Transcript of User Manual Capex Ps

  • mySAPERP2004 End user document (PS Module)

    V1.0

    Sep 2007

    English

    End User Documentation - PS

    mySAPERP2004 (ECC 6.0)

    SSTL1,6th Floor, Crown Court#128, Cathedral Road Chennai 600 086

    Solution/ Release: ECC 6.0 Page 1 of 183

  • mySAPERP2004 End user document (PS Module)

    Content

    1 Sequential operation of Project System (PS) module ................................................ 4

    2 Create Investment Program ...................................................................................... 21

    3 Create Investment Program Top Position ................................................................. 24

    4 Change Investment Program Structure .................................................................... 27

    5 Edit Original Budget ................................................................................................ 31

    6 Create Appropriation Request ................................................................................. 36

    7 Change Appropriation Request ................................................................................ 51

    8 Activate Project Definition ....................................................................................... 60

    9 Budget Distribution .................................................................................................. 66

    10 Release Appropriation Request ................................................................................ 73

    11 Change Project Definition ........................................................................................ 76

    12 Change Cost Planning ............................................................................................. 80

    13 Change Original Budget .......................................................................................... 85

    14 Create Network ........................................................................................................ 91

    15 Change Project Definition ..................................................................................... 105

    16 Create Purchase Requisition .................................................................................. 109

    17 Create Purchase Order ........................................................................................... 117

    18 Create Vendor Advance ......................................................................................... 122

    19 Post Vendor down Payment ................................................................................... 125

    20 Goods Receipts Purchase Order ............................................................................ 128

    21 Logistics Invoice Verification ................................................................................. 133

    Solution/ Release: ECC 6.0 Page 2 of 183

  • mySAPERP2004 End user document (PS Module)

    22 Create Reservation .................................................................................................. 151

    23 Goods Issue ............................................................................................................ 154

    24 Service Entry ......................................................................................................... 158

    25 Create Confirmations ............................................................................................ 162

    26 Payment with Printout ........................................................................................... 166

    27 Project Settlement .................................................................................................. 171

    28 Create Completed Asset ........................................................................................ 174

    29 Change Network Status Closed .......................................................................... 180

    30 Change Project Status Closed ............................................................................. 182

    Solution/ Release: ECC 6.0 Page 3 of 183

  • SAP ECC 6.0 End user document (PS Module) Sequential operation of Project System (PS) module

    I Creation of Investment Program

    a) Create Investment Program - Transaction Code: IM01As soon as the Financial Year Starts the Investment Program Creation needs to be done by the authorized person.The Following things are mentioned in the Investment Program

    1. Investment Program2. Approval Year3. Program Type4. Fiscal Year Variant5. Currency

    With this information the Investment Program is saved and the same is informed to Projects Department over phone and SAP Mail. The authorized person in SAP does this step.

    b) Create Investment Program Top Position - Transaction Code: IM11

    After Creating the Investment Program the Top Company Level position is created for the Investment Program. The Following things are mentioned in the Investment Program Top Position

    1. Investment Program2. Position ID3. Approval Year

    The authorized person in SAP does this step.

    c) Create Investment Program Structure - Transaction Code: IM22

    After Creating the Investment Program the Top Company Level position is created for the Investment Program the Investment Program Structure is created.The Following things are mentioned in the Investment Program Top Position

    1. Investment Program2. Position ID (Optional)3. Approval Year

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 4 of 183

  • SAP ECC 6.0 End user document (PS Module)

    II Maintaining Budget for Investment Program

    a) Edit Original Budget - Transaction Code: IM32

    After Creating the Investment Program Structure the Budget is maintained for the created Investment Structure. This can be maintained whenever the New appropriation request is assigned to the Position Ids.The Following things are mentioned in the Edit Original Budget

    1. Investment Program2. Position ID (Optional)3. Approval Year

    This step is done by the authorized person in SAP.

    III. Appropriation Request

    a) Create Appropriation Request Transaction Code : IMA11

    After getting the Feasibility Study for scaling up the Process in the Production Level. The authorized person in SAP creates the appropriation request.The Following things are mentioned in the Appropriation Request

    1. Appropriation Request Type2. Controlling Area after this in General Data 3. Appropriation Request4. Description5. Approval Year6. Planned Approval Date7. Implementation Start8. Person Involved for Approval User ID needs to be selected Level wise.

    In Control Data9. Investment Program /Year10. Position ID.

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 5 of 183

  • SAP ECC 6.0 End user document (PS Module) In Organizational Units

    1. Requesting Company code2. Requesting Business Area3. Requesting Cost Center4. Requesting Profit Center5. Requesting Company6. Object Class7. Plant8. Responsible Cost Center9. Responsible Profit Center10.Currency

    In Variants TabGeneral Data

    1. Completion Date Approximate date of Project completion date.Select Plan Values Tab

    Click on Create Cost Estimate Button below the screen.

    A new screen is opened where you need to click the button Show/Hide Item View. It would show a table where we need to feed in the values. The values to be fed are

    Item Categoryo M for Materialo V for other costs like manpower, QC etc. The cost element for V

    should be 7100150 Resource is where we select the RM name. The master would be

    entered by the Purchase person. This is not required for RM. Enter Quantity & hit enter.

    For V change the description to suit us. After completion of the entry, click confirm to record those values by

    SAP which would appear on the left hand side of the screen.

    Rows can be added, inserted, deleted accordingly. Filled values are shown below.

    Go Back or press F3. The total budget for the year 2007 (as the investment planned is for 2007) would appear as shown below. Save the Appropriation request.

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 6 of 183

  • SAP ECC 6.0 End user document (PS Module) Note: We would define the cost for 1 year and if the project spills over to the next year the remaining budget would also spill over.

    After mentioning all the required entries when the user saves the appropriation request as per the configuration the Appropriation request will go for approval process as SAP Workflow (predefined Process). The documents are uploaded through Document Management system as well as it can be uploaded in Change mode of Appropriation request by selecting the Service for Object Create Attachment.

    b) Approve Appropriation Request Transaction Code : IMA12/SBWP

    When the approving authority opens their SAP Mail Box through the transaction code SBWP the system will show all the Workflow process to be executed by him. He has to select the required appropriation request and Click on Approve button, if he wants to see the attachment. He can see the same in display mode of Appropriation request by selecting the Service for Object View Attachment or in the Document Tab. The authorized person in SAP does this step.

    c) Activate & Release Appropriation Request Transaction Code: IMA12

    After approval the Appropriation request needs to be activated and released. This will be done by the authorized person in the Measures/Assets Tab of the Appropriation request in change mode of Appropriation request transaction.

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 7 of 183

  • SAP ECC 6.0 End user document (PS Module) IV. Budget Distribution

    a) Distribute Budget for Project Definition Transaction Code: IM52After activating the Appropriation Request (Project Definition). The Following things are mentioned in the Distribute Budget

    1. Investment Program2. Position ID (Optional)3. Approval Year

    The Overall as well as Yearwise Budget has to be updated. This step is done by the authorized person in SAP.

    V. Creation of Project Structure

    a) Change Project Transaction Code: CJ02After updating the Budget for the Appropriation Request (Project Definition). The Following things are mentioned in the Change Project transactions. The authorized person in SAP does this step. In the Project Definition Header the Following things are mentioned

    1. Person Responsible2. Start Date and End date of Project will be defaulted from the

    Appropriation Request. 3. Company code4. Business Area5. Plant6. Profit Center

    In the WBS element Overview the Basic Data tab the following things are mentioned. 1. Level Number2. Description3. Upto Level 3 WBS elements are Created with Planning Element (if the

    level is below 4).In Responsibilties Tab4. Requesting Cost Center needs to be filled. 5. Which will automatically copy the Controlling Area (CA) and Requesting

    Company Code.6. if required Responsible Cost Center field will be filled.

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 8 of 183

  • SAP ECC 6.0 End user document (PS Module) V. Cost Planning for Project Definition

    a) Manual Cost Planning for Project Transaction Code: CJ40

    After updating the budget for the Top-level Project Definition the Lower Level (Level 3) the Overall as well as Year-wise planned cost has to be updated. The authorized person does this step.

    VI. Budget Updation for Project Definition (Level 3)

    a) Manual Budget Updation for Project Transaction Code: CJ30

    After manual Cost Planning for the Lower Level (level 3) WBS Elements the budget for the Lower Level (Level 3) the Overall as well as Year-wise planned cost has to be updated. The authorized person does this step.

    V. Creation of Network

    a) Create Network for Project Transaction Code: CN21

    In the initial Screen the Following things are mentionedNetwork ProfileNetwork TypePlantMRP Controller

    In the Network Header the following things are mentioned.Network Description In Assignment Tab Select the Project Definition, which will copy the Start Date and End Date of the Project if its maintained in the Project Definition. These dates are considered for individual activities in the Network. The Network activities are linked with relationship and these network activities will be scheduled. The Milestones or Milestone Groups are also used with the activities. A network can represent the sequence of activities in a project or the sequence of a single activity within a project. You can graphically display various structural elements of a project and their interdependencies in the Project System. During the life of a project, networks are used as a basis for planning, analyzing, controlling and monitoring schedules, dates, and resources.(such as personnel, machines, PRTs, materials, documents, and drawings)

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 9 of 183

  • SAP ECC 6.0 End user document (PS Module) These activities are three types 1. Internal Activities, 2. External Activities, 3. Primary Cost Activities.

    Internal Activities:Using internally processed activities you determine the amount of Work produced by machines or persons, and use this information in resource planning to plan the capacity requirement.

    External Activities:Using external processing you determine which services are required from other companies to carry out the project. The development of external processing occurs through purchasing.

    Primary Cost Activities:Using general costs activity you plan primary costs, for example, travel costs.

    V. Creation of Lower Level (Level 4) WBS & Release of Project

    a) Create Lower Level WBS (Level 4) & Release Project Transaction Code: CJ02

    In the initial Screen the Following things are mentionedProject Definition In the WBS element Overview

    the Basic Data tab the following things are mentioned. 1.Level Number (level 4)2. Description3 Planning Element (Tick)4. Account Assignment Element (Tick).In Responsibilties Tab5. Requesting Cost Center needs to be filled. Which will automatically copy the Controlling Area (CA) and Requesting Company Code.if required Responsible Cost Center field will be filled.

    Select EditStatus Release.The authorized person does this step.

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 10 of 183

  • SAP ECC 6.0 End user document (PS Module)

    V. Creation of Purchase Requisition for Materials

    a) Create Purchase Requisition Transaction Code: ME51/ME51N.In the initial Screen the Following things are mentionedAccount Assignment Category QDelivery DatePlantPurchasing GroupReq. Tracking NumberRequisitionerIn the Purchase requisition Item overview screen Material NumberQty. RequiredVal.Type WBS ElementThe Purchase requisition will be saved and will be released by the approving authorities. The authorized person does this step.

    VI. Creation of Purchase Order for Materials

    a) Create Purchase Order Transaction Code: ME21/ME21N.In the initial Screen the Following things are mentioned - HeaderVendorPurchasing OrganizationPayment TermGR Message (Tick)Net PriceIn Item Tax code wil be selected (if any)Select the PR and Adopt the PR.The Purchase order will be saved and will be released by the approving authorities. The authorized person does this step.

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 11 of 183

  • SAP ECC 6.0 End user document (PS Module) VII. Create & Post Vendor Down Payment Request

    a) Create Down Payment Request Transaction Code: F-47.After creating the Purchase order the Down Payment (Advance) to the vendor is raised. The authorized person does this step.In the initial Screen the Following things are mentioned - HeaderDocument DateCompany CodeCurrencyReference & Doc. Header TextVendor Account No.Spl.GL indicatorIn Detail Amount, Business Area, Due On, Purchase Order No./ Item.The down payment request will be saved.

    b) Post out Going Payment Transaction Code: F-48/F-53.After creating the Down Payment request, the Down Payment request (Advance) will be called and payment will be posted. The authorized person does this step.

    VIII. Goods receipts for Purchase Order

    a) Create Goods Receipts Transaction Code: MIGO.After the Purchase order is approved the material will be received by stores at Site. The authorized person does this step.In the initial Screen the Following things are mentioned HeaderPurchase Order NumberMovement TypeDelivery Note, Header TextQuantity, Storage Location, No.of Container, etc.,The goods receipts document will be posted.

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 12 of 183

  • SAP ECC 6.0 End user document (PS Module) IX. Enter Invoice

    a) Enter Invoice Transaction Code: MIRO.After the material will be received by stores at Site. The authorized person does this step.In the initial Screen the Following things are mentioned HeaderInvoice DateReference AmountIf tax is there (tick) on check box (calculate Tax)Purchase Order number. After simulation the invoice Verfication document will be posted.

    X. External Processing Activites : for Services

    a) Change Network Transaction Code: CN22.In the initial Screen the Following things are mentioned HeaderNetwork NumberIn activities overview In Ext. Processing Tick on ServiceDescription, Purch.Org., Material Group,Vendor,Pur.Grp,Outline Agreement,Line No.Requisitioner, Req.tracking No,WBS element.Service Number, Quantity.Prerequisite : The Project Definition System Status should be in REL Released mode.Select the Activity and Press Edit Status Release. Which will create a Purchase requisition for services with reference to the outline agreement entered.Purchase Order (Service PO ) will be created for the purchase requisition.

    When the order released for work, one PR for the services are generated. The PO will be released by the Purchase Department. The PO Copy is given to the Contractor by the Projects department. On completion of the work, contractor brings the Joint Measurement Sheet / Bill along with the PO reference.

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 13 of 183

  • SAP ECC 6.0 End user document (PS Module)

    b) Create Service Entry Transaction Code: ML81N.In the initial Screen the Following things are mentioned HeaderPurchase Order Number

    When the Contractor brings the Joint Measurement Sheet / Bill for the certification, the quantity entered in the JMC/Bill is verified by the Shift Engineer and the same quantity is certified in the Service Entry Sheet. This is subject to Release Procedure (Certification by Higher Official). On Certification the Project gets the Cost of the Services performed.

    c) Enter Invoice Transaction Code: MIRO.After the service confirmation is released. The authorized person does this step.In the initial Screen the Following things are mentioned HeaderInvoice DateReference AmountIf tax is there (tick) on check box (calculate Tax)Purchase Order number. After simulation the invoice Verfication document will be posted.

    XI. Create Reservation

    a) Create Reservation Transaction Code: MB21.The stocks are maintained as Special Stocks against the WBS elements. The reservations are created against WBS elements. This reservation can be done in Automatically while running MRP for Projects. In the initial Screen the Following things are mentioned HeaderBase date (When the material is required)Movement typePlantIn Create Reservation ScreenWBS elements, Material Code, Quantity, Batch Number, Goods recipient.The reservation is created.

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 14 of 183

  • SAP ECC 6.0 End user document (PS Module)

    XI. Goods Issue

    a) Create Goods Issue Transaction Code: MIGO/MB1A.When the Stores person saw the reservations pending for issues on that day he has to post the goods issue against the reservations. Creation needs to be done by the authorized person.The Following things are mentioned in the goods issue.Reservation numberQuantityMaterial Slip.Document header text.No.of Container.The Goods Issue document will be posted.

    XII. Create Confirmationsa) Create Confirmations Transaction Code: CN25/CN27.When the activities are completed, that needs to be confirmed by the users. The authorized person will do the confirmation. The Following things are mentioned in the goods issue.Network numberActivity number Work Center, Description, Actual finish Date. If the work is fully completed then Final Comp. Otherwise completion indicator (tick).

    XIII. Vendor Payment

    a) Post Outgoing Payments Transaction Code: F-58.After Invoice is verified the payment to the vendor needs to be posted. The authorized person will do the outgoing payment. The Following things are mentioned in the outgoing payment.

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 15 of 183

  • SAP ECC 6.0 End user document (PS Module)

    XIV. Project Settlement

    a) Actual Settlement Transaction Code: CJ88/CJ8G.This settlement will be run on periodic basis (every end of month). The authorized person will do the actual settlement. The Following things are mentioned in the actual settlement.Project DefinitionWith Hierarchy (tick)With Order (tick)Settlement PeriodFiscal YearTest runDetail ListCheck. Trans.dataThe actual consumption against the Project/ Network will be settled to the WBS elements.(AUC) asset Under Construction.

    b) Create Complete Asset Transaction Code: CJ02.After getting the confirmation from the Project Department that the Project is commissioned and handed over to the Production department for use. The authorized person will do the completed Asset creation. The Following things are mentioned in the Create Complete AssetProject DefinitionSelect the WBS elements and Extras Create Completed Asset.In Asset Create Screen Asset Class (sub Asset if required)Description Vendor & Manufacturer Asset Pur. New (tick)Purchase Used (tick)Group Asset / Sub NumberNeg. value Allowed (tick)

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 16 of 183

  • SAP ECC 6.0 End user document (PS Module) c) Actual Settlement Transaction Code: CJ88/CJ8G.This settlement will be run after getting the confirmation from the Project Department that the Project is commissioned and handed over to the Production department for use. The authorized person will do the completed Asset creation. The Following things are mentioned in the actual settlement.Project DefinitionWith Hierarchy (tick)With Order (tick)Settlement Period, Posting PeriodFiscal Year, Asset Value dateTest runDetail ListCheck. Trans.data

    XIV. Project Closure

    a) Change Network Transaction Code: CN22.Select all the Activities in the Network and select Edit Status Close.

    b) Change Project Transaction Code: CJ02.Select all the WBS elements in the Project Definition and select Edit Status Close.

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 17 of 183

  • SAP ECC 6.0 End user document (PS Module)

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 18 of 183

    Create Investment Program/Position ID(By Finance)

    Approve Appropriation Request(By Approving Authorities)

    SBWP/ IMA12

    Activate Project & Allocate Budget (By Finance)IMA12/IM52

    Create WBS up to 3 Level(By Projects)

    CJ02

    Allocate Budget for Level 3 (By Finance/Projects)

    CJ40 / CJ30

    Create Lower Level WBS elements (By Projects)

    CJ02

    Create Appropriation Request(By Projects)

  • SAP ECC 6.0 End user document (PS Module)

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 19 of 183

    Create PR/Release PR (By Projects/Approving

    Authorities)(ME51/ME55)

    Goods Receipts (By Stores )MIGO

    Create Reservation & Goods Issue

    (By Projects / Stores)MB21/MIGO

    Create Service PR / Release PR

    (By Projects/App.Autho.)

    Create Service PO/Release PO (By Purchase/App.Autho.)

    ME21N/ME28

    Create Service Entry/Approve(By Projects/App.Autho)

    ML81N/ML85

    Create PO/Release PO (By Purchase/Approving Authorities)ME21N/ME28

  • SAP ECC 6.0 End user document (PS Module)

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 20 of 183

    Create Confirmation(By Projects)CN25/CN27

    Create Completed Asset(By Finance)

    CJ02

    Network System Status as CLSD(Closed)

    (By Projects / Finance)CN22

    Actual Settlement (Automatic)(By Finance) CJ88/CJ8G

    Projects Definition System Status as CLSD(Closed)

    (By Projects / Finance)CJ02

  • SAP ECC 6.0 End user document (PS Module)

    Title: Create Investment Program Transaction CodeIM01Document No. Responsibility Version Supercedes Issue

    d onEffective Date

    Review Date

    SAP/EUD/PS/01 Finance 001 NIL

    Prepared by Reviewed by Approved by

    V.Ananthapadmanaban 10.03.2008

    2.1 Trigger

    Receipt of Intimation from Management or the Financial Year Change.

    Business Process Procedure Overview Creation of Capital Investment Program

    Via Menus Accounting Investment Management Program Master Data Investment Program Definition Create.

    Via Transaction Code IM01

    Input - Required Fields* Field Value / Comments

    Investment Program Type the Description of the Investment Program e.g. Shasun Investment

    Approval YearType the financial year e.g. 2007

    Program Type Select the option from the list e.g. ZSCD Capital Investment Program

    Some of the fields mentioned in the following may not be in your entry screen. This depends on the configuration of your system.

    Output Results CommentsCreation of Investment Program

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 21 of 183

  • SAP ECC 6.0 End user document (PS Module) Procedural Steps

    Access Create Investment Program transaction by:Via Menus Accounting Investment Management Program Master Data

    Investment Program Definition Create.Via Transaction Code IM01

    1.2. On screen Create Inv. Program Definition: Header Screen, enter information in the fields in the table below:

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 22 of 183

  • SAP ECC 6.0 End user document (PS Module)

    Field Name Description R/O/C User Action and Values Comments

    Investment Program

    Investment Program R Type the Description of the Investment Program e.g. Shasun Investment 07-08

    Approval Year Approval Year R Type the financial year e.g. 2007

    Program Type Program Type R Select from the list ZSCD or ZSRD.Based on the Project for Capital Expenditure or Research & Development

    Program Description

    Investment Program Description R Type Investment Program Description

    FI Variant Fiscal Year Variant R Select the option from the list e.g. V3 April March.

    Currency Currency R Company code Currency INR.

    (Note: On above table, in column R/O/C: R = Required, O = Optional, C = Conditional)

    Press Ctrl + S or Save Button from the Screen

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 23 of 183

  • SAP ECC 6.0 End user document (PS Module)

    Title:Create Investment Program Top Position

    Transaction CodeIM11

    Document No. Responsibility Version Supercedes Issued on

    Effective Date

    Review Date

    SAP/EUD/PS/01 Finance 001 NIL

    Prepared by Reviewed by Approved by

    V.Ananthapadmanaban 10.03.2008

    2.1 Trigger

    After Creating the Capital Investment Program.

    Business Process Procedure Overview Creation of Capital Investment Program Top Position.

    Via Menus Accounting Investment Management Program Master Data Investment Program Position Create Top Position.

    Via Transaction Code IM11

    Input - Required Fields* Field Value / Comments

    Investment Program Type the Description of the Investment Program e.g. SHA0708

    Position ID Type the Top level Position ID. e.g. SHASUN Investment 2007-08

    Approval Year Type the financial year e.g. 2007

    Some of the fields mentioned in the following may not be in your entry screen. This depends on the configuration of your system..

    Output Results CommentsCreation of Investment Program Top Position.

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 24 of 183

  • SAP ECC 6.0 End user document (PS Module) Procedural Steps

    Access Create Investment Program transaction by:

    Via Menus Accounting Investment Management Program Master Data Investment Program Position Create Top Position.

    Via Transaction Code IM111.2. On screen Create Inv. Program Position : Header Screen, enter information in the fields in the table below:

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 25 of 183

  • SAP ECC 6.0 End user document (PS Module)

    Field Name Description R/O/C User Action and Values Comments

    Investment Program

    Investment Program R Type the Description of the Investment Program e.g. Shasun Investment 07-08

    Position ID Top Position ID R Type the Top level Position ID. e.g. Shasun Investment 07-08

    Approval Year Approval Year R Type the financial year e.g. 2007

    Position ID Description

    Top Position ID Description R Type the Description of the Top Position ID.

    CO Area Controlling Area R Select the option from the list e.g. 1000

    Company Code Company Code O Select the option from the list e.g. 9000

    (Note: On above table, in column R/O/C: R = Required, O = Optional, C = Conditional)

    Press Ctrl + S or Save Button from the Screen

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 26 of 183

  • SAP ECC 6.0 End user document (PS Module)

    Title:Change Investment Program Structure

    Transaction CodeIM22

    Document No. Responsibility Version Supercedes Issued on

    Effective Date

    Review Date

    SAP/EUD/PS/01 Finance 001 NIL

    Prepared by Reviewed by Approved by

    V.Ananthapadmanaban 10.03.2008

    2.1 Trigger

    After Creating the Capital Investment Program Top Position.

    Business Process Procedure Overview Creation of Capital Investment Program Top Position.

    Via Menus Accounting Investment Management Program Master Data Investment Program Structure Change.

    Via Transaction Code IM22

    Input - Required Fields* Field Value / Comments

    Investment Program Type the Description of the Investment Program e.g.SHA0708.

    Position ID Type the Top level Position ID. e.g. SHASUN INVESTMENT 2007-08

    Approval Year Type the financial year e.g. 2007

    Some of the fields mentioned in the following may not be in your entry screen. This depends on the configuration of your system..

    Output Results CommentsCreation of Investment Program Structure.

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 27 of 183

  • SAP ECC 6.0 End user document (PS Module)

    Procedural Steps

    Access Change Inv. Program Structure transaction by:Via Menus Accounting Investment Management Program Master Data

    Investment Program Structure Change.Via Transaction Code IM22

    31 3.1. On screen Change Inv. Program Structure: , enter information in the fields as specified in the table below:

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 28 of 183

  • SAP ECC 6.0 End user document (PS Module)

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 29 of 183

    Click on Create

  • SAP ECC 6.0 End user document (PS Module)

    Field Name Description R/O/C User Action and Values Comments

    Investment Program

    Investment Program R Type the Description of the Investment Program e.g. SHA0708

    Position ID Top Position ID O Type the Top level Position ID. e.g. Shasun Investment 07-08.

    Approval Year Approval Year R Type the financial year e.g. 2007

    (Note: On above table, in column R/O/C: R = Required, O = Optional, C = Conditional)

    Press Ctrl + S or Save Button from the Screen

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 30 of 183

  • SAP ECC 6.0 End user document (PS Module)

    Title: Edit Original Budget Transaction CodeIM32Document No. Responsibility Version Supercedes Issue

    d onEffective Date

    Review Date

    SAP/EUD/PS/01 Finance 001 NIL

    Prepared by Reviewed by Approved by

    V.Ananthapadmanaban 10.03.2008

    2.1 Trigger

    After creating the Investment Program Structure the company Level Budget needs to be updated.

    Business Process Procedure Overview Edit Original Budget for the Company.

    Via Menus Accounting Investment Management Program Budgeting Edit Original.

    Via Transaction Code IM32

    Input - Required Fields* Field Value / Comments

    Investment Program Type the Description of the Investment Program e.g. Shasun Investment 07-08

    Position ID Select the Position ID from the List.

    Approval Year Type the financial year e.g. 2007

    Some of the fields mentioned in the following may not be in your entry screen. This depends on the configuration of your system..

    Output Results CommentsCompany level Budget is updated.

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 31 of 183

  • SAP ECC 6.0 End user document (PS Module)

    Procedural Steps

    Access Change Inv. Program Structure transaction by:Via Menus Accounting Investment Management Program Budgeting Edit

    Original.Via Transaction Code IM32

    31 3.1. On screen Change Inv. Program Structure: , enter information in the fields as specified in the table below:

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 32 of 183

  • SAP ECC 6.0 End user document (PS Module)

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 33 of 183

  • SAP ECC 6.0 End user document (PS Module)

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 34 of 183

  • SAP ECC 6.0 End user document (PS Module)

    Field Name Description R/O/C User Action and Values Comments

    Investment Program

    Investment Program R Type the Description of the Investment Program e.g. SHAN0708.

    Position ID Top Position ID O Type the Top level Position ID. e.g. Shasun Investment 07-08

    Approval Year Approval Year R Type the financial year e.g. 2007

    Enter the Amount to be Invested for each Position ID Overall and Yearwise Values. And Click on Edit Select Select All.

    Click on Edit Total up.Select Annual Values & Total Value.

    Click on Continue or Enter. (Note: On above table, in column R/O/C: R = Required, O = Optional, C = Conditional)

    Overall and the year wise budget needs to be updated, system will generate a Budget update document.

    Press Ctrl + S or Save Button from the Screen

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 35 of 183

  • SAP ECC 6.0 End user document (PS Module)

    Title: Create Appropriation Request Transaction CodeIMA11Document No. Responsibility Version Supercedes Issue

    d onEffective Date

    Review Date

    SAP/EUD/PS/01 Projects 001 NIL

    Prepared by Reviewed by Approved by

    V.Ananthapadmanaban 10.03.2008

    Trigger:

    Receipt of Intimation from Management or the Basic User Specifications from User Department and QA Specifications from QA Department.

    Business Process Description Overview Creation of Project Appropriation Requests.

    The Proposed Project Appropriation Request Numbering system is same as Project Numbering, will be based on External Alphanumeric numbering and as follows :

    First Character will represent CAP to represent the categories of Projects, and remaining 4 characters are numerals.

    e.g. CAP-07-P02-EXPANS represents Capital Expenditure related Project with Code No. EXPANS.

    Via Menus Accounting Investment Management Appropriation Requests Edit Appropriation Requests Individual Processing.

    Via Transaction Code IMA11

    Input - Required Fields* Field Value / Comments

    Press Create button from the Screen

    Appropriation Request Type Select S1 from the given list by drill down search method.

    Controlling Area Type 1000 and then Press Create button from the Screen or Select Create from the Menu.Appropriation Request Select from the Open Number. Find the next Open Number by giving the

    Starting Number. If the Project is related to Capex then you have to give the Project Coding Logic As defined CAP-00-XXX-XXXXXX-00-000.

    Some of the fields mentioned in the following may not be in your entry screen. This depends on the configuration of your system.

    Output Results CommentsCreation of Appropriation Request for the requested Project.

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 36 of 183

  • SAP ECC 6.0 End user document (PS Module) Procedural Steps

    Access Create Appropriation Request transaction by:Via Menus Accounting Investment Management Appropriation Requests

    Edit Appropriation Requests Individual Processing.Via Transaction Code IMA11

    31 3.1. On screen Create Appropriation Request: , enter information in the fields as specified in the table below:

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 37 of 183

  • SAP ECC 6.0 End user document (PS Module)

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 38 of 183

  • SAP ECC 6.0 End user document (PS Module)

    Field Name Description R/O/C User Action and Values CommentsControlling Area Controlling Area R Type 1000 and then Press Create button

    from the Screen or Select Create from the Menu.

    Appropriation Request Type

    R Select S1

    Project Profile Project Profile R Select ZP00001 for Capital Investment Projects.

    Appropriation Request Enter the Appropriation Request Number as per the Project Coding Logic CAP-00-XXX-XXXXXX-00-000.Then type the Description of Project.``

    General DataReason for Investment

    Environment Investment

    Scale

    R

    C

    O

    Select the reason for investment from the given list. If the selected reason is for Environmental Protection thenSelect the Environment Investment from the given list.Select the Scale from the given list

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 39 of 183

  • SAP ECC 6.0 End user document (PS Module) Priority Approval YearPlanned Approval Date

    Person InvolvedIM : Proposed By : (Partner field)IM : Supported By : (Partner field)IM : Supported By :IM : Approved Unit Head :IM : Approved Finance

    RO

    O

    R

    R

    Select the Priority from the given list.Type the Approval year of the Project.

    Select the date of approval.

    Select the Name of the Applicant (Project Manager) from the Given List.Select the Name of the Authorization Level (Finance ) from the given List.PRESS ENTER.

    As per the Approving Authorities. We have to select the approving Authorities.

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 40 of 183

  • SAP ECC 6.0 End user document (PS Module)

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 41 of 183

  • SAP ECC 6.0 End user document (PS Module)

    Field Name Description R/O/C User Action and Values CommentsControl Data :Investment Program

    Position ID

    R

    R

    Select SHA0708 from the given List. Year defaulted from the Program.

    Select the required Structure where the Project is going to Come.

    e.g. Shasun Investment R&D

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 42 of 183

  • SAP ECC 6.0 End user document (PS Module)

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 43 of 183

  • SAP ECC 6.0 End user document (PS Module)

    Field Name Description R/O/C User Action and Values CommentsOrg. Units :Req. Cost Center

    Plant

    Location

    Resp.Company

    R

    RO

    O

    Select the Requesting Costs center from the Existing Cost centers if the cost centers are available in that particular plant. If the cost centers are not there then It has to be created for that particular plant.

    Press ENTERAll other fields are automatically copied from the standard profile Setting.Select the required plant from the Given List.Select the required Location from the Given List.Select 1000 From the given List

    User Defined Fields

    Nature of Exp Nature of Expenditure

    R Select the required entry from the given list. DISPOSAL-,DisposalLEASE , -LeasePURCHASE - PurchaseTRANSFER - Transfer

    (Note: On above table, in column R/O/C: R = Required, O = Optional, C = Conditional)

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 44 of 183

  • SAP ECC 6.0 End user document (PS Module)

    Field Name Description R/O/C User Action and Values CommentsVariants

    General Data:Completion Date Project Completion Date.

    REnter Approximate Date of Project Completion

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 45 of 183

  • SAP ECC 6.0 End user document (PS Module)

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 46 of 183

    Click on Create Cost Estimate

    Click on Show/Hide Item View

  • SAP ECC 6.0 End user document (PS Module)

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 47 of 183

  • SAP ECC 6.0 End user document (PS Module)

    Field Name Description R/O/C User Action and Values CommentsVariants Plan Values:

    Item Cat M Material RSelect the Item Category from the List M or N or V as per the Requirement.

    Only M, N or V should be used.

    Item Cat N Service R

    Item Categoryo M for Materialo V for other costs like manpower, QC etc. The cost element for V

    should be 7100150 Resource is where we select the RM name. The master would be

    entered by the Purchase person. This is not required for RM. Enter Quantity & hit enter.

    For V change the description to suit us.

    Go Back or press F3. The total budget for the year 2007 (as the investment planned is for 2007) would appear as shown below. Save the Appropriation request.

    Note: We would define the cost for 1 year and if the project spills over to the next year the remaining budget would also spill over.

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 48 of 183

  • SAP ECC 6.0 End user document (PS Module)

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 49 of 183

  • SAP ECC 6.0 End user document (PS Module)

    Select the project in the left side of the screen and go to Approp. Request Menu and select the change option.

    Go to Control data Tab and click Form approval. The Appropriation Request needs to be sent for approval.

    Save the Appropriation Request.

    Press Ctrl + S or Save Button from the Screen

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 50 of 183

  • SAP ECC 6.0 End user document (PS Module)

    Title: Change Appropriation Request Transaction CodeIMA12/SBWPDocument No. Responsibility Version Supercedes Issue

    d onEffective Date

    Review Date

    SAP/EUD/PS/01 Projects 001 NIL

    Prepared by Reviewed by Approved by

    V.Ananthapadmanaban 10.03.2008

    Trigger:

    After Creating of Project Appropriation Request and its sent for Approval.

    Business Process Description Overview Releasing the of Project Appropriation Requests. The Authorized person whose name is mentioned in the Appropriation Request (IM : Authorization Partner field) will

    have the authorization to Release the Appropriation Request.

    Via Menus Accounting Investment Management Appropriation Requests Edit Appropriation Requests Individual Processing.

    Via Transaction Code IMA11/ IMA12 / SBWP

    Input - Required Fields* Field Value / Comments

    Appropriation req. No. Select the Appropriation Request Number to be Released from the list.

    Some of the fields mentioned in the following may not be in your entry screen. This depends on the configuration of your system..

    Output Results CommentsRelease Appropriation Request of the requested Project.

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 51 of 183

  • SAP ECC 6.0 End user document (PS Module) Procedural Steps

    Access Appropriation Request Individual Processing transaction by:

    Via Menus Accounting Investment Management Appropriation Requests Edit Appropriation Requests Individual Processing.

    Via Transaction Code IMA11/ IMA12

    1.0 On screen Change Appropriation Requests : Header Screen, enter information in the fields in the table below:

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 52 of 183

  • SAP ECC 6.0 End user document (PS Module)

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 53 of 183

  • SAP ECC 6.0 End user document (PS Module)

    System Will show the Display Mode of the Appropriation Request sent for Approval.In case of any further requirement on the same Appropriation Request press BACK.

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 54 of 183

  • SAP ECC 6.0 End user document (PS Module)

    Click on Create Attachment.

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 55 of 183

  • SAP ECC 6.0 End user document (PS Module)

    Click on SAVE and BACK Button.

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 56 of 183

  • SAP ECC 6.0 End user document (PS Module)

    Click on APPROVE.

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 57 of 183

  • SAP ECC 6.0 End user document (PS Module)

    Now Inbox Workflow will be blank.

    There will be a mail which goes to the Person Who has created the Appropriation Request. Which he can check in his login through the Transaction code SBWP INBOX Documents.

    Transaction Code : SBWP

    Field Name Description R/O/C User Action and Values CommentsSelect In Box SAP Business

    Work BenchR Select the Inbox Workflow

    Press Execute Button.

    Transaction Code : IMA11

    Field Name Description R/O/C User Action and Values CommentsWorklist Off / On

    R Toggle the Work list Button ON if it is OFF.Select the Project Name from the Work-list which was created by you.e.g. P-0001. Select the Change Button which is appearing like Pencil in the screen.Or select the Appropriation Request from the Menu and select Change Option.

    AssignmentProject R Select the Project Field.

    General Data Status R Select Approve.

    System gives message that the

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 58 of 183

  • SAP ECC 6.0 End user document (PS Module)

    Appropriation Request is approved.

    AssignmentWBS Element R Select the WBS Element Field.

    System automatically copies the Project Code. e.g. : M-0011

    (Note: On above table, in column R/O/C: R = Required, O = Optional, C = Conditional)

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 59 of 183

  • SAP ECC 6.0 End user document (PS Module)

    Title: Activate Project Definition Transaction CodeIMA11Document No. Responsibility Version Supercedes Issue

    d onEffective Date

    Review Date

    SAP/EUD/PS/01 Finance 001 NIL

    Prepared by Reviewed by Approved by

    V.Ananthapadmanaban 10.03.2008

    Trigger:

    After Approval of Project Appropriation Request & Activation of Project Definition.

    Business Process Description Overview Activating the Project Definition. The Authorised Person who is responsible for Activating the Project Definition will do this Transaction.

    Input - Required Fields* Field Value / Comments

    Appropriation Request Select the Appropriation Request for which Project Definition needs to be activated..

    Some of the fields mentioned in the following may not be in your entry screen. This depends on the configuration of your system..

    Output Results CommentsThe Budget is Distributed for the Appropriation Request of the requested Project.

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 60 of 183

  • SAP ECC 6.0 End user document (PS Module) Procedural Steps

    Access Appropriation Request Individual Processing transaction by:

    Via Menus Accounting Investment Management Appropriation Requests Edit Appropriation Requests Individual Processing.

    Via Transaction Code IMA11/ IMA12

    1.0 On screen Change Appropriation Requests : Header Screen, enter information in the fields in the table below:

    Field Name Description R/O/C User Action and Values CommentsMeasure / Assets

    Project Activate project R Click on Project .WBS Element Work Break Down Structure

    ElementR Click on WBS Element

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 61 of 183

  • SAP ECC 6.0 End user document (PS Module)

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 62 of 183

  • SAP ECC 6.0 End user document (PS Module)

    Click on Continue or Tick Mark.System will propose that Copy the Planned Values

    Click on Tick or Press Enter.

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 63 of 183

  • SAP ECC 6.0 End user document (PS Module)

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 64 of 183

  • SAP ECC 6.0 End user document (PS Module)

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 65 of 183

  • SAP ECC 6.0 End user document (PS Module)

    Title: Budget Distribution Transaction CodeIM52Document No. Responsibility Version Supercedes Issue

    d onEffective Date

    Review Date

    SAP/EUD/PS/01 Finance 001 NIL

    Prepared by Reviewed by Approved by

    V.Ananthapadmanaban 10.03.2008

    Trigger:

    After Approval of Project Appropriation Request & Activation of Project Definition.

    Business Process Description Overview Budget Distribution for the Project. The Person who is responsible for Budget Distribution will have the authorization to Distribute the Budget.

    Input - Required Fields* Field Value / Comments

    Investment Program Select the Investment Program from the List.

    Some of the fields mentioned in the following may not be in your entry screen. This depends on the configuration of your system..

    Output Results CommentsThe Budget is Distributed for the Appropriation Request of the requested Project.

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 66 of 183

  • SAP ECC 6.0 End user document (PS Module) Procedural Steps

    Access Budget Distribution transaction by:

    Via Menus Accounting Investment Management Programs Budgeting Budget Distribution Edit

    Via Transaction Code IM52

    1.1 On screen Budget Distribution : Header Screen, enter information in the fields in the table below:

    Field Name Description R/O/C User Action and Values CommentsInvestment Program The Investment Program R Select the Investment Program

    SHA0708 from the Given List.

    Press Enter.Select Execute option from the Menu or Select the Clock Button in the Screen.

    Original Budget Original Budget to be distributed For the Project.

    R Enter the amount to be distributed for the Project as Budget. e.g. CAP-2007-P02-EXPAN.

    Annual Overview R Select Annual Overview from the Screen and Enter the Original Budget distributed for that Project.Select Save Button from the Screen or Save from the Menu.

    System will display the message that

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 67 of 183

  • SAP ECC 6.0 End user document (PS Module)

    Document xxxxxxxxxx posted.

    Press Green Colour with Arrow Button / Back and come out of the Screen.

    (Note: On above table, in column R/O/C: R = Required, O = Optional, C = Conditional)

    Enter the Overall / year Wise Budget for the Appropriation Request / Project Definition

    Click on EDIT COPY VIEW Select the Planned total

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 68 of 183

  • SAP ECC 6.0 End user document (PS Module)

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 69 of 183

  • SAP ECC 6.0 End user document (PS Module) Select the Annual Year : 2007

    Click on EDIT COPY VIEW Select the Planned total

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 70 of 183

  • SAP ECC 6.0 End user document (PS Module)

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 71 of 183

    Check on CHECK

  • SAP ECC 6.0 End user document (PS Module)

    Click on check button and Save the system will generate the Budget document.

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 72 of 183

  • SAP ECC 6.0 End user document (PS Module)

    Title: Release Appropriation Request Transaction CodeIMA11Document No. Responsibility Version Supercedes Issue

    d onEffective Date

    Review Date

    SAP/EUD/PS/01 Finance 001 NIL

    Prepared by Reviewed by Approved by

    V.Ananthapadmanaban 10.03.2008

    Trigger:

    After Activation of Project Definition and Budget Updating for the Appropriation Request.

    Business Process Description Overview Release Appropriation Request. The Person who is responsible for Release Appropriation Request will have the authorization to Release the

    Appropriation Request.

    Input - Required Fields* Field Value / Comments

    Appropriation Request Select The Appropriation Request to be released.

    Some of the fields mentioned in the following may not be in your entry screen. This depends on the configuration of your system..

    Output Results CommentsThe Appropriation Request should be released..

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 73 of 183

  • SAP ECC 6.0 End user document (PS Module) Procedural Steps

    Access Appropriation Request Individual Processing transaction by:

    Via Menus Accounting Investment Management Appropriation Requests Edit Appropriation Requests Individual Processing.

    Via Transaction Code IMA11/ IMA12

    1.0 On screen Change Appropriation Requests : Header Screen, enter information in the fields in the table below:

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 74 of 183

  • SAP ECC 6.0 End user document (PS Module)

    Click on RELEASE. And click on SAVE.

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 75 of 183

  • SAP ECC 6.0 End user document (PS Module)

    Title: Change Project Definition Transaction CodeCJ02/CJ20NDocument No. Responsibility Version Supercedes Issue

    d onEffective Date

    Review Date

    SAP/EUD/PS/01 Finance 001 NIL

    Prepared by Reviewed by Approved by

    V.Ananthapadmanaban 10.03.2008

    Trigger:

    After the Approved Budget Appropriation Request form.

    Business Process Description OverviewThe project Lower Level WBS Elements has to be created. (Up to Level 3)

    Via Menus Logistics Project System Project Spl. Maintenance Function Work Break Down Structure (WBS) ChangeLogistics Project System Project Project Builder

    Via Transaction Code CJ02 /CJ20 N

    Input - Required Fields* Field Value / Comments

    Project Definition. Find the next Project number by pressing F4 button in this field and then Type the Project Definition Number.

    Some of the fields mentioned in the following may not be in your entry screen. This depends on the configuration of your system..

    Output - Results Comments

    Upto Level 3 WBS elements will be created.

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 76 of 183

  • SAP ECC 6.0 End user document (PS Module)

    Procedural Steps

    1.0 On screen Change Project Definition : Header Screen, enter information in the fields in the table below:

    Field Name Description R/O/C User Action and Values CommentsProject Definition Select Project Definition from the

    ScreenResponsible Person The person (Project

    Manager ) who is Responsible for that Project.

    R Select the Name of the Project Manager who is responsible for that Project from the given list.

    Applicant No. The User Department who requested to do the Project.

    O Select the Name of the Requested User Department from the given list.

    Start Date Start date of the Project R Type the start date or Select the Start date of Project from the Calender.

    This dates will be defaulted from Appropriation Request

    End Date End Date of the Project R Type the End date or Select the End date of Project from the Calender.

    This dates will be defaulted from Appropriation Request

    Company Code Company Code R Select the company code from the list

    Business Area Business Area R Select the Business Area from the List

    Plant Name of the Plant where the Project is going to take place

    R Select the Name of the Plant where the Project is going to take place.

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 77 of 183

  • SAP ECC 6.0 End user document (PS Module) Profit Center Profit Center R Select the Name of the Profit Center where

    Project is going to take place.Location Name of the Location where

    the Project is going to takeplace

    O Select the Name of the Locationwhere the Project is going to take place.

    Mask ID O Type ++++++ after two spaces from the Beginning of the Field.

    (Note: On above table, in column R/O/C: R = Required, O = Optional, C = Conditional)

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 78 of 183

  • SAP ECC 6.0 End user document (PS Module)

    Field Name Description R/O/C User Action and Values CommentsLevel WBS Level Number R Enter 2WBS Element WBS Element R Enter @-01 Description WBS Description R Enter the WBS Description CIVIL As required

    by the Project Engineers. The Project Structuring needs to be created.

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 79 of 183

  • SAP ECC 6.0 End user document (PS Module)

    Title: Change Cost Planning Transaction CodeCJ40Document No. Responsibility Version Supercedes Issue

    d onEffective Date

    Review Date

    SAP/EUD/PS/01 Projects 001 NIL

    Prepared by Reviewed by Approved by

    V.Ananthapadmanaban 10.03.2008

    2.1 Trigger

    After creating the Lower Level (3) WBS elements under the Project Definition.

    Business Process Procedure Overview Manual Cost Planning for the Lower Level WBS elements

    Via Menus Logistics Project System Financials Planning Cost in WBS Overall Values Change.

    Via Transaction Code CJ40

    Input - Required Fields* Field Value / Comments

    Project Definition Select the project definition from the list.

    Some of the fields mentioned in the following may not be in your entry screen. This depends on the configuration of your system..

    Output Results CommentsManual Cost Planning for the Project Definition will be done.

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 80 of 183

  • SAP ECC 6.0 End user document (PS Module)

    Procedural Steps

    Access Change Cost Planning transaction by:

    Via Menus Logistics Project System Financials Planning Cost in WBS Overall Values Change.

    Via Transaction Code CJ40

    1.2 On screen Change Cost Planning : Initial Screen, enter information in the fields in the table below:

    Give the Project Definition and Click on Cost PlanningEnter the Manual Cost planning for Overall and Annual.

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 81 of 183

  • SAP ECC 6.0 End user document (PS Module)

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 82 of 183

  • SAP ECC 6.0 End user document (PS Module)

    Click on Edit Total Up.

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 83 of 183

  • SAP ECC 6.0 End user document (PS Module)

    Tick on Annual and Total Value.

    Field Name Description R/O/C User Action and Values CommentsProject Definition Select Project Definition from the

    ScreenOverall & Year wise budget needs to be updated.

    (Note: On above table, in column R/O/C: R = Required, O = Optional, C = Conditional)

    Click on Save. After saving this the User needs to send an SAP Mail to Budgeting Department to Update the Cost Planned to Budget.

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 84 of 183

  • SAP ECC 6.0 End user document (PS Module)

    Title: Change Original Budget Transaction CodeCJ30Document No. Responsibility Version Supercedes Issue

    d onEffective Date

    Review Date

    SAP/EUD/PS/01 Projects 001 NIL

    Prepared by Reviewed by Approved by

    V.Ananthapadmanaban 10.03.2008

    2.1 Trigger

    After creating the Manual Cost planning for the Lower Level (3) WBS elements under the Project Definition.

    Business Process Procedure Overview Manual Cost Planning for the Lower Level WBS elements

    Via Menus Logistics Project System Financials Budgeting Original Budget Change.

    Via Transaction Code CJ30

    Input - Required Fields* Field Value / Comments

    Project Definition Select the project definition from the list.

    Some of the fields mentioned in the following may not be in your entry screen. This depends on the configuration of your system..

    Output Results CommentsBudget for the Lower Level WBS elements (level 3 ) for the Project Definition will be done.

    Solution/ Release: MySAPERP2004 (ECC6.0) Page 85 of 183

  • SAP ECC 6.0 End user document (PS Module)

    Procedural St