Update on Power Supplies and GTK carrier
M.Morel01.04.2014
Update on Power Supplies and GTK_carrier 2
1. Power Supplies2. Cables3. GTK_carrier4. Probe tester
01/04/2014
Update on Power Supplies and GTK_carrier 301/04/2014
1. Power Supplies2. Cables3. GTK_carrier4. Probe tester
Update on Power Supplies and GTK_carrier 401/04/2014
1V2 Digx 10 ch
1V2 AX 10 ch
1 x 2V5 Dig1 x 3V3 Dig1 x 5V Dig 3 x 5V3 Dig
3 modules in each EASY crateInterlocked with Temperature(OR of cooling and TDCpix)
Common to the 3 stations.Supplies the Temp logic(VDD_temp and 3V3_NI)
Low Voltage A3009 and A3009K modules
2 x A3009K + 1 x A3009
1 x A3009
Update on Power Supplies and GTK_carrier 5
- 3 x EASY CRATES 3000 - 6 x 3009K 3 x Analog and 3 x Digital 1V2- 1 x 3009K (prototype module) - 3 x 3009 2V5, 3V3, 5V- 1 x 3009 5V3 non interlocked*- 1 A3486 48V power supply
- 1 mainframe SY2527: 80CHF/month- 1 branch controller A1676A: 40CHF/m- 1 HV module A1821: 38CHF/m
- 1 SY4527: 5862 euros (profitable after 7 years)- 1 A1676A: 1800 euros (profitable 5 years)- 1 A1821: 5260 euros (profitable after 14 years)
* 5V3 non interlocked is connected to rad hard voltage regulatorswhich provide VDD_temp (1V2) and temp_logic (3V3)
What do we need?
Bought
Rented
Bought
01/04/2014
Update on Power Supplies and GTK_carrier 6
1. Power Supplies2. Cables3. GTK_carrier4. Probe tester
01/04/2014
Update on Power Supplies and GTK_carrier 701/04/2014
TCC8
Update on Power Supplies and GTK_carrier
Each Patch Panel:10 x 1.2V Digital10 x 1.2V Analog1 x 3.3V Dig1 x 2.5V Dig1 x 5V Dig1 x Analog senses1 x digital senses1 x 5.3V dig (NON interlocked)1 x Bias (~500 to 1000V)1 x 10 temperature interlocks
PatchPanel3
PatchPanel2
PatchPanel1
GTKStation 1
GTKStation 2
GTKStation 3
Electronic
Rack 2
Electronic
Rack 1
Electronic
Rack 3
Electrical cables routing scheme
8
4m
4m
4m
01/04/2014
18m9m20m
Update on Power Supplies and GTK_carrier 901/04/2014
• All the cables have been ordered• All the connectors and accessories have also been ordered• The company CONFECTRONIC (Yvonand) will assemble the connectors (318 cables)
Update on Power Supplies and GTK_carrier 1001/04/2014
1. Power Supplies2. Cables3. GTK_carrier4. Probe tester
Update on Power Supplies and GTK_carrier 1101/04/2014
GTK_CARRIER
Update on Power Supplies and GTK_carrier 12
Due to the complexity of the PCB, we would select a company capable to work with special techniques as:
• Small pitch• Blind and burried vias• Controlled impedance• Filled and capped vias• Nelco 4203-13• Ni/Au on the edges of the board• countersink
1. CERN.
2. GS Swiss PCB. KÜSSNACHT (CH) www.swisspcb.ch
3. ELTOS SAN ZENO Arezzo (IT) www.eltos.it
4. STEVENAGE circuits www.stevenagecircuits.co.uk
01/04/2014
PCB production
Update on Power Supplies and GTK_carrier 1301/04/2014
1. CERN. 2 x 2866CHF + tooling 1039CHF
2. GS Swiss PCB. 3 x 6103CHF + 2935CHF
3. ELTOS SAN ZENO 3 x 1485CHF + 1500CHF
4. STEVENAGE circuitsno answer
5 boards will be produce: expected delivered time: mid May
GTK_CARRIER production
Update on Power Supplies and GTK_carrier 1401/04/2014
1. Power Supplies2. Cables3. GTK_carrier4. Probe tester
Update on Power Supplies and GTK_carrier 1501/04/2014
Wentworth Prober
Missing part: small vacuum pumpNeeds modification of the carrier support
Update on Power Supplies and GTK_carrier 1601/04/2014
Conclusion
1. Status of the Power Supplies: ordered2. Status of the Cables: ordered3. Status of the GTK_carriers: ordered4. Prober: needs small modifications