Commercialization of UBC ® Process Shohei Manabe Executive Officer Head of Coal & Energy Division Head of Iron Unit Division Natural Resources & Engineering Business Kobe Steel, Ltd. -Upgrading the Future-

Transcript of -Upgrading the Future - Commercialization of UBC Process

Commercialization of UBC® Process

Shohei Manabe Executive Officer

Head of Coal & Energy Division Head of Iron Unit Division

Natural Resources & Engineering Business Kobe Steel, Ltd.

-Upgrading the Future-

Agenda

• Company Profile • Kobe Steel’s approach to low-quality

natural resources utilization • UBC Process • Commercialization of UBC

-Upgrading the Future-

Company Profile

• Kobe Steel is known as KOBELCO – A steel, aluminum, copper and machinery producer as well as

engineering company and coal-based power supplier (1400MW)

• Now focusing on low-grade natural resource utilization

– UBC Process – New ironmaking technology (pellet feed + steaming coal)

Kobe Steel’s approach to utilize low-quality natural resources

<Iron-making> • Pellet utilization in BF instead of lump ore 1966~ • Pulverized coal injection to BF 1980~ • FASTMET direct reduced ironmaking 1992~ • ITmk3 iron nugget making 1994~

<Energy industry> • Coal liquefaction in China 1939-1944 • Coal liquefaction in Australia 1981-1993 • UBC process development 1990~ • Hyper Coal process development 1999~

’81~: After the 2nd oil crisis, Brown Coal Liquefaction (BCL) project was started in Australia & Japan. (AC, 0.1t/d PDU, 50t/d Pilot Plant Operation) ’93~:Follow-up Studies in Japan (AC, 0.1t/d BSU Operation) ’99~:Indonesian BCL Feasibility Study ’04~:Follow-up Studies on Indonesian BCL ’08~:US PRB Coal Liquefaction Project

Catalyst Hydrogen

Gasoline Kerosene Gas-oil

H/C ratio: 0.8 H/C ratio: 1.5~2

Coal Liquefaction

Coal

450℃ 15MPa

Coal is hydrocracked & hydrogenated at high temperature and pressure to obtain liquid fuel.

50t/d PP (Morwell, Australia)

Over flow

Extraction temp 350-400℃

Slurry Making

Solvent extraction coal

Solid-Liquid

separation Solvent recovery

Solvent recovery settler

Hyper-Coal (HPC) Process Extracted Coal

HPC Over flow

Under flow

HPC

① Solvent recycled ② No hydrogen used ③ Low temperature, low pressure

Additive of coke for blast furnace

Residue

RC

Excellent thermal plasticity

HPC process

High Strength Coke

COAL

+ HPC

UBC Process

• Basic Concept • R&D Project in Indonesia • Process Description • Commercialization

-Upgrading the Future-

Basic Concept of UBC

Turn Un-utilized Low Quality Lignite into

High-Value Energy Resource

-Upgrading the Future-

Lignite & UBC spec.

Coal (Indonesian Lignites)

Type A Type B Type C

Raw UBC Raw UBC Raw UBC

Moisture wt% ar 33.6 <10 34.0 <10 60.5 <10

Heating Value kcal/kg 4,460 6,380 4,200 5,810 2,328 6,020

Ash wt%db 2.5 2.7 4.6 4.6 7.7 7.8

Volatile Matter wt%db 51.2 52.5 48.5 50.9 43.3 47.3

Fixed Carbon wt%db 46.3 44.8 46.9 44.5 34.2 38.6

Sulfur wt%db 0.48 0.49 0.17 0.19 0.26 0.27

-Upgrading the Future-

Process Flow

-Upgrading the Future-

Demonstration Project

• Capacity: 600 t/day on product basis (1,000 t/day on feed coal basis)

• Location: Satui, South Kalimantan • Coal run: from December 2008 to May 2011 • Raw coal: Arutmin Ecocoal (TM=35%)

Kalimantan

Java Pilot Plant (3t/d) 14

-Upgrading the Future-

R&D Project Structure <Japan – Indonesia GG-based R&D Project>

Participate as assigned entity

MOU

Strong Support

Kobe Steel PT Bumi Resources

PT Arutmin

MEMR Ministry of Energy and Mineral

Resources

Japan Indonesia METI

Ministry of Economic Trade and Industry

JCOAL Japan Coal Energy Center

Demonstration Plant

16

-Upgrading the Future-

Results of R&D Project

• Development of the UBC Process was successfully completed.

• Combustion and transportation tests were successfully conducted.

• Scaled up information was collected. • Capital and operation cost data were collected. • Several research subjects were found and

studies are underway.

-Upgrading the Future-

Towards Commercialization

-Upgrading the Future-

Commercialization Concept Lignite

<Disadvantages> •Low CV •Spontaneous combustion

<Advantages> •Widely spread in the world •Huge reserve •Cheap mining cost

Technology (UBC)

•Increase CV •Stabilize

Stable Energy Source •Stable Supply •Stable Cost

+

=

-Upgrading the Future-

Location and Client

Target Areas

Where will we built UBC plants?

Target clients With whom are we having discussions?

-Upgrading the Future-

Canada(6 .6bi l . t )

13%

53%34%

U.S.A .(237,3bi l .t)

42%

45%13%

China(114.5bi l .t)

16% 55%

29%

India(60.6bi l .t)

7%

93%

Indones ia(5.5bi l .t)

20%27%

53%

Others (As ian) (47.6bi l .t)

2%

52%46%

Austra l i a (76.4bi l .t)

49% 48%

3%

Russ ia(157bi l .t)

3% 33%

62%Europe(108bi l .t)

17%20%

63%

South Africa(30.2bil .t)

100%

Others (Africa)(1.5bil .t)

89%11%

Bitumino

us

Lignite

Sub-Bitumin

ous

Others(South Amer ica)(5 .8bi l . t )9% 0%

Colombia (6.8 bil.t)

Target Areas

<First priority area> • Indonesia <Second priority area> • India • China <Third priority area> • Australia • Russia

-Upgrading the Future-

Candidate Clients / Partners

• Mine owners who want to sell high-moisture lignite, which has no

commercial value now.

• Power utility companies who want to have a stable price & source of energy.

• Traders who want to use UBC as a calorie booster.

-Upgrading the Future-

UBC Application

<Briquette form: moisture 8-10%, 6000kcal/kg) • Ocean or rail transport for long distance • Mix with LRC as calorie booster

<Powder form: moisture 0%, 6670kcal/kg> • Direct feed to mine-mouth power plant • Feed to UBC power (including IGCC) plant in

distant location

-Upgrading the Future-

Project coming up

• F/S for 1st Commercial Plant is now in progress with PT DH Energy (Bumi Gr.) and an Asian power utility.

• The project is in Pendopo, South Sumatra. • We are also having discussions with several

lignite mine owners in Indonesia and in other countries.

-Upgrading the Future-

KOBELCO’s business scheme

• EPC Business

• License Business – Construction License to engineering company – Production License to producer of UBC

• UBC Production Business

– For Captive Use – For Merchant Sale

-Upgrading the Future-

Conclusion

• Kobe Steel has completed R&D of the UBC Process. The Process has now reached the commercialization stage.

• The UBC process gives calorific and commercial value to un-utilized lignite, which is available all over the world.

• The UBC process has various applications beside briquette export.

• A feasibility study for a 5-million-ton project in Sumatra is now under way.

• Kobe Steel is ready to discuss commercial projects with mine owners, power utility companies, traders and engineering companies.

-Upgrading the Future-

Thank you