USER MANUAL FOR USRP

13
USER MANUAL FOR USRP

Transcript of USER MANUAL FOR USRP

Page 1: USER MANUAL FOR USRP

USER MANUAL FOR USRP

Page 2: USER MANUAL FOR USRP

GUIDELINES FOR CONSUMER

Step1: Go to URL https://www.tnebltd.gov.in/usrp/ then click

Apply->Apply Online CFA

Step 2: Enter the name and consumer number and click ” validate ” button

Page 3: USER MANUAL FOR USRP

Step 3: Enter the personal details

Page 4: USER MANUAL FOR USRP

Step 4: Enter the Additional details

Step 5: Enter the Solar PV details

Page 5: USER MANUAL FOR USRP

Step 6: Click the Vendor details, Select the Vendor and submit the application.

Page 6: USER MANUAL FOR USRP

Step 7: Click Modify or submit in the Confirm details.

Page 7: USER MANUAL FOR USRP

Step 8: After successful registration, print the acknowledgement for your future

reference.

Page 8: USER MANUAL FOR USRP

Step 9: Make online Payment using the highlighted URL.

Page 9: USER MANUAL FOR USRP

GUIDELINES FOR VENDOR AND TEDA

-USRP

Page 10: USER MANUAL FOR USRP

STEP 1: Vendor

STEP 2: Teda AE

STEP 2:

Login as Vendor

Login as Teda AE

Ensure the feasibility of

application

Accept the Pending applications

Page 11: USER MANUAL FOR USRP

STEP 3: Teda HQ

STEP 4:Vendor

Login as Teda HQ

Issue the Work order

Save and print the Work order

Click the menu process ->Work

Status->update , to approve

work order

Login as Vendor

Click the menu process ->Work

Order download , to download

the work order

Click the menu process ->Work

Status->installation complete

and upload the files

Page 12: USER MANUAL FOR USRP

STEP 5:Teda AE

STEP 6:Teda AE

STEP 7:Teda HQ

Login as Teda AE

Ensure the Completion of work

by Vendor

Ensure all uploaded files of

Vendor by downloading it

Upload the Joint Inspection

Report

Login as Teda HQ

Upload the Project Completion

Report

Login as Teda AE

Page 13: USER MANUAL FOR USRP

TANGEDCO PROCESS FLOW

EE/O&M will transfer the application to AEE for feasibility

study.

AEE inspects the site and checks Transformer capacity etc

and confirm feasible / not feasible report to EE.

EE issues technical clearance to TEDA AE for further process.

Application moves to TANGEDCO AE for estimate preparation.

Process

1 by

TANGE

DCCO

Officials

TEDA AE checks site and either notifies defects in the

Installation or accepts the installation.

TANGEDCO AE Prepares estimate for bi-directional meter and

submits for sanction.

Once plant readiness details date entered by TEDA AE,

application is moved to AEE for safety inspection & to TEDA for joint inspection.

After safety inspection issued by AEE / CEIG and joint

inspection by TEDA with consumer and vendor, TANGEDCO

AE fixes bi-directional meter in the site.

EE / Distribution clears for Subsidy.

Process

2 by

TANGE

DCCO

Officials

Once the consumer has completed the payment through TANGEDCO portal, the application will move to concerned

EE / O&M for Technical feasibility.