The World Bank
Page 1 of 10
PublicDisclosureCopy
PublicDisclosureCopy
Report No: ISR8029
Implementation Status & Results
Indonesia
URBAN SECTOR DEVELOPMENT AND REFORM PROJECT (P071296)
Operation Name: URBAN SECTOR DEVELOPMENT AND REFORMPROJECT (P071296)
Project Stage: Implementation Seq.No: 11 Status:ARCHIVED Archive Date: 03-Dec-2012
Country: Indonesia Approval FY: 2005
Product Line: IBRD/IDA Region: EAST ASIA AND PACIFIC Lending Instrument: Specific Investment Loan
Implementing Agency(ies): Ministry of Public Works, DG Human Settlements
Key Dates
Board Approval Date 07-Jun-2005 Original Closing Date 30-Jun-2011 Planned Mid Term Review Date 15-Apr-2008 Last Archived ISR Date 03-Apr-2012
Effectiveness Date 18-Jan-2006 Revised Closing Date 31-May-2013 Actual Mid Term Review Date 16-Mar-2009
Project Development Objectives
Project Development Objective (from Project Appraisal Document)
The project development objective is to assist the Borrower to strengthen local governance and improve the provision of selected urban services by participating UrbanLocal Governments (ULGs) and additional participating ULGs.
Has the Project Development Objective been changed since Board Approval of the Project?
Yes No
Component(s)
Component Name Component Cost
Urban Reform and Institutional Support Component 9.00
Urban Investment Component 52.12
Overall RatingsPrevious Rating Current Rating
Progress towards achievement of PDO Moderately Satisfactory Moderately Sat isfactory
Overall Implementation Progress (IP) Moderately Satisfactory Moderately Sat isfactory
Overall Risk Rating
Implementation Status Overview
The project is nearing completion of physical works and governance reforms being undertaken by 10 urban local governments (ULGs). The investment subprojects are mostly aimed
at upgrading and rehabilitating public markets, and have already provided better, cleaner, and more modern facilities for vendors and customers, and increased revenues foroperation and maintenance. The ULGs have also strengthened governance by improving transparency and accountability, systematically disclosing public information, establishing
complaints handling mechanisms, evaluating performance of contractors/suppliers, improving financial management regulations and systems, and f inalizing the national urban
strategy, policy, and economic development plans.
-
7/27/2019 URDSP Sequence 011
2/10
The World Bank
Page 2 of 10
PublicDisclosureCopy
PublicDisclosureCopy
Report No: ISR8029
Locations
Country First Administrative Division Location Planned Actual
Indonesia Not Entered Kotamadya Yogyakarta
Indonesia Not Entered Toboli
Indonesia Not Entered Propinsi Sulawesi Tengah
Indonesia Not Entered Kabupaten Sidenreng-Rapang
Indonesia Not Entered Kotamadya Semarang
Indonesia Not Entered Kotamadya Parepare
Indonesia Not Entered Kota administratip Palu
Indonesia Not Entered Palopo
Indonesia Not Entered Kabupaten Musibanyuasin
Indonesia Not Entered Kabupaten Manokwari
Indonesia Not Entered Mangkang
Indonesia Not Entered Kota Administratip Cimahi
Indonesia Not Entered Kotamadya Blitar
Indonesia Not Entered Kemirimuka
Indonesia Not Entered Kecamatan Gamping
Indonesia Not Entered Kabupaten Sleman
Indonesia Not Entered Desa Umbulharjo
Indonesia Not Entered Kecamatan Pangkajene
Indonesia Not Entered Kotamadya Depok
Indonesia Not Entered Kecamatan Moutong
Indonesia Not Entered Lakessi
Results
Project Development Objective Indicators
-
7/27/2019 URDSP Sequence 011
3/10
The World Bank
Page 3 of 10
PublicDisclosureCopy
PublicDisclosureCopy
Report No: ISR8029
Indicator Name Core Unit of Measure Baseline Current End Target
Increased revenue, operations and
maintenance expenditures, and satisfactionrates among users and consumers of selected
urban services in at least 70% of ULGs withcompleted subprojects
Percentage Value 0.00 30.00 70.00
Date
Comments
18-Jan-2006
Overall ULG target (70%) is
based on achievement of four
sub-indicators that each havetheir own targets, and are inturn determined by individual
baselines and valuesachieved for each subproject.
At inception of the project,overall baseline is zero as the
project investments have notyet taken place.
18-Jul-2012
30 % ULG have increased
monthly revenue. At least
another 30 % ULGs arepreparing the USDRP-financed infrastructure to
operation. tThe PBME for assessing
users revenue andsatisfaction will be prepared
prior project closing.However, 10% ULGs have
carried out satisfaction surveyto traders and resulted that
more than 50% traders satisfyto the facilities provided and
the use of infrastructure
31-May-2013
Target value is the
percentage of participating
ULGs with completedinvestment sub-projects thathave achieved the individual
goalsin each of the four sub-indicators.
70% of ULGs increase their local revenue fromurban services financed by the project by at
least 10%
Percentage
Sub Type
Breakdown
Value 0.00 30.00 70.00
Date
Comments
18-Jan-2006
Sub-indicator based onindividual baselines for each
ULG and subproject. Data arecollected through municipal
records on revenues fromeach facility or service.
18-Jul-2012
30 % ULG have increasedmonthly revenue. At least
another 30 % ULGs arepreparing the USDRP-
financed infrastructure tooperation
31-May-2013
Percentage of ULGs withcompleted subprojects that
have met the revenue target.
70% of ULGs increase expenditures for O&Mof infrastructure financed by the project by at
least 10%
Percentage
Sub Type
Breakdown
Value 0.00 0.00 70.00
Date
Comments
18-Jan-2006
Sub-indicator based onindividual baselines for each
ULG and subproject. Data arecollected through municipal
records on O&M expendituresfor each service infrastructure
financed by the project.
18-Jul-2012
Seven ULGs have completedsubprojects in which five
ULGs have subprojects inoperation, but data on O&M
expenditures is not yetavailable.
31-May-2013
Percentage of ULGs withcompleted subprojects that
have met the O&Mexpenditure target.
Percentage of ULGs in which at least 50% ofusers express increased satisfaction in doing
business in the improved facility.
Percentage
Sub Type
Breakdown
Value 0.00 0.00 70.00
Date
Comments
18-Jan-2006
Baseline is zero because thetarget is based on percentage
of ULGs meeting targets for
18-Jul-2012
Data will be collected throughan impact assessment
(PBME) conducted either a
31-May-2013
Percentage of ULGs withcompleted subprojects that
-
7/27/2019 URDSP Sequence 011
4/10
The World Bank
Page 4 of 10
PublicDisclosureCopy
PublicDisclosureCopy
Report No: ISR8029
user satisfaction in facilitiesthat were not yet improved
and in some cases notidentified. Increased
satisfaction for individualsubprojects will not include
and ex-ante baseline butrather through a survey of
current users who also wereusers of the unimproved
infrastructure. "Users" refersto vendors orother
stakeholders that use thefacilities improved through
project investments toconduct business activities
and provide commercialservices.
year after each subproject'sinfrastructure becomes
operational, or at the close ofthe project. However, 10%
ULGs have carried outsatisfaction survey to traders
and resulted that morethan50% traders satisfy to the
facilities provided and the useof infrastructure
have met the user satisfactiontarget.
Percentage of ULGs in which at least 50% of
consumers express increase satisfaction ofusing the facilities
Percentage
Sub Type
Breakdown
Value 0.00 0.00 70.00
Date
Comments
18-Jan-2006
Baseline is zero because thetarget is based on percentage
of ULGs meeting targets forconsumer satisfaction in
facilities that were not yetimproved and in some cases
not identified. Increasedsatisfaction for individual
subprojects will not includeand ex-ante baseline but
rather through a survey of
current consumers who alsowere consumers of theservices before they were
improved. "Consumers" refersto customers of vendors or
recipients of servicesprovided through the facilities.
18-Jul-2012
Data will be collected throughan impact assessment
(PBME) conducted either ayear after each subproject's
infrastructure becomesoperational, or at the close of
the project. However, 10%ULGs have carried out
satisfaction survey to tradersand resulted that morethan
50% traders satisfy to the
facilities provided and the useof infrastructure
31-May-2013
Percentage of ULGs withcompleted subprojects that
have met the consumersatisfaction target.
Intermediate Results Indicators
-
7/27/2019 URDSP Sequence 011
5/10
The World Bank
Page 5 of 10
PublicDisclosureCopy
PublicDisclosureCopy
Report No: ISR8029
Indicator Name Core Unit of Measure Baseline Current End Target
Participating ULGs have public feedback
mechanisms in place incl:(i) the use of at leastone type of media(s) for public complaints-
managed by complaint handling unit; (ii)availability
Text Value 0.00 (i) 70%; (ii) 100%; (iii) 70% 80
Date
Comments
18-Jan-2006
At the inception of the project,
baseline was zero as the
project has not started itsfacilitation and values varyacross ULGs. Information is
collected during thesupervisions missions and
recorded in the AideMemoires with qualitative
information on the progress.Indicators were only specified
in June 2010 during projectrestructuring.
18-Jul-2012
70 % ULGs have a systematic
use of media for managing
complaints and feedback100 % ULGs have specificunit to manage
70 % ULGs have SOP ofcomplaints handling
31-May-2013
Participatory planning process: (i) allocation of
block grants to kecamatan and/or kelurahan
from the ULG and/or from at least oneagencywith Standard Operating Procedure for the useof block grants
Text Value 0.00 70% ULGs has block grant
mechanism or indicative
budget
50
Date
Comments
18-Jan-2006
At the inception of the project,baseline was zero as the
project has not started itsfacilitation and values vary
across ULGs. Information iscollected during the
supervisions missions andrecorded in the Aide
Memoires with qualitativeinformation on the progress.
Indicators were only specifiedin June 2010 during project
restructuring.
18-Jul-2012
70% ULGs has block grantmechanism or indicative
budget
31-May-2013
Participating ULGs practicing sound Fin. Mgt:(i) issuance of local regulation (PERDA or
Decree or Perbup/Perwal) on Principle ofRegional Financial Management; (ii) Issuance
of local regulation
Text Value 0.00 9i) 100%; (ii) 100%; and (iii)70%
80
Date
Comments
18-Jan-2006
At the inception of the project,baseline was zero as the
project has not started itsfacilitation and values vary
across ULGs. Information iscollected during the
18-Jul-2012
100 % ULGs have localregulation concerning the
Principle of Regional Finance100% ULGs have local
regulation concerningPolicies, Systems, and
31-May-2013
-
7/27/2019 URDSP Sequence 011
6/10
The World Bank
Page 6 of 10
PublicDisclosu
reCopy
PublicDisclosureCopy
Report No: ISR8029
supervisions missions andrecorded in the Aide
Memoires with qualitativeinformation on the progress.
Indicators were only specifiedin June 2010 during project
restructuring.
Procedures for thePreparation and Execution of
APBD70 % ULGs published annual
audited financial report
Center of Excellence: (i) Unit Informasi
Pembangunan Permukiman dan Bangunan(UIP2B) functioned as a Prov. Center of
Excellence to support reforms in the ULGs inthe province; (ii) Work Plan for
Text Value 0.00 1 PIP2B is established.
Organizational structure andbudget are available, and
annual work plan is issued
Center of Excellence: at least
1 Province has (i) and (ii)Local Economic Development
and City DevelopmentStrategy: At least 60%of
Partic ipating ULGs have (i)and at least 50% of
Participating ULGs having theLED-focu sed City
Development Strategyachieve (ii)
Date
Comments
18-Jan-2006
At the inception of the project,
baseline was zero as theproject has not started its
facilitation and values varyacross ULGs. Information is
collected during thesupervisions missions and
recorded in the AideMemoires with qualitative
information on the progress.Indicators were only specified
in June 2010 during project
restructuring.
18-Jul-2012
1 PIP2B is established.
Organizational structure andbudget are available, and
annual work plan is issued
31-May-2013
Participating ULGs implemented subprojects:(i) Participating ULGs sign Sub- project Loan
Agreements (SLAs) with Ministry of Finance forurban investment subprojects; (ii) Participating
ULGs complete
Text Value 0.00 (i) 10 ULGs; (ii) 7 ULGs (i) 100% of ParticipatingULGs signed SLAs (ii) At
least 80% of ParticipatingULGs completed construction
of urban investmentsubproject
Date
Comments
18-Jan-2006
At the inception of the project,
baseline was zero as theproject has not started its
facilitation and values vary
across ULGs. Information is
18-Jul-2012
100 % ULGs have signed
SLA70 % ULGs have completed
subproject construction
31-May-2013
-
7/27/2019 URDSP Sequence 011
7/10
The World Bank
Page 7 of 10
PublicDisclosu
reCopy
PublicDisclosureCopy
Report No: ISR8029
collected during thesupervisions missions and
recorded in the AideMemoires with qualitative
information on the progress.Indicators were only specified
in June 2010 during projectrestructuring.
Participating ULGs practicing soundProcurement: (i) Min. 75% of the bids be
awarded within the bid validity period, andpublicizedin the public domain, e.g. website,
local bulletin; (ii) Min 50% of
Text Value 0.00 i) 90%; (ii) 100%; (iii) 30% inprogress
At least 60 % of participatingULGs achieve (i) and (ii) and
at least 60% of participatingULGs achieve (iii)
Date
Comments
18-Jan-2006
At the inception of the project,
baseline was zero as theproject has not started its
facilitation and values varyacross ULGs. Information is
collected during thesupervisions missions and
recorded in the AideMemoires with qualitative
information on the progress.Indicators were only specified
in June 2010 during projectrestructuring.
18-Jul-2012
awarded the bids within bid
validity period, however only90% of ULGs published the
bid award in the publicdomain, e.g. website, local
bulletin(ii) 100% ULGs have national
certified tender committee(iii) At least 30% ULGs are
preparing institutions andmechanism for giving award
to best-performers
31-May-2013
Transparency, Participation and Accountability:ULGs that post semi-annual updates on
websites or in printed media for specifiedinformation
Percentage Value 0.00 90.00 80.00
Date
Comments
18-Jan-2006
At the inception of the project,baseline was zero as the
project has not started itsfacilitation and values vary
across ULGs. Information iscollected during the
supervisions missions andrecorded in the Aide
Memoires with qualitativeinformation on the progress.
Indicators were only specifiedin June 2010 during project
restructuring.
18-Jul-2012
Value: varies across ULGs,range from 70-100% for six
types of specified informationhave been published in
websites or in printed media(details are shown in the
following six indicators below)
31-May-2013
Value: At least 80% ofparticipating ULGs post the
specified information at sixmonths intervals
-
7/27/2019 URDSP Sequence 011
8/10
The World Bank
Page 8 of 10
PublicDisclosu
reCopy
PublicDisclosureCopy
Report No: ISR8029
Transparency, Participation and Accountability:
ULGs that post semi-annual updates onwebsites or in printed media for information on
local development activities/programs
Percentage Value 0.00 90.00 80.00
Date
Comments
18-Jan-2006
At the inception of the project,
baseline was zero as theproject has not started its
facilitation and values vary
across ULGs. Information iscollected during thesupervisions missions and
recorded in the AideMemoires with qualitative
information on the progress.Indicators were only specified
in June 2010 during projectrestructuring.
18-Jul-2012
100% ULGs published local
development activities/programs on the website or
printed media
31-May-2013
Value: At least 80% of
Participating ULGs post theinformation on local
development activities/
programs at six monthintervals
Transparency, Participation and Accountability:
ULGs that post semi-annual updates onwebsites or in printed media for specified
information: Mid-term development Plan(RPJMD)
Percentage Value 0.00 80.00 80.00
Date
Comments
18-Jan-2006
At the inception of the project,
baseline was zero as theproject has not started its
facilitation and values varyacross ULGs. Information is
collected during thesupervisions missions and
recorded in the AideMemoires with qualitative
information on the progress.Indicators were only specified
in June 2010 during projectrestructuring.
18-Jul-2012
90% ULGs published
summary RPJMD on thewebsite or printed media
31-May-2013
Value: At least 80% of
Participating ULGs post theinformation on RPJMD at six
month intervals
Transparency, Participation and Accountability:ULGs that post semi-annual updates on
websites or in printed media for specifiedinformation: summary of Local Budget (APBD)
Percentage Value 0.00 60.00 80.00Date
Comments
18-Jan-2006
At the inception of the project,baseline was zero as the
project has not started itsfacilitation and values vary
across ULGs. Information iscollected during the
supervisions missions andrecorded in the Aide
Memoires with qualitativeinformation on the progress.
Indicators were only specified
18-Jul-2012
70% ULGs publishedsummary of local budget of
the ongoing FY, and 60%published summary of budget
realization of previous FY
31-May-2013
Value: At least 80% ofParticipating ULGs post the
information on the summaryof APBD at six month
intervals
-
7/27/2019 URDSP Sequence 011
9/10
The World Bank
Page 9 of 10
PublicDisclosu
reCopy
PublicDisclosureCopy
Report No: ISR8029
in June 2010 during projectrestructuring.
Data on Financial Performance (as of 09-Oct-2012)
Financial Agreement(s) Key Dates
Project Ln/Cr/Tf Status Approval Date Signing Date Effectiveness Date Original Closing Date Revised Closing Date
P071296 IBRD-47860 Effective 07-Jun-2005 20-Oct-2005 18-Jan-2006 30-Jun-2011 31-May-2013
P071296 IBRD-77600 Effective 06-Jul-2009 06-Jul-2009 06-Jul-2009 30-Jun-2011 31-May-2013
P071296 TF-53555 Effective 20-Oct-2005 20-Oct-2005 18-Jan-2006 30-Jun-2011 31-May-2013
Disbursements (in Millions)
Project Ln/Cr/Tf Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed
P071296 IBRD-47860 Effective USD 45.00 45.00 0.00 0.00 0.00 0.00
P071296 IBRD-77600 Effective USD 45.00 38.44 6.57 34.64 3.80 90.00
P071296 TF-53555 Effective USD 5.00 5.00 0.00 4.26 0.74 85.00
Disbursement Graph
Key Decisions Regarding Implementation
The next supervision mission is scheduled for December 2012. It will include discussion of final steps to complete unfinished works and activities prior to project closing, and plans forensuring the long-term sustainability of project investments.
-
7/27/2019 URDSP Sequence 011
10/10
The World Bank
Page 10 of 10
PublicDisclosu
reCopy
PublicDisclosureCopy
Report No: ISR8029
Restructuring History
Level one Approved on 04-Jun-2010, Level two Approved on 13-Apr-2011, Level two Approved on 14-Jun-2012
Related Projects
There are no related projects.