UPDATING THE SCHEDULE OF MAXIMUM TAXI FARES … · Clause 6 – CityLink and EastLink tolls
Updating a Schedule
Transcript of Updating a Schedule
-
8/6/2019 Updating a Schedule
1/53
Updating a Schedule
December 13, 2007
Chris Carson, PSPProject Controls Manager
Alpha [email protected]
-
8/6/2019 Updating a Schedule
2/53
Schedule UpdatingDetermine Frequency of UpdatesData Collection
Status ScheduleCalculateCheck for Out-of-Sequence WorkVerify ScheduleAnalysis On Time CompletionHistorical Trending & StatisticsAnalysis Late Completion
Reporting - InternalNarrative External Reporting
-
8/6/2019 Updating a Schedule
3/53
Schedule Updating
Determine Frequency of Updates
-
8/6/2019 Updating a Schedule
4/53
Schedule Updating
Frequency of UpdatesBased on schedule purpose
Management tool
Meeting a specification requirementInternal reporting and predictionsLimited management use
BudgetBased on size of scheduleLarge schedule requires frequent updatesOverview schedule allows fewer updates
-
8/6/2019 Updating a Schedule
5/53
Schedule UpdatingData Collection
-
8/6/2019 Updating a Schedule
6/53
Schedule UpdatingData Collection
Field information should be kept on a daily basisActual Start DatesActual Finish DatesPredicted Finish for any activity started but not finished
Percent Complete if schedule is cost loadedUse Remaining Duration, not Percent Complete, for timereporting
Superintendents cannot provide accurate PercentComplete
Superintendents cannot provide accurate RemainingDurations
Recommend Superintendents walk job with update report
-
8/6/2019 Updating a Schedule
7/53
Schedule UpdatingStandard Field Update Report
-
8/6/2019 Updating a Schedule
8/53
Schedule UpdatingData Collection
Office informationGather status of buyout process; purchase orders &subcontracts what is not bought outGather Submittal & Approval status
Gather status of administrative tasks Utility paperwork status Permits site, building, right-of-way, Health Department Environmental releases, etc.
Gather status of materials fabrication and order time - LeadTime
-
8/6/2019 Updating a Schedule
9/53
Schedule UpdatingData Collection
Owner informationGather Status of Owner controlled activities
Owner utility applications & progress- Electricity
- Gas service- Water & sewer- Telephone- Cable or data- Security system
Delivery dates for Owner furnished equipment Other Owner contractual work Verify coordination with Owner work
-
8/6/2019 Updating a Schedule
10/53
Schedule UpdatingData Collection
Subcontractor informationGather Status of subcontractor activities
Lead Times for subcontractors materials Lead Times for subcontractors equipment
Lead Times for subcontractor mobilization on job (field?)- Are they committed to scheduled start date?- Are the other trades out of the work area?- What is the materials lay-down area availability?
Resource availability for subcontractors- Do the subcontractors have adequate workmen on site?
-
8/6/2019 Updating a Schedule
11/53
Schedule UpdatingStatus Schedule
-
8/6/2019 Updating a Schedule
12/53
Schedule UpdatingStatus Schedule
Simple progress stage of processMake no logic changes during this stage, only progressUse standard input layout to record progressInput Actual Start and Finish DatesChoose Data Date use last actual dates providedIf activities are started, set Remaining Durations sopredicted finish dates are met
-
8/6/2019 Updating a Schedule
13/53
Schedule UpdatingCalculate Schedule & Check for Out-of-Sequence
Work
-
8/6/2019 Updating a Schedule
14/53
Schedule UpdatingCalculate Schedule
Ensure software setting is Retained LogicSet Data Date to date chosen during ScheduleStatus stageCalculate schedule
Check for Out-of-Sequence WorkChange setting temporarily to Progress OverrideIf the completion date changes significantly, thenthere is a lot of out-of-sequence work needingcorrectingIf minimal change, no significant out-of-sequencework
Change the setting back to Retained Logic (default)
-
8/6/2019 Updating a Schedule
15/53
Schedule UpdatingVerify Schedule
-
8/6/2019 Updating a Schedule
16/53
Schedule UpdatingVerify Schedule
Internal verificationCheck that Early Finish dates match predicted finish datesprovided by SuperintendentCheck on any out-of-sequence work to see if those dateswere input correctly
External verificationChange to verification layout
Two week look-ahead filter (only starts & finishes within
2W) Send to Superintendent to verify that Early Start dates for
planned activities for the next two weeks are accurate Get feedback & correct any discrepancies
This is a reasonableness check, look it over
-
8/6/2019 Updating a Schedule
17/53
Schedule UpdatingPrepare for Schedule Analysis
-
8/6/2019 Updating a Schedule
18/53
Schedule UpdatingPrepare for Schedule Analysis
Use standard Layout with comparison to lastupdateCheck for slippage in Substantial Completion
dateIf no slippage, project predicts on time completion
Perform Standard Analysis, use standard reports andpublish
If slippage, go to Analysis of Slipped Schedule
-
8/6/2019 Updating a Schedule
19/53
Schedule UpdatingStandard Schedule Analysis (On-Time
Completion)
-
8/6/2019 Updating a Schedule
20/53
Schedule UpdatingStandard Schedule Analysis (On-TimeCompletion)
Three basic componentsCritical Path progress
Slippage will directly delay workNear Critical progress
Slippage could easily overtake Critical Path and delaywork
Non-Critical (mass volume) work Lack of progress will cause trade stacking and over-
crowding of work space at a later date Could easily allow too much work for areas available Good place to use Earned Value for monitoring Can use Float Dissipation to monitor Can use other methods to monitor
-
8/6/2019 Updating a Schedule
21/53
Schedule UpdatingStandard Schedule Analysis (On-TimeCompletion)
Two types of paths to watchCritical Path to end of project (Substantial Completion)Critical Path to Interim Milestones
Critical PathIdeally use Longest PathMonitor minimum Total Float value Critical Path
Interim MilestonesOne path per each Milestone to watch
-
8/6/2019 Updating a Schedule
22/53
Schedule UpdatingStandard Schedule Analysis (On-TimeCompletion)
Identify current period Critical Path (Longest Path)Identify current period Near-Critical activitiesIdentify easily identified Milestones for between this
update and next updateConcrete poursInspectionsTrade mobilizations
Identify historical trends and statistics (mass volume)Identify resource problems or concerns
-
8/6/2019 Updating a Schedule
23/53
Schedule Updating
Historical Trends
-
8/6/2019 Updating a Schedule
24/53
Schedule UpdatingHistorical Comparisons & StatisticsRun Tipper (TPR) reports
Run Total Float dissipation (Erosion of Float) reportsRun Free Float dissipation reports (monitorsdisruption)
Review Out-of-Sequence work by tradeWhich trade is causing most out-of-sequence work?Are they working out-of-sequence due to other tradefailures to complete?
Or working in open areas without regard for planning?Run Resource reports
Are appropriate resources working?
Check against Tipper reports
-
8/6/2019 Updating a Schedule
25/53
Schedule UpdatingReview (TPR) Time Performance Ratio trending
(AD/OD)
Time Performance Ratio
0.001.002.003.004.005.00
6.007.008.00
31-Oct
30-Nov-05
31-Jan-06
28-Feb-06
31-Mar-06
30-Apr-06
31-May-
06
30-Jun-06
31-Jul-06
31-Aug-
06
30-Sep-
06
31-Oct-06
30-Nov-06
31-Dec-
06
31-Jan-07
28-Feb-07
Total
Period Ending
T P R
-
8/6/2019 Updating a Schedule
26/53
Schedule UpdatingReview (TPR) Time Performance Ratio trending byMilestone by Responsible Contractor (AD/OD)
-
8/6/2019 Updating a Schedule
27/53
Schedule UpdatingReview (TPR) Time Performance Ratio per trade(AD/OD)
Time Performance Ratio
0.0
2.04.0
6.0
8.0
10.0
12.0
A d m
i n
S i t e w o
r k
C o n c r e
t e
M a s o n
r y
M e t a
l s
C a r p e n t
r y
R o o f i n
g
D o o r s
/ W i n d o w
s
F i n i s h
e s
E q u i p m e
n t
F u r n i s h i n
g s
E l e v a t o
r s
M e c h a n i
c a l
E l e c t r i
c a l
Type of Work
T P R
-
8/6/2019 Updating a Schedule
28/53
Schedule UpdatingReview (TPR) Time Performance Ratio trending by
trade (AD/OD)
Time Performance Ratio (Concrete)
0.00
1.00
2.00
3.00
4.00
5.00
6.00
7.00
8.00
3 0 - S e
p - 0 6
3 1 - O c
t - 0 6
3 0 - N o
v - 0 6
3 1 - D e
c - 0 6 3 1 -
J a n - 0 7
2 8 - F e b
- 0 7 T o t a l
Period Ending
T P R
-
8/6/2019 Updating a Schedule
29/53
Schedule UpdatingTrade Monitoring by Crew no resource loading
available, load single crew resources into activities
AMP Terminals Yard Project
-
8/6/2019 Updating a Schedule
30/53
Schedule Updating
Relative Total Float of Area Completion Milestones
-50
0
50
100
150
200
B L K N
0 8 K N
0 9 K N
1 0 K N
1 1 K N
1 2 K N
1 3 K N
1 4 K N
1 5 K N
1 6 K N
1 7 K N
1 8 K N
1 9 K N
2 0 K N
2 1 S I 2 2
S S 2 3
K N 2 4
K N 2 5
R e
l a t i v e
T o
t a l F l o a t
SCAC
MCAC/CCAC
Utility Bldg
MSGQ
NOB
Subst Comp
Watch erosion of float, do not let it continue Print by trade when assessing available resources
RCA
WH
NBB
WBN
-
8/6/2019 Updating a Schedule
31/53
Schedule UpdatingEarned Value Management Reporting
Earned Value and Actual Costs See separate training session
Ciudad Juarez Earned Value
$0.00
$10,000,000.00
$20,000,000.00
$30,000,000.00
$40,000,000.00
$50,000,000.00
$60,000,000.00
$70,000,000.00
S e p - 0
5 O c
t - 0 5
N o v - 0
5
D e c - 0
5 J a
n - 0 6
F e b - 0
6 M a
r - 0 6
A p r - 0
6
M a y - 0
6 J u
n - 0 6 J u l - 0
6
A u g - 0
6 S e
p - 0 6
O c t - 0
6 N o
v - 0 6
D e c - 0
6 J a
n - 0 7
F e b - 0
7 M a
r - 0 7 A p
r - 0 7
M a y - 0
7 J u
n - 0 7 J u l - 0
7
A u g - 0
7 S e
p - 0 7 O c
t - 0 7 N o
v - 0 7
D e c - 0
7 J a
n - 0 8
F e b - 0
8 M a
r - 0 8
Period Ending
B i l l i n g
V a l u e
Early Curve
Late Curve
Actual Curve
Project Update Earned Value
-
8/6/2019 Updating a Schedule
32/53
Schedule UpdatingEarned Value Management Reporting
SPI and CPI Watch trending
Schedule Performance Index
0.00
0.20
0.40
0.60
0.80
1.00
1.20
S e p - 0
5 O c
t - 0 5
N o v - 0
5
D e c - 0
5 J a n
- 0 6 F e
b - 0 6
M a r - 0
6 A p
r - 0 6
M a y - 0
6 J u n
- 0 6 J u l
- 0 6
A u g - 0
6 S e
p - 0 6
O c t - 0
6 N o
v - 0 6
D e c - 0
6 J a n
- 0 7 F e
b - 0 7
Period Ending
S P I ( E V / P V )
-
8/6/2019 Updating a Schedule
33/53
Schedule UpdatingSchedule Analysis Sequencing Review
Set up a Layout for SequenceGroup by Phase or Location Look for out-of-sequence work by trade
Summarize to Phase
Neck for non-work periodsReview the sequence shown by the summary bars
Set up a Layout for Responsibility
Group by ResponsibilitySummarize to ResponsibilityNeck for non-work periodsReview trade workload
-
8/6/2019 Updating a Schedule
34/53
Schedule UpdatingSchedule Analysis Constructability
Set up a Layout for weekly workGroup by Early StartOrder by WeekSort by ES, EF , TF
Zoom in to weekly weekSet Major Vertical Sight Lines to one weekExpose column for Responsibility and LocationReview work to be done weekly over the next few monthsfor reasonableness
-
8/6/2019 Updating a Schedule
35/53
Schedule UpdatingSchedule Analysis (Slipped Completion)
-
8/6/2019 Updating a Schedule
36/53
Schedule UpdatingSchedule Analysis (Slipped Completion)
If slippage is due to the Owner, then a timeextension is owed to the ContractorIf slippage is due to a Subcontractor
The Subcontractor owes the GC a Recovery Scheduleeffort
The Contractor (GC) still owes the Owner a RecoverySchedule
If slippage is due to the Contractor, then theContractor owes the Owner a Recovery ScheduleIf the Owner causes the delay and the Sub or GCcauses a concurrent delay, then a time extension isowed to the Contractor; no recovery schedule
required
-
8/6/2019 Updating a Schedule
37/53
Schedule UpdatingSchedule Analysis (Slipped Completion)
Identify previous period Critical Path (Longest Path)
Use layout to compare against current scheduleIdentify current Critical Path & changes fromprevious
Identify which activities slipped and drove progressCausal Activities drive progressIdentify Start Gain or LossIdentify Production Gain or Loss
Identify specific Causal Activity or Activities for delayDevelop process for dealing with slipped completionbefore needed
-
8/6/2019 Updating a Schedule
38/53
Request forUpdate Data
Collect AdminProgress Data
Collect FieldProgress Data
Identify ContractChanges
StatusSchedule
UpdateSchedule
Compare toBaseline
PublishUpdatedSchedule
Critical PathDelay?
Identify PreviousPeriodCritical Path
No
Yes
Verify AllData
Identify ChangesTo Critical Path
Identify CausalDelay Activities
QuantifyDelays
ResearchDocuments ForDriving Delays
AssessResponsibility
For Delays
AnyConcurrent
Delays?
Verify SingleSource DelayResponsibility
Is theOwner
ResponsibleFor Delay?
No
No
Discuss Delay &Mitigation withSubcontractor
PerformConcurrent Delay
Analysis
Yes
Yes
Discuss Delay
& MitigationWith Owner
Prepare Delay
Analysis& Change Order
Is theOwner
ResponsibleFor Delay?
No
Yes
Is aSubcontractorResponsibleFor Delay?
PrepareRecoverySchedule
No
Yes
Prop osed Sc hed ule UpdateInc luding Delay Ana lysis
ResolveSubcontractorContributions
-
8/6/2019 Updating a Schedule
39/53
Schedule Updating
Schedule Analysis (Slipped Completion)Quantify Four Delay/Gain Changes for Each CausalActivity by Working From the Beginning of the Period,Using a Standard Layout with Current Baseline asSchedule Target
Verify That the Totals Add Up to the Total CP ChangeResearch the Issues that Caused the Changes to theCausal Activities
Interview Project Management TeamReview Project Documents; Issue Files, Minutes,RFI/Submittal Logs, Field Reports, PhotographsThis Research is Usually a Discussion About ReasonablyCurrent Problems Quick, Painless, and Easy
-
8/6/2019 Updating a Schedule
40/53
Schedule Updating
Schedule Analysis (Slipped Completion)Identify the Driving Issues that Affect the Causal ActivitiesAssess Responsibility for Driving IssuesReview Concurrency of Driving Issues Can Be Delay and/orAcceleration/Mitigation
Work Through Concurrent Driving Issues from the Beginning ofthe Period, Identifying First Driving Issue, Establishing anyConcurrency with Next Driving IssuePerform a Careful Concurrent Delay Analysis, Record in Clear
Graphical FormatAssign Responsibilities for All Driving Concurrent Delays
-
8/6/2019 Updating a Schedule
41/53
Schedule UpdatingSchedule Analysis (Slipped Completion)
If Subcontractors are Responsible for any Driving Delays, orPortions of Concurrent Delay, Meet Face-to-Face
Provide Clear Documentation with Approximate Costs for DelaysDiscuss Ramifications & OptionsCollaborate and Gain Commitment for Mitigation/Acceleration
If Owner is Responsible for Any Driving Delays, or Portions ofConcurrent Delay, Meet Face-to-Face
Provide Clear Documentation with Approximate Costs for DelaysDiscuss Ramifications & OptionsCollaborate and Determine Best Approach; Owner Mitigation,paid Contractor Mitigation, or Time Extension
-
8/6/2019 Updating a Schedule
42/53
S h d l U d ti g
-
8/6/2019 Updating a Schedule
43/53
Schedule UpdatingSenior Management Report
-
8/6/2019 Updating a Schedule
44/53
Schedule UpdatingDeveloping senior management reports is crucial
Sched le Updating
-
8/6/2019 Updating a Schedule
45/53
Schedule UpdatingBest to keep update & report weekly (full metrics monthly)Report should include general status summaries:
S h d l U d ti
-
8/6/2019 Updating a Schedule
46/53
Schedule UpdatingProvide project managers with additional standard reports -Earned Value metrics
-
8/6/2019 Updating a Schedule
47/53
Schedule UpdatingCustomized reports PM - myPrimavera
h d l d
-
8/6/2019 Updating a Schedule
48/53
Schedule UpdatingCustomized reports PM - myPrimavera
-
8/6/2019 Updating a Schedule
49/53
S h d l U d i
-
8/6/2019 Updating a Schedule
50/53
Schedule UpdatingNarrative - External Reporting Checklist
Checklist for an Update Schedule Narrative
S h d l U d i
-
8/6/2019 Updating a Schedule
51/53
Schedule UpdatingNarrative - External Reporting Format
-
8/6/2019 Updating a Schedule
52/53
Project Management is what youare forced to do when you dont
Schedule!(Chris Carson, ~1986)
-
8/6/2019 Updating a Schedule
53/53
Questions?
Updating a ScheduleDecember 13, 2007
Chris Carson, PSPProject Controls Manager
Alpha Corporation