Uno Mas Final Presentationdwatkins/idesign09/2012/Uno Mas...Microsoft PowerPoint - Uno Mas Final...

18
1/11/2013 1 Water for Honey Hill: Supplying Water to the Community of Cerro Miel Brittany Allen – CE, Elizabeth Jefferson – ENVE, Manda Schierbeek – ENVE, Merete Sørum – ENVE Outline Background Data Collection Data Analysis Design Recommendations Cost Analysis and Construction Schedule Conclusion Water tap in community Photo by Manda Schierbeek

Transcript of Uno Mas Final Presentationdwatkins/idesign09/2012/Uno Mas...Microsoft PowerPoint - Uno Mas Final...

1/11/2013

1

Water for Honey Hill:

Supplying Water to the Communityof Cerro Miel

Brittany Allen – CE, Elizabeth Jefferson – ENVE, Manda Schierbeek – ENVE, Merete Sørum – ENVE

Outline

• Background

• Data Collection

• Data Analysis

• Design Recommendations

• Cost Analysis and Construction Schedule

• Conclusion

Water tap in communityPhoto by Manda Schierbeek

1/11/2013

2

Assessment Trip to Panama

paradisehunter.com

Community Background

• Located in a mountainous region

• Ngöbe People

• 300‐400 People in Community

• Subsistence Farming

• Learn Spanish in School

Ngöbe girls in traditional dressesPhoto by Brittany Allen

1/11/2013

3

Project Objectives and Background

• Primary Objective– Design a sustainable way to provide theDesign a sustainable way to provide the 

community with clean water

• Existing Systems– Old System

– New System

• Project Objectives– Improve Existing SystemImprove Existing System

– Expand System

– Educate People on 

Use and Maintenance  Storage tank for the new system in Cerro MielPhoto by Merete Sørum

Data Collection

• Survey and GPS

• Water Quality 

• Water Availability

Photo by Manda Schierbeek

Team members doing water quality testing

1/11/2013

4

Data Analysis 

• Google Earth Mapping

• Water Availability Analysis

• EPANET Modeling

Peña Blanca, near Cerro MielPhoto by Elizabeth Jefferson

Google  Maps by Elizabeth JeffersonTotal Length of Pipe: 16 milesPipe in Community: 7 miles

1/11/2013

5

1000 ft

13 Existing Taps48 Proposed Taps9 Taps for Unbuilt Houses70 Total Taps

1/11/2013

6

Water Availability and Quality

• Old system

– Flow rate: 4 8 gal/minFlow rate: 4.8 gal/min

– Spring source

– Good quality

• New system:

– Flow rate: 50.7 gal/min

– River source

– Low quality

Photo by Elizabeth Jefferson

Stream in Cerro Miel

Water Treatment

• Slow Sand Filter

• Inline Chlorination

• Located in Tugri

• Suggested move to Cerro Miel

Photo by Elizabeth Jefferson

Slow sand filter in Tugri

1/11/2013

7

Water Usage

• Christopher Kingsley’s Survey

• Ministry of Health Estimation• Ministry of Health Estimation

• Distributed over the day

• 240 gal/day

min

)U

sage

(ga

l/m

EPANET Model

Model by Merete Sørum

1/11/2013

8

2000 ft

Figure by Elizabeth Jefferson and Merete Sørum

250 ft

Figure by Elizabeth Jefferson and Merete Sørum

1/11/2013

9

Pressure Release

• High elevation changes cause high pressures in 

• Two options considered

– Mason‐Break Pressure 

pipes  Tanks

– HDP Pressure Tanks

goinsurancerates.com

Mason‐Break Pressure Tanks

• 3 Tanks Total

• Located within Cerro Miel

• Most Durable Option

Barefooteconomics.com

1/11/2013

10

Mason‐Break Pressure Tank

Drawing by Brittany Allen

HDP Pressure Tank

• Located by storage tank in Tugri

Drawing by Brittany Allen

Drawing by Brittany Allen

1/11/2013

11

Air Block

www.aplv.org 

Air Release Design 

Air Release Valve

1/11/2013

12

Air Release Valves

plastomatic.com asahi‐america.com

Air Release Locations

3550

3650

3150

3250

3350

3450

Elevation (ft)

Air Release LocationsLine 1

Line 2

Line 3

2850

2950

3050

0 2000 4000 6000 8000 10000 12000

Approximate Distance (ft)

Line 4

1/11/2013

13

Water Hammer

• Pressure increases from rapidly closing valve

Addi i l i b k• Additional pressure may cause pipe to break

maplesoft.com

Gully Crossings

Photo by Elizabeth Jefferson

Break in pipe between Tugri and Cerro Miel

1/11/2013

14

Suspension Bridges

Length of SpanLength of Span

Sag

Drawing by Manda Schierbeek

UV Protection

d d C i• UV Rays degrade PVC pipe

• Best Option:

Burying the pipe

• Alternative:

Painting the pipe g p p

drain‐experts.ca

1/11/2013

15

Cost Estimating

• Key Assumptions:• No Labor Cost

• Material Data• Bajo Salitre Cost 

• No Equipment CostBajo Salitre Cost Estimate

• Online Quotes

Coinquest.com

Final Cost Estimate

Item Cost

Pi li Fitti V l 4350Pipeline, Fittings, Valves 4350

Pressure Release 535

Air Release 215

Gully Crossing Supports 1380

UV P i 440UV Protection 440

Transportation of Materials 930

Total: $7,850

1/11/2013

16

Construction Schedule

• Total time to construct: 105 Daysconstruct: 105 Days

• Key Assumptions

– Crew of 17 workers each day

– 0.5 mi of pipe can be laid per day

– RS Means Data Valid

Ngöbe women in traditional dressesPhoto by Elizabeth Jefferson

Conclusions• Met the community’s needs• Designed a sustainable, reliable, and

economical project S• Supplied tools to help community maintain their system

Photo by Mike Drewyor

1/11/2013

17

Acknowledgments

Christopher KingsleyChet Hopp

Dr. Dave Watkins Mike Drewyor (PE)

1/11/2013

18

Questions

Team in front of the Panama Canal Expansion SitePhoto by Rebecca Bender