Urban Sanitation in Vietnam: Challenges Ahead
-
Upload
adbwaterforall -
Category
Documents
-
view
214 -
download
0
Transcript of Urban Sanitation in Vietnam: Challenges Ahead
8/6/2019 Urban Sanitation in Vietnam: Challenges Ahead
http://slidepdf.com/reader/full/urban-sanitation-in-vietnam-challenges-ahead 1/20
Urban Sanitation in Vietnam:
Challenges Ahead
Taro Katsurai,
Senior Specialist,
International Development Associates, [email protected]
Manila, June 29th, 2011
8/6/2019 Urban Sanitation in Vietnam: Challenges Ahead
http://slidepdf.com/reader/full/urban-sanitation-in-vietnam-challenges-ahead 2/20
Contents
Introduction
Issue 1: Scaling up
Issue 2: Institutional reforms
Summary and way forward
8/6/2019 Urban Sanitation in Vietnam: Challenges Ahead
http://slidepdf.com/reader/full/urban-sanitation-in-vietnam-challenges-ahead 3/20
1. Introduction: Urban Sanitation in VN
Brief overview Most urban area is flat and located in low altitude: vulnerable to sea
tide and flooding. Extensive combined sewers in most cities. Septic tanks are installed in most HH; greywater goes to the sewer
directly, blackwater to the septic tanks. But STs are not well built nor well maintained
Almost no WWTP at the end of the combined sewer system.(serviced population around 7%)
Government Goal: Percentage of treated urban wastewater (Prime Minister Decision No. 1930/2009) 2015: 40-50% 2020: 60% 2025: 70-80%
12 bil USD over the next 15 years.(WB estimation)
Sewer
8/6/2019 Urban Sanitation in Vietnam: Challenges Ahead
http://slidepdf.com/reader/full/urban-sanitation-in-vietnam-challenges-ahead 4/20
1. Introduction: Urban Sanitation in VN
How can we assist GoV in achieving theseambitious targets?
Intuitively, Scaling up financial assistances.
Catalyzing private finance
Building technical and institutional capacity inparallel
Empirically? Topic of today¶s presentation
8/6/2019 Urban Sanitation in Vietnam: Challenges Ahead
http://slidepdf.com/reader/full/urban-sanitation-in-vietnam-challenges-ahead 5/20
2. Scaling up
Map of 15th century Hanoi Hanoi in 1990s
8/6/2019 Urban Sanitation in Vietnam: Challenges Ahead
http://slidepdf.com/reader/full/urban-sanitation-in-vietnam-challenges-ahead 6/20
2.1 Hanoi: context
Drainage and Sewerage Master Plan (1993-1995) Target year: 2020 (25 years from 1995)
Serviced population: all inner city (around 1.5 mil)
Total cost: around 1 bil USD
Accordingly, series of loans were providedbetween 1995 to 2010 totaling 50.9 bil JPY (630
mil USD)
8/6/2019 Urban Sanitation in Vietnam: Challenges Ahead
http://slidepdf.com/reader/full/urban-sanitation-in-vietnam-challenges-ahead 7/20
Map of Hanoi Water
Environment Project Phase 1
and Phase 2
8/6/2019 Urban Sanitation in Vietnam: Challenges Ahead
http://slidepdf.com/reader/full/urban-sanitation-in-vietnam-challenges-ahead 8/20
2.2 Hanoi: Where are we now?
Progress Phase 1: completed but delayed for nearly 5 years.
Phase 2: construction has not even started but already
behind by 2.5 years.
Current treatment capacity Around 7,800 m3/day
Serviced population: 25,000
8/6/2019 Urban Sanitation in Vietnam: Challenges Ahead
http://slidepdf.com/reader/full/urban-sanitation-in-vietnam-challenges-ahead 9/20
9
2.3 Performance of Sewerage Projects ( 1)
* WWTP Capacity will be increased to 469,000 m3/day
* The largest WWTP in Tokyo is 629,130m3/day
Project WWTP Capacity(m3/day)
ServicePopulation
Hanoi 40,000 (2006)3,000 (2005)
4,800 (2005)13,300 (2013)
9,743
16,02841,200
HCMC 141,000 (2008)*469,000 (2015)
1,422,000
Hai Phong 36,000 (2015) 240,000
Binh Duong 17,560 (2013) 174,650
Vinh Phuc 5,000 (2014) 26,440
Hue 20,000 (2015) 145,600
What about the other cities?
8/6/2019 Urban Sanitation in Vietnam: Challenges Ahead
http://slidepdf.com/reader/full/urban-sanitation-in-vietnam-challenges-ahead 10/20
6WDQGDUG
+DQRL3KDVH
+&0&3KDVH
+DQRL3KDVH
+&0&3KDVH
+DLSKRQJ
%LQK'XRQJ
9LQK3KXF
+XH
\HDUV
3URFXUHPHQWRI&6 ''DQGSURFXUHPHQWRI&RQWUDFWRU &RQVWUXFWLRQ
2.3 Performance of Sewerage Projects ( 2 )
In fact, delay is not just a characteristic of Hanoi but ALLsewerage projects.
8/6/2019 Urban Sanitation in Vietnam: Challenges Ahead
http://slidepdf.com/reader/full/urban-sanitation-in-vietnam-challenges-ahead 11/20
6HZHUDJH
¡
RZHU
7UDQVSRUW
\HDUV
¡
URFXUHPHQWRI&6 ''DQGSURFXUHPHQWRI&RQWUDFWRU
2.3 Performance of Sewerage Projects ( 3)
Is it the characteristic of Vietnam? No, power and transport projects perform much better. (*not enough
data to compare construction schedule)
33&DOO
027(91
\HDUV
3URFXUHPHQWRI&6 ''DQGSURFXUHPHQWRI&RQWUDFWRU
It is the characteristic of PPC projects.
8/6/2019 Urban Sanitation in Vietnam: Challenges Ahead
http://slidepdf.com/reader/full/urban-sanitation-in-vietnam-challenges-ahead 12/20
2.3 Performance of Sewerage Projects (5 )
Why are sewerage projects slow? Physical
Covers a large surface area
Conducted in urban area
Institutional Local governments (PPCs) have minimum experience
handling large scale, ICB projects.
Harm of lack of experience Unclear demarcation of responsibilities between
agencies -> slow approval procedures. Inappropriate bidding contents -> bidding failures
Lack of understanding to ³changes´ (variation order,additional quantities, price adjustment) -> disputes ->delay of construction.
8/6/2019 Urban Sanitation in Vietnam: Challenges Ahead
http://slidepdf.com/reader/full/urban-sanitation-in-vietnam-challenges-ahead 13/20
2.4 Way forward
Conclusion Before ³scaling up´ financial assistances or discussing
about efficient operations, we need to strengthen
project implementation capacity of the local
governments.
What can we do?
Procurement training
FIDIC training
Trainings should target approval agencies and
inspection agencies also.
Facilitate knowledge transfer from Ministries to
Provinces.
%
L
O
-
3
<
$¢ ¢ £
& RP P LWP HQW $¢ ¢ £
'LVE
8/6/2019 Urban Sanitation in Vietnam: Challenges Ahead
http://slidepdf.com/reader/full/urban-sanitation-in-vietnam-challenges-ahead 14/20
4. Institutional Reforms for Sustainable
Management and Operation
Binh Hung WWTP in HCMC (capacity 141,000m3/day, financed by JICA)
8/6/2019 Urban Sanitation in Vietnam: Challenges Ahead
http://slidepdf.com/reader/full/urban-sanitation-in-vietnam-challenges-ahead 15/20
4.1 Institutional Reforms and HCMC
Background To create an enabling environment for private financing
To ensure sustainability of the management and operation of thesewerage facilities
Activities
Development of sewerage management
decree and circular
Capacity building (administrative,
management )
Capacity building (technical)
Central Gov.
Local Gov.
O&M Entity
8/6/2019 Urban Sanitation in Vietnam: Challenges Ahead
http://slidepdf.com/reader/full/urban-sanitation-in-vietnam-challenges-ahead 16/20
4.2 Sewerage Management Institutions
Local Gov.
(PPCs)
& Entity
Before Decree 88/2007
Local Gov.
(PPCs)
& Entity
Performance Based
Management Contract
(direct appointment or Open bidding)
Decree 88/2007 clearly defined: the roles and functions of stakeholders including the clear
separation of asset owner and operator.
the nature of the relationship between asset owner andO&M organization = performance based managementcontract
the principle of cost recovery and allowed setting seweragetariffs accordingly. (Before it was constrained to below 10%
of water tariff)
8/6/2019 Urban Sanitation in Vietnam: Challenges Ahead
http://slidepdf.com/reader/full/urban-sanitation-in-vietnam-challenges-ahead 17/20
4.3 Administrative Capacity Building
Application of Decree 88/2007 in HCMC Step 1:
Establishment of an administrative body to manage sewerage systems.
Step 2: Administrative capacity building of that entity (management information
system, sewerage ledgers, asset management systems, tariff
calculation, etc.) Preparation of performance based management contract.
Step 3: Committed back-finance for management contract
Local Gov.
(PPCs)
& Entity
(Public)
Performance Based
Management Contract
Sewerage
Administrator
& Entity
(Private)
Performance Based
Management Contract
8/6/2019 Urban Sanitation in Vietnam: Challenges Ahead
http://slidepdf.com/reader/full/urban-sanitation-in-vietnam-challenges-ahead 18/20
4.4 What happened?
What happened? Management contract was ready, back-finance ready, private
company eager to participate, but« the two sides could not cometo an agreement.
Why? (personal view«) Lack of technical understanding.
Many unreasonable requests: request to treat heavy metal
Could not evaluate the appropriateness of the proposed methodology andproposed cost.
Lessons Keep aware that sewerage system management is still new in
Vietnam.
Capacity building of both the administrative side (the owner) andthe operator side is necessary.
Even the administrative side require technical knowledge.
8/6/2019 Urban Sanitation in Vietnam: Challenges Ahead
http://slidepdf.com/reader/full/urban-sanitation-in-vietnam-challenges-ahead 19/20
5. Summary and Conclusion
Observation Large need to expand sewerage systems but the current
bottleneck is NOT financing but project execution.
Raising the capacity of the administrator/owner of the seweragesystem is crucial to the sustainability of the system and the
involvement of the private sector.
(Bold) prescription towards a sustainable seweragesector STEP 1: Strengthen project execution capacity.
STEP 2: Strengthen technical capacity (these technical peoplebecomes the resource pool of the administrator)
STEP 3: Strengthen administrative capacity
STEP 4: PPP
8/6/2019 Urban Sanitation in Vietnam: Challenges Ahead
http://slidepdf.com/reader/full/urban-sanitation-in-vietnam-challenges-ahead 20/20
Thank you