US 491 South Corridor FLH-666-1(49)17 CN 2357 Navajo 9 to Sheep Springs (NM 134) MP 15 to MP 46...
-
Upload
cameron-sheehan -
Category
Documents
-
view
213 -
download
1
Transcript of US 491 South Corridor FLH-666-1(49)17 CN 2357 Navajo 9 to Sheep Springs (NM 134) MP 15 to MP 46...
US 491South Corridor FLH-666-1(49)17
CN 2357 Navajo 9 to Sheep Springs (NM 134)
MP 15 to MP 46
Public Information MeetingNovember 1, 2006
Benediction
Presentation Outline
1) Introductions
2) US 491 Background & History
3) Engineering Re-Evaluation
4) Environmental Assessment
5) Navajo Nation Role in the Project
6) Question and Comments Session
7) Closing
Introduction
New Mexico Department of Transportation
Introductions
Presenters, Study Team Members & Guests
• Ricardo Roybal (NMDOT)
• Albert M. Thomas (Bohannan-Huston)
• Eric Johnson (Marron & Assoc.)
• Gene Martinez (NNDOT)
• Navajo Nation Officials
• NMDOT representatives
Navajo Nation Involvement
• Office of the President
• Office of the Speaker
• Oversight Committees
• Chapters
• Tribal Departments
• General Public
Project Agencies
• NDOT - Navajo Department of Transportation
• NMDOT - New Mexico Department of Transportation
• FHWA - Federal Highway Administration
• BIA - Bureau of Indian Affairs
Other Agency Involvement
• Governor’s Office
• Legislators & Public Officials
• Indian Health Service
• School Districts
Consultant Project Team
• Bohannan-Huston, Inc.
• Marron & Associates
• Gannett Fleming West
• Wilson & Company
• HDR Engineering
• AMEC Earth and Environmental
• SWCA Environmental
• TBE Group
Purpose of Public Meeting
US 491 South Corridor• Present the Findings of the
Engineering Re-Evaluation
• Describe the Environmental Investigations being conducted
• Solicit Public Input & Comments
US 491
Project Background
New Mexico Department of Transportation
Project Background
• Previous Study recommended 4-lanes on US 491
• NMDOT Committed to 4-Lanes
• 1 Program / 2 Corridor Study Limits – North Corridor
Sheep Springs to Navajo Road 13– South Corridor
Navajo Road 9 to Sheep Springs
(See Project Map)
Study Limits
Study Limits
Project Status
• Engineering Re-Evaluation– Existing Lanes to Remain– 2 New Lanes with 46 ft median
• Environmental Assessment– One document completed for North Corridor– One document under development for South
Corridor
Project Schedule
• US 491 North Corridor– Environmental Clearance complete– Right-of-Way Agreements being reviewed– Design will be complete by January 2007– Construction programmed to begin by Early 2008
• US 491 South Corridor– Environmental Clearance by December 2006– Design will be complete by April 2007– Right-of-Way Agreements by Summer 2007– Construction programmed to begin Early 2009
Engineering Re-Evaluation
Bohannan-Huston, Inc.
Existing Road
Enhanced 2-Lane$108 Million
4-Lane Reconstruction$240 Million
New Typical Section Concept
• Leave Existing Lanes
• Build 2 New Lanes Adjacent to Existing
• Separate Traffic with 46’ Divided Median
• Majority of Earthwork within ROW Easement
2-Existing & 2-New Lanes
Typical SectionOption 1
Typical SectionOption 2
Right-of-Way Issues
• Option 1 – West Alignment– 180 Acres of new ROW Easement for New Lanes– 5 Acres of Easements needed for Drainage– 2 Acres of Temporary Construction Permits– Less than 200 Acres Total
• Option 2 – East Alignment– 168 Acres of new ROW Easement for New Lanes– 124 Acres of additional easement for Borrow Ditch– 20 Acres of additional easements for Drainage– 6 Acres of Temporary Construction Permits– Over 300 Acres Total
South CorridorRight-of-Way Needs
• Right-of-Way Easement– Expand existing wide enough to build roadway prism
• Construction Maintenance Easements CME– Minor Easements for Drainage & Permanent Facilities
• Temporary Construction Easement/Permit TCP– Driveway/Turnout Reconstruction– Fixing/Replacing Cattlegaurds at ROW fence
Project Improvements
• Public Transit and School Bus
• Bicycle and Pedestrian Traffic
• Street Lighting at Intersections
• School Flashers where warranted
• Livestock Crossings
• Median Crossovers at ½ Mile Spacing
• Turn Lanes at Major Intersections
Environmental Review
andPublicInvolvement
Marron and Associates, Inc.
Environmental AssessmentProcess
• Guided by Location Study Procedures and National Environmental Policy Act
• Collect data
• Conduct public involvement
• Prepare environmental assessments
• 30-day comment period and public hearing
• Issue Finding of No Significant Impacts
Environmental Investigations
• Biological Surveys
• Wetland Surveys
• Cultural Resources
• Hazardous Materials
Public Involvement
• Comment Form for tonight’s input
• Website (www.US491.com) containing general project information has been established
• Contacts– Ricardo Roybal NMDOT (505)827-9852– Albert Thomas (505)823-1000– Eric Johnson (505)898-8848
• Public Hearing anticipated Early 2007
Navajo Nation Role
Navajo Department of Transportation
Navajo Nation Role
• Division of Natural Resources1. Archaeology2. Right-of-Way 3. Water4. Aggregate
• Navajo Nation Department of Transportation
Questions
and
Comments
Project Description