Update on FCPS Construction/Renovation Projects May 2009.

27
Update on FCPS Construction/Renovation Projects May 2009 May 2009

Transcript of Update on FCPS Construction/Renovation Projects May 2009.

Page 1: Update on FCPS Construction/Renovation Projects May 2009.

Update on FCPS Construction/Renovation Projects

May 2009

May 2009

Page 2: Update on FCPS Construction/Renovation Projects May 2009.

Cassidy Elementary – Renovation Architect: Tate.Hill.Jacobs: Architects

General Contractor: D.W. Wilburn, Inc.

Substantial Completion Date: August, 2010 Contract Sum: $9,061,000

Change Orders to Date: $0

Current Phase: 1 (On Schedule)

May 2009

Page 3: Update on FCPS Construction/Renovation Projects May 2009.

Cassidy Elementary – RenovationRendering of Final Façade

May 2009

Page 4: Update on FCPS Construction/Renovation Projects May 2009.

Cassidy Elementary – RenovationWork Completed in Last 30 Days:

New staff parking lot @ Tates Creek Rd. cut to subgrade. Subgrade for new 2-Story Administration/Classroom Addition

completed and foundations begun. Original Stage and Music Room demolition complete. Miscellaneous interior demolition continued as needed.

Current Work Effort (May): Stone installed in new parking lot for temporary staging area. New Music Room/Mechanical Room Addition foundation and

concrete slab will be complete. New 2-Story Administration/Classroom Addition foundation and

concrete slab will be complete. Masonry to begin with concrete block walls on 2 additions. Underground sanitary and plumbing rough-in work to start under

new additions. Underground electric feeds and below slab rough-in to continue.

May 2009

Page 5: Update on FCPS Construction/Renovation Projects May 2009.

Cassidy Elementary – RenovationNew 2-Story Admin Addition

foundationNew Staff Parking Lot subgrading,

Tates Creek Rd

May 2009

New Underground Detention System excavation

New Music Rm./Mech. Rm. Addition site

Page 6: Update on FCPS Construction/Renovation Projects May 2009.

Russell Cave Elementary – Renovation

Architect: Pearson & Peters Architects

General Contractor: Congleton-Hacker Construction

Substantial Completion Date: August, 2010

Contract Sum: $5,001,150

Change Orders to Date: $0

Current Phase: 1

May 2009

Page 7: Update on FCPS Construction/Renovation Projects May 2009.

Russell Cave Elementary – RenovationRendering of Final Façade

May 2009

Page 8: Update on FCPS Construction/Renovation Projects May 2009.

Russell Cave Elementary – RenovationWork Completed in Last 30 Days:

Building pad and foundation bearing have been tested and approved.

Footings and foundation walls: 125 feet of footings have been poured and 61 feet of foundation wall have been poured.

Existing sprinkler line has been relocated.Current Work Effort (May):

Additional work on footings and foundation at the new addition will continue.

Installation of the new leach fields for the septic system will begin installation in the front lawn of the building.

New electrical conduits will be installed in the existing crawlspaces to feed wiring to new addition and the existing kitchen.

New cooler/freezer and hood roof curb for kitchen renovation is scheduled for delivery the week of June 8th. Work will begin as soon as school is out.

May 2009

Page 9: Update on FCPS Construction/Renovation Projects May 2009.

Russell Cave Elementary – RenovationFoundation Work 5.5.09 Foundation Work 5.5.09

May 2009

Foundation Work 5.5.09

Foundation Work 5.5.09

Page 10: Update on FCPS Construction/Renovation Projects May 2009.

Arlington Elementary – Renovation

Architect: RossTarrant Architects

General Contractor: W/S Construction

Substantial Completion Date: August, 2010

Contract Sum: $9,920,194

Change Orders: $36,900 (#1--Demo)

Current Phase: 1

May 2009

Page 11: Update on FCPS Construction/Renovation Projects May 2009.

Arlington Elementary – RenovationRendering of Final Façade

May 2009

Page 12: Update on FCPS Construction/Renovation Projects May 2009.

Arlington Elementary – RenovationWork Completed in Last 30 Days:

Demolition completedWork at Site to begin in mid-May

May 2009

Page 13: Update on FCPS Construction/Renovation Projects May 2009.

Arlington Elementary – RenovationDemo – Main Bldg. Demo – Main Bldg.

May 2009

Demo – Gym Demo – Gym

Page 14: Update on FCPS Construction/Renovation Projects May 2009.

Bryan Station Middle – Renovation

Architect: Clotfelter-Samokar Architects

General Contractor: Preston Construction Group

Substantial Completion Date: August, 2010

Contract Sum: $10,769,400

Change Orders to Date: $0

Current Phase: Phase 1 to begin June 1

May 2009

Page 15: Update on FCPS Construction/Renovation Projects May 2009.

Bryan Station Middle – RenovationRendering of Final Façade

May 2009

Page 16: Update on FCPS Construction/Renovation Projects May 2009.

Bryan Station Middle – RenovationWork Completed in Last 30 Days:

GC conducting preparatory activitiesWork at Site to Begin June 1

May 2009

Page 17: Update on FCPS Construction/Renovation Projects May 2009.

Leestown Middle – Renovation

Architect: Lucas/Schwering Architects

General Contractor: D.W. Wilburn, Inc.

Substantial Completion Date: August, 2010

Contract Sum: $11,182,000

Change Orders to Date: $0

Current Phase: Phase 1a, 1b, 1c to begin June 1

May 2009

Page 18: Update on FCPS Construction/Renovation Projects May 2009.

Leestown Middle – RenovationRendering of Final Façade

May 2009

Page 19: Update on FCPS Construction/Renovation Projects May 2009.

Leestown Middle – RenovationWork Completed in Last 30 Days:

Pre-construction meeting held on 5/5/2009.Work at Site to Begin June 1

May 2009

Page 20: Update on FCPS Construction/Renovation Projects May 2009.

Lafayette High Stadium – Replacement

Architect: Strand & Associates

General Contractor: Set to bid July 1

Substantial Completion Date: July, 2010

Contract Sum: TBD

Change Orders to Date: $0

Current Phase: Construction Documents

May 2009

Page 21: Update on FCPS Construction/Renovation Projects May 2009.

Lafayette High Stadium – Replacement

UPDATED – Existing Campus

May 2009

Page 22: Update on FCPS Construction/Renovation Projects May 2009.

Lafayette High Stadium – Replacement

UPDATED – Existing Football Stadium

May 2009

Page 23: Update on FCPS Construction/Renovation Projects May 2009.

Lafayette High Stadium – Replacement

UPDATED – New Football Stadium

May 2009

Page 24: Update on FCPS Construction/Renovation Projects May 2009.

Central Bus Garage – Adaptive Reuse

Architect: Lucas/Schwering Architects

General Contractor: James R. Leake & Sons, Inc.

Substantial Completion Date: August, 2009

Contract Sum: $2,782,000

Change Orders to Date: $0

Current Phase: Construction

May 2009

Page 25: Update on FCPS Construction/Renovation Projects May 2009.

Central Bus Garage – Adaptive ReuseFaçade

May 2009

Page 26: Update on FCPS Construction/Renovation Projects May 2009.

Central Bus Garage – Adaptive ReuseProposed Floor Plan

May 2009

Page 27: Update on FCPS Construction/Renovation Projects May 2009.

Tonight’s Agenda ItemsProject Agenda Item

Arlington Elementary Approval of BG-4 – Final Payment to Contractor for Demolition Work Superior Demolition: $44,724.30 Total Demolition Cost: $124,148

Lafayette Stadium Approval of Design Development & Construction Documents Total Estimated Cost: $5,795,500

Liberty Elementary Approval of Change Order #5 Total Credit for Unused DPOs: ($17,392.32)

William Wells Brown Elementary

Approval of Change Order #7 Total Credit for Unused DPOs: ($13,041.47) Change to GC Contract: ($439.62)

May 2009