U.S. 90A/Eldridge Road Proposed Grade Separation
Transcript of U.S. 90A/Eldridge Road Proposed Grade Separation
Workshop Objectives Review CIP Development Process Review & Discuss Projects Input on Proposed Projects Identify Projects to Follow Up with
More Info Identify Projects to be added
CIP Development Process Year 1 CIP budget is established with
adoption of annual budget Years 2 - 5 are presented for financial
planning purposes only Charter does not require out years to be fiscally
constrained Financial planning requires cost estimate/opinions Staff constrains CIP based on affordability within five
year long-range financial plan
Allows for priority project scheduling
CIP Process Refinement What Becomes Year 1 CIP Study/Assessment/Preliminary Engineering
Design/Final Engineering Design Construction projects only if design is at
least 60% done by May 31 What Becomes Years 2-5 CIP Study/Assessment/Preliminary Engineering
Design/Final Engineering Design Construction projects only if a
study/preliminary engineering/schematic design already completed
CIP Process Refinement Update Cost Estimates to Reflect
Market Conditions Unit cost development Thorough development of scope
Program coordination Easements/ROW needs
Construction Cost Contingencies Analysis/studies/schematics – 30% (for Years 2-5
projects) Preliminary engineering – 20% (for Years 2-5 projects) Design – 10% (for Year 1 projects)
CIP Process Refinement Construction Cost Estimating Example – Unit Price
Unit Prices for FY16-FY20 Project Cost Updates
Sugar Creek Austin Pkway Street Sugar Mill Ragus Lake Lakefield
Item Unit Cost Phase II Bid (1/22/15) Recon Bid (1/15/15) Drainage Bid
(1/13/14) Drainage Bid (9/9/13) Recon Bid (09/11/14)
Hydromulching SY $3 $3.48 Install 10ft Type H Inlet EA $6,200 Install 5ft Type H Inlet EA $3,400 Install 5x3 Box Culvert LF $315 $386.80 Install 6x4 Box Culvert LF $385 Install 8x5 Box Culvert LF $540 $545.65 Install 8x6 Box Culvert LF $610 $522.67 Install 10x6 Box Culvert LF $910 Install 4x3 Box Culvert LF $250 $343.20 Install 4x4 RCB LF $300 Install 15ft Inlet EA $7,500 Install 24in RCP (Type III) LF $95 $121.00 $90.40 $82.25 Install 30in RCP LF $120 $164.00 Install 36in RCP LF $145 $182.67 Install 42in RCP LF $220 $200.53 $163.00 Install 48in RCP LF $290 $323.33 $253.47 $296.25 Install 54in RCP LF $315 Install 60in RCP LF $300 Install Junction Box - Cast in Place EA $15,000.00 $9,804.00 $25,992.50 Install Storm Sewer Manhole EA $4,000 $3,550.67 Pond Embankment & Compaction - onsite CY $5 Pond Embankment & Compaction - offsite CY $10 Removal - Inlet Structure EA $500 $416.67 $548.35 $387.50 $322.00 Removal - RCP LF $8 $8.15 $19.33 Removal - Concrete Paving SY $5 $11.67 $7.20 $11.04 $4.70 $4.93 Removal - Driveway/Sidewalk SY $5 $751.67 $7.36 $11.03 $4.00 $4.33 Install Rip Rap SY $35 $82.33 $139.00 Roadway Base Material SY $10 Trench Safety LF $1 $0.70 $2.75 $1.28 $1.15 $2.33 Concrete Paving - 6" SY $60 $86.67 $48.17 $34.65 Concrete Paving - 7" SY $62 $50.23 Concrete Paving - 8" SY $65 $72.29 Concrete Sidewalk - 4" SY $58 $61.57 $60.85 $55.33 Replace Driveway SY $60 $4,666.67 $66.04 $7.33 $51.00 Concrete Curb LF $4 $5.67 $3.63 $3.80 $3.48 $3.60 Waterline Replacement - 6" LF $60 $103.33 $58.92 Waterline Replacement - 8" LF $80 $63.23 $135.75 $61.73
CIP Process Refinement Construction Cost Estimating Example – Unit Price
Item Unit Cost Sugar
Creek (1/22/15)
Austin Parkway (1/15/15)
Sugar Mill
(1/13/14)
Ragus Lake
(9/9/13)
Lakefield
(9/11/14)
Concrete Curb LF $4 $5.67 $3.63 $3.80 $3.48 $3.60 Concrete Paving - 6" SY $60 $86.67 $48.17 $34.65 Concrete Paving - 8" SY $70 $72.29
CIP Process Refinement Construction Cost Estimating Example – Sugar Creek
Drainage
Item Quan. Unit Description Unit Price Cost
22 14,893 SY Remove Old Concrete (Roadway) $ 5.00 $ 74,465
23 7,120 CY Roadway Excavation $ 10.00 $ 71,200
24 14,893 SY Lime Stabilized Subgrade $ 5.00 $ 74,465
25 465 Ton Lime (8%) $ 200.00 $ 93,000
26 14,893 SY 6” Concrete Pavement w/ Gutter
$ 60.00 $ 893,580
CIP Overview Projects for Today’s Discussion Enterprise CIP:
Airport, Wastewater, Water, Surface Water
General CIP: Drainage, Municipal, Parks, Park’s Bond Projects,
Streets, & Traffic
Projects are Not Fiscally Constrained Future Budget Workshops will
Discuss Cost, Funding Capacity & Sources
Project Input Sources Master Plans Developer Agreements Mandates City Council City Staff Intergovernmental Residents Planning & Zoning Infrastructure Assessments
Key to Phase Categories E = Study/Assessment/Preliminary
Engineering/Schematic Design D = Design C = Construction
Red = New Projects/Changes in
Scope/Project Schedule Black = No Changes
Airport Projects FY16-FY20 Project Phase Year Parallel Taxiway Relocation & Hangars ALD #4 & ALD #11
C
FY16
Airport Development Plan E
FY16
Airport Maintenance Building E FY16
Runway Safety Area Improvements
C
FY17
Approach Lighting System C FY17
Security Fencing D/C FY18
Wastewater Projects FY16-FY19 Project Phase Year
Rehab 24-inch Forcemain from Lexington LS to Sweetwater LS C FY16
Replacement of Force main Crossing at US59/Central Dr. C FY16
Lift Station Rehabilitation D C FY16-20
Collection System Rehab (D & East & West Interceptor)
E D C
FY16 FY17 FY18
Wastewater Master Plan E FY17
Wastewater Projects FY16-FY19
Project Phase Year
Lift Station 48 Improvements (MUD 136 Reg. LS #1) D/C FY18
Force Main from North WWTP to West WWTP
D C
FY19 FY20
West WWTP Expansion – Phase I D C
FY19 FY20
Water Projects FY16-FY19 Project Phase Year Replacement of Waterline Crossing- @ US59 & Commerce Green Blvd.
C
FY15
Upgrade 18-inch to 24-inch Waterline from Fire Station No.4
C
FY16
Elevated Storage Tank Rehab (add Circulation Pumps) C FY16
Well Rehab D/C FY16-20 Ground Storage Tank Rehab
D/C
FY16-20
Distribution System Water Main Rehabilitation Program
D/C
FY16-FY20
GST Rehab Assessment E FY18
Surface Water Projects FY16-FY20
Project Phase Year Brooks Lake Diversion/Amil Gate Replacement C FY16
Riverstone Ground Water Plant Improvements
D C
FY16 FY17
Riverstone Ground Water Plant Connections
D C
FY16 FY17
Drainage Projects FY16-FY20 Project Phase Year Localized Drainage Improvements
C
FY16-20
Sugar Creek Drainage Improvement – Longview Dr. & Golf Course
C FY16
Covington Woods Drainage Improvement – Offline pond C FY16
Lexington Blvd. at Oyster Point Drainage Improvement
D FY16
Drainage Projects FY16-FY20 Project Phase Year Covington Woods Drainage Improvement – Ivymount
D C
FY16 FY17
Sugar Creek Drainage Improvement – Montclair
D C
FY16 FY17
Covington Woods Drainage Improvement – Bournewood/Ditch A22 to Bournewood Trunk Line
C FY17
Covington Woods Drainage Improvement – Jess Pirtle Side St. & Greywood Dr.
D C
FY17 FY18
Drainage Projects FY16-FY20
Project Phase Year Sugar Creek Drainage Improvement – Brunswick Dr. & Fairway Dr.
D C
FY18 FY19
Sugar Creek Drainage Improvement – East Ditch
D C
FY18 FY19
Sugar Creek Drainage Improvement – Chevy Chase Dr.
D C
FY18 FY19
Drainage Projects FY16-FY20 Project Phase Year Covington Woods Drainage Improvement – BP Ditch & JP Bridge
D C
FY18 FY19
Covington Woods Drainage Improvement – Covington West & Imperial Woods
D C
FY19 FY20
Covington Woods Drainage Improvement – Sugar Land MS/Sugar Mill Relief Line
D C
FY19 FY20
Drainage Master Plan E FY19
Municipal Projects FY16-FY20
Project Phase Year Public Works Service Center-FFE
C FY16
Facility Renovations C FY16-18
Animal Shelter Expansion E FY16
Facilities Building Assessment E FY17
Facilities Master Plan E FY20
Parks Projects FY16-FY20
Project Phase Year Parks, Recreation & Open Space Master Plan E FY16
ROW Planting & Irrigation Rehabilitation
C
FY16-20
Park Infrastructure Rehabilitation C FY16-20
Parks Projects FY16-FY20
Project Phase Year
Brazos River Park (PH 2) – Landscaping & Irrigation C FY16
Ditch H Trail (PH 1)– Design & Construct Sec. 1. Connection from Imperial to Austin Parkway
D C
FY17 FY18
Brazos River Park – Mid Lake D C
FY17 FY18
Ditch H Trail (PH 2) – Sec.2 & Sec. 3 trails C FY19
Streets Projects FY16-FY20 Project Phase Year Bridge Rehabilitation C FY16-20 Pavement Rehabilitation C FY16-20 Sidewalk & Trail Rehabilitation C FY16-20
Hwy 6 Maxicom Irrigation Retrofit - Brook St. to Oyster Creek Park C FY16
US59 Landscape Beautification Phase IV – Univ. Blvd. to Brazos River
D C
FY16 FY17
Streets Projects FY16-FY20 Project Phase Year Pedestrian & Bicycle Master Plan Improvements C FY16-FY19
Williams Trace PH1 – Austin Pkwy to SH 6 C FY17
Thoroughfare Master Plan Update E FY18
Sweetwater PH1 – Palm Royale to TC Blvd at Ditch A
D C
FY18 FY19
William Trace PH2 – Lexington to SH6 D FY20
Sweetwater PH2 – Austin Pkwy to Palm Royale
D C
FY19 FY20
Traffic Projects FY16-FY20
Project Phase Year Traffic Evaluation and Safety Improv. C FY16-20
Street Lights Replacement C FY16-FY20
ITS/Traffic Signal Management C FY16/FY17
Next Steps Fiscally Constrain All CIP Projects Proposed Five-Year CIP filed with FY16
Proposed Budget Future Budget Workshops will Discuss Funding Capacity & Sources