cooling demand 3,0 MW
Katrineholm Sport CentreKatrineholm Sport CentreCommunity clustersCommunity clusters
ICE RINK
Cooled sep-may
OFFICE
Heated sep-may
GYMNASIUM
Heated sep-may
SWIMMING POOL
Heated all year
CommonCommon groundground sourcesource
Outdoor ICE RINK
Cooled when air below 0 C
p y
Outdoor SOCCER
Heated when air above 0 C
y
![Page 22: Using case studies - Renewable heat · Using case studies to understand the integration of ground storage of energy intoground storage of energy into building and underground structures](https://reader031.fdocuments.in/reader031/viewer/2022011817/5e7ac4aaa23ae3029a48fa08/html5/thumbnails/22.jpg)
18/04/2011
22
POWER GENERATION
• Hydro, wind, solar, geothermal, biomass
THERMAL ENERGY PRODUCTION
ExampleExample: IKEA : IKEA goesgoes renewablerenewable
THERMAL ENERGY PRODUCTION
• “Green” DH/DC (biomass, waste heat)
• Solar (collectors)
• Geothermal (deep and shallow)
• Natural (air, surface water, snow/ice)
At present two office/service buildings and four stores areusing borehole storage (BTES) or aquifer storage (ATES) for combined heating and cooling
IKEA – Applications in Sweden
• Distribution Centre, Torsvik, installed 1999 (BTES + horizontal GSHP)
• IKEA Meeting Point in Helsingborg, installed 2003 (BTES)
• IKEA Store in Karlstad, installed 2007 (BTES)
• IKEA Store in Uppsala, installed 2008 (BTES) pp , ( )
• IKEA Store in Malmö, installed 2009 (ATES)
• IKEA Store in Väla, under construction (BTES)
![Page 23: Using case studies - Renewable heat · Using case studies to understand the integration of ground storage of energy intoground storage of energy into building and underground structures](https://reader031.fdocuments.in/reader031/viewer/2022011817/5e7ac4aaa23ae3029a48fa08/html5/thumbnails/23.jpg)
18/04/2011
23
General for a 25 000 m2 store in Swedish climate(European system design)
IKEA – Applications in Sweden
50-60 % of the heat load covered by the HP, represents 85-90 % of the annual heat demand
Peak load covered by electric boiler, bio fuel burner or DH
60 % of the cooling load covered by free cooling from the storage,
t 70 80 % f th l ldrepresents 70-80 % of the annual cold demand
Peak load covered by running the HP as a chiller. Dry cooler used for disposal of condenser heat
IKEA – Meeting point 5,000 m2, Helsingborg
Facts:• 36 boreholes, 140 m deep, single U-pipe• Heat pump, 90 kW piston compressors• System heat capacity, 270 kW
S t li it 350 kW• System cooling capacity, 350 kW• SPF (measured) 6,3
Pay-back timeExpected, 5,5 years (2003)Actual, 4,5 years (2007)
![Page 24: Using case studies - Renewable heat · Using case studies to understand the integration of ground storage of energy intoground storage of energy into building and underground structures](https://reader031.fdocuments.in/reader031/viewer/2022011817/5e7ac4aaa23ae3029a48fa08/html5/thumbnails/24.jpg)
18/04/2011
24
Heat demand• Max load, 1200 kW• Energy, 1200 MWh/year
Cold demand
IKEA – Store 25,000 m2, Karlstad
• Max load, 800 kW• Energy, 500 MWh/year
BTES system installed 2007 100 boreholes, 120 m deep, spaced 4,5 m
Expectations• SPF heating, 3.8 (boiler included)• SPF cooling, 7.3 • Payback time, 6 years
Drilled on excavated rock (granite) Water filled holes, with single U-pipe Construction time 10 weeks (2 rigs) High water yields caused problem
Linked to a 620 kW heat pump/chiller
Heat demand• Max load, 1 300 kW• Energy, 2 200 MWh/year
Cold demandM l d 1 300 kW
IKEA – Store 36,000 m2, Uppsala
BTES system installed 2008 100 boreholes,168m deep, spaced 5 m
• Max load, 1 300 kW• Energy, 1 500 MWh/year
Expectations• SPF heating, 4.3 (boiler included)• SPF cooling, 6.5 (Americ. design) • Payback time, 5.5 years
100 boreholes,168m deep, spaced 5 m 20 m casing through soil into granite Water filled holes, with double U-pipes Construction time 10 weeks (3 rigs) Highly fractured rock caused problem Linked to 2 x 660 kW heat pumps/chillers
![Page 25: Using case studies - Renewable heat · Using case studies to understand the integration of ground storage of energy intoground storage of energy into building and underground structures](https://reader031.fdocuments.in/reader031/viewer/2022011817/5e7ac4aaa23ae3029a48fa08/html5/thumbnails/25.jpg)
18/04/2011
25
ATES system installed 2009 5 warm and 6 cold wells, 90 m deep into a fractured limestone Average well capacity, approx. 10 l/s Construction time 6 weeks (1 rig) Linked to 2 x 410 kW heat pumps/chillers
IKEA – Store 44,000 m2, Malmö
Linked to 2 x 410 kW heat pumps/chillers
Heat demand• Max load, 1 300 kW• Energy, 2 350 MWh/year
Cold demand• Max load, 1 300 kW• Energy, 1 450 MWh/annuallygy, / y
Expectations• SPF heating, 4.3 (boiler included)• SPF cooling, 45 (100 %) • Payback time, 4.5 years
Arlanda Airport
World’s largest open loop system –savings 3-4 Gwh electricity, 10-15 Gwh heatPayback time 6-7 years
![Page 26: Using case studies - Renewable heat · Using case studies to understand the integration of ground storage of energy intoground storage of energy into building and underground structures](https://reader031.fdocuments.in/reader031/viewer/2022011817/5e7ac4aaa23ae3029a48fa08/html5/thumbnails/26.jpg)
18/04/2011
26
Server room coolingServer room cooling
Installed at 200 sites; 40 with ground sourceInstalled at 200 sites; 40 with ground source
Server room coolingServer room cooling
![Page 27: Using case studies - Renewable heat · Using case studies to understand the integration of ground storage of energy intoground storage of energy into building and underground structures](https://reader031.fdocuments.in/reader031/viewer/2022011817/5e7ac4aaa23ae3029a48fa08/html5/thumbnails/27.jpg)
18/04/2011
27
Server room coolingServer room cooling
Server room coolingServer room cooling
•Few moving parts and simple technology•Low operational and maintenance costs•High-temperature cooling
![Page 28: Using case studies - Renewable heat · Using case studies to understand the integration of ground storage of energy intoground storage of energy into building and underground structures](https://reader031.fdocuments.in/reader031/viewer/2022011817/5e7ac4aaa23ae3029a48fa08/html5/thumbnails/28.jpg)
18/04/2011
28
Telia’s ground cooling projectsTelia’s ground cooling projectsSite Length (m) Cooling rate
borehole (kW)
Stockholm 30 5100 220Stockholm 30 5100 220Aspudden 26 4160 150Hageby 17 2720 111Hässleholm 19 3135 105Kalmar 14 2520 85Sundbyberg 14 2170 83,3Hässelby 16 1920 70Ludvika 5 750 55Karlskrona 12 1980 55Linköping 7 1120 45,5Tumba 6 960 45Ulriksdal 7 1120 42Växsjö 6 930 35Borlänge 5 750 32,5Örnsköldsvik 3 690 28
Geothermal tunnel liningsGeothermal tunnel linings
How to deal with air temperatues in tunnelsHow to deal with air temperatues in tunnels
![Page 29: Using case studies - Renewable heat · Using case studies to understand the integration of ground storage of energy intoground storage of energy into building and underground structures](https://reader031.fdocuments.in/reader031/viewer/2022011817/5e7ac4aaa23ae3029a48fa08/html5/thumbnails/29.jpg)
18/04/2011
29
Geothermal tunnel liningsGeothermal tunnel linings
AirAir
Rock wallRock wall
Temperature conditions along tunnelsTemperature conditions along tunnels
Geothermal tunnel liningsGeothermal tunnel linings
Annual variations of rock surrounding tunnelAnnual variations of rock surrounding tunnel
![Page 30: Using case studies - Renewable heat · Using case studies to understand the integration of ground storage of energy intoground storage of energy into building and underground structures](https://reader031.fdocuments.in/reader031/viewer/2022011817/5e7ac4aaa23ae3029a48fa08/html5/thumbnails/30.jpg)
18/04/2011
30
Vienna metro projectVienna metro project
Four metro stationsFour metro stations-- 449 kW heating capacity449 kW heating capacity-- 213 kW cooling capacity 213 kW cooling capacity
Vienna metro projectVienna metro project
Diaphragm wallsDiaphragm wallsBase slabsBase slabsTunnel wallsTunnel walls
Heating and cooling of Heating and cooling of buildingsbuildings
Ice preventionIce preventionHeating points sensible to coldHeating points sensible to cold
![Page 31: Using case studies - Renewable heat · Using case studies to understand the integration of ground storage of energy intoground storage of energy into building and underground structures](https://reader031.fdocuments.in/reader031/viewer/2022011817/5e7ac4aaa23ae3029a48fa08/html5/thumbnails/31.jpg)
18/04/2011
31
Vienna metro projectVienna metro project
Heating and cooling requirementsHeating and cooling requirements
Vienna metro projectVienna metro project
Examples of ”absorber” installationsExamples of ”absorber” installations
![Page 32: Using case studies - Renewable heat · Using case studies to understand the integration of ground storage of energy intoground storage of energy into building and underground structures](https://reader031.fdocuments.in/reader031/viewer/2022011817/5e7ac4aaa23ae3029a48fa08/html5/thumbnails/32.jpg)
18/04/2011
32
Vienna metro projectVienna metro project
Energy fleece with embedded pipes for tunnel liningsEnergy fleece with embedded pipes for tunnel linings
Vienna metro projectVienna metro project
Rock temperatures along a proposed alp tunnelRock temperatures along a proposed alp tunnel
![Page 33: Using case studies - Renewable heat · Using case studies to understand the integration of ground storage of energy intoground storage of energy into building and underground structures](https://reader031.fdocuments.in/reader031/viewer/2022011817/5e7ac4aaa23ae3029a48fa08/html5/thumbnails/33.jpg)
18/04/2011
33
Karlstad’s Hospital, SwedenKarlstad’s Hospital, Sweden
Heating and cooling with combined groud and river sourceHeating and cooling with combined groud and river source
![Page 34: Using case studies - Renewable heat · Using case studies to understand the integration of ground storage of energy intoground storage of energy into building and underground structures](https://reader031.fdocuments.in/reader031/viewer/2022011817/5e7ac4aaa23ae3029a48fa08/html5/thumbnails/34.jpg)
18/04/2011
34
Karlstad’s Hospital, SwedenKarlstad’s Hospital, SwedenEnergy demand (=bought energyEnergy demand (=bought energy))
BEFORE (2000)BEFORE (2000)District heatingDistrict heating 26,4 GWh/year26,4 GWh/yearElectricityElectricity 23 6 GWh/year23 6 GWh/yearElectricityElectricity 23,6 GWh/year23,6 GWh/yearTotalTotal 50,0 GWh/year50,0 GWh/year
Step 1Step 1. Energy efficiency measures. Energy efficiency measures-- Changing windows, improving thermal insulationChanging windows, improving thermal insulation
Step 2Step 2. Change of energy production. Change of energy production-- Installation of groundInstallation of ground--source heat pump/energy storage with free source heat pump/energy storage with free cooling during summer and preheating of outdoor air during wintercooling during summer and preheating of outdoor air during winterg g p g gg g p g g
AFTER (2011)AFTER (2011)District heatingDistrict heating 2,5 Gwh/year2,5 Gwh/yearHVAC/GSHP electricityHVAC/GSHP electricity 22,2 GWh/year22,2 GWh/yearTotalTotal 24,7 MWh/year24,7 MWh/year
Savings 24,1 GWh heat (91 %) 1,4 Gwh electricity Savings 24,1 GWh heat (91 %) 1,4 Gwh electricity Payback time 5 yearsPayback time 5 years
CSK Hus 41 Värme- energiproduktion Alt 0
2750
3000
3250
3500
3750
4000
4250
4500
W]
Fjärrvärme
Energy supply Energy supply -- beforebefore
HeatDistrict heating
CSK Hus 41 Kyl-energiproduktion Alt 0
Frikyla älvVKA
VKA
0
250
500
750
1000
1250
0 350 701 1051 1402 1752 2102 2453 2803 3154 3504 3854 4205 4555 4906 5256 5606 5957 6307 6658 7008 7358 7709 8059 8410 8760
Timmar [h]
Fjärrvärme
0
250
500
750
1000
1250
1500
1750
2000
2250
2500
0 350 701 1051 1402 1752 2102 2453 2803 3154 3504 3854 4205 4555 4906 5256 5606 5957 6307 6658 7008 7358 7709 8059 8410 8760
Eff
ekt
er [
kW
Heatheating
6868
VKA1500
1750
2000
2250
2500
2750
3000
3250
3500
3750
4000
4250
4500
Eff
ekt
er
[kW
]
VKAVKAFrikyla älv
ColdFree cooling / river
Coolingmachine
![Page 35: Using case studies - Renewable heat · Using case studies to understand the integration of ground storage of energy intoground storage of energy into building and underground structures](https://reader031.fdocuments.in/reader031/viewer/2022011817/5e7ac4aaa23ae3029a48fa08/html5/thumbnails/35.jpg)
18/04/2011
35
System designSystem designDistrict heating Heating load
Cooling loadCool machine
Heat pump Heat exchanger
River Ground
Energy supply Energy supply -- afterafter
HeatDistrict heating
CSK Hus 41 Värme- energiproduktion Alt 9 - 80 berghål
Fjärrvärme
2500
2750
3000
3250
3500
3750
4000
4250
4500
kW]
FjärrvärmeEL VPAÄlvBerg 1KB-systemet
District heating
Heat pump electricity
River
Heat
F li /
heating
KB-systemet som värmekälla
Berg 1
Älv
EL VPA
0
250
500
750
1000
1250
1500
1750
2000
2250
0 350 701 1051 1402 1752 2102 2453 2803 3154 3504 3854 4205 4555 4906 5256 5606 5957 6307 6658 7008 7358 7709 8059 8410 8760
Ti [h]
Eff
ekte
r [k
RiverGround
Hc fluid
CSK Hus 41 Kyl-energiproduktion Alt 9 - 80 borrhål
KB-systemet VKA
Frikyla berg 1
VKA
0
250
500
750
1000
1250
0 350 701 1051 1402 1752 2102 2453 2803 3154 3504 3854 4205 4555 4906 5256 5606 5957 6307 6658 7008 7358 7709 8059 8410 8760
Timmar [h]
H fl id F li /Cold
Free cooling / river
Coolingmachine
1500
1750
2000
2250
2500
2750
3000
3250
3500
3750
4000
4250
4500
Eff
ekte
r [k
W]
VKAFrikyla berg 1VKAKB-systemet
Hc fluid Free cooling / ground
Coolingmachine
River
![Page 36: Using case studies - Renewable heat · Using case studies to understand the integration of ground storage of energy intoground storage of energy into building and underground structures](https://reader031.fdocuments.in/reader031/viewer/2022011817/5e7ac4aaa23ae3029a48fa08/html5/thumbnails/36.jpg)
18/04/2011
36
Specific energy demandSpecific energy demand
BeforeBefore GSHP with 80 boreholes (four different versions)GSHP with 80 boreholes (four different versions)
Kristinehamn’s Hospital, SwedenKristinehamn’s Hospital, SwedenEnergy demand (=bought energy)Energy demand (=bought energy)
BEFOREBEFOREDistrict heatingDistrict heating 2135 MWh/year2135 MWh/yeargg /y/yHVAC electricityHVAC electricity 605 MWh/year605 MWh/yearTotalTotal 2740 MWh/year2740 MWh/year
Step 1Step 1. Energy efficiency measures. Energy efficiency measures-- Changing windows, improving thermal insulationChanging windows, improving thermal insulation
Step 2Step 2. Change of energy production. Change of energy production-- Installation of groundInstallation of ground--source heat pump/energy storage with free source heat pump/energy storage with free cooling during summer and preheating of outdoor air during wintercooling during summer and preheating of outdoor air during wintercooling during summer and preheating of outdoor air during wintercooling during summer and preheating of outdoor air during winter
AFTERAFTERDistrict heatingDistrict heating 155 MWh/year155 MWh/yearHVAC electricityHVAC electricity 465 MWh/year465 MWh/yearTotalTotal 620 MWh/year620 MWh/year
Savings 2120 MWh (78 %) Payback time 5 yearsSavings 2120 MWh (78 %) Payback time 5 years
![Page 37: Using case studies - Renewable heat · Using case studies to understand the integration of ground storage of energy intoground storage of energy into building and underground structures](https://reader031.fdocuments.in/reader031/viewer/2022011817/5e7ac4aaa23ae3029a48fa08/html5/thumbnails/37.jpg)
18/04/2011
37
Kristinehamn’s Hospital, SwedenKristinehamn’s Hospital, Sweden
2500
3000
HVAC electricity
District heating
1000
1500
2000
Bought energy (M
Wh)
0
500
Before After energy efficiency measures After installation of GSHP
Bought energy (MWh)
Performance
Heating
Seasonal performance factor
3-4g Heating and cooling Heating and predominantly free
cooling (without cooling machine) Free cooling*
3-4
5-6
12-35
* Free cooling with boreholes is used in Sweden for telephone switching stations and broadcasting stations (about 100 installations). Ground temperatures are in the range 4-10 C.
![Page 38: Using case studies - Renewable heat · Using case studies to understand the integration of ground storage of energy intoground storage of energy into building and underground structures](https://reader031.fdocuments.in/reader031/viewer/2022011817/5e7ac4aaa23ae3029a48fa08/html5/thumbnails/38.jpg)
18/04/2011
38
Installation costs
Drilling* 25-35 EUR per m
Complete system (borehole heat exchanger, installation, heat pump)
1500 EUR per kW heating capacity
*Depending on local geological conditions
Profitability
Heating
Pay-back time (years)
5-10+g
Heating and cooling Heating and predominantly free
cooling (without cooling machine)
4-10+
3-10+
* Depending on local conditions (geology, climate, distribution system, competing technology, costs, etc). Rough indication achieved for suitable applications.
![Page 39: Using case studies - Renewable heat · Using case studies to understand the integration of ground storage of energy intoground storage of energy into building and underground structures](https://reader031.fdocuments.in/reader031/viewer/2022011817/5e7ac4aaa23ae3029a48fa08/html5/thumbnails/39.jpg)
18/04/2011
39
Based on developed techniques and parts Based on developed techniques and parts Low operational costsLow operational costs
Reasonable payReasonable pay--back timesback times
Large hybrid groundLarge hybrid ground--source systemssource systems
p yp y
Seasonal energy storageSeasonal energy storage
Potential for further developmentPotential for further development
Heating Heating andand coolingcooling Large fraction renewable energy (75Large fraction renewable energy (75--85 %)85 %)
HeatingHeating HeatingHeating Recharging with renewable (water, air, solar)Recharging with renewable (water, air, solar)
CoolingCooling Techniques for highly efficient highTechniques for highly efficient high--temperature ground source temperature ground source
cooling availablecooling available