Update on the Siting of the 5 th Comprehensive High School IUSD Board Meeting March 18, 2014 1

Transcript of Update on the Siting of the 5 Comprehensive High School · June 2, 2014 – August 11, 2016...

Page 1: Update on the Siting of the 5 Comprehensive High School · June 2, 2014 – August 11, 2016 September 1, 2014 – August 31, 2016 October 1, 2014 – September 30, 2016 November 1,

Update on the Siting of the 5th Comprehensive High School

IUSD Board Meeting

March 18, 2014

1

Page 2: Update on the Siting of the 5 Comprehensive High School · June 2, 2014 – August 11, 2016 September 1, 2014 – August 31, 2016 October 1, 2014 – September 30, 2016 November 1,

Topics for Discussion

State Approval Update – High School Site A & Site B – Environmental Studies – California Department of Education Site Review – State Funding

Construction Update – HS Site A – Grading Coordination – Impact on Design Timeline

Project & Construction Timeline and Phasing Options – Site A – Site B

High School Enrollment Projection

2

Page 3: Update on the Siting of the 5 Comprehensive High School · June 2, 2014 – August 11, 2016 September 1, 2014 – August 31, 2016 October 1, 2014 – September 30, 2016 November 1,

State Approval Update Environmental Studies

SITE A COMPLETION

Phase I Environmental Site Assessment, DTSC Approved December 2012

Geologic and Environmental Hazard Assessment Report March 2013

Pipeline Safety Hazard Assessment (PSHA) July 2013

Environmental Impact Report Board Certified November 2013

Preliminary Environmental Assessment (PEA) Work Plan, DTSC Approved

December 2013

Preliminary Environmental Assessment Report Submitted to DTSC

January 2014

DTSC Determination (expected April 2014) Pending

3

Page 4: Update on the Siting of the 5 Comprehensive High School · June 2, 2014 – August 11, 2016 September 1, 2014 – August 31, 2016 October 1, 2014 – September 30, 2016 November 1,

State Approval Update Environmental Studies

SITE B Proposed Schedule

Draft Preliminary Environmental Assessment (PEA) Work Plan March 31, 2014

DTSC Comments Due on Draft PEA April 2014

PEA Report Submittal to DTSC July 2014

Geologic and Environmental Hazard Assessment Report July 2014

Health Risk Assessment (Proximity to Freeways) July 2014

Pipeline Safety Hazard Assessment (PSHA) July 2014

EMF Exposure Hazard Assessment July 2014

DTSC Determination September 2014

Environmental Impact Report Certification October 2014

4

Page 5: Update on the Siting of the 5 Comprehensive High School · June 2, 2014 – August 11, 2016 September 1, 2014 – August 31, 2016 October 1, 2014 – September 30, 2016 November 1,

State Approval Update California Department of Education

Site A • Site Review Package Submitted November 2013 • DTSC Determination expected no later than April 4, 2014 • CDE will complete their review of entire site package, then

issue Site Approval Site B • Preliminary Environmental Assessment draft Work Plan

Review Pending – Once DTSC reviews, staff will recommend further site

investigations, including starting CEQA Studies and Traffic Analysis

5

Page 6: Update on the Siting of the 5 Comprehensive High School · June 2, 2014 – August 11, 2016 September 1, 2014 – August 31, 2016 October 1, 2014 – September 30, 2016 November 1,

State Approval Update State Funding

• Future State Funding remains uncertain

• Potential for a November 2014 Bond still remains

– Important to submit funding application to get in line for future facilities bond

• Delay in funding application submittal

– Potential risks in running out of funding authority

6

Page 7: Update on the Siting of the 5 Comprehensive High School · June 2, 2014 – August 11, 2016 September 1, 2014 – August 31, 2016 October 1, 2014 – September 30, 2016 November 1,

Construction Update Site A

Grading Coordination & Impact to Design Timeline

• Infrastructure Coordination

• Grading

• Property Line and Landscape Zone

• Design Impact – Buildings, Fields, Parking

• Plan Review Impact – DSA, CGS

7

Page 8: Update on the Siting of the 5 Comprehensive High School · June 2, 2014 – August 11, 2016 September 1, 2014 – August 31, 2016 October 1, 2014 – September 30, 2016 November 1,

Construction Update Site A

8

Page 9: Update on the Siting of the 5 Comprehensive High School · June 2, 2014 – August 11, 2016 September 1, 2014 – August 31, 2016 October 1, 2014 – September 30, 2016 November 1,

9

Phase

Environmental Studies/Approvals

CDE Site Review/Approval

Develop Architectural Plans

CDE Plan Review/Approval

Site Acquisition

DSA Review/Approval

Construction

11/13/2013 – 4/30/2014

5/8/2012 – 4/3/2014

11/4/2013 – 4/30/2014

1/30/2014 – 4/30/2014

7/1/2012 – 12/19/2013

2013 2nd Half

2014 1st Half

2014 2nd Half

2015 1st Half

2015 2nd Half

2016 1st Half

2016 2nd Half

2017 1st Half

2017 2nd Half

11/19/2013 – 9/15/2014

6/2/2014 – 8/11/2016

Project & Construction Timeline High School #5 Site A

Page 10: Update on the Siting of the 5 Comprehensive High School · June 2, 2014 – August 11, 2016 September 1, 2014 – August 31, 2016 October 1, 2014 – September 30, 2016 November 1,

10

Phase

Environmental Studies/Approvals

CDE Site Review/Approval

Develop Architectural Plans

CDE Plan Review/Approval

Site Acquisition

DSA Review/Approval

Construction

10/3/2014 – 12/1/2014

10/2/2013 – 10/1/2014

8/1/2014 – 12/30/2014

12/1/2014 – 12/30/2014

4/11/2014 – 12/1/2014

2013 2nd Half

2014 1st Half

2014 2nd Half

2015 1st Half

2015 2nd Half

2016 1st Half

2016 2nd Half

2017 1st Half

2017 2nd Half

12/1/2014 – 10/1/2015

11/1/2015 – 1/1/2018

Project & Construction Timeline High School #5 Site B

Page 11: Update on the Siting of the 5 Comprehensive High School · June 2, 2014 – August 11, 2016 September 1, 2014 – August 31, 2016 October 1, 2014 – September 30, 2016 November 1,

Project & Construction Timeline High School #5 Site A

Construction Schedule Options

Scenario 1

Site Acquisition April 30, 2014

Scenario 2

Site Acquisition August 15, 2014

Scenario 3

Site Acquisition September 15, 2014

Scenario 4

Site Acquisition October 15, 2014

2014 2015 2016

J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D

11

(All facilities completed by August 11, 2016)

(All facilities completed by August 31, 2016)

(Performing Arts Completed by September 30, 2016)

June 2, 2014 – August 11, 2016

September 1, 2014 – August 31, 2016

October 1, 2014 – September 30, 2016

November 1, 2014 – October 31, 2016

(Performing Arts, Administration & Student Union Completed by October 31, 2016)

Page 12: Update on the Siting of the 5 Comprehensive High School · June 2, 2014 – August 11, 2016 September 1, 2014 – August 31, 2016 October 1, 2014 – September 30, 2016 November 1,

High School Enrollment Projection Excluding Entitled Heritage Fields Units

Year Existing

2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023

Total High School Students 8,641 9,427 9,877 10,472 11,130 11,660 12,120 12,728 12,968 13,062 13,387

Potential Heritage Fields Students

(0) (83) (152) (211) (323) (417) (486) (564) (614) (732) (885)

Total High School Students Less Heritage Fields

8,641 9,344 9,725 10,261 10,807 11,243 11,634 12,164 12,354 12,330 12,502

Note: 1. Projected High School Students – Excluding all Entitled Heritage Fields Development Units 2. Threshold of 10,400 Existing and Projected 9-12 Students met in fall 2017 if Heritage Fields Developments are excluded.

12

High School Projection Per Mitigation Agreement (Sans Creekside HS and Out of District Students) Source: IUSD14Mod 2014 Developer