    Air Mobility Commands aircraft maintenance troops do greatwork in keeping the fleet ready to do its Global Reach mission.They need help to make sure they can get spare parts quicklyand easily, and thats what this Flight L ine Support FacilityDesign Guide is all about.

    This Guide provides the roadmap for planning, programming,and designing projects that will give AMC the facilities it needsto preposition parts on the flight line and put them into thehands of maintainers when they need them. The result will beimproved morale and productivity for AMCs people andgreater mission capability for the Air Mobility Team.

    The A ir M obility Team... Responsive Global Reach for America.. . Every Day!

  • 7/28/2019 USAF Flight Line Facilities Design Guide

    3/34

    AMC FLIGHT LINESUPPORT FACILITY

    ii

    Chapter 1Introduction

    A. Purpose........................................1

    B. Design Guide Scope and Use.........1

    1.Project Initiation

    2.Site Selection

    3.Design

    4.Interior Finishes and Furnishings

    C. Flight Line Support

    Facility.........................................2

    Chapter 2Program

    A. General.........................................3

    1.Planning and Programming

    Considerations

    2.Flight Line Support Facility

    3.Aircraft Parts Flow Process

    B. Administrative Functions..............4

    C. Support Area Functions................4

    D. Warehouse Functions....................4

    Chapter 2Program(Contd)

    E. Special Storage Functions..............5

    1.Inside Storage

    2.External Storage

    F. Space Criteria...............................5

    1.Planning Considerations

    2.Standard Facility Requirements

    G. Site Evaluation..............................9

    1.Location

    2.Size

    H.Special Project Considerations.....10

    Chapter 3Overall ProjectDesign

    A. General.......................................11

    B. Site Design.................................111.Selection

    2.Access

    3.Utilities

    4.Landscaping

    Chapter 3Overall ProjectDesign (Contd)

    C. Building Design..........................12

    1.Organization and Circulation

    2.Architectural Character,

    Materials, and Finishes

    3.Supervision and Security

    4.Flexibility and Expansion

    Potential

    5.Disabled Access

    6.Special Considerations for

    Renovations

    D. Building Systems.........................14

    1.Structural

    2.Heating, Ventilating, and Air

    Conditioning

    3.Plumbing

    4.Electrical

    5.Fire Protection6.Communications

    7.Material Handling System

    Table of Contents

  • 7/28/2019 USAF Flight Line Facilities Design Guide

    4/34

    AMC FLIGHT LINESUPPORT FACILITY

    iii

    Chapter 4Functional Areaand Space Criteria

    A. General.......................................19

    B. Administration............................19

    1.Design Considerations

    2.Parts and Components

    Administration

    3.Flight Line Support

    Administration

    4.OICs/NCOICs Office

    Chapter 4Functional Areaand Space Criteria(Contd)

    C. Support Areas.............................20

    1.Design Considerations

    2.Customer Service Entrance

    3.Mechanical Room

    4.Electrical Room

    5.Communications Room

    6.Rest Rooms

    7.Janitors Closet

    D. Warehouse..................................21

    1.Design Considerations

    2.High-Density Parts Storage

    3.Readiness Spares Packages Pallet

    Storage Space

    4.Readiness Spares Packages

    Buildup Area

    5.Readiness Spares Packages

    Loading Dock

    6.Truck Loading Dock

    Chapter 4Functional Areaand Space Criteria(Contd)

    7.Parts Counter

    8.Bulk Storage Area

    9.Reparable Parts/Tail Number

    Parts/TCTO Parts

    E. Special Storage Requirements......23

    1.Design Considerations

    2.Avionics and Electronic

    Components Storage

    3.Classified Storage

    4.Battery Storage

    5.Outside Storage

    Chapter 5Interior Finishes

    A.General.......................................25

    B. Finish Schedule...........................25

    C. Furniture....................................26

    References.........................28

    Table of Contents (Cont'd.)

  • 7/28/2019 USAF Flight Line Facilities Design Guide

    5/34

    AMC FLIGHT LINESUPPORT FACILITY

    iv

    Table of Contents (Cont'd.)

    List of Tables

    Table Number Page Number Description

    Table 2-A 6 Space Requirements for the Flight Line Support Facility andStorage Areas

    Table 2-B 7 RSP Space Requirements for PalletsTable 2-C 8 Space Requirements for the Administration Areas

    Table 2-D 8 Space Requirements for the Support Areas

    Table 2-E 8 Space Requirements for the Warehouse Areas

    Table 2-F 8 Space Requirements for the Special Storage Areas

    Table 2-G 9 Space Requirements for a Typical Flight Line Support Facility

    Table 5-A 26 Finish Schedule for the Flight Line SupportFacility Administration

    Table 5-B 27 Finish Schedule for the Flight Line SupportFacility Support Areas

    Table 5-C 27 Finish Schedule for the Flight Line SupportFacility Warehouse

    Table 5-D 27 Finish Schedule for the Flight Line SupportFacility Special Storage

    List of Figures

    Figure Number Page Number Description

    Figure 1-A 2 Functional Area Relationships for the Warehouse and SupportAreas within the Flight Line Support Facility

    Figure 2-A 5 Functional Area Relationships for the Flight Line Support Facility

    Figure 2-B 7 Graphic Illustration of Readiness Spares Package (RSP) PalletStorage Space

    Figure 3-A 11 Site Organization Concept for the Flight Line Support Facility

    Figure 3-B 13 Site Organization Relationships for the Flight LineSupport Facility

    Figure 4-A 21 Floor Plan for the Typical Flight Line Support Facility

    Figure 5-A 30 Color Boards

  • 7/28/2019 USAF Flight Line Facilities Design Guide

    6/34

    Chapter 1

    AMC FLIGHT LINESUPPORT FACILITY

    1

    Introduction

    A.Purpose

    This guide provides the basic criteriato evaluate, plan, program, and designAir Mobility Command (AMC) flightline support facilities to sustain a sup-

    ply of parts and components to main-tain aircraft. This facility supports thefollowing AMC aircraft: C-5, C-17,C-141, and KC-135. The C-9, C-21,and KC-10 are supported by Con-tractor Operated and Managed BaseSupply (COMBS), and their facilityrequirements are governed by govern-ment contracts.

    It is intended to make commandersand their staffs aware of importantdesign considerations and to aid inproject development. Planning andprogramming for a flight line supportfacility should consider all aspects ofparts storage and handling necessaryto support aircraft maintenance andrepair. Additionally, a quality designwill maximize effective use of avail-able space to support an efficient air-craft parts flow process.

    B. Design GuideScope and Use

    This guide applies to the design ofall new construction and renovationprojects for flight line support facili-ties. It provides the overall criteriafor determining requirements, site

    evaluation and planning, and designof exterior and interior areas.

    Use this guide to supplement otherAir Force and Department of Defense(DoD) policies and instructionsto identify individual constructionproject requirements. The Require-ments and Management Plan(RA MP) defines the program fordesign of an individual MilitaryConstruction (MILCON) project.It includes functional requirements,design criteria, and cost information.

    The material in this guide providesthe basis for preparing the RAMP.

    1. Project I nitiation

    Information required for preparationof the DD Form 1391, which initiatesproject development, is found inChapter 2. This includes considera-tions of the space criteria to deter-mine overall building size, siteevaluation, and special factors to beused in the cost estimates.

    2. Sit e Selecti on

    This is generally part of the master

    planning process. It is completedprior to preparing a DD Form 1391for an individual project. However,project programming requirementsdeveloped in the DD Form 1391phase may require a re-evaluation ofsite selection decisions.

    For guidance in evaluating sites for aproject, see Chapter 2, Section G, SiteEvaluation.

    3. Design

    a.The design of a project is typically

    developed in progressive phases, i.e.,planning and programming, conceptand preliminary drawings, and finalworking drawings. Design guidancefor all of these design phases is cov-ered in Chapters 2 through 4.

    b. Chapter 2 provides basic planningand programming criteria, along withtables for determining square footagerequirements.

    c. Chapter 3 presents concept andpreliminary design considerationssuch as the location of a facility ona site, the design of the facility andsupport utilities, as well as specifictechnical guidance.

    d. Chapter 4 addresses specific designissues concerning individual function-al areas, which are important forpreliminary and working drawings.In this chapter, illustrative designs and

    photographs help clarify the designguidance of the preceding chapters.

  • 7/28/2019 USAF Flight Line Facilities Design Guide

    7/34

    AMC FLIGHT LINESUPPORT FACILITY

    2

    CUSTOMERSERVICEENTRANCE

    SPECIALSTORAGE

    SUPPORTAREAS

    WAREHOUSE

    TWO ADMINISTRATION AREAS PARTS AND COMPONENTS

    ADMINISTRATION(UPPER LEVEL)

    FLIGHT LINE SUPPORTADMINISTRATION(LOWER LEVEL)

    Figure 1-A: Functional Area Relationships for the Warehouse and Support Areas within the Flight Line Support Facility.

    4. I nterior Fini shes and

    FurnishingsChapter 5 provides recommendationsfor selection of interior materials, fin-ishes, and colors. Carefully selectedinterior finishes and furnishings areessential for a quality design.

    C.Flight LineSupportFacility

    See Figure 1-A for functional arearelationships of the warehouse andsupport areas within the flight linesupport facility.

    a.The flight line support facility isan essential element of the aircraftmaintenance program. Its functionis to provide maintenance units withavionics, components, spare parts,

    and assemblies necessary to maintainaircraft. Also, the readiness spares

    packages (RSPs) are assembled andmaintained in this area.

    b.This facility has four components:

    Administrative Areas

    Parts and components

    Flight line support

    Support areas

    Warehouse

    Special storagec.The administrative space isseparated into two different spaces(flight line support administration,and parts and components administra-tion). Space requirements mayinclude private supervisory offices andadministrative support for ordering,tracking, and distributing aircraft

    avionics, components, spare parts,and assemblies. Parts and compo-

    nents administration also providesvisual security for the warehouse area.

    d.The support area includes spacefor electrical, communications,mechanical, and rest rooms.

    e.The warehouse includes spaceto store and retrieve aircraft parts.Specific space requirements arenecessary for high-density storage,RSP pallet buildup, RSP pallet stor-

    age, bulk storage, RSP loading dock,truck loading dock, parts counter, andreparable parts, tail number parts, andtime compliance technical order(TCTO) parts.

    f. The special storage area includesavionics and electronic components,classified storage (sensitive/pilferablematerials), and battery storage.

  • 7/28/2019 USAF Flight Line Facilities Design Guide

    8/34

    AMC FLIGHT LINESUPPORT FACILITY

    3

    A. General

    1. Planning and Programming

    Considerations

    a. Planning, programming, anddesigning a flight line support facility

    normally requires extensive coordina-tion. This coordination is importantbecause of the different organizationsinvolved in developing facilityrequirements.

    b. Personnel likely to have facilityplanning and design inputs areas follows:

    Wing commander

    Wing safety officer

    Operations group commander

    Logistics group commander

    Support group commander

    Supply squadron commander

    Aircraft generation squadroncommander

    Communications squadroncommander

    Transportation squadroncommander

    Civil engineer squadroncommander

    Fire chief

    Security police squadroncommander

    2. Fli ght L ine Support Facili ty

    a.The supply and distribution ofstored aircraft parts and war reserveoperating materials are managed inthis facility. Major supply functionsinclude the following:

    Demand processing and missioncapable stock control

    Reparable parts processing

    Inventory processing

    Bench stock inventory control

    Processing of readiness spares andin-place spares packages

    Storage and issue of stocks

    Re-supply of enroute system

    Combat supply operations

    3. A ir craft Part s Flow Process

    a.To fully understand the functionalarea relationships of this facility, itis important to consider the variousactivities and flow of parts, compo-nents, and assemblies through theflight line support facility.

    b.There are specific requirements for

    each type of aircraft when developinga functional layout for a flight linesupport facility. Investigate shippingand receiving requirements, and tailorthem to the base supply system ofoperation. In developing the require-ments for support facilities, the prima-ry consideration is the flow of materialinto and out of the facility.

    Chapter 2

    Program

    Facilities should present a cohesive architectural image as the facility above demonstrates.

  • 7/28/2019 USAF Flight Line Facilities Design Guide

    9/34

    AMC FLIGHT LINESUPPORT FACILITY

    4

    c. After receipt of a part, component,or assembly at the flight line supportfacility, the item is processed andstored in its respective storage area.Special storage areas for specific mate-rial items are required as follows:

    Aircraft Electronic Components -An environmentally controlledarea

    Batteries -A specifically designedbattery room

    Classified Storage -A secure roomd.The parts and components admin-istration function requisitions specificparts, components, or assemblies whena minimum inventory stockage leveloccurs.

    e. Deployable units have RSP kitrequirements. These kits are main-tained in the RSP pallet area on cargopallets. Flight line support is responsi-ble for inventorying and restockingthe kits.

    B. AdministrativeFunctions

    a. Parts and Components Admin-istration -Coordinates the requisitionand distribution of parts, components,and assemblies to support aircraftoperations 24-hours a day, seven daysa week.

    b. Flight Line Support Admin-istration - Provides the primaryinterface with the customer, andmanages the flight line support facility24-hours a day, seven days a week.

    c. Officer-in-Charge/Noncommis-sioned Officer-in-Charge (OICs/NCOICs) Office-For managementfunctions in the facility

    C. Support AreaFunctions

    a. Customer Service Entrance -Locate the entrance so that it is clear-ly visible for public access of visitorsand customers.

    b. Rest Rooms -Centrally locate restrooms for men and women.

    c. Mechanical Room -Space forheating, ventilating, and air condi-tioning equipment (HVAC), electri-cal service, and fire detection andalarm equipment.

    d. Electrical Room -Room for prima-ry electrical systems necessary tosupport the entire facility.

    e. Communications Room -A loca-tion for the building telecommunica-tions systems and telephone switchingequipment.

    D.WarehouseFunctions

    a. High-Density Storage -This areaconsists of a number of high bay stor-age racks with aisles wide enough for

    the material handling equipment tomaneuver easily.

    b. RSP Pallet Buildup Area -Thislarge open area within the warehouseis for the buildup and maneuveringof RSPs.

    c. RSP Pallet Storage Area -Thetype of aircraft and the squadron sizewill determine the overall size of thisarea. This area is adjacent to the RSPbuildup area and accommodates theRSP containers and cargo pallets.Position the pallets in single rows.

    d. Bulk Storage - Provide an areafor parts that are too large for high-density storage. Locate these itemson the mezzanine above the RSP pal-let storage area.

    e. RSP Loading Dock -This area isfor 463L cargo pallets and loaderequipment. Provide an in-floormounted scale that will handle cargopallets and is capable of accuratelymeasuring cargo pallet weights of up

    to 10,000 pounds. Locate the scalenear the RSP dock.

    f. Truck Loading Dock - A locationto receive parts and components frombase supply or depots.

    g. Parts Counter - An area locatednear the customer service entrance.

    h. Reparable Parts/Tail NumberParts/TCTO Parts - An area nearthe truck loading dock for storageof parts until they are picked up bya maintenance unit.

  • 7/28/2019 USAF Flight Line Facilities Design Guide

    10/34

    AMC FLIGHT LINESUPPORT FACILITY

    5

    E. Special Storage

    Functions1. I nside Storage

    a. Avionics and ElectronicComponents Storage -An environ-mentally controlled storage area foravionics and other electroniccomponents.

    b. Classified Storage - An area forstorage of sensitive or pilferable mate-rials. Enclose this roomwith fire-rated

    walls and a vault door.

    c. Battery Storage - A special storagearea with ventilation and specialexhaust for nickel cadmium batterycells. Provide a battery shop andrecharging capability within the flightline support facility if the base doesnot have one.

    2. External Storage

    a. Outside Storage -A fenced, paved,and lighted area for material and foroperating material handling equipment.

    b. Covered Storage -Spaceto storesupplies, equipment, and material notrequiring closed warehouse space, but

    requiring covered protection from theweather. Covered storage space isconstructed without complete sideand end walls. This space can beincluded within the warehouse in coldclimates.

    F. Space Criteria

    1. Planning Considerati ons

    a. Define the size, type, number, andfunctional area relationships of spacesrequired to support the flight line sup-port facility.

    b. Development of space require-ments should take into consideration

    TWO STORAGE LEVELS MEZZANINE BULK

    STORAGE AREA(UPPER LEVEL)

    RSP PALLET STORAGE AREA(LOWER LEVEL)

    HIGH-DENSITYSTORAGE

    RSP PALLET BUILDUP AREA

    ORDERPICKERRECHARGE

    RSPLOADINGDOCK

    TRUCKLOADINGDOCK

    CUSTOMERSERVICEENTRANCE

    RSPWEIGHTSCALESAREA

    PARTSCOUNTER

    RESTROOM

    BATTERYSTORAGE

    AVIONICSANDELECTRONICCOMPONENTS

    STORAGE

    MECHANICALROOM

    ELECTRICALROOM

    COMMUNICATIONSROOM

    CLASSIFIEDSTORAGE

    ADMINISTRATIONENTRANCE

    OIC'S ANDNCOIC'SOFFICE

    TWO ADMINISTRATION AREAS PARTS AND COMPONENTS

    ADMINISTRATION(UPPER LEVEL)

    FLIGHT LINE SUPPORTADMINISTRATION(LOWER LEVEL)

    REPARABLE PARTS/TAIL NUMBER/TCTO PARTS

    Figure 2-A: Functional Area Relationships for the Flight Line Support Facility.

  • 7/28/2019 USAF Flight Line Facilities Design Guide

    11/34

    AMC FLIGHT LINESUPPORT FACILITY

    6

    the existing facilities relative to cur-rent and future needs. Requirementsare governed largely by the types ofaircraft assigned to the base and thenumber of parts and componentsnecessary to support the overall main-tenance effort. Other considerationsare as follows:

    Circulation and storage of materialhandling equipment

    Sufficient space for the number ofRSPs necessary to support a 30-day

    deployment

    Administrative areas for account-ability and control of parts

    Space for receiving and shipmentof reparable parts, components, andassemblies between the facility,depots, and manufacturers

    2. Standard Facilit y

    Requirementsa.The size of the facility is deteminedby the number of aircraft assignedand RSP pallet requirements.

    Table 2-A: Space Requirementsfor the Flight Line Support Facilityand Storage Areas -Use this table todetermine space requirements and howto calculate the gross square footage forthe C-5, C-17, C-141, and KC-135flight line support facilities and open/covered storage.

    Table 2-B: RSP Space Require-ments for Pallets -Use this table todetermine space requirements for theRSP pallet storage and buildup areasfor the C-5, C-17, C-141, and KC-135aircraft. In addition, a formula isincluded to calculate the square

    footage requirements. (Figure 2-Bgraphically illustrates the RSPstorage space.)

    b.The recommended sizes of thefunctional areas for a flight line sup-port facility are shown in Tables 2-Cthrough 2-F, and graphically illustrat-ed in Figure 2-A, page 5.

    Table 2-C: Space Requirementsfor Administration Areas -Squarefootage requirements for the partsand components administration,and flight support administrationopen office areas are determinedfrom this table.

    Table 2-D: Space Requirementsfor Support Areas -This table pro-vides an example of areas required forthe flight line support facility.

    Space Requirements per Assigned Aircraft TypeC-5 C-17 C-141 KC-135

    Flight Line Support Facility(1) 857 SF 625 SF 546 SF 625 SF

    Open Storage 396 SF 396 SF 198 SF 198 SF

    Covered Storage 100 SF 100 SF 30 SF 30 SF

    Gross Square Footage Calculation Example

    Assume: 32 assigned C-5 aircraft

    Example:

    Flight Line Support Facility 32 aircraft x 857 SF = 27,424 SF 2,548 SM(2)

    Open Storage 32 aircraft x 396 SF = 12,672 SF 1,177 SM(2)

    Covered Storage 32 aircraft x 100 SF = 3,200 SF 297 SM(2)

    Legend for Table 2-A.

    SF - Square Footage (1) Square footage has been adjusted for high-density storage and storage requirements

    SM - Square Meters for RSP are included (see Figure 2-B for space allocation).

    (2) SM = .0929 x SF (all measurements are rounded).

    Table 2-A: Space Requirements for the Flight Line Support Facility and Storage Areas.

  • 7/28/2019 USAF Flight Line Facilities Design Guide

    12/34

    AMC FLIGHT LINESUPPORT FACILITY

    7

    Space Requirements for RSP Pallets

    Type of Storage C-5 C-17 C-141 KC-135

    RSP Pallet Storage Area (per Pallet) 146.4 SF 146.4 SF 146.4 SF 146.4 SF

    RSP Pallet Buildup Area (per Pallet) 32 SF 32 SF 32 SF 32 SF

    Established Criteria:

    A 463L cargo pallet is 108 x 88 (7.3 x 9) or 65.7 SF

    Using Figure 2-B for illustration, the space required to store 25 pallets of RSP, including 5 foot aisles on all sides,

    plus an additional pallet space to permit pallet movement while on the conveyor system would be:

    48.8 x 75 = 3,660 SF

    3,660 SF divided by 25 pallets = 146.4 SF of storage space per pallet

    Example using 32 Pallets (Note that Figure 2-B does not apply):

    RSP Pallet Storage Area: 32 pallets x 146.4 SF per pallet = 4,685 SF 435 SM(1)

    RSP Pallet Buildup Area: 32 pallets x 32 SF per pallet = 1,024 SF 95 SM(1)

    Legend for Table 2-B.

    SF - Square Footage (1) SM = .0929 x SF (all measurements are rounded).

    SM -Square Meters

    9' 9' 9' 9' 9'

    1

    2

    3

    4

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    18

    19

    20

    21

    22

    23

    24

    25

    (36.5

    FT

    .X75FT.=2737.5

    SF)

    36.5

    65.7SF

    AISLE

    5'

    AISLE

    5'

    AISLE

    5'

    AISLE

    5'

    AISLE

    5'AISLE

    5'

    AISLE

    5'

    463L CARGO PALLET108" X 88"

    EXTRA EXTRA EXTRA EXTRAEXTR APALLETPOSITIONFOR MOV ING

    5

    75'

    (48.8 FT. X 75 FT. = 3,660 SF)

    7.3

    '

    7.3

    '

    7.3'

    7.3

    '

    7.3

    '

    7.3

    '

    7.3

    '

    7.3

    '

    43

    .8'

    48.8

    '

    7.3

    '

    Table 2-B: RSP Space Requirements for Pallets.

    Figure 2-B: Graphic Illustration of Readiness Spares Package (RSP) Pallet Storage Space.

  • 7/28/2019 USAF Flight Line Facilities Design Guide

    13/34

    AMC FLIGHT LINESUPPORT FACILITY

    8

    Area SF SM

    Avionics and ElectronicComponents Storage(3) 1,000 93

    Classified Storage(3)

    300 28Battery Storage(3) 150 14

    Net Subtotal SpecialStorage 1,450 135(1)

    Area SF SM

    Customer Service 100 9

    Mechanical Room(4) 240 22

    Electrical Room 48 4

    Communications Room 48 4

    Rest Rooms(5)

    408 38Break Room(6) 600 56

    Janitors Closet 50 5

    Net Subtotal Support Area 1,494 139(1)

    Area SF SM

    Parts and ComponentsAdministration(2) 990 92

    Flight Line SupportFacility Administration(2) 990 92

    OICs/NCOICs Office(3) 270 25

    Net Subtotal Administration 2,250 209(1)

    Area SF SMHigh-Density Storage 12,383 1,150

    RSP Pallet Storage Area(7) 4,685 435

    RSP Pallet Buildup Area(7) 1,024 95

    RSP Loading Dock 150 14

    Truck Loading Dock 250 23

    Reparable Parts/Tail Number Parts/TCTO Parts(3) 1,500 139

    Net Subtotal Warehouse 19,992 1,856(1)

    Functional Space Requirements for

    Administration

    Legend for Tables 2-C Through 2-F.

    SF - Square Footage

    SM - Square Meters(1) SM =.0929 x SF (all measurements are rounded). (4) Square footage is based on 8% of gross administration area.(2) Square footage is based on 90 Net SF per person with systems furniture. (5) Square footage is based on National Plumbing Code for occupancy and(3) Individual units may have specific requirements which drive number of fixtures for up to 100 people.

    an increase or decrease in space for specific functional areas. These (6) Square footage is based on 40 seats at 15 SF per seat, plus vending area.deviations from this standard should be fully justified and documented (7) Square footage is based on 32 pallets (see Table 2-B and Figure 2-B).during planning and programming of the facility.

    Functional Space Requirements forSupport Areas

    Table 2-C: Space Requirements for the Administration Areas.

    Table 2-D: Space Requirements for the Support Areas.

    Functional Space Requirements

    for Warehouse

    Table 2-E: Space Requirements for the Warehouse Areas.

    Functional Space Requirementsfor Special Storage

    Table 2-F: Space Requirements for the Special Storage Areas.

  • 7/28/2019 USAF Flight Line Facilities Design Guide

    14/34

    AMC FLIGHT LINESUPPORT FACILITY

    9

    Table 2-E: Space Requirementsfor Warehouse Areas - Arearequirements for general purposeand support areas include high-density storage, RSP pallets, load-ing docks, reparable parts, and

    TCTO kits.

    Table 2-F: Space Requirements forSpecial Storage Areas -Use thistable to determine square footagerequirements for areas that havespecial needs, i.e. security fencing,

    special ventilation and exhaust, andsecurity/surveillance.

    Table 2-G: Space Requirementsfor a Flight Line Support Facility -

    This table provides an exampleofthe square footage requirementsfor a typical facility.

    G.Site Evaluation

    1. Location

    a. Locate the flight line supportfacility adjacent to the flight line,near the center of aircraft mainte-nance activities.

    b. Include vehicle access for partsdelivery and pickup.

    c. Include sufficient parking forpersonnel and customers.

    2. Si ze

    a. Site size depends upon gross buildingsquare footage; space required foraccess, maneuvering and parking oftractor trailers; and space requiredfor access and parking of government-owned vehicles (GOVs) and privatelyowned vehicles (POVs) away from themajor roadways.

    b. Prior to the preparation of DDForm 1391, preliminary site designshould be performed to ensure the

    facility, parking, loading docks, andexterior storage can be accommodated.

    c. Include fire lanes in accordancewith local fire codes.

    Area SF SM

    Subtotal Administration 2,250 209(Table 2-C)

    Subtotal Support Area 1,494 139(Table 2-D)

    Subtotal Warehouse 19,992 1,856(Table 2-E)

    Subtotal Special Storage 1,450 135(Table 2-F)

    Net Total Flight Line Support Facility 25,186 2,339

    15% Walls and Circulation 3,778 351Gross Total Flight Line Support Facility 28,964 2,690

    (1)

    Gross Total Functional Space Requirementsfor a Flight Line Support Facility

    Table 2-G: Space Requirements for a Typical Flight Line Support Facility.

    Legend for Table 2-G.

    SF - Square Footage

    SM - Square Meters

    (1) SM =.0929 x SF (all measurements are rounded).

  • 7/28/2019 USAF Flight Line Facilities Design Guide

    15/34

    AMC FLIGHT LINESUPPORT FACILITY

    10

    H.Special Project

    ConsiderationsConsider special factors when estab-lishing initial estimates of projectcosts (see relevant sections ofChapters 3 and 4). Specialconsiderations are:

    Weather Conditions -Evaluatelocal wind, snow, and seismicconditions for their impact onproject costs.

    Preliminary Soil Analysis -Determine whether specializedsite and foundation work will berequired.

    High-Bay Construction -Requiredto support high-density storagewith 30-foot minimum clearanceunder the roof structure.

    Mezzanine -Design structuralcolumns to accommodate a mezza-nine at a height of 15 feet abovethe floor.

    High-Density Rack Storage -In earthquake zones, incorporatebracing.

    Mid-Level Sprinklers - Locatein high-density rack storage andunder mezzanines in accordancewith applicable fire coderequirements.

    Standby Power Generation -Install an uninterruptible powersupply for computers controllinginventory and electrical materialhandling equipment.

    Recessed Floor-Mounted Scale -Provide a scale to weigh cargo

    pallets.

    Floor Design -Floors must belevel. Design to support 500pounds per square foot loadingfor rack storage and materialhandling equipment.

  • 7/28/2019 USAF Flight Line Facilities Design Guide

    16/34

    Overall ProjectDesign

    AMC FLIGHT LINESUPPORT FACILITY

    A.General

    This chapter presents broad criteria

    for locating a flight line supportfacility on a site, design of the facilityand its supporting utilities, and tech-nical requirements.

    B. Site Design

    1. Selecti on

    a. See Figure 3-A for the site organi-zation concept.

    b. Facilities should comply with air-field clearance requirements for build-ing height and setbacks.

    c. A typical site layout and the sitesorganizational relationship to theflight line and maintenance units are

    illustrated in Figure 3-B.d. Building orientation should takeinto account the following factors:

    Protection from winds and glare

    Chapter 3

    PARTSPICKUPPARKING

    ADMINISTRATIONENTRANCE

    CUSTOMERENTRANCE

    FENCE

    SQ

    OPS/AMU

    RSP

    SHIPPING

    HANGAR

    AIRCRAFT

    PARKING

    APRON

    OUTSIDESTORAGE

    CUSTOMERPARKING

    COVERED STORAGE

    TRUCKLOADINGDOCK

    MAIN ENTRANCE

    MECHANICALENTRANCE

    STAFFPARK ING

    ALTERNATE TRUCK ENTRANCE

    FLIGHT LINESUPPORTFACILITY

    Figure 3-A: Site Organization Concept for the Flight Line Support Facility.

    11

  • 7/28/2019 USAF Flight Line Facilities Design Guide

    17/34

    12

    AMC FLIGHT LINESUPPORT FACILITY

    Shade from excessive sun inwarm climates

    Orient operable windows to takeadvantage of summer breezes

    Maximum sun exposure in coldclimates

    2. Access

    a. Locate the building on the sitewith two vehicle entrances: a conve-nient main entrance and an alternatetruck entrance.

    b. Design a clearly identifiable accessroute to the customer entrance fromthe customer parking lots.

    c. Segregate service traffic fromother traffic and pedestrian access.Keep traffic control signs to a mini-mum and use them only for safe inte-gration of vehicle traffic.

    3 . Ut i l it ies

    a. In accordance with local serviceprocedures, provide:

    Water, sanitary sewer, andstormwater systems, plus naturalgas, steam service, or fuel/oilsystems

    Electric, telephone, sprinkler, firealarm, and communications systems

    4. Landscaping

    a. Use landscape elements to definethe site and the main entrances.Landscaping should present an attrac-tive image for the facility, as well asnatural screening for separationbetween parking areas.

    C.BuildingDesign

    1. Organization and

    Circulationa.The main entrance should providedirect access to the parts counter.

    b. Design functional spaces for maxi-mum flexibility to allow for efficientstorage and retrieval of aircraft parts.

    The general warehouse consists oflarge, open bay areas of bulk, bin,and RSP storage. The maximumstorage height is 24 feet.

    c. Locate the mezzanine above theRSP pallet storage area. This areaprovides storage for large bulk items.

    d. Maintain a large open area, adja-cent to the RSP area, for buildup andmaneuvering of the RSP pallets.

    e. Locate the loading dock for RSPshipping on the side of the buildingnearest the flight line.

    f. Locate the parts and componentsadministration office so that the staffcan maintain visual supervision andsecurity of the warehouse.

    g.The rest rooms should have a cen-tralized, prominent location.

    2. Ar chitectural Character,

    M ateri als, and Fin ishes

    a. Integrate the architectural andinterior design of the facility. Thearchitectural style and form should be

    consistent with the base ArchitecturalCompatibility Guide.

    b.The design team should usecomprehensive interior design servicesto ensure interior finishes and furnish-ings are properly coordinated, as wellas appropriate. See Chapter 5 forsuggested interior finishes.

    c.The overall complex should pre-sent a cohesive architectural image.

    d. Provide a variety of spaces andsubspaces to accommodate differentsize groups and activities. Use modu-lar systems furniture in the parts andcomponents and flight line supportadministration areas to economize onspace, to provide flexibility, and topromote a sense of organization andvisual order.

  • 7/28/2019 USAF Flight Line Facilities Design Guide

    18/34

    AMC FLIGHT LINESUPPORT FACILITY

    13

    Figure 3-B: Site Organization Relationships for the Flight Line Support Facility.

    AIRCRAFT MAINTENANCE

    HANGAR

    SQ OPS/

    AMU

    AIRCRAFT

    PARKING

    APRON

    OUTSIDE

    STORAGECOVERED

    STORAGE

    LANDSCAPINGAS VISUAL

    BUFFER

    TYPICAL

    FLIGHT LINESUPPORT

    FACILITY

    TYPICAL

    FLIGHTLINE

    BUILDING

    TYPICAL

    FLIGHT

    LINE

    BUILDING

  • 7/28/2019 USAF Flight Line Facilities Design Guide

    19/34

    14

    AMC FLIGHT LINESUPPORT FACILITY

    3. Supervision and Securit y

    a.The flight line support administra-tive facility handles a high-valueinventory which requires security andsupervision.

    b.The parts and components admin-istration function should provide visualsupervision of the warehouse area.

    c. Limit access to high-value storageareas to assigned personnel. Use cardaccess for all access points inside and

    outside the facility. The access systemshould identify and record all personswho enter or leave the facility.

    4. Flexibili ty and Expansion

    Potential

    a. Design the warehouse site toaccommodate change or expansion asmission or assigned aircraft change.Consider providing land adjacent tothe warehouse to accommodate a

    100% facility expansion.b.The large RSP buildup area isa perfect example of flexible spaceusage since it is used for buildup ofpallets, movement of parts, and otherlarge components.

    5. D isabled Access

    All areas should be barrier free andaccessible to the physically disabled inaccordance with the Americans with

    Disabilities Act (ADA) and UniformFederal Accessibility Standards.

    6. Special Considerations for

    Renovationsa.Two factors that may necessitatenew construction are the availabilityof high-bay areas with a minimumclearance of 30 feet, and the ability ofthe floor to sustain 500 pounds persquare foot loadings. This may limitthe use of otherwise availableexisting space.

    b. When retrofitting an existingbuilding, select a suitable, permanentstructure large enough to accommo-date the full range of storage func-tions. The structural system andfloors should be open and relativelycolumn-free. The building layoutshould control customer access andprovide security for the warehouse.

    c. Survey and analyze existing build-ings for energy efficiency upgrade.

    D.BuildingSystems

    1. Structural

    a. Select a cost-effective framingsystem based on size, projectedload requirements, and availabilityof materials and local labor.

    Projected load requirements for thefacility include the following:

    Floor slab

    High-bay parts storage systemloading

    Bulk storage loading

    High-bay clear spans

    b. Select and design the structuralsystem based on analysis of projectedfuture needs to accommodate expan-sion easily and economically; howev-

    er, do notover design the initialconstruction.

    c. Design building structural compo-nents to reflect space requirements,economy, and subsystem dimensions(e.g., ceiling grid, masonry units, fram-ing members, etc.).

    2. Heating, Ventilating, and

    A ir Conditioning

    a. Perform a life-cycle cost analysisof available energy sources.

    b. Interior design temperatures andrelative humidity levels should con-form to Air Force standards.

    c. Provide mechanical air circulationin public areas with limited or no airconditioning.

    d.The mechanical air system shouldintroduce outside fresh air.

  • 7/28/2019 USAF Flight Line Facilities Design Guide

    20/34

    e. Design this facility to meet federal

    energy conservation standards definedin 10 CFR (Code of Federal Regula-tions), Energy Conservation Volun-tary Performance Standards for NewBuildings; Mandatory for FederalBuildings.

    f. Providezone controls (temperaturesensors with remote adjustmentinstead of thermostats) to maintaindifferent environmental conditions

    in all functional areas. Some areasof the facility may require operation ofenvironmental systems when otherareas are closed.

    g. Provide mechanical exhausts forthe rest rooms.

    h. Provide for connection to the base

    Energy Monitoring and ControlSystem (EMCS).

    3. Plumbing

    a. Provide domestic hot and coldwater, sanitary and storm drainage,plus propane or natural gas systems,if required.

    b. For general use, provide hot andcold water to all rest rooms, sinks, and

    janitors closets.

    c. Provide shut-off valves at allplumbing fixtures.

    d. Provide frost-free hose bibs on allexterior walls if local climate condi-tions justify them.

    4. Electrical

    a. Provide electric service, includingdistribution equipment, wiring, recep-tacles and grounding, interior andexterior lighting and controls, emer-gency lighting, telephone, and firealarms.

    b. Provide a back-up generator for24-hour operation.

    c. Evaluate and include the followingpower needs to determine the totalelectric service capacity:

    Photo card key access

    Engine warming receptacles whenneeded in severe cold climates

    15

    AMC FLIGHT LINESUPPORT FACILITY

    A large open area is required to build up and maneuver RSP pallets. The mezzanine area is used for bulk storage. (Grand Forks AFB, ND)

  • 7/28/2019 USAF Flight Line Facilities Design Guide

    21/34

    16

    AMC FLIGHT LINESUPPORT FACILITY

    d. All service equipment should beUnderwriters Laboratories-listed.

    As an alternative, providepublished proof from a bona fideindependent testing laboratory.

    e. General convenience receptaclesand special power outlets should becommercial grade. Conveniencereceptacles should be a maximum of12 feet apart. Provide special poweroutlets and circuits for all computerequipment as required.

    f. General lighting in office areasshould be fluorescent with low tem-perature energy efficient ballastsand lamps. Indirect lighting systemsof the high-intensity discharge orfluorescent types may be used wherepractical.

    g. Use of incandescent lightingshould be kept to a minimum becauseof energy efficiency and frequency of

    maintenance. Incandescent lightingshould have an extended life of atleast 2,500 hours.

    h. Lighting control systemsshould include dimmers to auto-matically reduce intensity levels ofartificial lighting when natural lightis available.

    i. Use high-intensity discharge lightsources for exterior lighting of parking

    areas, walkways, and buildingentrances.

    j. Install illuminated exit signs, pub-lic address systems, and battery pow-ered emergency lighting.

    k. Surveillance systems in designatedareas should have at least two levelsof detection.

    5. Fire Protection

    a. Facilities should be of noncom-bustible construction.

    b. Hazardous or combustible suppliesmust be contained within a fire-ratedenclosure.

    c. Provide sprinkler coverage in theaircraft wheel and tire assemblies stor-

    age area.

    6. Communications

    a.The base communicationssquadron, in coordination with thesystem telecommunications engineer-ing manager, can provide details oncommunications requirements anddesign for the buildings internal andexternal phone and data connectivity,as well as alarm system wiring.

    b. Incorporate requirements intobuilding design specifications andinclude connectivity to base phones,with data infrastructure systemssufficient to support the maximumplanned number of building occu-pants. These requirements areas follows:

    Phone Connections - Providesufficient preinstalled connections

    to support the maximum plannednumber of people in each area.Consider future growth, modemconnections, and special require-ments (pay phones, etc.).

    Administrative Data Connections(Local Area Networks - LANs) -Provide administrative computerand LAN printer connectivity.Also provide specialized computerconnectivity to support the basemission when required.

    FiberOptic Connectivity - Maybe required (internally to severallocations and/or externally to sys-tem nodes) to support AMC com-mand, control, communications,

    and computer systems. Hands-Free, Two-Way Intercom

    (Public Address System) - Providethroughout the facility, with wall-mounted speaker units.

    7. M ateri al Handling System

    a.The Material Handling Engineer-ing Branch at Wright-Patterson AFB,OH (DSN: 787-3078), is the focalpoint for designing and funding

    material handling systems. The fol-lowing material handling guidanceincludes recommendations that maybe altered after further study atbase level.

    b. Store most parts in a high-densitysystem with a maximum storage heightof 24 feet. Storage should be a combi-nation of the following:

    Bins-Stored on adjustable shelv-

    ing set initially 6 inches apart. Open Shelf Storage -Wire rack

    over framework, 24 inches highand/or 30 inches deep, withadjustable heights for maximum use.

  • 7/28/2019 USAF Flight Line Facilities Design Guide

    22/34

    AMC FLIGHT LINESUPPORT FACILITY

    17

    Pallet racks - Design for standardAir Force Pallets, 40 deep x 48wide (not to be confused with 463Lcargo pallets which are 108 x 88).Design should consider a possibleload overhang of four inches totalin either direction, a 3,000 poundload, and adjustable verticalspacing for maximum use.

    Special Rack - For storage of tireand wheel assemblies. This rackmaintains the tires in an upright,

    secured position to prevent themfrom rolling. Because of tire weightand size, they should be stored onthe floor or on the first level of theracks.

    Parts Carousel -For small parts

    Cantilever Racks -For storinghydraulic tubing, sheet metal,and items too bulky for rackstorage. The length of the sup-port arms and load capacitymust be suitable for specificitems to be stored.

    c. Items that are too bulky for rackstorage can be stored on the openmezzanine above the cargo palletstorage area.

    d. Aircraft parts in the high-densitysystem are stored and retrieved usingman-up turret trucks. Note that

    storing high-demand items at levelsbelow six feet will permit manualpicking of many of these items with-out the turret trucks.

    e. In-rack sprinkler systems arerequired for racks over 12 feet high.

    f. Use a pallet jack to move materialsstored on the mezzanine. Equip themezzanine storage areas with a 1,000-pound capacity vertical reciprocatingconveyor (VRC) for lifting and lower-ing material to the mezzanine level.

    The mezzanine should also have aremovable section of railing for liftingitems too bulky for the VRC and as abackup in case of VRC malfunction.

    Vertical spacing of high-density storage racks should be adjustable for maximum use. (Grand Forks AFB, ND)

  • 7/28/2019 USAF Flight Line Facilities Design Guide

    23/34

    18

    AMC FLIGHT LINESUPPORT FACILITY

    g. Provide floor-mounted roller con-veyors for staging the cargo pallets.

    h. Building floors should be levelwithin 0.125 inches in 10 feet, withno more than 0.5 inch deviation inthe entire building area used by turrettrucks. Aisle width between rack facesshould be 68 inches for turret trucksand 60 inches for order-picking trucks.

    i. The storage racks and shelvesshould be designed for rail guidance.(The floor rail down the aisle andcurbs at the ends of the shelving,painted yellow in the photo below,prevent the turret truck from comingin contact with the storage racks.)

    The lowest level of storage must beeven with or above the top of the rail.Design the racks, shelves, and railguidance so that the area under therack or shelf is either cleanable or

    sealed to prevent the accumulation oftrash or dust.

    j. Provide a battery charging areafor the turret trucks. This area shouldbe large enough for two to three vehi-cles and permit removal of batterieswith minimum manual effort. Provideadequate ventilation to prevent hydro-gen accumulation during charging.

    High density storage and mechanized turret trucks contribute to efficient handling of aircraft parts. (Grand Forks AFB, ND)

  • 7/28/2019 USAF Flight Line Facilities Design Guide

    24/34

    AMC FLIGHT LINESUPPORT FACILITY

    19

    A. General

    This chapter presents criteria fordesigning a flight line support facility.Primary design considerations include

    the use, performance, organization,character, and relationships of compo-nent spaces. For each area, specificcriteria are provided concerning spacesize and critical dimensions. Theserecommendations may be modified toreflect mission requirements. The sizesof functional areas are specified in Tables2-C through 2-F, page 8.

    B. Administration

    1. Design Considerat ions

    See Figure 4-A for an illustrativefloor plan.

    a. Use and Performance

    Two administrative functionsare contained within a flight linesupport facility:

    Parts and components admin-istration is for ordering and

    expediting parts. Flight line support administra-

    tion is the primary customerinterface.

    Collocate the administrative areasso that rest rooms and support func-tions can be shared.

    b. Space Organization andCharacter

    Provide a private office for the OIC

    and NCOIC within the flight linesupport administration area.

    2. Part s and Component

    Administration

    a. Furnishings and Equipment

    Use modular systems furniture forthe work stations and privateoffices.

    Provide lockable cabinets forstorage of manuals.

    Include an area for file cabinetsand vertical files.

    b. Technical Requirements

    Wiring for LAN computers.

    Provide telecommunicationsdata/computer outlets.

    3. Fli ght L ine Support

    Administration

    a. Furnishings and Equipment

    Use modular systems furniture forwork stations.

    The parts and components administration area should overlook the entirewarehouse area. Ordering, tracking, and accounting for specific parts requirea well-organized computer area. (Grand Forks AFB, ND)

    Chapter 4

    Functional Areaand Space Criteria

  • 7/28/2019 USAF Flight Line Facilities Design Guide

    25/34

    20

    AMC FLIGHT LINESUPPORT FACILITY

    Provide lockable cabinets forstorage of manuals.

    Include an area for file cabinetsand vertical files.

    b. Technical Requirements

    Wiring for LAN computers.

    Provide telecommunicationsdata/computer outlets.

    4. OICs/NCOICs Office

    a. Furnishings and Equipment

    Desks and desk chairs

    Side chairs

    File cabinets

    Personal computers

    b. Technical Requirements

    Telecommunications data/computer outlets

    Wiring for LAN computers

    Security devices to controlpublic access

    C. Support Areas

    1. Design Considerat ions

    a. Use and Performance

    The support areas should includethe following:

    Customer Service Entrance -Mainentrance should be easy to identifyfrom the principal access road.

    Interior traffic areas should be logi-cal, efficient, and easy to followfrom the main entrance.

    Mechanical Room -Location ofprimary equipment for HVAC,plumbing, and other buildingsystem equipment

    Electrical Room -Location ofprimary electrical systems for thebuilding

    Communications Room -Containscomputer distribution equipmentand telephone service panels

    Rest Rooms -Locate centrallywithin the facility.

    b. Space Organization andCharacter

    The mechanical room should have

    outside access. All mechanical, electrical, and

    communications rooms shouldbe adjacent to each other forservicing convenience.

    2. Customer Service Entrance

    a. Furnishings and Equipment

    Provide pedestrian entrance mats.

    b. Technical Requirements

    Provide easily cleaned, water-

    and mud-resistant flooringmaterials at all entrances.

    3. M echanical Room

    a. Furnishings and Equipment

    Provide a floor-mountedmop sink.

    b. Technical Requirements

    Size and critical dimensionswill vary with building systemrequirements and climateconditions.

    4. Electr ical Room

    a. Technical Requirements Provide for standby power

    generation and uninterruptiblepower supply.

    Locate adjacent to the computerand mechanical rooms.

    5. Communicati ons Room

    a. Technical Requirements

    Provide for various personalcomputers, as required.

    Provide surge protection for allcomputer equipment.

    Design for a sound transmissionclass rating of 52.

    6. Rest Rooms

    a. Furnishings and Equipment

    Men: Water closets, lavatories,urinals, soap dispensers, papertowel dispenser and disposal units,toilet paper holders, grab bars,mirrors, coat hooks, and partitions

    Women: Same as men, minus uri-nals, plus sanitary napkin dispenserand disposal units

    b. Technical Requirements

    Sound transmission class rating:45 between adjacent rooms

    Finish floors with non-skidceramic tile.

    Finish walls with ceramic tileinstalled either full height oras a wainscot.

    Use plastic laminate for lavatorycounters.

  • 7/28/2019 USAF Flight Line Facilities Design Guide

    26/34

    AMC FLIGHT LINESUPPORT FACILITY

    21

    7. Janit ors Closet

    Provide a floor-mounted mop sink. Provide shelves and hooks for

    cleaning and maintenanceequipment.

    Provide a water-resistant, easily

    maintained floor material, sloped

    to a floor drain.

    D.Warehouse

    1. Design Considerat ions

    a. Use and Performance

    Primary areas of the warehouse

    provide fully integrated flight linesupport for aircraft maintenance.

    High-Density Parts Storage -Usedfor efficient storage of a large num-ber of small items.

    CLASSIFIEDSTORAGE

    PARTS C OUNT ER

    RSPLOADING DOCK

    463LSCALE

    TWO STORAGE LEVELS MEZZANINE BULK

    STORAGE AREA (UPPER LEVEL) RSP PALLET ST O RAGE AREA (LOWER LEVEL)

    HIGH-DENSITYPA RTS STORAGE

    JAN.

    RSP PALLET BUILDUP AREA

    LINE OF MEZZANINE ABOVE

    WAREHOUSE

    BATTERY

    STORAGE

    AVIONICS ANDELECTRONICCOMPONENTSSTORAGE

    MECHANICALROOM

    ELECTRICALROOM

    COMMUNICATIONS

    ROOM

    OIC'S/NCOIC'SOFFICE

    FLIGHT LINESUPPORT FACILITYADMINISTRATION

    ORDERPICKERRECHARGER

    SHIPPING ANDRECEIVING

    REPARABLE PARTS/TAIL NUMBER PARTS/TCTO PARTS

    TRUCKLOADINGDOCK

    CUSTOMERENTRANCE

    PARKING

    CUSTOMERPARKING

    PARKING

    PARTS AND COMPONENTSADMINISTRATION

    WINDOWSOVERLOOKINGWAREHOUSE

    CONTROLLEDACCESS ADMINISTRATION

    ENTRANCE

    CONTROLLEDACCESS

    UP

    REST ROOMS

    CONTROLLEDACCESS

    EYEWASH ANDDELUGE SHOWER

    Figure 4-A: Floor Plan for the Typical Flight Line Support Facility.

  • 7/28/2019 USAF Flight Line Facilities Design Guide

    27/34

    22

    AMC FLIGHT LINESUPPORT FACILITY

    RSP Pallet Storage Space -Thisarea includes floor-mounted rollersfor storage of RSP kits.

    RSP Pallet Buildup Area- An areato assemble and maneuver RSPcontainers.

    RSP Loading Dock-The dockprovides a transfer area for RSPcontainers to and from theflight line.

    Truck Loading Dock -The dockprovides a transfer area to receivecomponents from base supply,depots, and manufacturers.

    Parts Counter- Customer partspick-up is at this counter.

    Bulk Storage Area -Parts toolarge for high-density storage arekept in this area.

    Reparable Parts/Tail NumberParts/TCTO Parts - An area forstoring parts until they are sentout for repair.

    b. Space Organization andCharacter

    Provide a large work area for pack-ing, unpacking, and maneuveringRSP kits on cargo pallets with andwithout material handling equip-ment. Area should be a large, con-tiguous open space.

    Locate the RSP pallet storage space

    adjacent to the dock. Provide anin-floor mounted scale sized tohandle cargo pallets, and capable ofaccurately measuring a pallet whichweights up to 10,000 pounds.

    RSP pallet storage space should beadjacent to the RSP buildup area.

    The RSP loading dock should beadjacent to the buildup area.

    2. H igh-Densit y Part s Storage

    Refer to Chapter 3, paragraph D7,Material Handling System, for adescription of storage rack systemsand equipment.

    a. Furnishings and Equipment

    The high-density storage shelf

    system should be at least 24 feethigh.

    b. Technical Requirements

    Ensure that traffic aisles, storageshelving aisles, and equipmentcan accommodate the material han-dling equipment.

    Arrange the area so that therequired exits are remote from eachother, but within 200 feet or less of

    any point within the facility. Floor finish should reflect light

    and be easily cleaned.

    Provide high-bay construction with30 feet minimum clearance underthe roof structure.

    In earthquake zones, brace high-density storage racks to resistearthquake forces.

    3. Readiness Spares Packages

    Pal let Storage Spacea. Furnishings and Equipment

    Provide floor-mounted rollerconveyors sized to handlethe RSP kits.

    Locate the cargo pallets inthis area.

    b. Technical Requirements

    Ensure floors are level within0.125 inch in 10 feet with no more

    than 0.5 inch deviation.4. Readiness Spares Packages

    Buil dup A rea

    a. Furnishings and Equipment

    Locate the cargo pallets in this area.

    b. Technical Requirements

    Provide natural light wheneverpossible, along with metalhalide lighting.

    The floor finish should reflect lightand be easily cleaned.

    5. Readiness Spares Packages

    Loading Dock

    a. Furnishings and Equipment

    Provide dock levelers to correct theelevation differences between theloading dock and truck bed. Alsoprovide truck restraints to keep thetrailer from pulling away from thedock, and dock door seals forweather protection.

  • 7/28/2019 USAF Flight Line Facilities Design Guide

    28/34

    AMC FLIGHT LINESUPPORT FACILITY

    23

    b. Technical Requirements

    Use overhead rolling doors atdock openings.

    Incorporate a surveillancesystem with card key to controlaccess from the exterior.

    Include ramps for forklift traffic atloading docks.

    6. Truck Loading Dock

    a. Furnishings and Equipment

    Provide dock levelers to correct the

    elevation differences between theloading dock and truck bed. Alsoprovide truck restraints to keep thetrailer from pulling away from thedock, and dock door seals forweather protection.

    Incorporate a surveillance systemwith card key to control accessfrom the exterior.

    b. Technical Requirements

    Use overhead rolling doors atthe dock opening.

    7. Parts Counter

    a. Furnishings and Equipment

    Provide a service counter toseparate warehouse workersfrom customers.

    Provide sufficient space totemporarily store a small numberof items.

    b. Technical Requirements Wiring for LAN computers.

    Provide telephone/computeroutlets.

    Control access to the warehousefrom the parts counter area.

    8. Bulk Storage Area

    a. Furnishings and Equipment Provide a VRC to carry workers

    and warehouse items from theground floor to the mezzanine level.

    Include a storage system for tiresand wheel assemblies.

    b. Technical Requirements

    Design structural columns for amezzanine at 15 feet above thefloor.

    Install mid-level sprinklers undermezzanines in accordance withapplicable fire code requirements.

    9. Reparable Parts/Tail

    Number Part s/TCTO Parts

    a. Furnishings and Equipment

    Provide shelving and storage bins.

    Incorporate rollers/materialconveyors.

    Include a customer counter inthis area.

    b. Technical Requirements

    Install wiring for LAN computers.

    E. Special StorageRequirements

    1. Design Considerati ons

    See Figure 4-A , page 21, for locationof special storage areas.

    a. Use and Performance

    The following are the primaryareas that have specific storagerequirements:

    Avionics and ElectronicComponents Storage-These itemsrequire a separate environmentallycontrolled storage area to precludedamage to these sensitive parts.

    The turret truck and vertical conveyor efficiently move material from the mezzaninestorage area to the RSP buildup and storage areas. (Grand Forks AFB, ND)

  • 7/28/2019 USAF Flight Line Facilities Design Guide

    29/34

    24

    AMC FLIGHT LINESUPPORT FACILITY

    Classified Storage-Requires anarea enclosed with fire-rated wallsand vault door.

    Battery Storage-For storage ofnickel cadmium cells and refrigerat-ed storage of individual cells

    Outside Storage -A large space forstorage of bulk items and equip-ment that can be stored outdoors,thus freeing space within thewarehouse.

    b. Space, Organization, andCharacter

    Locate battery storage away fromadministrative areas to facilitate theunobstructed exhausting of fumes.

    Because of the need for security,locate classified storage near theadministrative areas.

    2. Avionics and Electronic

    Component s Storagea. Furnishings and Equipment

    Provide a shelving systemappropriate to accommodatethe items to be stored.

    b. Technical Requirements

    Provide separate environmentalcontrols.

    Wiring for LA N computers.

    Provide telephone/data

    communications outlets.

    3. Classifi ed Storage

    a. Furnishings and Equipment

    Include a shelving systemto accommodate the itemsto be stored.

    b. Technical Requirements

    Allot approximately 300 square feetfor this space.

    Provide fire-rated walls and ceiling.

    Install a vault door.

    4. Battery Storage

    a. Furnishings and Equipment

    Provide safety equipment and facili-ties, e.g., eyewash, deluge shower.

    Include space to accommodaterefrigeration equipment.

    b. Technical Requirements

    Use quarry tile or acid-resistantfloor coating.

    Use explosion-proof receptacles.

    Finish interior ceiling and wallswith non-combustible materials.

    Maintain temperatures in accord-ance with the manufacturersrecommendations for explosion-

    proof heaters. Provide positive air ventilation

    and special exhaust to conformto established design requirementsand local building codes.

    Provide sufficient electrical outletsto accommodate charging equip-ment and refrigeration equipment.

    5. Out side Storage

    a. Furnishings and Equipment

    Security fencing is required.b. Technical Requirements

    Provide a controlled-access gate.

    Paved surfaces are required.

    Provide lighting for night-timevisibility and surveillance.

    Locate the covered storage spacein this area.

    A typical RSP storage area beneath a mezzanine should be equipped with floor-mountedrollers for easy maneuverability. (Grand Forks AFB, ND)

  • 7/28/2019 USAF Flight Line Facilities Design Guide

    30/34

    AMC FLIGHT LINESUPPORT FACILITY

    25

    A.General

    Finish materials and furnishingsshould be selected using professionalinterior design services. Selectionsshould be based on anticipated use,

    maintenance requirements, life-cyclecost, fire and other life safety require-ments, as well as aesthetic qualities.

    Coordinate materials, finishes, colors,and texture selections to complementthe overall building design and image.Select colors and finishes to expressprofessionalism, warmth, and a strong,positive image.

    B. Finish Schedule

    Use colors and finishes to highlightand differentiate spaces designed toaccommodate different types and

    levels of activity. For example, thewarehouse areas require extremelydurable and easy to maintain finishes.

    Color schemes should be predomi-nantly neutral. The designer shouldconsider the seasonal temperaturerange of the base when selecting acolor scheme, such as cool colors(blue, green) in hot climates andwarm colors (beige, tan) in coldclimates.

    Furniture is an integral part of the building design and image.

    Chapter 5

    Interior Finishes

  • 7/28/2019 USAF Flight Line Facilities Design Guide

    31/34

    26

    AMC FLIGHT LINESUPPORT FACILITY

    Permanent and semi-permanentsurface materials, such as tile, carpet,and the majority of the wallcoverings,should be in neutral colors such asbeige, taupe, or gray tones.

    Patterned carpet (bold tweeds) can bethe basis for the overall color scheme,as well as mask traffic wear.

    Paint mechanical and electricaldevices to match the background sur-face. Room finish schedules are listedin Tables 5-A through 5-D. Thedashed numbers after the abbrevia-tions (e.g., P-1, VCT-2, VWC-3, etc.)in Tables 5-A through 5-D refer tospecific material color board samplesin Figure 5-A, pages 30 and 31.

    C.Furniture

    Furniture is an integral part of theoverall building design and image.Coordinate furniture selection forconsistency with finish materials, tex-tures, and colors of built-inelements.

    Choose furniture that is durable,comfortable, modular, and flexible.Systems furniture, which can be fund-ed as part of a military construction

    project, is recommended for alladministrative areas.

    List of Abbreviations

    ACT Acoustical Ceiling Tile MTL Metal

    CB-E Concrete Block, Epoxy NA Not Applicable

    CB-P Concrete Block, Painted PL Plastic Laminate

    CONC-S Concrete, Sealed QT Quarry Tile

    CPT Carpet VB Vinyl Base

    CT Ceramic Tile VCT Vinyl Composition Tile

    EXP-P Exposed Structure, Painted VWC Vinyl Wallcovering

    GWB-P Gypsum Board, Painted

    Finish Schedules

    Flight Line Support AdministrationFunctional Area Name Floors Base Walls Ceiling

    Parts and ComponentsAdministration CPT VB VWC-3 ACT

    Flight Line SupportAdministration CPT VB VWC-3 ACT

    Table 5-A: Finish Schedule for the Flight Line Support Facility Administration.

  • 7/28/2019 USAF Flight Line Facilities Design Guide

    32/34

    AMC FLIGHT LINESUPPORT FACILITY

    27

    Flight Line Support Facility-Warehouse

    Functional Area Name Floors Base Walls Ceiling Laminate

    High-Density Parts Storage CONC-S NA CB-P-2/MTL EXP-P-3 NA

    RSP Pallet Storage Area CONC-S NA CB-P-2/MTL EXP-P-3 NA

    RSP Buildup Storage Area CONC-S NA CB-P-2/MTL EXP-P-3 NA

    RSP Loading Dock CONC-S NA CB-P-2/MTL EXP-P-3 NA

    Parts Counter VCT VB CB-P-2 ACT PL-2

    Bulk Storage (Mezzanine) MTL NA CB-P-2/MTL EXP-P-3 NA

    Reparable Parts/Tail Number

    Parts/TCTO Parts CONC-S NA CB-P-2 ACT NA

    Flight Line Support Facility-Support Areas

    Functional Area Name Floors Base Walls Ceiling LaminateMechanical CONC-S NA CB-P-1 EXP-P-3 NA

    Electrical CONC-S NA CB-P-1 EXP-P-3 NA

    Communications CONC-S NA CB-P-1 EXP-P-3 NA

    Rest Rooms (men) CT-1 CT-3 VWC-2/CT-3 GWB-P-3 PL-1

    Rest Rooms (women) CT-2 CT-3 VWC-3/CT-3 GWB-P-3 PL-2

    Janitors Closet CONC-S NA CB-P-1 EXP-P-3 NA

    Table 5-C: Finish Schedule for the Flight Line Support Facility Warehouse.

    Table 5-B: Finish Schedule for the Flight Line Support Facility Support Areas.

    Flight Line Support Facility-Special Storage

    Functional Area Name Floors Base Walls Ceiling

    Avionics and ElectronicComponents Storage CONC-S NA CB-P-1 EXP-P

    Classified Storage CONC-S NA CB-P-1 EXP-P

    Battery Storage QT NA CB-E EXP-P

    Table 5-D: Finish Schedule for the Flight Line Support Facility Special Storage.

  • 7/28/2019 USAF Flight Line Facilities Design Guide

    33/34

    28

    AMC FLIGHT LINESUPPORT FACILITY

    AFM 67-1 Mechanized Material Handling Systems andVol. II, Part I Storage Aids Systems

    AFM 86-2(1) Standard Facility Requirements

    AFM 88-3 Structural Design Criteria Loads

    AFR 89-1(2) Design and Construction ManagementAFR 125-37(3) Protection of USAF Resources

    ADA Americans with Disabilities Act

    DoD 4145.21M1 Material Handling/Storage

    DoD 4270.1-M Construction Criteria Manual

    FED STD. 795 Uniform Federal Accessibility Standards

    MIL-HDBK 1008B Military Handbook for Fire Facilities Engineering,Design, and Construction

    MIL-HDBK 1190 Military Building Code

    NFPA-231 and 231C Sprinkler Protection for Flammable Liquid Storage

    NFPA-101 Life Safety Code 101

    NFPA 30: 4-5.6 Flammable and Combustible Liquid Storage for General PurposeWarehouse

    AMC Commanders Guide to Facility Excellence

    AMC Bases Architectural Compatibility Plans

    AMC Hazardous Material Pharmacy Facility Planning and Design Guide

    AMC Interior Design Guide

    Legend(1) When published, A FI 32-1024 (Standard Facility Requirements) will supersede AFM 86-2.

    (2) When published, A FI 32-1023 (Design and Construction Standards and Execution of Facility Construction)will supersede AFR 89-1.

    (3) When published, A FI 31-209 (Air Force Resources Protection Program) will supersede AFR 127-37.

    References

  • 7/28/2019 USAF Flight Line Facilities Design Guide

    34/34

    AIR MOBILITY COMMAND

    GLOBAL REACH FOR AMERICA

    Prepared by Directorate of Civil Engineering