Updated May 5, 2016 - Midwestern Governors · BULK POWER SYSTEM OVERVIEW AND IT’S ... connect new...
Transcript of Updated May 5, 2016 - Midwestern Governors · BULK POWER SYSTEM OVERVIEW AND IT’S ... connect new...
BULK POWER SYSTEM OVERVIEW AND IT’S EVOLUTION TO THE FUTURE GRIDOctober 6, 2016
MGA Grid Modernization: Understanding Technology Advancements
Jay Caspary, Director – Research, Development & Tariff Services
Southwest Power Pool
2
SPP’s 2015 Capacity and Energy Mix
7
42.6
33.3%
4.1%
14.9%
3.2% 0.2%
Gas
(42.58%)
Coal
(33.25%)
Hydro
(4.11%)
Wind
(14.86%)
Nuclear
(3.16%)
Other
(0.15%)
Installed Capacity
21.6%
55.1%
1.5%
13.5%
8.1% 0.1%
Gas
(21.63%)
Coal
(55.06%)
Hydro
(1.54%)
Wind
(13.52%)
Nuclear
(8.11%)
Other
(0.14%)
Energy Consumption
WHY WE NEED MORE TRANSMISSION?
• In the past, built least-cost transmission to meet local needs
• Today, proactively building “highways” to benefit region
11
HOW SPP MAKES TRANSMISSION DECISIONS• Generation Interconnection Studies
Determines transmission upgrades needed to connect new generation to electric grid
• Aggregate Transmission Service Studies
Determines transmission upgrades needed to transmit energy from new generation to load
• Integrated Transmission Planning process
Iterative study process to assess SPP transmission system reliability and economic needs
• Specific transmission studies
12
APPROVED RENEWABLES
• Wind (In-Service)
13GW on wires
• Wind/Solar (under GIA) including I.S. Grandfather
10.1GW
• Total Approved - 23GW +
17
APPROVED + REQUESTED RENEWABLES
• Existing Wind/Solar plus GIAs = 23GW+
• Wind/Solar in DISIS-2015-001/002 = 10.2GW
• Wind/Solar in DISIS-2016-001 = 10.7GW
• Total Potential Wind/Solar = 44GW +
• OPERATIONAL CHALLENGES TO DATE SPP Actual Minimum Load is less than 20GW Actual Wind Penetration Rates Have Exceeded
49%
18
DOE-FUNDED, NREL-LED SEAMS STUDY
• $1.2M, 18 month EI-WECC Seams and HVDC Overlay Study approved as part of GMLC
• Strong industry support
• Scope finalized in March Opportunity to not just replace in-kind the aging
B2B HVDC Ties between EI and WECC Three DC Scenarios
Status Quo
Modernized/Optimized Seam with Rightsized/Relocated B2B and/or Links
Macro Grid Overlay
• Kickoff meeting for TRC held June 27-28.
• Promising preliminary results
24
SPP’s Value of Transmission Study
27
• Evaluated 348 projects from 2012-14, representing $3.4B of transmission investment
• Evaluated benefit metrics
Adjusted Production Cost (APC) Savings
Reliability and Resource Adequacy Benefits
Generation Capacity Cost Savings
Market Benefits
Other industry and SPP-accepted metrics
• APC Savings alone calculated at more than $660k/day, or $240M/year.
• Overall NPV of all benefits for considered projects are expected to exceed $16.6B over 40 years.
For every $1 of transmission investment made in 2012-2014, SPP
expects at least $3.50 of benefit to be provided to rate-payers