University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of...

114
JUNE 1, 2001 PREPARED BY: JBA Incorporated, Planning H+L Architecture in association with Shepley Bulfinch Richardson and Abbott 5Design, Incorporated, Landscape Architecture Bierbach Consulting Engineers, Structural Engineering Cator, Ruma & Associates, Co., Mechanical/Electrical Engineering University of Colorado Health Sciences Center FITZSIMONS LIBRARY PROGRAM PLAN UCHSC DENISON MEMORIAL LIBRARY UCHSC Office of the Chancellor Institutional Planning FitzLibraryCov.qxd 6/6/01 9:17 AM Page 1

Transcript of University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of...

Page 1: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

JUNE 1, 2001

PREPARED BY:JBA Incorporated, PlanningH+L Architecture in association withShepley Bulfinch Richardson and Abbott5Design, Incorporated, Landscape ArchitectureBierbach Consulting Engineers, Structural EngineeringCator, Ruma & Associates, Co., Mechanical/Electrical Engineering

University of Colorado Health Sciences Center

FITZSIMONS LIBRARY PROGRAM PLAN

UCHSC DENISON MEMORIAL LIBRARYUCHSC Office of the Chancellor

Institutional Planning

FitzLibraryCov.qxd 6/6/01 9:17 AM Page 1

Page 2: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

June 1, 2001

University of Colorado Health Sciences Center Fitzsimons Library Program Plan

Table of Contents

Section Subject Page I. Preface and Summary 2 Executive Summary 2 Program Plan Process 3 II. Program Information 6 Description of Program 6 History, Role & Mission, Unique Program(s) 8 Program Needs and Trends 13 Relationship to Academic or Institutional Strategic Plan(s) 14 Program Alternatives 17 III. Facilities Needs 18 Total Space Requirements 18 Unique or Special Features 18 Health, Life Safety, and Code Issues 19 Site Requirements 20 Diagrammatic Site Plans 3 pages follow 23 Equipment Requirements 24 Acquisition of Real Property 24 IV Project Description 25 General Project Description/Scope of Work 25 Diagrammatic Floor Plans/Adjacencies 7 pages follow 33 Project Cost Estimate 34 Life-Cycle Estimate 35 Financial Analysis 35 Project Schedule 35 V. Relation to Master Plan/Other Projects 36 VI. Facilities Alternatives 37 VII. Appendices 38 7.01 Participants in the Planning Development Process 7.02 Strategic Brief for the Library at Fitzsimons (DEGW Architects and Planners) 7.03 Library (L-Tables) and Building Space Tables 7.04 Student Demographics (Enrollment Trends and Class/Lab Information) 7.05 Life Cycle Owning and Operating Cost Analyses 7.06 Financial Operation Performa Information 7.07 IS Design Requirements 7.08 Program Plan Regulatory Analysis 7.09 Independent Third Party Review

Page 3: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

June 1, 2001

I. Preface and Summary Executive Summary The mission of the University of Colorado Health Sciences Center (UCHSC) is to educate and train health care professionals, advance knowledge through research in the health sciences, and deliver health care and community service. With the conveyance of the former Fitzsimons Army Medical Center in Aurora, the UCHSC has the extraordinary opportunity to develop a campus that will move the institution into the country’s top tier of health science centers. This ambitious goal was outlined in the institutional master plan, approved by the University of Colorado Board of Regents in October 1998 and the Colorado Commission on Higher Education in December 1998. At the core of the Master Plan is the development of a new UCHSC campus at Fitzsimons that will be developed over the next decade. This program plan requests approval for the construction of the new UCHSC library facility at Fitzsimons.

The UCHSC is among the nation’s leading academic health science centers, but to be able to reach its goal of becoming a top tier health sciences institution, the campus must grow and flourish. The new Fitzsimons campus will allow the UCHSC to reach its goal by accommodating program growth needs through the next century. The UCHSC/University Hospital campus space inventory at 9th Avenue and Colorado Boulevard in Denver totals approximately 2.7 million gross square feet (gsf) on a 46-acre campus. The Fitzsimons campus development will involve a phased construction program totaling approximately five million square feet of new program space and associated infrastructure for the Health Sciences Center and University Hospital. Education-related space will total more than 600,000 gsf, which includes a new state-of-the-art library totaling approximately 116,000 gross square feet. As the only comprehensive health sciences library in the state of Colorado, the current UCHSC Denison Library is the library of record and the last recourse for biomedical materials unavailable elsewhere in the region. Today, nearly 325,000 users rely annually on the Denison Memorial Library to provide vital, up-to-the-minute information for patient care and research, personalized assistance in tapping knowledge sources, and a diverse collection recording the scholarly record of the health sciences. The aging facilities and inadequate physical plant at the 9th and Colorado campus site are significant obstacles to the continued success of the academic, research, and clinical programs at the UCHSC. The current space allocated for the Denison Library program is inadequate to support changes in curricula, teaching, technology, and research. Although Denison Library spaces have been partially renovated in recent years, the renovations merely allow UCHSC to compete in the health profession education, research, and clinical care marketplaces. The current Denison Library’s area of 48,000 assignable square feet (asf) is cramped; its learning tools are out of date; its study areas do not accommodate collaborative learning; staff now work in small and inappropriate spaces; and the growing collection of periodicals and books has been accommodated by reducing the number of reader seats. The UCHSC aspires to provide its campus community and citizens of Colorado with a state-of-the-art health sciences library at Fitzsimons.

The University of Colorado Health Sciences Center Master Plan provides a vision for the new learning environment at Fitzsimons, which includes the library and its services. The vision emphasizes that for UCHSC to maintain and enhance its ongoing commitment to form and reform educational programs that respond to health workforce needs, the library must be continuously responsive, dynamic, evaluation-conscious and future-oriented. The success of this goal depends in large part on effective use of the appropriate evolving information technologies and other learning methods. The new library will be the focal point to access information from emerging technologies. The library will be the hub of knowledge at Fitzsimons linking the critical components that comprise the institution’s mission. It

Page 4: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

will embody the new campus’ vision for its physical facilities by integrating the academic, research and clinical endeavors of the institution. The library project will consist of the construction of a new 116,000 gross square foot(76,972 assignable square feet (asf) facility to house the current Denison Library programs that will be relocated from the existing facility at 9th Avenue and Colorado Boulevard campus site. As now envisioned, the new library will be a four level facility sited immediately to the north of the Administration Building (Building 500). In addition to administrative space (2,155 asf), circulation space (2,320 asf), and general space (8,320 asf), the new facility will contain space for the learning resource center (2,860 asf), reference services (2,550 asf), resources services (1,210 asf), systems-databases (3,775 asf), material storage (23,607 asf), education and health informatics (2,945 asf), information access and study space (19,530 asf), the drug information center (2,330 asf), the History of Medicine collection (2,950 asf), and specialized building support space (2,420 asf). Specific highlights of the new library will include: 1) open, quiet study areas for comfortable reader seating; 2) small group study rooms for collaborative learning; 3) stacks (meeting Americans with Disabilities Act guidelines) that will accommodate print materials more efficiently; 4) an open, circulating collection of books and bound journals, special collections and archives, reference collections and current journals; 5) wireless and Personal Data Assistant (PDA) technology that will allow computer laptops and other portable devices to be used throughout the facility; 6) adequate, well-designed and user-accessible staff space; and, 7) cutting-edge graphic and virtual reality technology. The total project budget for the design and construction of the library facility is estimated to total $35 million. The sources of the funds for the entire project will be $20.25 million in state capital construction funds, $9.75 million in Fitzsimons trust funds, and $5.0 million in University cash funds. The design of the project will commence following state legislative authorization in July 2002. Construction will begin one year later, with the project tentatively scheduled for completion in December 2004. Program Plan Process The planning process used to develop this program plan involved numerous University personnel and consultants. Each person was able to contribute their expertise through multiple meetings, worksessions, on-site research, specific studies, experience, and other general planning practices. This program plan is a result of the valuable input gathered from all those involved and is considered to be the best solution for the relocation of the Denison Library to the Fitzsimons campus. A brief description of the process follows. Visioning and Preplanning: The conceptual foundation for the new library began with the visioning process for development of Fitzsimons and the way programs would be recast in this new environment. In the Denison Library administrators began building a Library Council, an advisory board of influential and diverse individuals who could encouraged the use of a consultant to help define the strategic decisions requserved at Fitzsimons; and in March of 2001 DEGW Architects and ConsultaAppendix 7.02) that reflected a new vision for the library.

“The UCHSC library at Fitzsimons will link people, trustworsupport of effective learning, quality health care, and the latest

campus-wide UCHSC’s spring of 2000 Leadership

guide the broad planning for the facility. The Council ired in rethinking the mission and mix of user populations nts produced a briefing document (reproduced as

thy biomedical knowledge and technology in research.”

Page 5: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

Fitzsimons Library Program Plan University of Colorado Health Sciences Center

June 1, 2001

Following receipt of the DEGW strategic briefing, the campus began a formal process to create this program plan.Initial meetings started with facilities personnel to perform pre-programming requirements. A planning process wasthen developed for the project to assure consistency during the planning phase. Concurrently, investigations of thebuildings and site allowed the consulting team to gain familiarization with the existing Denison facility and libraryoperation, as well as its new site at Fitzsimons. This phase also included gathering initial facilities information andspace data.

Program Information:The consultants and at least one member of the planning committee met with all appropriate library faculty and staffto develop complete understanding of the programs. Discussion of current and future operational issues such aslibrary service strategies, material storage issues, teaching methodologies, program trends, logistical problems, andany program deficiencies was included. Enrollment trends and material acquisition rates were developed consistentto that which has been established with CCHE.

Develop Facilities Needs:This phase took the program data and developed facilities needs from that information. Using the current andprojected enrollment, faculty and staff projections, space needs were developed based upon actual requirements – aswell as acquisition rates and new library functions to perform the various functions of the library. Discussionsaround actual program delivery were then conceptualized into space needs to “check” the traditional “statistical”planning done previously. Space relationships were then defined. Bubble diagrams and space description sheetshelped describe how the various programs and spaces work together. Any unique conditions, special spaces, andequipment were also determined. Finally, space and equipment needs were summarized.

Conceptual Design:When the planning team completed thefacilities needs process, solutions werestudied as to how the spaces should be placedin order to begin the actual layout of the newfacility. Various options were developed andtested. Relationships with existing programsand planned programs at Fitzsimons helpedshape the proposed solution. Various worksessions provided valuable input and buy-infor the conceptual plan.

Project Description:All the variables described above were thenassembled to begin to describe the scope of workproject scope was then developed along with proArchitectural, structural, mechanical and electricadeveloping the project’s concept solution.

Implementation: With the help of the University, a funding plan anvision statements for the new UCHSC Library atprepared during the Spring of 2001 for submittal anticipated to be received by May 2002 with a sc

4

needed. This included all requirements for the new facility. Theject budgets, life cycle cost issues, and operating costs.l/telecommunication considerations were taken into account when

d project schedule were developed as follows. The mission and Fitzsimons were determined by early 2001. The program plan wasto CCHE in June 2001. Funding for design and construction isheduled project completion in December 2004.

Page 6: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

Fitzsimons Library Program Plan University of Colorado Health Sciences Center

June 1, 2001 5

Project Relationships: This phase summarized how the project fits the “total” picture within the University, including the relationship tocapital construction and controlled maintenance plans, master plans, and University goals and objectives. Otherrelationships of importance include the University of Colorado Hospital, the new Fitzsimons Campus, thecommunity, and the goals and objectives of the State of Colorado.

Page 7: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

Fitzsimons Library Program Plan University of Colorado Health Sciences Center

June 1, 2001 6

II. Program Information

It should be noted that this section describes both existing conditions and the ongoing development of a world-classhealth sciences center at Fitzsimons. It is the latter, however, that drives this program plan and compels constructionof a new library.

Description of Program

University of Colorado Health Sciences Center:One of four campuses of the University of Colorado system, the University of Colorado Health Sciences Center(UCHSC) campus is governed by the Board of Regents and headed by a chancellor. Located in the residential heartof Denver, the University of Colorado Health Sciences Center encompasses the Graduate School and the Schools ofMedicine, Nursing, Dentistry, and Pharmacy. Its widely renowned cluster of health sciences institutions includestwo teaching hospitals (University of Colorado Hospital and Colorado Psychiatric Health), the NCI-designatedUniversity of Colorado Cancer Center, and a constellation of research and treatment institutions listed among themost prestigious in the country.

More than 11,000 people – patients and their families, students, faculty, staff, and visitors from all over the world –stream in and out of UCHSC buildings every day. Students at the University of Colorado Health Sciences Centerenroll in undergraduate, graduate and post graduate education programs that offer emphases on basic and clinicalstudies, individual and community health programs, creative and preventive health practices as well as individualand team efforts. One of the buildings with the highest number of daily visitors is the library.

The University of Colorado Health Sciences Center is the major health research base in Colorado, annuallyattracting more than $200 million in research and training grants and contracts that advance the knowledge ofbiomedical sciences through basic and applied research.

Denison Memorial Library:Denison Memorial Library is the primary source of health sciences information for the University of ColoradoHealth Sciences Center. To support the campus mission, the library collects and/or provides access to materialsrelated to dentistry, medicine, nursing, pharmacy, and selected allied health disciplines, basic life sciences, and otherhealth sciences disciplines represented on the campus.

Within constraints of restricted funding, the library provides resources including scholarly books and journals, majorindexing and abstracting tools, reference materials, audiovisual media, and electronic resources, to support UCHSCcurricula, dissertation preparation, independent research, and clinical practice.

The library provides resources at the instructional support and research levels. In general, resources added to thecollection are appropriate for individuals studying at a graduate level or above, health care practitioners, and/orresearch professionals. Undergraduate level materials are not acquired, except for UCHSC programs that offerbaccalaureate degrees.

The library strives to provide adequate coverage in the areas of dentistry, medicine, nursing, pharmacy, selectedallied health disciplines, and the basic life sciences. As the only academic health sciences library in Colorado,Denison Library collects materials published by state health related agencies that are relevant to the needs ofUCHSC personnel. The library is not a depository for U.S. government publications, but selectively acquiresdocuments issued by the U.S. Department of Health and Human Services and other U.S. government documents thatare directly related to the health sciences.

Page 8: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

Fitzsimons Library Program Plan University of Colorado Health Sciences Center

June 1, 2001 7

The library maintains copies of master’s theses from the UCHSC school of nursing and dissertations for theUCHSC schools of medicine, nursing, pharmacy, and the graduate school. Dissertations and theses fromother institutions are not purchased. Books published by UCHSC faculty are acquired, as funds allow. Thelibrary is not funded to purchase rare, historical health sciences materials. These items are acquired onlythrough donations.

The following special collections are unique resources at Denison Library:

• Amesse Leisure Reading Collection – The small Amesse Collection is named for three generationsof Amesse family physicians. It includes current novels, biographies, non-fiction, and a selectionof magazines and newspapers. The collection provides a quiet diversion from the hectic world ofmedicine.

• Diversity Corner – The purpose of the Diversity Corner is to promote multicultural awareness andincrease sensitivity to racial, cultural, ethnic, and gender issues. The collection contains over 300fiction and non-fiction books and audiovisuals.

• Florence G. Strauss Complementary and Indigenous Medicine Collection – This growingcollection, supported by the Strauss Endowment, offers books, journals, and audiovisual resourcesrelated to complementary and alternative therapies from around the world. These resourcesprovide an opportunity to learn about different healing traditions, practices, and attitudes towardhealth and illness.

• Isabelle T. Anderson Library Science Collection – The small Isabelle T. Anderson Collection is aproject of the Education Committee of the Colorado Council of Medical Librarians. It containsinformation of interest to library professionals.

• Learning Resources Center Collection – A variety of health sciences audiovisual and computerresources are provided for lecture support and self-instruction by UCHSC faculty, staff, andstudents. Included in the collection are atlases, audiocassettes, slide sets, videocassettes,videodisks, CD-ROM’s, applications software, and instructional software.

• Reference Collection – The library maintains a non-circulating reference collection of print andelectronic resources to respond efficiently to requests for brief, factual information. Materialsinclude almanacs, bibliographies, biographies, core health science textbooks, dictionaries,directories, encyclopedias, indexes an abstracts, legal resources, statistical publications, and stylemanuals.

• Reserve Collection – Books, audiovisual media, and photocopies of journal articles may bedesigned for the reserve collection by a USHSC instructor or Denison Library staff member.These materials do not circulate but are checked out for use in the library.

• Waring (History of the Health Sciences) Collection – The Waring Collection includes modernimprints on the history of medicine and the health sciences, and rare medical books. It is namedafter James J. Waring, M.D., the first full-time Professor of Medicine at the University ofColorado School of Medicine.

Interlibrary Loan allows Denison Library staff to supplement the library’s permanent collection byobtaining copies and/or loans of items not available at Denison for library clients. Electronic interlibraryloan systems are used to obtain items needed by Denison clients and to extend the library’s resources toresearchers and users from other institutions.

Denison Library is one of five major University of Colorado libraries. The five libraries include theUniversity Libraries at the University of Colorado at Boulder, the Law Library at the University ofColorado at Boulder, the Kraemer Library at the University of Colorado at Colorado Springs, and AurariaLibrary at the University of Colorado at Denver. The university libraries are Denison’s primary resourcefor non-health sciences materials, especially basic sciences, behavioral sciences, and social sciences. Inturn, Denison Library is the primary source of health science materials for all university libraries.Additionally, by extending resources among the group through interlibrary loans, the university librariescollaborate on joint purchases of electronic products.

Page 9: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

Fitzsimons Library Program Plan University of Colorado Health Sciences Center

June 1, 2001 8

Denison Library is a member of the Colorado Alliance of Research Libraries. Alliance member librariescollaborate to acquire electronic products through group purchasing arrangements.

History, Role & Mission, Unique Program(s)

UCHSC:The University of Colorado Health Sciences Center is a public higher education institution and the onlyacademic health center in the State of Colorado and the Rocky Mountain Region. It is one of fourcampuses of the University of Colorado (CU) governed by the University of Colorado Board of Regents.

The UCHSC encompasses the Schools of Medicine, Nursing, Dentistry, and Pharmacy, the GraduateSchool, Colorado Psychiatric Hospital, University of Colorado Hospital Authority (UH), and variousrelated affiliated institutions. Several other health sciences institutions supporting the UCHSC include theBarbara Davis Center for Childhood Diabetes, the C. Henry Kempe National Center for the Prevention andTreatment of Child Abuse and Neglect, the John F. Kennedy Child Development Center, the UniversityPhysicians, Inc. (UPI), the Webb-Waring Institute, and the Eleanor Roosevelt Institute for CancerResearch.

With the three-part mission of education, research, and service, both clinical and academic, the campusserves as a hub of a broad network for health care delivery. These activities contribute to the overallmission of the campus – to improve human health. The University of Colorado Health Sciences Center hasachieved a national and international reputation for excellence in teaching, service, and research and is trulya unique regional and state resource.

The current mission statement for the campus was originally drafted in the late 1970s. Since that time, thestatement has been regularly updated through consultative processes. The campus’ mission statement isdescribed in full below.

The UCHSC Mission Statement:The mission statement of the University of Colorado Health Sciences Center (UCHSC) reflects the mainpurposes of the institution, that are: (1) the education of health professionals; (2) the delivery of both healthcare and community service; and (3) the advancement of knowledge through research in the healthsciences. The detailed mission statement for the campus is as follows:

• UCHSC offers programs and role models for the undergraduate, graduate and postgraduateeducation, and training of professional health practitioners. The programs reflect a balancedintegration of the basic and clinical sciences, individual and community health problems, curativeand preventive health practices, and individual and team efforts. The UCHSC develops andmaintains educational and training opportunities for continuing education of practicing healthprofessionals in the state through educational programs.

• UCHSC directly provides health care to patients at University of Colorado Hospital Authority,Colorado Psychiatric Hospital, the Children’s Diagnostic Center and the Dental Clinic, as well asat several campus affiliates. The University of Colorado Hospital Authority has a responsibility toprovide health care to many Colorado residents who are financially unable to secure such hospitalcare elsewhere. Health care services are comprehensive, ranging from first contact (primary) careto highly specialized (tertiary and quaternary) care. The health care services also serve as afoundation for teaching and research activities.

• UCHSC advances health knowledge through basic and applied research, functioning as the majorhealth-related research base in the state. UCHSC maintains high standards regarding humansubjects throughout its research activities and ensures that any protocols used are intended tobenefit both the individual and mankind.

Page 10: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

Fitzsimons Library Program Plan University of Colorado Health Sciences Center

June 1, 2001 9

• UCHSC is an integral part of the University of Colorado’s multi-campus educational system. Thecenter is also a major technical and professional resource for other institutions in the RockyMountain Region dealing with health issues. The UCHSC communicates with manyconstituencies, including the administration, faculty, and staff at other campuses and schools,alumni, professional and civic groups, foundations, governmental representatives and agencies,and the public.

• UCHSC supports its educational, health care, research and external affairs programs by servicesaimed at achieving coordinated development, efficient and effective resource management, timelyand appropriate informational exchanges, and programmatic accountability. The center alsosupports its programs by maintaining a safe, secure, and pleasant environment for its patients andpersonnel, while upholding all aspects of diversity as a necessary condition to achieving theinstitution’s stated objectives and mission.

Denison Memorial Library:The mission of Denison Memorial Library is to support the University of Colorado Health Sciences Centerin advancing education, research, patient care, and community service.

Denison Memorial Library is a gateway to the world’s biomedical information, assisting the University ofColorado Health Sciences Center in accomplishing its missions and goals in education, research, patientcare, and community service. The information needs of UCHSC is the library’s paramount concern. Inaddition, within the constraints of limited funding, the library serves state and regional clients. The staff ofDenison Memorial Library strives for the highest quality of service as access is enhanced to the literature ofthe health sciences. The library provides instructional opportunities to acquire skills in information retrievaland management, acquires a specialized collection of print and electronic resources, and obtains remoteinformation in a rapid and cost-effective manner. Denison delivers data, information, and knowledge tolocal and remote users through the use of state-of-the art technology, especially health care providers inrural Colorado. Library faculty focuses on the practice of information service and teaching, with limitedtime for research activities.

Library history and current facility:Denison Memorial Library has been an essential part of the University of Colorado Health SciencesCenter’s history and development. The library was started with an endowment made by Ella StrongDenison, whose husband, Dr. Charles Denison, was an early Colorado physician and Professor of ChestDiseases and Climatology at the University of Denver, 1881-1885. Mrs. Denison donated funds in 1924for “The Charles Denison, M.D., Memorial Library.” The funds made it possible to furnish a library on thesecond floor of the School of Medicine. She also gave funds annually to purchase journal subscriptions.The library opened with 7,500 books and soon outgrew its quarters. In 1935, Mrs. Denison donated morethan $90,000 to build a new library building and badly needed auditorium which were completed in 1937.The library has continued to flourish, requiring new additions in 1962 and 1977.

Nearly 10 years ago, the UCHSC campus in Denver recognized that Denison was inadequate to meet itsusers’ changing needs. The Campus Center program plan, which was approved by the Board of Regentsand the CCHE in 1993, included a newly designed 120,000 gross square foot (gsf) library for the UCHSC’sDenver campus. That project, however, was halted when the Fitzsimons opportunity arose.

Denison Library’s area of 48,000 asf is cramped, and its study areas do not accommodate collaborativelearning. Staff is working in awkward and inadequate spaces, and in recent years the growing collection ofperiodicals and books has been accommodated by reducing the number of reader seats. Lack of space,inadequate information/study facilities, and inflexibility to meet changing educational needs have resultedin the institution receiving negative accreditation remarks. Although the library recently has alleviatedsome of its most critical deficiencies, these were intended only as a stop-gap measure until the campuscould build a state-of-the-art health sciences library at Fitzsimons.

Page 11: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

Fitzsimons Library Program Plan University of Colorado Health Sciences Center

June 1, 2001

Through IMPULSE, the library’s online catalog, users can locate audiovisuals, periodicals and books in thelibrary. In addition, the library staff creates linkages to thousands of online databases and journalsavailable via the World Wide Web. Multimedia teaching graphics and real-time video are alreadyaccessible to enhance the learning process in Denison Library, but the current facility lacks space tointroduce the latest technologies. The library has become the home for student email instruction andsupport along with allowing them to learn clinical techniques and master new skills through multimediatechnologies. Although the library also plays a key role in teaching information management skills, it hasnumerous limitations that complicate the ability of students and faculty to utilize the most recentinstructional software, adapt curriculum to new technologies, and, in general, enhance life-long learning.

Denison Memorial Library is a central point or home where many students and faculty conduct researchand study. Unfortunately, faculty and student demand exceeds the available seating. Adequate study spacejust does not currently exist. When the School of Pharmacy moved from the Boulder campus in 1992,nearly 500 new users arrived with no corresponding increase in library study space. The curriculum forhealth sciences students has changed to allow them to work in small groups, a learning technique thatresults in better retention of information and excellent professional judgment. Denison Library has a verysmall number of rooms where groups can discuss collaborative learning projects while consultinginformation resources. According to Colorado Commission on Higher Education standards, the librarynow has only 50% of the seating that should be available, and each year the library sees more users walkthrough its doors. Visitors now exceed 325,000 users per year, and recent studies and audits confirm thisnumber should double with the completion of a new facility.

The New Library at Fitzsimons – a broader vision:The new Fitzsimons library will be a signature building facing the northern side of the campus. Theplanned building will meet the more intensive needs of Fitzsimons development by growing from 48,800asf to 76,972 asf, at an estimated cost of $35 million.

“Today’s information technology isreinventing the ways in which we learn,work, and even think. But, technologytools do not replace people or theirinteraction.”

The new library will be the hub of knowledge atFitzsimons, linking critical components that comprisethe institution’s mission and serving as one of threemajor telecommunications switching points on thecampus. The library will support the new campusvision of an environment where advanced informationtechnologies are used by all personnel to conduct theessential daily activities of learning, research andclinical care. The scope of the future library print andelectronic collection will cover medicine, dentistry,nursing, pharmacy and such allied health subjects asdental hygiene, physical therapy and medicaltechnology. Basic science subjects such asbiochemistry, microbiology, immunology, cellular andstructural biology, biometrics, biophysics, genetics andpharmacology will be collected to support campusgraduate study and as a basis for the concepts,methodologies and data useful in health care andhealth care research.

10

Page 12: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

Fitzsimons Library Program Plan University of Colorado Health Sciences Center

June 1, 2001 11

“Information access in a heartbeat.”

The library will continue to be the primary health information provider to the Health Sciences Centerfaculty, students, staff and outside community. At the new library, users will be able to access up-to-the-minute information from online journals or databases from computers at the library, from their laptopcomputers at docking outlets throughout the facility, and from their office and home computers. Users alsowill have access to expert librarians, who are able to direct them to the best sources of reliable knowledgeand train users to search through the vast quantities of data on the Information Superhighway. The serversand network connections in the new library will provide an organized gateway to knowledge wherever itexists. With one click of a computer mouse, users will connect instantly to slides, videos or taped lectures.Or, by walking into the new virtual classroom they can interact with three-dimensional simulations andcutting-edge learning technologies.

The library will develop new partners at Fitzsimons to enhance patient education. More than one-fifth ofDenison Library’s present walk-in users come from off campus in their search for personal healthinformation. The new library facility will continue to play a major new role in serving Coloradoans. Incooperation with the Anschutz Center for Advanced Medicine, patient education information will beavailable to assist consumers in the community in making sound health care decisions. The library also willcontinue to service the information needs of independent health practitioners throughout the Denvermetropolitan area, the state of Colorado and the Rocky Mountain region. In addition, service to emergingbiotechnology firms at Fitzsimons will link the library with business and industry.

Recent advances in health care have created a new discipline that marries medicine with computer science.This new field, called health informatics, allows health providers to tap the incredible power of computingto study and solve health problems. Informatics reaches across all the health professions. Because thisemerging discipline requires fast response from computers and telecommunication networks, the campuswill house a new multi-disciplinary informatics center in the library, serving as one of three main digitalhubs for the exchange of electronic information. Programming the biomedical library of the future:In keeping with the revolutionary approaches to learning, research and health care at Fitzsimons, the newlibrary departs from the traditional and time-honored concept of a building that warehouses printcollections. Just as the University of Colorado Hospital redesigned its facility to be centered around andresponsive to the patient, so the new library begins by emphasizing user services and the space requiredthat fulfill its mission.

“The library is seen as a link between people and knowledge in this technology-intensiveera, helping to overcome barriers, meeting needs for information and providing navigationassistance.”

“Information Access and Study” space will occupy over 30,000 gsf in the building, all designed to meetdemands for computer access and interaction in small learning groups, the hallmark of how students andfaculty learn and work today. Reader seating will include a mix of open tables, stations wired for networkaccess, quiet individual spaces, and options for individuals to work collaboratively. High-end computerstations will allow users to tap multimedia resources and other computing-intensive tools that wouldoverpower the limited capacity of student or home PCs.

Due to the complexities of using modern information technologies, current campus personnel stream intothe library on a daily basis to receive individual assistance in tapping the digital world. Today andtomorrow, the library faculty and staff play an essential role in linking users with the information theyrequire, reducing the barrier technology can impose. The trend in academic health sciences centers is forusers to require both dedicated public computers as well as options for linking personal computers to thecampus network, either with physical plugs or via wireless technology. The new library will support all ofthese applications.

Page 13: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

Fitzsimons Library Program Plan University of Colorado Health Sciences Center

June 1, 2001 12

Library services will be delivered to users by departments organized and located around the concept of userconvenience, with the first floor emphasizing public service support from Circulation, Reference, and the DrugInformation Center (DIC). The DIC is a part of the School of Pharmacy purposely located in the library because ofits reliance on up-to-the-minute drug information sources and its complementary mission in dispensingpharmaceutical information to campus personnel and biotechnology firms.

On the second floor user space will also include the “Learning Resources Center” at approximately 4,000 gsf and the“Education/Health Informatics” area with another 4,500 gsf. Both of these spaces highlight support of students withthe latest learning technologies, including the rapidly developing three-dimensional simulations and othereducational technologies created by the UCHSC Center for Human Simulation and complimentary programsdeveloped by the National Library of Medicine. The library will feature a virtual reality room that allows users tointeract with these sophisticated learning programs in real-time and in 3D.

“Material Storage”space is only 34,000 gsf, decreased from the amount found in traditional libraries because onethird of the print collection will be housed in the more cost- and space-efficient Preservation and Access ServiceCenter for Colorado Academic Libraries (PASCAL) facility already operating at Fitzsimons under the direction ofDenison Library staff. PASCAL is designed to store research materials that receive limited usage, and it is notefficient to store more highly demanded volumes in this facility. Projections for future space needs have beenreduced to reflect expectations that print acquisitions will continually decline as more and more information isreleased in electronic format. Journals will be located on the third floor of the new library in stack ranges that canbe re-purposed as reader stations or for other uses as the library progresses further in re-balancing print with digitalresources, and as campus needs change. In traditional health sciences libraries the print journals are often located ona lower floor, but this program plan reflects an emphasis on use of electronic journals by the time the facility opens.Print books and special collections will be located on the top floor along with administrative offices.

Unique Programs:As the only comprehensive health sciences library in the state of Colorado and the Rocky Mountain region, DenisonLibrary provides unique collections and programs drawn upon by all higher education institutions in the state.Health sciences libraries share many characteristics with general academic libraries, but there are also significantdifferences related to the mission of a health sciences campus.

People who wish to educate themselves about a particular condition or appropriate therapy will have the services ofa Consumer Health Center. Here they will be directed to appropriate print resources, databases, and reliableinformation from the Internet. Because the new library at Fitzsimons will have a greater presence in the community,this program is expected to face increasing demand.

Denison’s Outreach Program provides assistance to rural health educators, distant students, and Colorado healthprofessionals who wish to obtain information necessary for high quality academic performance or clinical decision-making. This information support is often not available to users in their local areas, and the library serves as acentral resource to offer training opportunities or for answering inquiries at any time of the day or night.

The Research Support Service provides customized library services for UCHSC researchers, including advice onadvanced strategies for searching complex information technologies, guidance in selection of appropriate electronicdatabases and systems, and referrals to additional sources of information. This service will be closely integrated intoresearch and educational programs located in the new research complex at Fitzsimons.

Instruction in Health Informatics competencies is becoming a part of each professional school curriculum.Librarians teach UCHSC faculty and students basic and advanced strategies for databases and Internet searching,

Page 14: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

Fitzsimons Library Program Plan University of Colorado Health Sciences Center

June 1, 2001 13

database structure, indexing and vocabulary control, and application of evidence-based health care practice.

The Center for Emerging Information Technology’s (CEIT) mission is to provide cutting edge technology andexpertise for educational project development. Initial projects will include building a collection of streaming videoand construction of a multimedia database that supports the educational mission of the University of ColoradoHealth Sciences Center.

MedConnect is a cooperative program whereby nine Denver hospital libraries contribute their library holdings to theDenison Library Impulse online catalog. This affords Denison Library clients the opportunity to locate onlinematerials that are available in other local medical collections.

As the major health sciences information resource in the state of Colorado, Denison Library’s Interlibrary Loan andDocument Delivery Program provided over 10,000 loans to other Colorado libraries in FY 1999/00.

Denison Library has a unique special collection of over 5,000 books in the history of medical sciences, including anumber of rare books that are not available elsewhere in the state or region.

The Florence G. Strauss Complementary and Indigenous Medicine Collection specializes in books and audiovisualmaterials on various alternative therapies and indigenous health care practices. The collection is growing rapidlyand includes some of the most in-demand titles in the entire print collection.

Program Needs and Trends

Significant factors that shaped the Program Plan and conceptual building solution are as follows:

• Technology requirements and adjacency with the types of sequencing and entering a building all becomeimportant.

• Proposed library has 50% more area than Denison.• There is a growing student need for small group study “hi-tech work centers” as well as different

carrel/reading table design with computer outlets, task-lighting and at certain locations, wirelesstechnology.

• Today’s science libraries need more user seating than previously thought.• A satellite facility will remain at 9th Avenue and Colorado Boulevard.• Due to a transition from print to electronic media, space requirements for material storage must be balanced

with an ever-increasing need for IT/electronic media support.• The user split is 20% public walk-in traffic to 80% medical center students and faculty. It is anticipated

that unaffiliated visitors will increase even more as the library relocates to Fitzsimons, within the Auroracommunity.

• The anticipated bulk of reference use will continue to be students and faculty who are coming into thelibrary.

• Denison remains the prime Colorado medical library while serving a broader population outside of thestate. It is isolated within the Rocky Mountain West, because of its position between Omaha and Salt LakeCity and between Wyoming and Arizona. There is not another significant health science library collectionwithin this region.

• Denison has more demand for library faculty involvement with informatics than there are good,knowledgeable staff to fill this need.

• The library has become a central point of expertise in trying to help interface between people andtechnology and where there is a need to navigate links with electronic information. This trend willcontinue into the future indefinitely.

Page 15: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

Fitzsimons Library Program Plan University of Colorado Health Sciences Center

June 1, 2001 14

• Denison will provide teaching skills through the curriculum and one-on-one assistance with walk-in usersat the library. This prime educational role is becoming a major focus for the faculty.

It is projected that the University will increase its enrollment in the next five to ten years to 2,800 students. Thelibrary expansion will meet the growing information needs of students and faculty by expanding its collections,providing greater access to electronic databases, providing global retrieval of materials, and increasing instructionspace.

The major force behind construction of a new facility for the Denison Library is the relocation of the entireUniversity of Colorado Health Sciences Center. In addition, there is a need to respond to new demands forinformational services and an expanded mission that cannot be met at the existing location.

Currently, Denison Library experiences approximately 900 visitors per day and almost 325,000 annually. Patronscome for a variety of reasons including, but not limited to, refuge for study, obtaining materials, seeking assistancewith information access, research, group interaction and study, presentation or project development, etc. No matterwhat the reason, patrons are seeking additional levels of service. Libraries of today are not just warehouses; they arethe critical link connecting patrons with the information they need and a vital player in what many refer to as the“Information Age.”

New services have put additional pressures on library programs. While new technologies may improve efficiencyfor some programs, they demand additional time, resources, and facilities for libraries. Teaching a student how toaccess today’s nearly unlimited resources, manipulate data sets, present multi-media presentations, shareinformation, perform research, and prepare communications are just some examples of the new trends in libraryservices. Each and every trend is causing the need for additional space as well. Contrary to the perception thattechnology is saving space, the average amount of space needed per patron is on the rise due to constantly changingtechnology, improved education, and demand for new services.

Relationship to Academic or Institutional Strategic Plan(s)

Relation to Other Programs/Agencies:In the concept of a new advanced learning environment at Fitzsimons, some educational space will be distributedthroughout the campus, integrated with research and clinical space, while reflecting learner-centered approaches –long a hallmark of library service. The research sector and biotech park adjacent to the campus will encourage newopportunities for public/private partnerships and lead to new knowledge, for which the library can provide timely,effective access and support. Clinical facilities will be developed to reflect new approaches in health care, andinformation services professionals from the library are important participants in clinical teams searching andevaluating the latest evidence to support team decisions. Innovation in education, research and clinical care will becomplemented by the library’s vision of innovation in knowledge management, delivery and learning.

The UCHSC library is actively developing its services for consumer health. It has just created a consumer healthlibrarian position in conjunction with the National Network of Libraries of Medicine and is initiating other newprograms. The School of Nursing is also a strong advocate for supporting consumer health, and the University ofColorado Hospital is increasingly involved in providing information to its patients. In the future, the general publicwill be able to access some of the library’s resources via the Internet, some through their local libraries, atinformation centers on the Fitzsimons campus, and by walking into the UCHSC library itself. The UCHSC library’sintent is to work with regional public library systems as well as other institutions and libraries - so that locallibrarians can provide the first line of basic public health information - while providing links to the UCHSC libraryresources when consumers need a more detailed level of information. A network of consumer health informationcenters is being created in the new ambulatory and inpatient care facilities at the Anschutz Center for Advanced

Page 16: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

Fitzsimons Library Program Plan University of Colorado Health Sciences Center

June 1, 2001 15

Medicine to serve patients and their relatives on campus, and these will also will refer patients to the library formore advanced inquiries.

Denison Memorial Library is the largest biomedical library in Colorado, providing essential information andservices to the UCHSC community. The library periodically reviews and updates its mission, vision statements andvalues consistent with the mission and vision of the institution. The primary purpose of the Denison Library is toassist the UCHSC in accomplishing its mission and goals in education, research, patient care and communityservice. Denison Library enhances access to the biomedical literature, provides instructional opportunities forindividuals to acquire skills in information retrieval and management, acquires a specialized collection of resources,and obtains remote materials in a rapid and cost-effective manner. The library faces many challenges in the future.Ongoing, thoughtful strategic planning coupled with imaginative mechanisms to garner support assures the librarywill be positioned to support the campus.

In June 1996, the Chancellor appointed an Information Technology Council (ITC) to create a strategic plan for thecampus and recommend policies, procedures, and standards in computing and telecommunications. The DenisonLibrary continues to play an essential role in the ITC. The ITC provides the institutional structure for planning,oversight, and evaluation of technology programs and policies. The role of the ITC in establishing technologyplanning goals for the library is especially important.

The campus ITC Strategic Plan was completed in September 1998. As a precursor to the development of the campusvision statement for the Master Plan and campus IT Strategic Plan, the ITC prepared a self-assessment in nine keyareas: academic computing, research computing, clinical computing, scholarly systems, health informatics,administrative applications, TeleHealth/TeleEducation, strategic business systems, and infrastructure/architecture.Those specific areas in which the library plays a major role include:

Support of Academic Computing:In support of the total learning environment, all schools continue to update portions of their curriculum. Campusefforts are underway in distance/distributed education, informatics, development of Internet sites, and enhancementof student computing. The UCHSC schools are currently implementing student competency requirements, facultydevelopment programs, and several models for the incorporation of technology into new learning approaches, whichare being implemented and evaluated. New learning spaces, including “smart classrooms,” are being planned forincorporation into the design of the new educational facilities at Fitzsimons. Migration towards digitized files isproviding vast new educational resources for faculty and students. The library has taken on a leadership role in thisarea.

Scholarly Systems:The range of electronic scholarly resources available to UCHSC faculty and students has expanded to include: theDenison Library’s online catalog of local holdings and linkages to remote resources, bibliographic data bases, full-text books and journals, sound and image files, numeric and other data banks, specialized knowledge data bases,patient/consumer health information tools, digitized versions of print or audiovisual materials, and instructionalcomputing programs. The library will continue moving in the direction of making all tools available across thenetwork and in adopting information standards that facilitate accomplishment of this goal.

Health Informatics:Health informatics is becoming an area of increasingly high priority at UCHSC. The discipline and issues of healthinformatics have been the focus of efforts by selected faculty members for many years. Informatics faculty continueto contribute new areas of research and are increasingly becoming critical team members of basic and appliedresearch groups. Informatics faculty in all of the UCHSC and Denison Library are involved in the establishment offaculty development programs, student competency issues, and IT infrastructure planning. The rate at whichinformatics components are integrated into the curricula across the schools is accelerating rapidly.

Page 17: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

Fitzsimons Library Program Plan University of Colorado Health Sciences Center

June 1, 2001 16

Support of TeleHealth/TeleEducation:The UCHSC recognizes that TeleHealth and TeleEducation programs have the potential to support the delivery ofhealth care in a more efficient manner that helps generate revenue for clinical programs. Several successfulprograms are in place, including a TeleHealth contract for services between the Department of Corrections, UCHSCand selected affiliates. UCHSC is committed to maintaining a core of TeleHealth services and will expand themwhere new partnerships are mutually beneficial. The library will continue to support the expanding campustelehealth and teleeducation program initiatives.

The expanding role of the Denison Library, including the vision for the new library facility at Fitzsimons, is alsointertwined into the campus 2020 vision statement that guides the continuing development of the institutional masterplan. As stated in its 2020 vision statement, the University of Colorado Health Sciences Center's paramount andtime-honored mission of education, research, patient care, and community service will continue into the nextcentury. UCHSC is a unique regional public resource because it generates new knowledge and translates thesediscoveries to superior health education and human health.

The UCHSC, in partnership with health network and affiliates, will be responsive to the community's health careneeds by educating individuals as members of interdisciplinary professional health care teams, and by preparingtomorrow's leading health scientists. Physical proximity and integral working relationships among and betweenclinicians and scientists will foster new levels of collaboration and integration. Partnerships among faculty,students, staff, affiliates, and the community will foster the development of new knowledge, and this knowledge willbe applied to the prevention and treatment of human disease and to the improvement of human health. Theinstitution also will create partnerships among faculty, students, and consumers in offering the highest quality ofhealth care, and providing access for citizens to the latest scientific findings concerning the promotion of health andthe treatment of disease.

The UCHSC will serve as an umbrella organization for superior science in the region, providing the basic andapplied health-related research technology and the intellectual capital to enhance activities of other regionaleducation, research, and industrial entities. The integration of functions in academic and clinical endeavors, set intothe new Fitzsimons campus, will foster a sense of community for faculty, students, staff, and patients. Thosefunctions and facilities will create a supportive culture that promotes the highest technological advances as well ashuman caring throughout the continuum of science and health care. The UCHSC will collaborate with and provideservices to a global community through the use of innovative technology applications in all of its missions. The newlibrary at Fitzsimons is truly an essential part of this exciting vision, a place where all personnel come together.

Existing Programmatic/Operational Deficiencies:The current Denison Library facility fails to meet campus programmatic needs in several areas. Space is notavailable to add new technology or computers to reflect the numbers required by users or in a teaching room. Thereare few areas for quiet reflection. Unmet user demand for small spaces that support collaboration has resulted ininappropriate group conversations occurring everywhere in the building, often raising noise and distraction levels tothe point where they are a constant source of irritation to other users. The library staff receives constant complaintsabout ambient noise.

Staff is forced to work in cramped spaces that do not meet CCHE guidelines restricting their ability to interact withand serve library users. Space is not available for additional staffing to meet increasing user demands. The physicallayout is confusing and creates numerous areas that users avoid because of physical discomfort due to poor air flowor temperature control. Lack of a loading dock complicates service delivery of any materials or hardware, andmovement of people or materials within the building is cumbersome and inefficient.

Page 18: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

Fitzsimons Library Program Plan University of Colorado Health Sciences Center

June 1, 2001 17

Program Alternatives

Three options were considered for this program plan, and Option 1B was selected as most efficient in meeting theprogrammatic needs of the Fitzsimons campus. They are as follows.

Option 1:Build a state-of-the-art library at Fitzsimons in conjunction with the opening of the first major educational andresearch buildings. Two sub-options came out of this, which are:

1A. Reflecting the general pattern of the new campus, decentralize library staff and services across thespecialized education, research and clinical care buildings.

Use of this option would place some resources at the greatest convenience for some users, but wouldgreatly fracture most services and collections in a way that would frustrate and confuse the majority ofusers. Most library staff and materials serve multiple users and purposes, making it impossible to divideand place them in only one of the three major campus zones.

1B. Construct a central facility near the center of Fitzsimons that can be reached by all.

This option provides a strong central library that supports the popular desire for ‘one-stop shopping’ andbrings together both the latest information technologies and the staff who can assist users in masteringthese complex tools. In an information era the library becomes a point of interface between user anddigitized knowledge, where librarians teach information competencies and enable users to locate and applywhat they seek. This is best accomplished from one landmark location.

Option 2:Serve the new campus from the present location at 9th Avenue and Colorado Boulevard.

The advent of electronic databases of full-text books and journals promises a time when the content of manytraditional publications can be tapped remotely from any physical location. However, publishers remain highlyconservative about abandoning print, and pricing often makes digital information prohibitively expensive. At thesame time, print remains the most convenient and appealing format for many purposes, meaning it will not disappearby the time the new library is operating. Programs that move to Fitzsimons would be greatly handicapped if therewere no library personnel present to facilitate users’ access to complicated technology or providing currentinformation required in making sound decisions. Students are the largest group of walk-in users of the library, andtheir needs for personal assistance, access to computers and study areas cannot be met by the limited space andfeatures of the first Education building.

Option 3:Relocate the entire print collection to PASCAL.

PASCAL provides the cheapest and most efficient storage option for research materials in limited demand. Thedesign of its shelf configuration, however, is based on the premise that items will not be requested frequently. It iscumbersome and costly to have to pull and re-shelve volumes on two-thirds of the stored materials because they arenot within convenient reach, and the aisles are not designed to accommodate multiple vehicles. Consequently, itwould be slow and expensive to retrieve and re-shelve popular materials from this facility. Operating costs wouldmake this an inefficient option.

Page 19: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

III. Facilities Needs Total Space Requirements Space required by library services is what drives the size of the facility. A complete space analysis projects space needs to be 76,972 assignable square feet. This translates to a projected total building area of 116,000 gross square feet. The following summary outlines the projected space per program. The detailed analysis is included in Appendix Section 7.03, Library (L-Tables) and Building Space Tables. The appendix includes needs per program along with modified versions of the Colorado Commission on Higher Education “L-Tables” which projects library specific spaces. It was determined not all L-Tables were applicable or accurate enough to use for the entire analysis. Function-specific breakouts and space per program was more realistic. This was verified by the preliminary concept design results, which are included in the program plan. Space Type ASF GSF General 8,320 10,563 Administrative 2,155 3,171 Circulation 2,320 3,397 Learning Resources Center 2,860 4,141 Reference Services 2,550 3,754 Resources Services 1,210 1,765 Systems-Databases 3,775 5,251 Material Storage 23,607 33,076 Education/Health Informatics 2,945 4,359 Information Access and Study 19,530 29629 Drug Information Center 2,330 3,386 History of Medicine 2,950 4,074 Specialized Building Support 2,420 3,119 Roof Mechanical* 0 6,315 TOTAL 76,972 116,000 *The roof mechanical penthouse is enclosed, “raw” unheated space and not considered assignable area. Vertical circulation is labeled as “specialized building support” on the plan, but is programmed within the “General” area. Unique or Special Features

“The UCHSC Library…faculty and staff will lead the region in meeting multiple needs for excellent health information and in providing the personalized assistance that enables users to tap effectively the latest electronic and print resources…As a unique Colorado resource, it will serve all residents of the West who seek to improve their health.”

- Mission statement, “Library @ Fitzsimons” October 2000

The library as proposed in the program plan responds to its central mission, expressed in the space planning and all of its component systems that have shaped the solution. Siting was selected by UCHSC to emphasize centrality of the library’s function as it will be a major informational hub for the Fitzsimons hospital facilities, educational and research institutions, and the biotech partners located on Campus.

Page 20: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

Fitzsimons Library Program Plan University of Colorado Health Sciences Center

June 1, 2001 19

A further linkage to neighboring communities will be created by the eventual access provided from the future lightrail and bus stop located at the north end (East Montview Boulevard) of Fitzsimons Commons. There will be noother resource in the Rocky Mountain region as effective as the Fitzsimons library that can serve so many diverseuser groups.

“What is the library for the next millennium? It is a place, not a virtual reality. It will includeconnections, links, access, outreach, distance learning, and education as well as books, journals,media and databases. It will be a place where students and readers can come to search forinformation or delve into the treasures of the past. It will be a place to read today’s latest medicalnews or to sit and contemplate. It must continue to support scholarship and research.”

- Bull.Med.Libr.Assoc.87(2) April 1999

Because library services are likely to continue to change and evolve over the coming decades, functional spacesmust be easily adaptable to shifting patterns of service and use as well as technological transformation. Flexibility isof primary importance in planning space for electronic resources, due to the difficulty of predicting future needs anduser demands beyond the next ten years. An academic library needs to be highly flexible, while at the same timestill performing traditional teaching and service roles.

The new Fitzsimons Library will be designed for convertibility, with intellectual and social interaction that does notimpinge on privacy. The built solution must take advantage of minimal partitions, allocating as much usable area aspossible to open space, incorporating ubiquitous telecommunications and power capabilities, while providingversatile, “smart” mechanical/electrical systems.

All floors will have access to abundant natural light (with potential natural ventilation) for study and officefunctions, expansive views looking out at all directions including the north reflecting pools and generous landscapedmall at Fitzsimons Commons. They will add to an ambience that enhances the daily experiences for both staff andusers alike. Space adjacencies have been conceptually determined with adequate areas provided for current andfuture expansion needs.

The final design of the Fitzsimons library must harmonize with and complement the original Fitzsimons hospitalbuilding (Building 500), an important landmark on the Fitzsimons campus. A secondary entrance connecting thelibrary to the south campus buildings - directly opposite the historic Building 500 - has been proposed which willcirculate through a twenty-four hour study / coffee bar area: an important amenity of the library that uniquely servesthe immediate needs of the UCHSC Campus. The primary north front entrance, facing the future FitzsimonsCommons, will eventually fulfill its intended role as a prominent gateway towards the emerging biotech researchpark and regional community access.

Health, Life Safety, and Code Issues

The following codes govern this project:

• 1997 Uniform Building Code (UBC)• 1997 Uniform Mechanical Code• 1997 Uniform Plumbing Code• 1997 Uniform Fire Code• 1997 Uniform Building Code Standards• 1997 National Electrical Code (NFPA No. 70)• 1994 Life Safety Code (NFPA No. 101)

Page 21: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

Fitzsimons Library Program Plan University of Colorado Health Sciences Center

June 1, 2001 20

• National Fire Codes (13 Volumes by NFPA)• American National Standards Institute Standard Safety Code ASME with Interpretations A17.1, A17.3,

A17.5, QEI-1 (most recent)• 1994 (as amended) 2nd Edition – State of Colorado Model Energy Efficiency Construction and Renovation

Standards for Non-Residential Buildings• C.R.S. (Colorado Revised Statutes) Volume 3B – Title 9, Article 2 – Safety Glazing Materials• 1991 Americans with Disabilities Act• 1997 Uniform Code for Building Conservation• Uniform Federal Accessibility Standards (UFAS)

There are no health, life safety, or code issues as this is new construction. The general UBC requirements for thisproject are included in Appendix Section 7.08, Program Plan Regulatory Analysis..

Site Requirements

Campus Framework:The master planned campus structure is made up of analternating framework of pedestrian and vehicularcorridors. These corridors are coordinated with theexisting and proposed underground utilities on thecampus. The proposed site for the library lies directly tothe north of the administration building or Building 500,which anchors the core of the UCHSC campus.Opposing the system of east/west pedestrian andvehicular corridors is a series of campus greens or openspace quadrangles which run north/south and serve toorganize the land use and architectural framework of thecampus.

Building 500 forms the terminus of the primary campusentry and identity axis from East Colfax Avenue. The proposed library site forms the south end of the plannedFitzsimons Commons which runs north/south from the historic Red Cross Building toward the back of Building 500.The library building would best benefit from the planned Fitzsimons Commons by orienting its primary frontentrance to the north, thereby establishing a formal and ceremonial relationship with the green.

Facing the building south would cause the building to have a very limited landscaped forecourt, and its role as anacademic anchor land use would be diminished by the tension caused due to the back of house activities associatedwith the administration building. Orienting the library’s main entry to the south would also diminish the functionand animation of the Fitzsimons Commons and would cause the entry to compete with service, loading and trashactivities. These two strong, campus core axes are therefore “back to back” and facing away from one another.Phased diagrammatic site plans and alternate for the proposed library follow this section.

Development Phasing: Although the planned long range relationship between these two buildings will support the overall master plannedframework and north entry concept, the short term access and interrelationship of these buildings will indicate ahigher desire to approach the building and enter from the south. The planned pedestrian spine running east/west justnorth of the library site will not be developed for several years after the completion of the library. The InterimDental Clinic, or Building 514, immediately north of the library site, will also need to function for several yearsprior to the final phase development of the master plan.

Page 22: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

Fitzsimons Library Program Plan University of Colorado Health Sciences Center

June 1, 2001

For these reasons a secondary, south library entrance is planned. The development of the library site shouldaccommodate this phased access approach. Particular attention will be given to the immediate interrelationshipbetween the library and Building 500 both in the short and long term. The service and trash activities of the library,Building 500, and the research and education buildings should be concentrated to the east and west of thenorthernmost portion of Building 500. The landscape and urban design of the space immediately between these twobuildings would then be of a pedestrian nature, safe from vehicular and service traffic.

In the very long term, there may be reason to connect thetwo buildings with some type of bridging element,recognizing that this would introduce security and otherservice complications. From a campus planningperspective, it is appropriate to acknowledge that thenorthernmost portions of the Campus Master Plan will berealized in the final phases and thereby increasingly activatethe placement of the library’s front entry in laterdevelopment phases. The careful consideration to the southside of the library site and its phased development shouldserve to avoid adversely effecting the interim campusfunction. Future Library Expansion:During the early phases of the campus master plan’sdevelopment the sites immediately to the east and west of the lifor a west side parking area is not included in the Phase 1 budgehold the potential for eventual library building expansion. Thisthe master plan are realized and the parking structure proximate

Pedestrian Access:As previously discussed, pedestrian access ways will change ovimplemented. During initial development, the library will be acof the campus development, a secondary library entry route andprovided that additional operating costs can be funded. Those pcampus, the research and education greens, and the Anschutz Othe south. Strong, clearly defined pedestrian routes will need tothrough the many service and utility functions and appurtenanceresearch, education and library buildings. As the master plan’s entrance should be reinforced and accentuated as the primary acthe Alumni Center, the northern pedestrian spine, the Fitzsimonall serve to legitimize and superbly justify the northern library m

Vehicle Access and Parking:Just as the pedestrian routes will change over time, the vehicle aterm needs. In the initial phase of the library site development, proposed library building is accessed on the east side with a smsite from east to west, the disabled parking spaces are located inbuilding’s front entry. A small component of parking spaces foeliminated for eventual building expansion. These spaces are faUltimately, the disabled parking spaces will be in the planned pnorth of the library’s main entrance. Costs for a west side parkirequest for the library.

21

brary will serve as interim surface parking lots. Costtary request for the library. These adjacent sites

would best occur only after the northern portions of to the library is built and functional.

er time as elements of the master plan arecessed primarily from the south. In the early stages entrance may be necessary and appropriate,edestrians arriving from the existing developedutpatient Pavilion will all approach the building from be established in order to guide the pedestrians related to the back sides of the administration,final phases are developed, the northern librarycess point. The development of the Campus Center,s Commons and the adjacent parking structure willain entrance.

ccess is planned to meet both short term and longvehicle access is served by East 19th Avenue. Theall parking lot. Due to the grade change across the the east lot, proximate and at grade with ther staff and visitors will remain after these lots arecing south along the north side of 19th Avenue.arking structure to be built immediately west andng lot are not included in the Phase 1 budgetary

Page 23: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

Fitzsimons Library Program Plan University of Colorado Health Sciences Center

June 1, 2001 22

Service and Loading:Because of the grade change from east to west, the loading and building service dock is planned on the western sideof the rear of the building. Care should be taken to visually screen this area from the south entry to the building andthe centerline pedestrian connection to the administration building. Service vehicle entry will be from theeasternmost site access off of 19th Avenue thereby allowing the trucks to back into the loading dock and drivestraight out the western site entry off of 19th. The service drive between the east and west parking areas shouldinclude specialty pedestrian paving as a visual cue to vehicles that this is a pedestrian environment.

Bicycle Parking:Bicycle parking for the library site can be accommodated in the adjacent vehicle lots on the east or west of thelibrary or in the south pedestrian zone outside of the rear entrance. Ample numbers of bike racks should be plannedto accommodate at least 50 bicycles and should be associated with designated campus-wide bicycle routes.

Utilities:The campus master plan identifies a phased utilities development scenario and addresses the routing and timing ofinfrastructure development. The site is well served on three sides with all necessary utilities and communications.East 19th Avenue serves as a campus wide utility corridor and the open space pedestrian linkages directly to the eastand west of the library expansion sites are also primary utility corridors. Alignment adjustments to the existingsteam distribution line north of the library will be necessary to provide the library’s intended alignment along thepedestrian spine north of the entry.

Landscaping:Landscaping, landscape materials selections, and outdoor lighting for the library site are to be developed in supportof and in coordination with the UCHSC Landscape Master Plan. The library site is interwoven into the fabric andpatterns of the campus landscape theme, character and urban design framework. Every effort should be made topreserve existing mature trees and enhance and integrate the patterns established within surrounding developmentprojects.

Key to the success of the library site is the ultimate development of the Fitzsimons Commons onto which the libraryfronts. Although this area is planned to include a significant retention pond, the Commons should be designed toprovide passive outdoor use for reading, outdoor eating, strolling or waterside interaction and small group meeting.The program diagram indicates paired, geometrically shaped ponds, although a single pond on axis to the librarymay serve as well. Costs for this work are not included in the Phase 1 budgetary request for the library.

Topography: Given the flat nature of the campus as a whole, the library should be placed vertically so as not to be affected bypotential high water storm events. The proximity of the retention ponds and the lack of significant topographyindicate the need for detailed study of the building’s vertical layout and placement. In all cases positive drainageaway from the library structure must be ensured.

Alternate Development Framework:As an alternate, the campus master development plan may address the notion of terminating vehicle traffic on 19th

Avenue at either side of Building 500. This idea, if feasible from an overall campus circulation standpoint, wouldfurther support the pedestrian connectivity between the library and the administration building. Eliminating vehicleand service traffic from the north of Building 500 to the south library entry would potentially ease the “back ofhouse” impact of these two buildings while resolving the tension between the opposing cross-campus axialrelationships. A diagrammatic site plan of this alternative follows this section. Costs for this work are not includedin the Phase 1 budgetary request for the library.

Page 24: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

Fitzsimons Library Program Plan University of Colorado Health Sciences Center

June 1, 2001 23

Diagrammatic Site Plans

The following pages graphically depict site design proposals described in the text above:

• Proposed Library Site Plan for Phase 1 Construction• Proposed Library Site Plan for Current Campus Master Plan• Proposed Alternate Library Site Plan at East 19th Avenue

Page 25: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

5Design, Inc. Landscape Architecture and Planning

Page 26: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

5Design, Inc. Landscape Architecture and Planning

Page 27: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

5Design, Inc. Landscape Architecture and Planning

Page 28: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

Fitzsimons Library Program Plan University of Colorado Health Sciences Center

June 1, 2001 24

Equipment Requirements

“Today’s information technology is reinventing the ways in which we learn, work, and eventhink…And that’s where librarians are rising to the challenge of augmenting access to digitalresources, imparting technological competencies, and giving personalized guidance in findingscattered kernels of knowledge in a vast universe of data.”

Special equipment needs associated with this project include the acquisition of technology for instructional spaceswithin the new library. Teleconferencing, information access and study areas will require new technologies that willbe available throughout the Fitzsimons campus allowing higher utilization rates and improved teachingmethodologies. High-tech rooms will need to be capable of being “smart” classrooms when the building opens.These rooms need to be equipped with a combination of new projection and sound systems, internet and campusnetwork access, computer ports for lap top connection, lighting control, video/data jacks, high tech lecterns withVCR and disk capabilities, and possibly one or two document cameras.

It is assumed that approximately 8.7% of the total project cost of this facility will be allocated to furnishings andequipment. The estimated construction cost of $35,000,000 includes fixed equipment such as shelving, circulationand reference desks. The estimated cost of conventional furnishings and equipment will be $4,010,000. Includedunder the category of conventional library furnishings and equipment are user and staff computer workstations,printers, scanners, photocopiers, digitizing workstations, data drops/electrical outlets, wired furniture, circulationequipment, and security equipment.

The furnishings and equipment for the virtual environment and simulations facility are not considered conventional,however, and thus could add an addition of $1.2 million to the cost of the project for these facilities. This additionalcost is included in the fundraising campaign and is not part of the capital construction request from the State ofColorado.

A space in the new library will be constructed in order to accommodate a virtual reality studio with the followingminimum specifications: a 10x10x10 foot structure that sits in a 35x25x13 foot darkened room with high resolution,3-D graphics video and audio capabilities, rear projected screen walls, and a front-projected floor.

This studio will also include the requisite workstations, applications software, networking software, and virtualreality (VR) input/output devices as another set of minimums. There are at least six VR companies who marketcomplete studios, and groundbreaking work on VR studio design and applications research is currently underway atthe University of Illinois Electronic Visualization Laboratory and similar laboratories at the University of Michiganand University of Washington. Thus, by the time of construction, selection on studio design can be made on thebasis of best practice. See Appendix 7.10, IS Design Requirements for UCHSC standards that apply totelecommunications for this project.

Acquisition of Real Property

All property pertaining to this project is already University (State of Colorado) property. There is no need for theacquisition of additional lands, buildings, or other properties for this project.

Page 29: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

Fitzsimons Library Program Plan University of Colorado Health Sciences Center

June 1, 2001

IV. Project Description

General Project Description/Scope of Work

Master Plan Vision Themes:

“Design the library as a place to think…”

The conceptual site, architectural and engineeringsolutions proposed herein are responding to currentprogram standards and infrastructure needs of the libraryat Fitzsimons and how it can best serve its constituents:the UCHSC staff, patients, students, biotech researchpartners and the community at large. Each component ofdesign, as presented in the following summaries, is part ofan overall matrix which will successfully express andenhance the library’s mission, already clearly defined in previ

Key thematic determinants that influence this particular facili

• Interdisciplinary – encourage collaborative interdisc• Integration – support greater integration amongst ed• Access – provide access to current, high quality kno

educational, research and clinical experiences – andconsumers in the region;

• External partners – develop external partners throug• Core support services – provide an infrastructure tha• Technologies – provide leadership in the application

of knowledge;• Flexibility – develop an environment notable for its f

Role of Remote Storage:PASCAL is a state-funded facility that represents an importanfacility will hold up to 1.6 million volumes in temperature anddesigned to reduce library operational costs for Denison LibraLibrary, the University of Denver, and other potential library which are transferred to PASCAL will continue to be reflectewill be able to request delivery back to their home campus by

Denison Library began transferring materials to PASCAL in tcritical part of a health sciences library collection, older seldois estimated that between 2,000 and 5,000 volumes will be moThis reduces the need for stack capacity in the new library.

Backfill space for the existing Denison Library:Since the Schools of Nursing and Pharmacy will remain at theFitzsimons, in order to serve these programs, it is proposed thscaled-down satellite operation. This could provide study spareference assistance and fuller electronic assistance via Virtua

25

ous sections of this Program Plan.

ty are:

iplinary work, scholarship and practice;ucation, research and clinical activities;wledge which is effectively integrated with USCHC

to share that knowledge with professionals and

h alliances and affiliations;t enables the library to meet users’ needs effectively; of new technologies to the management and utilization

lexibility and adaptability.

t public-private partnership. This high-density storage humidity controlled high-density storage space. It isry, the University of Colorado at Boulder, Aurariapartners. Valuable but low-use research materialsd in the online catalog of the owning library, and users a number of options.

he spring of 2001. Because journals are the mostm-used books will be the first materials transferred. Itved annually to PASCAL over the next four years.

9th Avenue campus when the new library opens atat the first floor of Denison Library be maintained as ace (preferably 24 hours a day); limited personall Reference Software; computers for accessing the

Page 30: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

Fitzsimons Library Program Plan University of Colorado Health Sciences Center

June 1, 2001

online catalog, the Internet and other electronic resources; a very small print collection of essential referencematerials not available in digital format; a small print reserve collection to support circular assignments; and dailycourier service for materials delivery between campuses. Other space in the building could be re-purposed or shutdown temporarily. It is assumed that the necessary furniture and computers would be retained, with replacementsbeing part of the program budget for the new building. One issue that would need to be dealt with at this site, is thelack of handicapped accessible toilets on the first floor. Building remediation at the Denison site is not included inthe budget for the new Fitzsimons library.

Site Issues:For scope of work regarding site design, seePart III, Site Requirements section of theProgram Plan.

Architectural Issues:State-of-the-art library design, powerful siteinfluences, campus needs and an ability toexpand help shape the building footprint thatultimately meets Phase II space requirementsthrough FY2019/20. The program plansolution addresses Phase I building space andpreliminary library departmental adjacencies. The structure consists of four floors of approximately 26,000 grosssquare feet each, plus a partial usable basement and mechanical penthouse.

Library issues that influenced the internal workings of conceptual floor plans, include:

• New ways of working – spaces that can accommodate new functions and patterns of use;• Virtual reference – mobile technologies and universal network access;• 24/7 service – a computing laboratory (study area) that is open 24 hours, seven days a week (also serving as

a secondary access into the library);• Managing the right balance of resources – planning for the appropriate mix of print (material storage) and

electronic resources;• Support the right balance of collaborative versus private settings – mix of various work environments that

encourage learning, study and research;• Create the best distribution of library and

information access/study areas –valued, time-honored qualities can beretained alongside an increasingly virtualfuture.

A powerful influence on building massing andselection of exterior materials is the necessaryharmonious relationship between the library and itsmassive historic neighbor to the south, Building500. The library siting as the “front door” toFitzsimons Commons makes it a preeminentstructure that deserves careful formalconsiderations worthy of a profound architecturalstatement.

26

Page 31: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

Fitzsimons Library Program Plan University of Colorado Health Sciences Center

June 1, 2001

Through design, UCHSC Institutional Master Plan standards must also be fulfilled by choosing appropriatehierarchies of scale, textural and color palettes as well as meeting guidelines for sustainable and “smart” buildingdesign.

Specific exterior treatments proposed include brick masonry, pre-cast limestone lintels and base, large windowedareas for sweeping north-facing views that are deeply recessed with metal sunscreens for reducing solar loads at theeast and west. As the library is a free-standing structure, glass and metal “eyebrows” have been placed at the rooflevel for visual identification of the library as it is approached from all directions.

Each floor plan is organized around a large flexible rectangular box that provides maximum flexibility while flankedby internal light wells and smaller areas for office functions and study. The first floor contains two entrances, theprimary facing Fitzsimons Commons and a secondary one through the 24-hour computer/study area (with coffeebar) directly opposite Building 500.

While two entrances are not optimal forlibrary materials management and circulation,the unique requirements of the UCSHCcampus at Fitzsimons necessitated thisdecision. Other functions on the first floorinclude reference services, information accessand study areas, resource services, theloading dock and the School of Pharmacy’sdrug information center.

The second floor contains information accessstudy areas, systems-databases, the learningresource center, education and health informaticsaccess and study areas. The fourth floor is planngallery/display area and the special collections.

The partial basement will include central storagetelecommunications rooms. The enclosed roof pview. Use of roof space for social events or outd

Structural Issues:Overview:The structural system for the proposed library musshould:

• Have the capability to support stack load• Have sufficient mass to provide a quiet e

numerous partitions;• Be of sufficient inherent lateral strength t

solid elements;• Have the capability to allow for variation

elements, etc.

The reinforced concrete system proposed is one stFitzsimons library. The design proposes to configu

27

. The third floor will house the journal collection with informationed for book stacks, administrative offices, staff spaces, a secured

for the entire library, mechanical, electrical andenthouse is entirely for mechanical equipment screened from publicoor reading may be considered in final design.

t have a variety of unique capabilities. Among other requirements it

s with enough flexibility to allow for many different configurations;nvironment in large opening areas without the dampening effects of

o allow for large open use areas with the smallest amount of wall and

s in the floor plan like changes in bay size, curved and radial

ructural system having all of the capabilities that are desirable for there this system as a two-way beam and slab utilizing the concrete

Page 32: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

Fitzsimons Library Program Plan University of Colorado Health Sciences Center

June 1, 2001 28

beam and column frame in combination with any amount of concrete core walls that may be included in the floor plan.For the initial study, a 30 x 30 foot bay size has been established as it works well with the anticipated use.

Foundations:A geo-technical report will be prepared for this structure that will determine the appropriate foundation for theanticipated column and wall loads. In keeping with allowing for future adjacent construction it is anticipated that thefoundation will most likely be a shallow footing system. Sizes may be estimated after the preliminary geo-technicalinvestigation is conducted.

Basement Walls, Grade Beams:Basement Walls: Provide at least 12” thick reinforced concrete basement walls with reinforcing ranging from 62 to 90pounds per lineal foot, depending on the depth of the basement below the exterior grade. At locations without abasement, provide at least a 12 inch wide by 48 inch deep reinforced concrete grade beam with reinforcing rangingfrom 24 to 72 pounds per lineal foot, depending of the exterior wall and foundation configuration.

Basement and First Floor Slab Construction: Provide a 6” concrete slab on 6” of aggregate on natural material or non-swelling structural fill as indicated by the geo-technical report. The slab will be reinforced with #4 @ 12” each way and jointed with soft cut sawn control joints notexceeding 144 square feet.

Structural Floors: Provide a cast-in-place two-way beam and slab system. The total depth of the structure will not exceed 24” except atthe exterior spandrel beams where it is determined by the best way to support exterior wall construction. Slabs range inthickness from 8 to 10 inches depending upon the loading and opening configurations. Beams range from between 24”deep by 60” wide to 24” deep by 72” wide depending upon the loading and span configurations. Beams frame toreinforced concrete columns ranging from 24” to 30” square. The structural frame is designed to achieve the followingfire protection ratings:

• Construction Type I-FR • Concrete columns 3 hrs. • Concrete floor construction 2 hrs. • Concrete roof construction 2 hrs.

Lateral Load, Resistance:The structural requirement to support all lateral loads (resistance to wind and seismic forces) will be provided by adual system of beam column frames and shear walls. Shear wall and frame interaction will be determined once thequantity of wall elements available has been determined. This system has the flexibility to utilize any amount (nomatter how small) of walls to provide the most economical support system.

Design Loads:Minimum floor loading will be designed for a 100 pounds per square foot (psf) live load. Stack areas, or potentialstack areas are assumed to carry a minimum of 150 psf up to 400 psf live load depending upon the need or desire forcompact shelving.

Concrete Properties:Provide normal weight coarse and fine aggregate plant mixed concrete mixed with Type II cement at foundations,Type I Cement elsewhere. Fly Ash use will be encouraged and should range to around 20% of the cement total. A28-day compressive strength of 4,000 psi will be utilized for footings, walls and grade beams and slabs on grade. A 28-day compressive strength of 5,000 psi will be utilized for all beams and columns. Reinforcement shall conform to

Page 33: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

Fitzsimons Library Program Plan University of Colorado Health Sciences Center

June 1, 2001 29

ASTM 615, Grade 60. All column and wall column splices to be made with mechanical couplers that are capable ofdeveloping 125% of the tensile strength of the reinforcing.

Concrete Curing and Finishing Expectations:

• Curing: Shall comply with ACI 318 but not less than 7 days, utilizing a moisture retaining covering.• Finishing Horizontal Surfaces:

Broom finish - exterior wearing surfaces;Steel trowel finish - interior slabs that are visible or covered with carpet or resilient flooring.

• Hardener: Required for visible interior concrete wearing surfaces.• Finishing Vertical Surfaces: Provide rubbed finish for concrete exposed to sight. As such it shall be formed

against selected form lining, and rubbed with approved abrasive rocks and a Portland cement paste to auniformly smooth and evenly colored surface.

Concrete Form Removal Expectations:Remove forms to comply ACI-318. Horizontal forming removal shall not commence until the concrete has reached100% of the design strength nor sooner than 14 days after placement.

Miscellaneous Structural Steel Properties:All steel shall conform to ASTM-A572 or ASTM-36/50 dual specification with FY=50 ksi. All plates bars andangles shall conform to ASTM-A36. All tubes shall conform to ASTM-A500 with FY=50 ksi. All anchor boltsshall conform to ASTM-A449.

No painting will be required, with the exception of loose lintel angles, which shall be galvanized.

Mechanical Issues:Existing Mechanical System Utilities:Chilled water and steam utilities located in the 19th Avenue utility corridor are available to serve the library building.Chilled water is provided from the central plant at 40�F and steam is provided at 125 psig.

Twenty (20) inch diameter chilled water pipes and a 16-inch diameter high-pressure steam main serve the libraryarea. There are two (2) vaults (V3 and V4) which have valved tee-connections to which the library piping can beconnected. Vault V5 has steam connection points, but no chilled water tees.

Connections at either vault V3 or V4 will be determined during the design phase of the project. Chilled water andsteam meters are required at the connections for monitoring building energy consumption.

Proposed Mechanical Systems:Heating:

Heating will be provided through use of steam-to-hot water heat exchangers. A heat exchanger heating system will be provided for the terminal units (reheat coils) and the hot water preheat coil in the air handling unit. A separatesystem will be provided for the perimeter heating system (baseboard radiation or convectors). Each system willhave a parallel pumping arrangement, providing partial redundancy in the event of pump failure.

Air Handling Systems:

The air handling and distribution system will be configured so that three or four systems serve the building. Areasof the building which are occupied twenty-four hours a day should be on a dedicated unit, which will reduce theneed for operating systems and conditioning areas of the building unnecessarily. The air handling systems will

Page 34: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

Fitzsimons Library Program Plan University of Colorado Health Sciences Center

June 1, 2001 30

likely be located in a mechanical penthouse space. The units shall be indoor-type units with access by a serviceelevator for maintenance purposes.

Air system terminal units will be Variable Air Volume (VAV) boxes with reheat coils. Controls would be DirectDigital Controls (DDC). The return air shall have its own duct system to the air handling units.

Cooling will be provided either through an air-side economizer when outside temperatures allow or through chilledwater coils connected to the Campus chilled water system.

The Rare Book area will have a dedicated air conditioning unit with humidification control.

Chilled Water:

Connections to the Campus chilled water system will be done in accordance with the Fitzsimon’s Campus StandardPiping and Control Detail. The building will have its own building pumps that will be decoupled from the Campusdistribution system through a bridal connection. The building pumps should be variable flow for energy efficiency.Chilled water is available from the central plant year-round, 12 months a year.

Plumbing:

All restrooms and lounge areas will be furnished with fixtures that conform to the University of Colorado HealthSciences Center standards, building codes, and ADA requirements. Domestic hot water will be provided through asteam to water converter. Hot water will be distributed through a re-circulation system.

Fire Protection:

In accordance with the Uniform Building Code requirements for Group B Occupancy, the building will have a firesprinkler system. In addition, buildings four (4) stories or more, as with the proposed library, are required to have aClass I standpipe system.

To meet the pressure requirements of the system, a building fire pump may be required.

Snow Melt System:

The walkways located on the north side of the building will be provided with a snow melt system. The system iscomprised of a steam to glycol heat exchanger, imbedded plastic pipe in the walkways and controls.

Building HVAC Controls:

The heating, ventilating and air conditioning (HVAC) controls will be DDC and will conform to the current UCHSCStandard. At the time the Program Plan is being prepared, the type and manufacturer of the Building AutomationSystem (BAS) has not been finalized. All control actuation in mechanical spaces will be pneumatic type.

Cooling for Computer Servers/Telecommunication Rooms:

Rooms with high-density equipment cooling requirements will have dedicated room cooling units.

Electrical Issues:Site Utilities:

Page 35: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

Fitzsimons Library Program Plan University of Colorado Health Sciences Center

June 1, 2001 31

An existing electrical and communication infrastructure system (see Appendix Section 7.07, IS DesignRequirements) has been previously provided to this portion of the campus. An underground ductbank system hasbeen installed for both the 13.2 KV primary electrical service and the campus communications system. Theunderground system is routed below 19th Avenue, which is directly south of the proposed new library building.

Power:

The proposed new electrical service will be extended via new underground A&B ductbanks from an existing 13.2KV sectional switch located east of the existing building #511 parking lot. The sectional switch is fed from theexisting underground primary electrical service that consists of two separate utility feeds from the substation. The13.2 KV feeders will serve a pad mounted utility transformer for the new 480/277V building electrical service.

Communications:

The campus communications system will be extended from existing manhole #N8 located in the street on the southside of proposed new library building via approximately eight (8) new 4� underground conduits in a concreteductbank. New fiber optic and copper cabling will be installed by UCHSC Information Services from the newlibrary service entrance (SE) room located on the ground floor to the existing campus communications centerlocated in administration Building 500. The cabling will be installed through the new ductbank and the existingunderground infrastructure system and routed to Building 500.

Building Electrical System:

New electrical switchgear will consist of a 480/277V main switchboard. The switchboard will be located near theincoming service entrance point. Power will be distributed via two (2) satellite electrical rooms (one at each side ofbuilding) per floor and rise vertically to the stacked electrical rooms. Distribution boards, step-down transformersand branch distribution panels will be provided at the satellite electrical rooms. The anticipated electrical service isestimated at 3,000-4,000 amps which breaks down for the various system as follows: 60 KVA exterior lighting, 300KVA interior lighting, 120 KVA general purpose receptacles, 480 KVA computers and supporting equipment, 80KVA elevators, 1200 KVA mechanical and plumbing equipment and 120 KVA allotted for miscellaneous supportequipment for a combined total of 2,360 KVA or 2,840 Amps. Transient voltage surge suppression (TVSS)equipment will be implemented in the main and secondary electrical distribution equipment (i.e., main switchboard,secondary distribution boards and communication equipment room panels).

Building Communications System:

The library’s new communications system will be comprised of one (1) service entrance room (SE) located on theground floor for bringing campus backbone media into the building. Two (2) telecommunications rooms (TR) willbe provided on each floor; one at each end of the building. The rooms will be vertically stacked and aligned. Thevertically stacked telecommunications rooms will be interconnected vertically with three (3) 4� sleeves infloor/ceiling of each room. The two rooms on a floor will be connected with 3� deep, 18� deep ladder-type cabletray horizontally. A telecommunications room is also anticipated for the basement area.

All telecommunication rooms will be provided with wall-to-wall, floor-to-ceiling plywood mounting backboards forequipment that UCHSC IS will install. Room locations will be designed to best facilitate cabling runs so as not toexceed 250 LF from any individual workstation. Electrical power for these rooms shall be designed to supportbuilding backbone, horizontal distribution communications systems hardware (i.e., Cisco Catalyst 4000concentrator, 3424 switches and 6509 GbE switch) and backed up by the Standby Emergency Power System.

Page 36: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

Fitzsimons Library Program Plan University of Colorado Health Sciences Center

June 1, 2001 32

The service entrance and equipment room systems will be protected by an FM200 Fire Extinguishing System andinterconnected with the building fire alarm system. Electrical devices to be interconnected to a room emergencypower off (EPO) pushbutton and interlocked with room FM200 control panel and building FACP to disconnectbuilding backbone equipment from power prior to FM200 release.

Audio/Visual & Television Systems:

Existing audio, visual and television systems will be extended to the new library building as determined by theCampus Facilities Planning and the educational support services staff. Installed systems shall conform to Universityof Colorado Health Sciences Center standards, industry standards and all applicable codes.

Grounding System:

The grounding electrode system for the new library building will consist of a main ground bus bar located in themain electrical room with ground conductor sized and bonded per N.E.C. to main electrical equipment. “UFER�ground ring should be installed in or below the building foundation, ground rods and building cold water pipe. Inaddition, all satellite electrical and telecommunications rooms an auxiliary ground bus bar will be installed to enablea clean ground path to equipment within each room. Auxiliary ground bus bars will be interconnected by means of avertical riser and continuing on to building main ground bus bar in main electrical room. Satellite electrical roomground bus risers to be kept isolated and separated from satellite telecommunication room ground bus risers forminimizing harmonic transmissions between systems.

Lightning Protection System:

The lightning protection system will consist of a ground electrode loop around perimeter of building and groundrods bonded to every third structural column. The system shall conform to all industry standards, codes and shall beUL master labeled.

Emergency System:

The emergency systems for the new library building will be accommodated by an on-site standby emergency dieselfueled generator complete with automatic transfer switch(es) day tank, main fuel tank and all auxiliary components,controls, distribution panels and branch circuit panels. The anticipated emergency loads are estimated as follows:60.0 KW emergency exit signage and egress lights, 15.0 KW site security/night lights, 90.0 KW telecommunicationsequipment, 60.0 KW fire pump, 25.0 KW elevator, 40.0 KW smoke purge equipment and 10.0 KW miscellaneousemergency equipment (i.e., fire alarm, security, etc) for a combined total of 300 KW (375 KVA @ .8 PF) or 451.0Amps @ 480 volt, 3 Phase. A generator would be sized to accommodate the anticipated loads and an additional25% spare capacity. Design of the exterior equipment enclosure to include 15 feet maintenance clearance aroundgenerator to be designed.

Lighting Systems:

Lighting systems for the various occupancies to consist of 2x4, 3 lamp, 18 cell parabolic recessed fluorescenttroffers with two ballasts for dual level switching in office and support areas; 2x4, 2 lamp recessed direct/indirectfluorescent troffers with perforated shields in corridors; 4 ft, one lamp wall mounted fluorescent vanity light andcompact floor downlights for general illumination in toilet rooms; and decorative pendant mounted direct/indirectfluorescent luminaires in study, collection, computer, resource and learning areas.

Lighting levels to be designed to accommodate and enhance specific tasks and environments. All fluorescentluminaires shall be specified with high color rendering T8 lamps (4100 Kelvin, 82 Color Rendering Index) and high

Page 37: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

Fitzsimons Library Program Plan University of Colorado Health Sciences Center

June 1, 2001 33

efficiency electronic ballasts with low inrush current and no greater than 10% total harmonic distortion. Allelectrical and telecommunications equipment room lighting to be furnished with additional radio interference filters(RIF).

Dual tech (ultrasonic/infrared) occupancy sensors should be provided in all restrooms, conference rooms and publicareas. Dual level wall switches are proposed in offices, copy and break rooms, single level switching in equipmentrooms. Exterior lighting will be controlled by a roof-mounted photocell connected a digital time-clock systemlocated in the main electrical room.

Illumination levels throughout will be designed to conform to UCHSC standards and Illumination EngineeringSociety (IES) recommendations.

Fire Alarm and Detection System:

The fire Alarm and Detection System will be a fully automatic intelligent reporting addressable type to meet theUCHSC standards and requirements. Photoelectric or thermal type smoke detection system will be incorporatedinto the design to comply with UBC, NFPA, NEC and Life Safety codes. A smoke detection system will beinstalled throughout entire building and cover elevator pit and shaft. Elevator recall and shutdown will be providedthrough the shaft, lobby and equipment room detection. Heat detection devices in the equipment room and shaftwill be interlocked with a shunt trip circuit breaker serving the elevator for elevator shutdown prior to sprinklerflow. The elevators would be recalled to designated floors by activation of the smoke detectors prior to emergencyshut down. Monitoring devices will be provided for tamper/flow switches and pre-action systems where required.

Control devices will be installed for door hold open devices to release doors and at duct smoke detectors to shutdown associated HVAC equipment. A remote graphic fire alarm annunciator panel will be installed near the mainentry. All systems associated with fire alarm detection and extinguishing will be fed from the emergency powersystem.

Security System:

The type of security or access control system required for the new Fitzsimons library will be determined during thedesign phase of the project.

Diagrammatic Floor Plans/Adjacencies

The following pages graphically depict concept floor plans of preliminary adjacencies for the new library facility:

• Building Space Summary• Basement Plan• First Floor Plan• Second Floor Plan• Third Floor Plan• Fourth Floor Plan• Roof Plan

Page 38: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

GENERALADMINISTRATIONCIRCULATIONLEARNING RESOURCE CENTERREFERENCE SERVICESRESOURCE SERVICESSYSTEMS-DATABASESMATERIAL STORAGEEDUCATION/HEALTH INFORMATICSINFORMATION ACCESS AND STUDYDRUG INFORMATION CENTERHISTORY OF MEDICINE AND SPECIAL COLLECTIONSSPECIALIZED BUILDING SUPPORT

PROGRAM

10,9263,2793,5144,2833,8831,8265,432

34,2164,509

30,6513,5024,2143,226

PROJECTED GSF

BUILDING SPACE SUMMARY

COLOR KEY:

(MECHANICAL PENTHOUSE EXCLUDED)

UCHSC LIBRARY @ FITZSIMONS, AURORA, CO

H+L ArchitectureShepley Bulfinch Richardson Abbott

PROGRAM AREACOLOR CODE

Page 39: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

FIRE STAIR

TELECOM SERVICE ROOM

FREIGHT ELEVATOR/ CUSTODIAL

CLCL

CL

CL

CENTRAL STORAGE

OUTLINE OF FIRST FLOOR ABOVE

OUTLINE OF FIRST FLOOR ABOVE

MECHANICAL ROOM

ELEV.MACH.RM.

ELECTRICAL ROOMFIRE PUMP ROOM

UP TO LOADING DOCK

BASEMENT PLANUCHSC LIBRARY @ FITZSIMONS, AURORA, CO

H+L ArchitectureShepley Bulfinch Richardson Abbott

Page 40: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

TOILETS

STUDY

STUDY

STU

DY

LIGHT WELL

LIGHT WELL

FIRE STAIR

MAIN STAIR

TELE-COMSTUDY

FREIGHT ELEVATOR/ CUSTODIAL

ELEV.

ELEV.

CLCL

CL

STU

DY

OPEN TO FOURTH FLOOR ABOVE

STUDY

CL

JOURNAL COLLECTION/STACKS

TELE-COM

THIRD FLOOR PLANUCHSC LIBRARY @ FITZSIMONS, AURORA, CO

H+L ArchitectureShepley Bulfinch Richardson Abbott

Page 41: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

TOILETS

STUDYSTUDY

STU

DY

EDUCATION AND HEALTH INFORMATICS

LIGHT WELL

LIGHT WELL

FIRE STAIR

MAIN STAIR

TELE-COM

SYSTEMS DATABASE

STUDY

FREIGHT ELEVATOR/ CUSTODIAL

ELEV.

ELEV.

CLCL

CL

STU

DY

LEARNING RESOURCE CENTER

OPEN TO LEVEL BELOW

STUDY

CL

TELE-COM

STUDY

SECOND FLOOR PLANUCHSC LIBRARY @ FITZSIMONS, AURORA, CO

H+L ArchitectureShepley Bulfinch Richardson Abbott

Page 42: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

COFFEE BAR

24 HOUR STUDY

TOILETS

FIRE COMMAND CENTER

DISABILITY CENTER LOBBY

CIRCULATION OFFICES

RESOURCE SERVICES

DRUG INFORMATION CENTER (SCHOOL OF PHARMACY)

LIGHT WELL

LIGHT WELL

SECONDARY ENTRANCE

PRIMARY ENTRANCE

IN OUT

VESTIBULE

FIRE STAIR

MAIN STAIR

TELECOM

REFERENCE OFFICES

LOADING AREA

FREIGHT ELEVATOR

ELEV.

ELEV.

CLCL

CL

CIRCULATION DESK

READY- REFERENCE STACKS

REFERENCE DESK

INFORMATION ACCESS AND STUDY

OPEN TO SECOND FLOOR ABOVE

CUSTODIAL

EMERG.EXIT

EMERG.EXIT

DNUP

ELEVATORMACHINEROOM

TELE-COM

EMERG.EXIT

SERVICE

H+L ArchitectureShepley Bulfinch Richardson Abbott

FIRST FLOOR PLANUCHSC LIBRARY @ FITZSIMONS, AURORA, CO

Page 43: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

TOILETS

STAFFWORKROOM

ADMINISTRATION/OFFICES(RECEPTION)

BOOK COLLECTIONS/STACKS

LIGHT WELL

LIGHT WELL

FIRE STAIR

MAIN STAIR

TELE- COM

FREIGHT ELEVATOR/ CUSTODIAL

ELEV.

ELEV.

CLCL

CL

OPEN TO LEVEL BELOW

HIST. OF MED.

CL

HISTORY OF MEDICINE

GALLERY/DISPLAY

LOUNGE/ BREAK ROOM

TELE-CONF.ROOM

TELE-COM

STU

DY

STUDY

STU

DY

FOURTH FLOOR PLANUCHSC LIBRARY @ FITZSIMONS, AURORA, CO

H+L ArchitectureShepley Bulfinch Richardson Abbott

Page 44: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

FOURTH LEVEL LOWER ROOF

MECHANICAL PENTHOUSE(FOURTH FLOOR UPPER ROOF)

SKYLIGHT OVER PENTHOUSE

FIRE STAIR

FREIGHT ELEVATOR/ CUSTODIAL

CLCL

CL

OPEN TO LEVEL BELOW AND SKYLIGHT ABOVE

CL

FOURTH FLOOR UPPER ROOF

FOURTH FLOOR LOWER ROOF

FOURTH FLOOR UPPER ROOF

FOURTH FLOOR LOWER ROOF

SKYLIGHT OVER PENTHOUSE

(NON-PROGRAMMED SPACE)6,533 SF

PENTHOUSE/ROOF PLANUCHSC LIBRARY @ FITZSIMONS, AURORA, CO

H+L ArchitectureShepley Bulfinch Richardson Abbott

Page 45: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

June 1, 2001

Project Cost Estimate The project budget outlines the costs associated with each component based on 2001 dollars. Escalation of costs over time will be determined within the capital construction budget request process. Inflation rates are determined by the State of Colorado and the project budget will be adjusted accordingly.

Construction Cost: $25,016,757 Total Project Cost: $34,998,669

Page 46: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

Fitzsimons Library Program Plan University of Colorado Health Sciences Center

June 1, 2001 35

Life-Cycle Estimate

Life cycle costs were not a determining factor as to how the project solution was developed. Space needs andprogrammatic changes in Library services are significant drivers behind the actual scope. Although life cycle costsdid not determine what the solution was, it is important to understand what long range costs are when associatedwith a project of this size.

Maintenance and utility costs are seen even before a structure is finally occupied. Based upon current operatingcosts at Denison, the following are estimated expenses for the new library building.

Grounds & Maintenance $ 233,748.00 annuallyCustodial 87,372.00 annuallyUtilities 458,419.00 annuallyPolice 81,698.00 annuallyEnv. Health/Insurance 53,331.00 annually

TOTAL $ 914,568.00 annually

Operating costs, combined with repair and replacement, govern life cycle costs for a building. Those associated withthe value of today’s dollar are what gives the total life cycle costs of any investment. The life cycle costs indicateoperating, maintenance, and replacement costs that are likely to occur once this project is complete, and can befound in Appendix Section 7.05, Life Cycle Owning and Operating Cost Analyses.

Beyond the facility life cycle costs are those associated with operating the library program; see Appendix Section7.06, Financial Operation Information. Depending on final design decisions, such as inclusion of multiple buildingentrances, operating costs may vary from those determined in developing the program plan.

Financial Analysis

The financial plan to fund the project involves a partnership between the University and the State of Colorado. TheUniversity proposes providing cash funds acquired through an aggressive development effort, to supplement statefunds via the Capital Construction Budget Request process. The University contribution will be approximately $5.0million of the $35 million. The remaining $30 million is scheduled to be split between $9.75 million in Fitzsimonstrust funds, and $20.25 million requested in the University’s Capital Construction Budget Request to the State ofColorado. Since the project will take longer than one fiscal year, the first request will be made in FY 2002 for $4.8million. The $15.3 million balance will be requested in FY 2003/04 and FY 2004/05. A detailed breakout is locatedin the Project Cost Estimate, which precedes this section.

Project Schedule

The following schedule best represents a timeline associated with design and construction once the project is funded.The following page outlines a project schedule that assumes funds will be available in the spring of 2002. If this isnot the case the overall schedule of the project is still valid, except the start and completion dates must adjustaccordingly. The length of the time required for design and construction will likely remain.

Project Activity: Completion Date: Project Activity: Completion Date:

Program Plan Completion May 2001 Initiate Schematic Design July 2002Regent Approval June 2001 Design and CD Completion June 2003Legislative Authorization May 2002 Construction Completion, Phase I December 2004Selection of Architect June 2002 Occupancy December 2004

Page 47: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

Relation to Master Plan/Other Projects The new Fitzsimons campus presents the University of Colorado Health Sciences Center with an extraordinary opportunity to compete and prevail as a top tier health professions education, research and clinical institution. The institutional master plan for the new campus, approved by the Colorado Board of Regents and the Colorado Commission on Higher Education in 1998, provides for the UCHSC to expand from its cramped 46-acre Denver campus to 217 acres at the former Fitzsimons Army Medical Base in Aurora. The Fitzsimons campus development will involve a phased construction program totaling approximately five million square feet of new program space and associated infrastructure for the Health Sciences Center and University Hospital. Education-related space will total more than 600,000 gross square feet, which includes a new state-of-the-art library with approximately 116,000 gsf area. Today, nearly 325,000 users rely annually on the Denison Memorial Library for vital, up-to-the-minute information on patient care and research, personalized assistance in tapping knowledge sources, and a diverse collection recording the scholarly record of the health sciences. Nearly 20% of walk-in clients are from outside the campus. As the only comprehensive health sciences library in the state of Colorado, the Denison Library is the library of record and the last recourse for biomedical materials unavailable elsewhere in the region. Unfortunately, library space and technology do not meet current demands and will be unable to meet future demands as users increase and learning methods change. The University of Colorado Health Sciences Center Master Plan provides a vision for the new learning environment at Fitzsimons, which includes the library and its services. The vision emphasizes that for the UCHSC to maintain and enhance its ongoing commitment to form and reform educational programs that respond to health workforce needs, the library must be continuously responsive, dynamic, evaluation-conscious and future-oriented. The success of this goal depends in large part on effective use of the appropriate evolving information technologies and other learning methods. The library will be the focal point to access information from emerging technologies. In the information age, the concept of learning environments and modalities will continuously evolve. The use of educational technologies shall better accommodate differences among learners, including real and virtual learning environments, demand and just-in-time learning opportunities, and increased access and time flexibility in distributed learning modalities. The new library meets these evolving needs with a flexible design that allows library scientists to adjust to constantly changing technology.

Page 48: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

Fitzsimons Library Program Plan University of Colorado Health Sciences Center

June 1, 2001 37

VI. Facilities Alternatives

There are no acceptable alternatives other than moving the Denison Memorial Library to its proposed site at theUCHSC Fitzsimons Campus. Because the program plan is conceptual by nature, it is understood that during theDesign Phase modifications may be required.

Prior to the kick-off of the program plan process and after evaluating several options, UCHSC determined that thesite directly north of Building 500 was the correct choice for locating the new library.

Page 49: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

Fitzsimons Library Program Plan University of Colorado Health Sciences Center

June 1, 2001 38

VII. Appendices

7.01 Participants in the Planning Development Process

7.02 Strategic Brief for the Library at Fitzsimons (DEGW Architects and Planners)

7.03 Library (L-Tables) and Building Space Tables

7.04 Student Demographics (Enrollment Trends and Class/Lab Information)

7.05 Life Cycle Owning and Operating Cost Analyses

7.06 Financial Operation Information

7.07 IS Design Requirements

7.08 Program Plan Regulatory Code Analysis

7.09 Independent Third Party Review

Page 50: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

Fitzsimons Library Program Plan University of Colorado Health Sciences Center

June 1, 2001 40

Appendix Section 7.01

Participants in thePlanning Development

Process

Page 51: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

Fitzsimons Library Program Plan University of Colorado Health Sciences Center

June 1, 2001 39

Specific persons involved with the planning development included:

University Representatives:

• Jerry Scezney, Senior Institutional Planner, Institutional Planning, Office of the Chancellor• Rick Forsman, Director, Denison Memorial Library• Pat Nelson, Assistant Director, Denison Memorial Library• Library Oversight Committee• Administrative Working Group• ADWG/Support Team• Library Leadership Council• Library Faculty and Staff

Consultants:

• Joe Bilotta, JBA Incorporated (Planning)• Mike Ossian, H+L Architecture• Steve Gottesman, H+L Architecture• Goeff Freeman, Shepley Bulfinch Richardson and Abbott • Ralph Jackson, Shepley Bulfinch Richardson and Abbott • Spencer Nickel, 5Design, Inc. (Landscape Architecture and Planning)• Steve Bierbach, Bierbach Consulting Engineers (Structural Engineering) • Bruce Appel, Cator, Ruma & Associates, Co. (Mechanical Engineer)• Marc Valerius, Cator, Ruma & Associates, Co. (Electrical/Telecommunications Design)

Page 52: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

Fitzsimons Library Program Plan University of Colorado Health Sciences Center

June 1, 2001 41

Appendix Section 7.02

Strategic Brief for theLibrary at Fitzsimons

(DEGW Architects andPlanning)

Page 53: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

Fitzsimons Library Program Plan University of Colorado Health Sciences Center

June 1, 2001

Appendix Section 7.03

Library (L-Tables) andBuilding Space Tables

Page 54: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

Table L-1 & Table L-2 Historical Library Collection Acquistions

Revised 4/19/01

Funding (Dollars) Total Print Book Bound Active Electronic Audio/Visual Electronic Archives Reference Consumer Year Volumes Volumes Journal Print Journal and Micro- Books (linear ft.) Volumes Health

Print & Electronic Volumes Journal Titles Computer (Abstracts &Av. Volumes Titles Titles Support Indexes)

ItemsHistoricalLibraryCollection

FY 1995/96 $781,671 $74,844 239,751 94,928 144,823 1,725 No data 17,051 0 650 No data

FY 1996/97 $829,330 $79,923 244,748 96,681 148,067 1,609 104 17,044 0 650 No data

FY 1997/98 $835,044 $128,098 249,024 98,266 150,758 1,661 289 16,961 0 650 No data

FY 1998/99 $920,166 $400,000 253,104 99,829 153,275 1,621 342 12,133 15 650 No data

FY 1999/00 $1,055,521 $169,175 258,008 102,110 155,898 1,384 762 5,071 60 650 9,418

LibraryCollectionGrowth

FY 2004/05 $1,266,625 $500,000 280,008 111,110 168,898 1,200 4,000 6,000 2,000 650 8,000 1000

FY 2009/10 $1,519,950 $1,000,000 297,258 118,610 178,648 800 6,000 6,000 3,000 650 6,000 1000

FY 2014/15 $1,823,940 $1,500,000 309,758 124,610 185,148 400 8,000 6,000 4,000 650 5,000 1000

FY 2019/20 $2,188,728 $2,000,000 317,508 129,110 188,398 400 8,000 6,000 5,000 650 5,000 1000

Notes: The 9,418 "reference volumes" in FY 1999/00 are included in total print volume count. "Funding Dollars" are campus funds and do not include significant shared resources funded from other sources.

Page 55: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

Table L-3 Collection Storage SpaceRevised 4/19/01

Existing Collection Planning Phase I - FY 2010 Planning Phase II - FY 2020

Type of Material Number Items Storage ASF Total Number Items Storage ASF Total Number Items Storage ASF Totalof Per Units Per ASF of Per Units Per ASF of Per Units Per ASF

Items Unit Unit Items Unit Unit Items Unit Unit(A) (B) (A/B=C) (D) (C*D=E) (A) (B) (A/B=C) (D) (C*D=E) (A) (B) (A/B=C) (D) (C*D=E)

Standard ShelvingBook Volumes 92,110 105 877 10.3 9,036 68,610 105 653 10.5 6,861 79,110 105 753 10.5 7,911Bound Journal Volumes 155,898 105 1,485 10.3 15,293 118,648 105 1,130 10.5 11,865 118,398 105 1,128 10.5 11,840Active Print Journals 1,384 15 92 15.4 1,421 800 14 57 15.5 886 400 14 29 15.5 443Electronic Journals 762 500 2 15 23 6,000 500 12 15 180 8,000 500 16 15 240Audio Visual/Micro Supt. 5,071 35 145 10.3 1,492 6,000 35 171 10.5 1,800 6,000 35 171 10.5 1,800Electronic Books 60 60 1 10.3 10 3,000 240 13 10.5 131 5,000 240 21 10.5 219Archives (Lineal Feet) 650 20 33 18 585 650 20 33 18 585 50 20 3 18 45Reference 9,418 75 126 15.4 1,934 6,000 75 80 15 1,200 5,000 75 67 15 1,000Consumer Health 0 105 0 15.4 0 1,000 105 10 10.5 100 1,000 105 10 10.5 100

Subtotal 265353 29,794 210,708 23,608 222,958 23,597

High Density Stg. (PASCAL)Books 10,000 105 95 7.5 714 50000 105 476 7.5 3,571 50000 105 476 7.5 3,571Bound Journal Volumes 0 60000 60000 105 571 7.5 4,286Active Print Journals 0 0 0Electronic Journals 0 0 0Audio Visual/Micro Supt. 0 0 0Electronic Books 0 0 0Stored Archives (Lineal Feet) 0 600 75 8 12 96 600 75 8 12 96Reference 0 0 0Consumer Health 0 0 0

Subtotal 10,000 714 110,600 3,667 110,600 7,953

TOTAL 275,353 30,508 321,308 27,275 333,558 31,551

Notes: The "Archives" data is collected and planned using a linear foot calculation.

Page 56: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

Table L4 &Table L-5 Number of Reader Stations/Reader Stations by Station Type

Revised 4/19/01

Number of Stations ASF Per Station Phase I Phase IIPhase I Phase I Phase II Phase II Total Total

Student Reader Type Existing Campus Non-Campus Campus Non-Campus Existing New ASF ASF

Regular Carrel 120 75 15 90 23 35 3,150 3,938

Electronic/Computer 50 100 10 120 15 40 4,400 5,400Carrel

Hi-Tech Work Center 0 50 0 60 0 0 30 1,500 1,800(4-6 persons)

Tables 145 150 12 180 18 30 4,860 5,940

Group Study Rooms 38 50 2 60 3 25 1,300 1,575(5-10 stations)

Group Study Rooms 13 100 0 120 0 20 2,000 2,400(10-25 stations)

Casual 38 35 5 42 8 35 1,400 0Furniture

Other 16 20 3 24 5 40 920 1,140

TOTAL 420 580 47 696 71 19,530 22,193

Page 57: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

BUILDING SPACE Revised 4/19/01

SUMMARY(Denison)

Existing Projected ASF ProjectedPROGRAM ASF ASF Deficit GSF NotesGeneral 1,945.3 8,320.0 6,374.7 10,926.9Administration 1,654.9 2,155.0 500.1 3,279.5Circulation 342.3 2,320.0 1,977.7 3,514.1Learning Resource Center 6,853.1 2,860.0 -3,993.1 4,283.7Reference Services 890.8 2,550.0 1,659.3 3,883.1Resource Services 582.3 1,210.0 627.8 1,826.2Systems-Databases 2,245.4 3,775.0 1,529.6 5,432.3Material Storage 24,549.7 23,607.8 -941.9 34,216.7Education/Health Informatics 563.0 2,945.0 2,382.0 4,509.2Information Access & Study 7,806.7 19,530.0 11,723.3 30,651.9Drug Information Center 1,000.0 2,330.0 1,330.0 3,502.6History of Medicine & Special Collections 368.8 2,950.0 2,581.2 4,214.3Specialized Building Support 0.0 2,420.0 2,420.0 3,226.7TOTAL: 48,802.2 76,972.8 28,170.5 113,467.1

67.84% Percent Efficient

Page 58: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

GENERAL Revised 4/19/01

Space Existing Location Projctd ASF/GSF Projctd ASFCode SPACE TYPE Bldg Rm # ASF ASF Ratio GSF Deficit Notes

300 OFFICE SPACE 0315 Staff Work Room 108 1D06A 344.2 350.0 70% 500.0 5.8

0.0400 STUDY FACILITIES 0.0455 Study Service - Photocopy 108 0D00 24.0 -24.0455 Study Service - Photocopy 108 0D11 24.0 -24.0455 Study Service - Photocopy 108 1D06 24.0 -24.0455 Study Service - Photocopy 108 2D04 701.0 750.0 70% 1,071.4 49.0

0.0600 GENERAL USE FACILITIES 0.0650 Lounge/Breakroom 108 0D05 400.9 500.0 70% 714.3 99.1350 Teleconference Room 350.0 70% 500.0 350.0 Service in Building Support

0.0700 SUPPORT FACILITIES 0.0730 Central Storage 108 0D07 164.8 -164.8730 Central Storage 108 0D10 198.8 -198.8730 Central Storage 108 1D03E 63.6 2,500.0 85% 2,941.2 2,436.4

0.0Other

610 Lobby (all floors combined) 1,500.0 80% 1,875.0 1,500.0620 Gallery/Display (General) 1,500.0 75% 2,000.0 1,500.0160 Reception 300.0 80% 375.0 300.0410 Disability Access Center 270.0 60% 450.0 270.0 4 Stns @ 60 ASF, +1 spt630 Coffee Bar 300.0 60% 500.0 300.0

TOTAL 1,945.3 8,320.0 10,926.9 6,374.7

Page 59: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

ADMINISTRATION Revised 4/19/01

Space Existing Location Projctd ASF/GSF Projctd ASFCode SPACE TYPE Bldg Rm # ASF ASF Ratio GSF Deficit Notes

300 OFFICE SPACE310 D. Miller 108 1D04 198.2 135.0 65% 207.7 -63.2310 C. Waters 108 1D04 198.2 120.0 65% 184.6 -78.2310 P. Nelson (Asst. Director) 108 1D04A 126.5 180.0 65% 276.9 53.5310 M. Graber (Deputy Director) 108 1D04B 132.3 180.0 65% 276.9 47.7310 R. Forsman (Director) 108 1D04C 176.3 200.0 65% 307.7 23.7310 Development Officer 150.0 65% 230.8 150.0310 R. Robinson 108 2D04E 47.9 120.0 65% 184.6 72.1 Photocopy310 L. Hoffecker (.5 student) 108 85.0 65% 130.8 85.0310 1 TBA - Support Staff 120.0 65% 184.6 120.0315 Work Room/Drug Information Ctr 108 1D04D 52.0 0.0 65% 0.0 -52.0 Included in Drug Info Center350 Conference Room 108 0D11A 639.6 90.0 65% 138.5 -549.6 3 Stations @ 30 ASF/Stn350 Conference Room 108 1D11A 84.0 350.0 65% 538.5 266.0 Dedicated Building Wide610 Reception 150.0 65% 230.8 150.0315 Copy Room/Mail 100.0 65% 153.8 100.0315 Storage 175.0 75% 233.3 175.0 25 ASF/Person

Total 1,654.9 2,155.0 3,279.5 500.1

Page 60: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

CIRCULATION/RESERVES Revised 4/19/01

Space Existing Location Projctd ASF/GSF Projctd ASFCode SPACE TYPE Bldg Rm # ASF ASF Ratio GSF Deficit Notes

300 OFFICE SPACE310 C. Hirschfield (Dept. Head) 108 1D09 110.0 150.0 65% 230.8 40.0310 Circulation Office 108 1D10 168.0 85.0 60% 141.7 -83.0310 M. Bennett 108 85.0 60% 141.7 85.0310 J. Gibson 108 85.0 60% 141.7 85.0310 S. MacGowan 108 85.0 60% 141.7 85.0310 H. White 108 85.0 60% 141.7 85.0310 C. Driese 108 85.0 60% 141.7 85.0310 M. McKereghan (.6) 108 85.0 60% 141.7 85.0310 R. Garriss 108 85.0 60% 141.7 85.0310 L. Schwalm (.6) 108 85.0 60% 141.7 85.0310 R. Lewis (.6) 108 85.0 60% 141.7 85.0310 Students (1.3) 108 170.0 60% 283.3 170.0 2 stns310 .5 TBA - Support Staff 85.0 60% 141.7 85.0315 Office Service 108 2D04D 64.3 -64.3455 Service Desk Circulation/Reserves 400.0 75% 533.3 400.0315 Copy Room/Mail 50.0 65% 76.9 50.0315 Storage 195.0 75% 260.0 195.0 15 ASF per person420 Dedicated Material Storage/Staging 300.0 75% 400.0 300.0 Reserve Collection350 Conference 120.0 70% 171.4 120.0 4 persons @ 30 ASF/Stn

TOTAL 342.3 2,320.0 3,514.1 1,977.7

Page 61: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

LEARNING RESOURCE CENTER Revised 4/19/01

Space Existing Location Projctd ASF/GSF Projctd ASFCode SPACE TYPE Bldg Rm # ASF ASF Ratio GSF Deficit Notes

300 OFFICE SPACE 310 T. Le 108 3D06A 207.9 120.0 65% 184.6 -87.9 Learning Resource Center310 M. Mauck 108 3D06A 207.9 120.0 65% 184.6 -87.9 Learning Resource Center310 K. Protz 108 3D06A 207.9 120.0 65% 184.6 -87.9 Learning Resource Center310 J. Storey 108 3D06A 207.9 120.0 65% 184.6 -87.9 Learning Resource Center310 J. Kuntzman 108 3D06M 260.0 135.0 65% 207.7 -125.0 Education Management310 E. Kinsella (Dept. Head) 108 3D06P 97.8 150.0 65% 230.8 52.2 Education Management310 Vacant (Library Tech II) 108 120.0 65% 184.6 120.0310 Students (.75) 108 85.0 60% 141.7 85.0315 Work Room/Computer Staging 108 3D06B 420.0 725.0 65% 1,115.4 305.0 Learning Resource Center315 Server Room 108 3D06B1 152.0 200.0 75% 266.7 48.0 Learning Resource Center

2 TBA Library Technicians 170.0 65% 261.5 170.0 2 stations @ 85 ASF/StnTBA Info Tech Professional 135.0 65% 207.7 135.0

400 MATERIAL STORAGE (Stacks)430 Open-Stack Study Room 108 3D06 236.3 0.0 -236.3 Education Mngmnt (L-Tables)430 Open-Stack Study Room 108 3D06 4,363.8 0.0 -4,363.8 Learning Res Cntr (L-Tables)

400 STUDY FACILITIES (SEATING)410 Study Room 108 3D06C 92.9 0.0 -92.9 Learning Res Cntr (L-Tables)410 Study Room 108 3D06D 113.5 0.0 -113.5 Learning Res Cntr (L-Tables)410 Study Room 108 3D06H 84.7 0.0 -84.7 Learning Res Cntr (L-Tables)410 Study Room 108 3D06J 52.4 0.0 -52.4 Learning Res Cntr (L-Tables)410 Study Room 108 3D06K 59.4 0.0 -59.4 Learning Res Cntr (L-Tables)410 Study Room 108 3D06L 88.7 0.0 -88.7 Learning Res Cntr (L-Tables)

455 Service Desk 150.0 75% 200.0 150.0610 Reception 100.0 65% 153.8 100.0315 Copy Room/Mail 50.0 65% 76.9 50.0315 Storage 120.0 75% 160.0 120.0 15 ASF per person420 Dedicated Material Storage/Staging 150.0 75% 200.0 150.0350 Conference 90.0 65% 138.5 90.0 3 persons @ 30 ASF/Stn.

TOTAL 6,853.1 2,860.0 4,283.7 -3,993.1

Page 62: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

REFERENCE SERVICES Revised 4/19/01

Space Existing Location Projctd ASF/GSF Projctd ASFCode SPACE TYPE Bldg Rm # ASF ASF Ratio GSF Deficit Notes

300 OFFICE SPACE 0310 P. Blomquist 108 1D08 70.9 135.0 60% 225.0 64.1 Reference310 M. Burroughs 108 1D08 70.9 135.0 60% 225.0 64.1 Reference310 L. Fox 108 1D08 70.9 135.0 60% 225.0 64.1 Reference310 M. Walsh 108 1D08 70.9 135.0 60% 225.0 64.1 Reference310 W. Weathersby 108 1D08 70.9 120.0 60% 200.0 49.1 Reference310 E. D'Antonio-Gan 108 1D08 70.9 135.0 60% 225.0 64.1 Reference310 Vacant (.5 - Library Tech II) 108 1D08 70.8 120.0 60% 200.0 49.2 Reference310 Students (.5) 108 1D08 70.8 85.0 60% 141.7 14.2 Reference310 S. Parker (Dept. Head) 108 1D08B 118.8 150.0 65% 230.8 31.3 Reference310 TBA Librarians (2) 270.0 65% 415.4 270.0

0.0410 Computer Access 0.0 65% 0.0 0.0 Included in L-Tables610 Reception 100.0 75% 133.3 100.0315 Copy Room/Mail 100.0 65% 153.8 100.0315 Storage 108 1D11 205.0 300.0 75% 400.0 95.0 9 persons @ 15 ASF/Person350 Conference 90.0 65% 138.5 90.0 3 persons @ 30 ASF/Stn420 Dedicated Material Storage/Staging 120.0 75% 160.0 120.0455 Service Desk 300.0 75% 400.0 300.0420 Ready Reference Collection 0.0 75% 0.0 0.0 Included in L-Tables455 Private Work Stations (2-3) 120.0 65% 184.6 120.0

TOTAL 890.8 2,550.0 3,883.1 1,659.3

Page 63: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

RESOURCE SERVICES Revised 4/19/01

Space Existing Location Projctd ASF/GSF Projctd ASFCode SPACE TYPE Bldg Rm # ASF ASF Ratio GSF Deficit Notes

300 OFFICE SPACE310 P. Andrews (Collection Dvlpmnt) 108 1D07 100.0 120.0 65% 184.6 20.0 ILL310 W. Lundy 108 1D07 100.0 85.0 60% 141.7 -15.0 ILL310 W. Sarutzki 108 1D07 100.0 85.0 60% 141.7 -15.0 ILL310 Vacant (Library Tech II) 108 1D07 100.0 85.0 60% 141.7 -15.0 ILL310 Student (.3) 108 1D07 62.3 85.0 60% 141.7 22.8 ILL310 C. Reiter (Dept. Head) 108 1D07D 120.0 150.0 65% 230.8 30.0

610 Reception 75.0 65% 115.4 75.0315 Copy Room/Mail 50.0 65% 76.9 50.0315 Storage 135.0 75% 180.0 135.0 9 persons @ 15 ASF per person350 Conference 90.0 65% 138.5 90.0 3 persons @ 30 ASF/Stn420 Dedicated Material Storage/Staging 250.0 75% 333.3 250.0

TOTAL 582.3 1,210.0 1,826.2 627.8

Page 64: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

SYSTEMS/DATABASES Revised 4/19/01

Space Existing Location Projctd ASF/GSF Projctd ASFCode SPACE TYPE Bldg Rm # ASF ASF Ratio GSF Deficit Notes

300 OFFICE SPACE 0310 T. Drew 108 0D11 40.0 85.0 60% 141.7 45.0 Serials/Acquisitions310 D. Norsworthy 108 0D11 40.0 135.0 65% 207.7 95.0 Serials/Acquisitions310 E. Epstein 108 1D11 189.3 135.0 65% 207.7 -54.3 Cataloging310 E. Hall 108 1D11 189.3 85.0 60% 141.7 -104.3 Cataloging310 C. Livingston 108 1D11 189.3 85.0 60% 141.7 -104.3 Cataloging310 S. Arnesen (Dept. Head) 108 1D11B 130.0 150.0 65% 230.8 20.0310 C. Darden 108 0D11 103.5 85.0 60% 141.7 -18.5310 K. Louden (.25) 108 0D11 103.5 85.0 60% 141.7 -18.5310 D. McBride 108 0D11 103.5 85.0 60% 141.7 -18.5310 G. Gardner 108 0D11 103.5 135.0 75% 180.0 31.5455 Student Workstation 85.0 65% 130.8 85.0

400 STUDY FACILITIES 0.0440 Processing Room 108 0D09 1,053.5 1,200.0 75% 1,600.0 146.5 Staffing, binding,shipping

610 Reception 75.0 75% 100.0 75.0315 Copy Room/Mail 50.0 65% 76.9 50.0315 Storage 180.0 75% 240.0 180.0 12 persons @ 15 ASF/Person350 Conference 120.0 65% 184.6 120.0 4 erpsons @ 30 ASF/Stn.420 Dedicated Material Storage/Staging 550.0 75% 733.3 550.0 5000 Volumes Support455 Mending/binding 200.0 60% 333.3 200.0455 Shipping/Receiving 250.0 70% 357.1 250.0

0.0TOTAL 2,245.4 3,775.0 5,432.3 1,529.6

Page 65: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

MATERIAL STORAGE Revised 4/19/01

Space Existing Location Projctd ASF/GSF Projctd ASFCode SPACE TYPE Bldg Rm # ASF ASF Ratio GSF Deficit Notes

400 MATERIAL STORAGE (Stacks)420 Stacks - Journals 108 0D00 3,144.0 -3,144.0420 Stacks - Books 108 0D11 4,311.9 -4,311.9420 Stacks - Journals 108 1D03 1,876.6 -1,876.6 Indexes & Abstracts420 Stacks - Journals 108 1D06 176.0 -176.0420 Stacks - Journals 108 1D12 1,756.4 -1,756.4 Older Journals420 Stacks - Journals 108 1D12A 887.9 -887.9 Older Journals420 Stacks - Journals 108 2D00 1,974.9 -1,974.9420 Stacks - Books 108 2D01 871.9 -871.9420 Stacks - Journals 108 2D04 4,436.5 -4,436.5420 Stacks - Books 108 2D-1A 655.3 -655.3420 Stacks - Journals 108 MD03 1,742.5 -1,742.5420 Stacks - Books 108 MD03 1,144.8 -1,144.8430 Open-Stack Study Room 108 1D06 351.0 -351.0 Circulation430 Open-Stack Study Room 108 1D06 1,220.0 -1,220.0 Reference

0.0420 Books 6,861.0 70% 9,801.4 6,861.0 From L-Tables420 Bound Journal Volumes 11,864.8 70% 16,949.7 11,864.8 From L-Tables420 Active Print Journals 885.7 65% 1,362.6 885.7 From L-Tables420 Electronic Journals 180.0 70% 257.1 180.0 From L-Tables420 Audio Visual/Micro Supt. 1,800.0 65% 2,769.2 1,800.0 From L-Tables420 Electronic Books 131.3 70% 187.5 131.3 From L-Tables420 Archives 585.0 65% 900.0 585.0 From L-Tables420 Reference 1,200.0 65% 1,846.2 1,200.0 From L-Tables420 Other 100.0 70% 142.9 100.0 From L-Tables

0.00.0

Totals 24,549.7 23,607.8 34,216.7 -941.9

Page 66: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

EDUCATION AND HEATLH INFORMATICS Revised 4/19/01

Space Existing Location Projctd ASF/GSF Projctd ASFCode SPACE TYPE Bldg Rm # ASF ASF Ratio GSF Deficit Notes

100 CLASSROOM110 Classroom 108 3D06N 411.3 -411.3 Education Management

1,050.0 65% 1,615.4 1,050.0 35 Stations @ 30 ASF0.0

300 OFFICE SPACE 0.0310 L. Traditi (Dept. Head) 108 3D06M1 90.6 150.0 65% 230.8 59.4 Education Management310 K. Near 108 3D06M2 61.1 135.0 65% 207.7 73.9 Education Management310 2 Informatics Faculty 270.0 65% 415.4 270.0310 1 Informatics Support Staff 120.0 60% 200.0 120.0

0.0110 Virtual Reality Learning Room (1-4 people) 300.0 65% 461.5 300.0 5 stations @ 60 ASF/Stn110 Computer Teaching Lab 600.0 65% 923.1 600.0 2 labs @ 10 stns, 30 ASF/Stn350 Conference Room 90.0 65% 138.5 90.0 3 stns @ 30 ASF/Stn610 Reception 75.0 75% 100.0 75.0315 Storage 105.0 75% 140.0 105.0 7 persons @ 15 ASF/Person315 Copy/Mail Room 50.0 65% 76.9 50.0

TOTAL 563 2,945.0 4,509.2 2,382.0

Page 67: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

INFORMATION ACCESS & STUDY Revised 4/19/01

Space Existing Location Projctd ASF/GSF Projctd ASFCode SPACE TYPE Bldg Rm # ASF ASF Ratio GSF Deficit Notes

400 STUDY FACILITIES (SEATING)410 Study Room 108 0D11B 50.8 -50.8410 Study Room 108 0D11C 64.4 -64.4410 Study Room 108 0D11D 88.1 -88.1410 Study Room 108 0D11E 86.9 -86.9410 Study Room 108 0D11F 49.5 -49.5410 Study Room 108 0D11G 49.4 -49.4410 Study Room 108 0D11H 50.8 -50.8410 Study Room 108 0D11J 52 -52.0410 Study Room 108 1D03D 227.7 -227.7430 Open-Stack Study Room-Reading Areas 108 0D00 152.8 -152.8430 Open-Stack Study Room-Reading Areas 108 0D11 1337.6 -1,337.6430 Open-Stack StudyRoom 108 1D06 208 -208.0430 Open-Stack Study Room-Reading Areas 108 1D06 2226.5 -2,226.5430 Open-Stack Study Room-Reading Areas 108 2D00 270.4 -270.4430 Open-Stack Study Room-Reading Areas 108 2D01 248.9 -248.9430 Open-Stack Study Room-Reading Areas 108 2D04 1901.4 -1,901.4430 Study Room 108 2D04A 51.5 -51.5430 Study Room 108 2D04B 92.1 -92.1430 Study Room 108 2D04C 92 -92.0430 Open-Stack Study Room-Reading Areas 108 MD03 505.9 -505.9

430 Regular Carrel 3,150.0 62% 5,080.6 3,150.0 L-Tables430 Electronic/Computer Carrel 4,400.0 62% 7,096.8 4,400.0 L-Tables430 Shared Computer Stations (4-6 persons) 1,500.0 65% 2,307.7 1,500.0 L-Tables430 Tables 4,860.0 65% 7,476.9 4,860.0 L-Tables410 Group Study Rooms (5-10 Stations) 1,300.0 65% 2,000.0 1,300.0 L-Tables410 Group Study Rooms (10-25 Stations) 2,000.0 68% 2,941.2 2,000.0 L-Tables430 Casual Furniture 1,400.0 60% 2,333.3 1,400.0 L-Tables430 Other 920.0 65% 1,415.4 920.0 L-Tables

TOTAL 7806.7 19,530.0 30,651.9 11,723.3

Page 68: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

DRUG INFORMATION CENTER (SCHOOL OF PHARMACY) Revised 4/14/01

Space Existing Location Projctd ASF/GSF Projctd ASFCode SPACE TYPE Bldg Rm # ASF ASF Ratio GSF Deficit Notes

300 OFFICE SPACE310 Staff 120 270 65% 415.4 150310 Support Staff (1 FTE) 120 135 65% 207.7 15310 2 Pharmacy 150 270 65% 415.4 120 2 stations to support 6 head count310 TBA (3 FTE) 200 405 65% 623.1 205 3 @ 135 ASF

0Resource Collection 0

420 Resource Collection 160 400 75% 533.3 240455 Research Response Workstation 100 300 65% 461.5 200455 Training 50 300 65% 461.5 250

0315 Work Room/Copy/File 100 250 65% 384.6 150 Includes 4 computer stns

TOTAL 1000 2,330.0 3,502.6 1,330.0

Page 69: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

HISTORY OF MEDICINE & SPECIAL COLLECTIONS Revised 4/14/01

Space Existing Location Projctd ASF/GSF ProjctdCode SPACE TYPE Bldg Rm # ASF ASF Ratio GSF Deficit Notes

400 MATERIAL STORAGE (Stacks) 0 0430 Leisure Reading Materials (Amesse Room) 108 1D03 368.8 450.0 70% 642.9 81.2420 Alternative Medicine 500.0 70% 714.3 500.0420 Diversity Materials 200.0 70% 285.7 200.0420 Historical & Rare Books 750.0 70% 1,071.4 750.0 Climate Controlled420 Historical Materials Conf.Reader Area 300.0 70% 428.6 300.0 enough space for small party/reception420 History of Medicine 750.0 70% 1,071.4 750.0

0.00.00.0

TOTAL 368.8 2,950.0 4,214.3 2,581.2

Page 70: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

Building Support Revised 4/14/01

Space Existing Location Projctd ASF/GSF ProjctdCode SPACE TYPE Bldg Rm # ASF ASF Ratio GSF Deficit Notes

0.0710 Telecommunication Rooms 800.0 75% 1,066.7 800.0 2 per floor @ 80 ASF, plus hub715 Telecommunication Service 300.0 75% 400.0 300.0715 Teleconference Service Room 120.0 75% 160.0 120.0 teleconference room in "General"710 Bldg. Automtn, Fire Cmnd Room 120.0 75% 160.0 120.0750 Custodial Closets/Zones/Storage 1,080.0 75% 1,440.0 1,080.0 2 per floor @ 120 ASF, Bsmnt stg

TOTAL 0 2,420.0 3,226.7 2,420.0

Page 71: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

Fitzsimons Library Program Plan University of Colorado Health Sciences Center

June 1, 2001

Appendix Section 7.04

Student DemographicsEnrollment Trends

Class/Lab Information

Page 72: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

UNIVERSITY OF COLORADO HEALTH SCIENCES CENTERStudent Headcount Enrollment - 20 Year Master Plan

Summary Enrollment Data - Annualized - (Dec 2000 Update based on Fall Census)

2000-2001 Actual 2001-2002 2002-2003 2003-2004 2004-2005 2005-2006 2006-2007 2007-2008 2008-2009 2009-2010Res N-Res Total Res N-Res Total Res N-Res Total Res N-Res Total Res N-Res Total Res N-Res Total Res N-Res Total Res N-Res Total Res N-Res Total Res N-Res Total

SCHOOL OF MEDICINE MD 509 32 541 511 33 544 513 28 541 513 28 541 513 28 541 513 28 541 513 30 543 513 30 543 513 30 543 513 30 543 CHA/PA MS 74 1 75 100 5 105 108 8 116 112 8 120 112 8 120 112 8 120 112 8 120 112 8 120 112 8 120 112 8 120 CHA/PA BS 26 4 30 0 0 0 0 0 0 0 0 0 MS/MSPH 159 15 174 160 20 180 162 24 186 164 30 194 168 35 203 174 37 211 176 40 216 180 41 221 188 42 230 195 42 237 Basic Sci (PhD) 150 49 199 152 52 204 154 55 209 156 59 215 157 62 219 163 66 229 165 70 235 170 71 241 175 71 246 182 72 254 PT (MS) 89 14 103 76 14 90 75 14 89 75 15 90 77 15 92 78 16 94 86 31 117 88 31 119 90 30 120 90 30 120 Genetic Assoc (MS) 11 5 16 11 5 16 10 6 16 10 6 16 10 6 16 10 6 16 10 6 16 10 6 16 10 6 16 10 6 16 Special Students PT (MS) 24 0 24 24 0 24 28 0 28 25 0 25 25 0 25 25 0 25 25 0 25 25 0 25 25 0 25 25 0 25TOTAL School of Medicine 1042 120 1162 1034 129 1163 1050 135 1185 1055 146 1201 1062 154 1216 1075 161 1236 1087 185 1272 1098 187 1285 1113 187 1300 1127 188 1315

SCHOOL OF DENTISTRY Dental Students (DDS) 108 38 146 105 40 145 110 34 144 119 39 158 131 41 172 143 43 186 155 45 200 155 45 200 155 45 200 155 45 200 Dental Programs 35 5 40 37 2 39 40 3 43 45 6 51 55 8 63 57 10 67 59 10 69 63 11 74 63 11 74 63 11 74TOTAL School of Dentistry 143 43 186 142 42 184 150 37 187 164 45 209 186 49 235 200 53 253 214 55 269 218 56 274 218 56 274 218 56 274

SCHOOL OF NURSING ND 121 4 125 121 7 128 120 10 130 120 12 132 120 13 133 120 13 133 120 13 133 120 13 133 120 13 133 120 13 133 MS 217 14 231 208 15 223 202 20 222 198 24 222 195 27 222 195 28 223 195 28 223 195 30 225 195 30 225 195 30 225 BS 220 6 226 252 8 260 252 10 262 254 11 265 255 10 265 255 10 265 255 10 265 255 10 265 255 10 265 255 10 265 PhD 42 19 61 39 18 57 39 20 59 42 21 63 42 22 64 42 23 65 42 23 65 42 23 65 42 23 65 42 23 65TOTAL School of Nursing 600 43 643 620 48 668 613 60 673 614 68 682 612 72 684 612 74 686 612 74 686 612 76 688 612 76 688 612 76 688

SCHOOL OF PHARMACY PharmD I 0 80 18 98 361 34 395 381 35 416 402 35 437 410 35 445 411 35 446 416 35 451 416 35 451 416 35 451 PharmD II 150 6 156 218 5 223 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 PhD 23 11 34 26 6 32 31 3 34 35 5 40 35 5 40 35 5 40 36 5 41 36 5 41 36 5 41 37 5 42 Undergrad 140 24 164 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0TOTAL School of Pharmacy 313 41 354 324 29 353 392 37 429 416 40 456 437 40 477 445 40 485 447 40 487 452 40 492 452 40 492 453 40 493

CAMPUS TOTAL 2098 247 2345 2120 248 2368 2205 269 2474 2249 299 2548 2297 315 2612 2332 328 2660 2360 354 2714 2380 359 2739 2395 359 2754 2410 360 2770

Page 73: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

SCHOOL OF MEDICINE MD CHA/PA MS CHA/PA BS MS/MSPH Basic Sci (PhD) PT (MS) Genetic Assoc (MS) Special Students PT (MS)TOTAL School of Medicine

SCHOOL OF DENTISTRY Dental Students (DDS) Dental ProgramsTOTAL School of Dentistry

SCHOOL OF NURSING ND MS BS PhDTOTAL School of Nursing

SCHOOL OF PHARMACY PharmD I PharmD II PhD UndergradTOTAL School of Pharmacy

CAMPUS TOTAL

2010-2011 2011-2012 2012-2013 2013-2014 2014-2015 2015-2016 2016-2017 2017-2018 2018-2019 2019-2020Res N-Res Total Res N-Res Total Res N-Res Total Res N-Res Total Res N-Res Total Res N-Res Total Res N-Res Total Res N-Res Total Res N-Res Total Res N-Res Total

513 30 543 513 30 543 513 30 543 513 30 543 513 30 543 513 30 543 513 30 543 513 30 543 513 30 543 513 30 543112 8 120 112 8 120 114 8 122 114 8 122 114 8 122 114 8 122 114 9 123 116 11 127 118 10 128 120 10 130

0 0 0 0 0 0 0 0 0 0200 43 243 205 44 249 210 45 255 215 45 260 217 45 262 220 45 265 225 45 270 230 45 275 230 45 275 230 45 275187 73 260 190 74 264 195 75 270 200 75 275 202 75 277 205 75 280 208 75 283 210 75 285 215 75 290 215 75 290

90 30 120 90 30 120 90 30 120 90 30 120 90 30 120 90 30 120 90 30 120 90 30 120 90 30 120 90 30 12010 6 16 10 6 16 10 6 16 10 6 16 10 6 16 10 6 16 10 6 16 10 6 16 10 6 16 10 6 1625 0 25 25 0 25 25 0 25 25 0 25 25 0 25 25 0 25 25 0 25 25 0 25 25 0 25 25 0 25

1137 190 1327 1145 192 1337 1157 194 1351 1167 194 1361 1171 194 1365 1177 194 1371 1185 195 1380 1194 197 1391 1201 196 1397 1203 196 1399

155 45 200 155 45 200 155 45 200 155 45 200 155 45 200 155 45 200 155 45 200 155 45 200 155 45 200 155 45 20063 11 74 63 11 74 63 11 74 63 11 74 63 11 74 63 11 74 63 11 74 65 11 76 65 11 76 65 11 76

218 56 274 218 56 274 218 56 274 218 56 274 218 56 274 218 56 274 218 56 274 220 56 276 220 56 276 220 56 276

120 13 133 122 13 135 122 13 135 122 14 136 124 14 138 125 14 139 126 14 140 126 14 140 128 15 143 130 15 145195 30 225 198 30 228 200 30 230 203 34 237 205 34 239 207 35 242 210 35 245 213 35 248 215 35 250 219 35 254260 10 270 260 10 270 262 10 272 264 10 274 269 10 279 273 10 283 275 10 285 275 10 285 278 10 288 282 10 292

42 23 65 44 23 67 42 23 65 42 23 65 44 24 68 45 25 70 46 25 71 47 25 72 48 25 73 50 25 75617 76 693 624 76 700 626 76 702 631 81 712 642 82 724 650 84 734 657 84 741 661 84 745 669 85 754 681 85 766

416 35 451 416 35 451 416 35 451 416 35 451 416 35 451 416 35 451 416 35 451 416 35 451 416 35 451 416 35 4510 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

37 5 42 37 5 42 38 5 43 38 5 43 38 5 43 39 5 44 39 5 44 39 5 44 39 5 44 40 5 450 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

453 40 493 453 40 493 454 40 494 454 40 494 454 40 494 455 40 495 455 40 495 455 40 495 455 40 495 456 40 496

2425 362 2787 2440 364 2804 2455 366 2821 2470 371 2841 2485 372 2857 2500 374 2874 2515 375 2890 2530 377 2907 2545 377 2922 2560 377 2937

Page 74: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

Fitzsimons Library Program Plan University of Colorado Health Sciences Center

June 1, 2001

Appendix Section 7.05

Life Cycle Owning andOperating Cost Analyses

Page 75: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

LIFE CYCLE COST ANALYSISMAJOR REPAIR AND REPLACEMENT COSTS

Project: UCHSC New Library at FitzsimonsDate: 23 May, 2001

Inflation Factor: 5%Construction Cost: $22,859,267

Study Period: 30 years

TotalProvision Annual

Useful Current for FV factor Total Replace. ProvisionLikely Life % of Pjct. Replace. Renewal 5%, Cost with for FV

Facility Subsystem Life Range Chosen Costs Cost w/o Inflation useful life Inflation: Renewal

Foundations/structure n/a n/a 23% 5,257,631Roofing 25 15-40 20 3% 571,482 28,574 2.653 1,516,141 $75,807Exterior Cladding n/a 50 up 30 17% 3,794,638 126,488 4.322 16,400,427 $546,681Interior Partitions 50 25 up 30 4% 914,371 30,479 4.322 3,951,910 $131,730Interior Finishings 10 5-15 15 12% 2,743,112 182,874 2.079 5,702,930 $380,195Elevators 40 25 up 30 4% 914,371 30,479 4.322 3,951,910 $131,730Plumbing 30 20-80 40 2% 457,185 11,430 7.040 3,218,585 $80,465HVAC - moving 15 15-25 15 15% 3,428,890 228,593 2.079 7,128,662 $475,244HVAC - static 50 30-75 50 8% 1,828,741 36,575 11.467 20,970,177 $419,404Electrical - moving 35 20-50 25 5% 1,142,963 45,719 3.386 3,870,074 $154,803Electrical - static 50 30-75 40 6% 1,371,556 34,289 7.040 9,655,754 $241,394Fire Protection 50 20-100 40 1% 228,593 5,715 7.040 1,609,292 $40,232Special Equip/Misc 30 10-50 20 1% 228,593 11,430 2.653 606,456 $30,323

TOTALS 100% $22,882,126 $772,643 $78,582,319 $2,708,008

Note: Foundation and Structural Costs ususally dictate when a building has met its useful lifeand should be razed. These figures can be ignored when considering a major repairand replacement costs for a fcility, unless special circumstances dictate otherwise.

Page 76: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

LIFE CYCLE COST ANALYSIS

Project: UCHSC New Library at FitzsimonsStudy Period: 30 years

Discount Rate: 6%Date: 23 May, 2001

Study Method: Present Value of One Dollar Building Value: $22,859,267

Addtitonal Optg & Maint Costs: $398,280 first yearAdditonal Energy/Utilities: $458,419 first year

Inflation Factor: 5%

Princ & Int and/or Major Repair Operating & Energy/ Salvage Discount PresentYear Investment & Replacement Maintenance Utilities Value Total Rate Value

1 $22,859,267 $398,280 $458,419 $23,715,966 0.9434 $22,373,6422 $418,194 $481,340 $899,533 0.8900 $800,5853 $439,103 $505,407 $944,510 0.8396 $793,0114 $461,059 $530,677 $991,736 0.7921 $785,5545 $484,111 $557,211 $1,041,322 0.7473 $778,1806 $508,317 $585,071 $1,093,389 0.7050 $770,8397 $533,733 $614,325 $1,148,058 0.6651 $763,5738 $560,420 $645,041 $1,205,461 0.6274 $756,3069 $588,441 $677,293 $1,265,734 0.5919 $749,18810 $617,863 $711,158 $1,329,021 0.5584 $742,12511 $648,756 $746,716 $1,395,472 0.5268 $735,13412 $681,193 $784,052 $1,465,245 0.4970 $728,22713 $715,253 $823,254 $1,538,507 0.4688 $721,25214 $751,016 $864,417 $1,615,433 0.4423 $714,50615 $6,172,002 $788,567 $907,638 $7,868,207 0.4173 $3,283,40316 $827,995 $953,020 $1,781,015 0.3936 $701,00717 $869,395 $1,000,671 $1,870,065 0.3714 $694,54218 $912,864 $1,050,704 $1,963,569 0.3503 $687,83819 $958,508 $1,103,240 $2,061,747 0.3305 $681,40720 $800,074 $1,006,433 $1,158,401 $2,964,909 0.3118 $924,45921 $1,056,755 $1,216,322 $2,273,076 0.2942 $668,73922 $1,109,592 $1,277,138 $2,386,730 0.2775 $662,31823 $1,165,072 $1,340,995 $2,506,066 0.2618 $656,08824 $1,223,326 $1,408,044 $2,631,370 0.2470 $649,94825 $1,142,963 $1,284,492 $1,478,446 $3,905,902 0.2330 $910,07526 $1,348,716 $1,552,369 $2,901,085 0.2198 $637,65927 $1,416,152 $1,629,987 $3,046,139 0.2074 $631,76928 $1,486,960 $1,711,487 $3,198,446 0.1956 $625,61629 $1,561,308 $1,797,061 $3,358,369 0.1846 $619,95530 $5,623,380 $1,639,373 $1,886,914 ($74,292,618) ($65,142,951) 0.1741 ($11,341,388)

Total Present Value for Owning and Operating Costs over the Study Period: $33,905,558

Page 77: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

OPERATION COST ANALYSES UCHSC New Library at Fitzsimons

University of Colorado Health Sciences Center

Operational Costs (in $ per GSF)

Utilities (annual)1 x 0 GSF (1) $02 4.04 x 113,470 GSF (2) $458,419

Police1 x 0 GSF (1) $02 0.72 x 113,470 GSF (2) $81,698

Grounds and Maintenance1 0.26 x 113,470 GSF (1) $29,5022 1.80 x 113,470 GSF (2) $204,246

Custodial1 x 0 GSF (1) $02 0.77 x 113,470 GSF (2) $87,372

Environmental Health & Insurance1 0.25 x 113,470 GSF (1) $28,3682 0.22 x 113,470 GSF (2) $24,963

8.06 TOTAL $914,568

* It is anticipated that the only operational costs implications associated with the renovated space are those related to the increase in utility and maintenance costs. Utility costs rise due to the additional air system required for the lower levels. Additional air will become available for the upper levels since the new system eliminates the need for the existing building system to support these two floors. The assumption is the building system will continue to operate as today, just distributing air in different locations. Thusthe new system is considered additional operating costs. Maintenance costs will rise only slightly due to additional laboratory equipment.

Page 78: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic
Page 79: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic
Page 80: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic
Page 81: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

Fitzsimons Library Program Plan University of Colorado Health Sciences Center

June 1, 2001

Appendix Section 7.06

Financial OperationInformation

Page 82: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

LIBRARY PROGRAM PLANFINANCIAL SECTION

This program plan includes increases to operating costs in 2004/05 when the new facilityopens. Because the new Library will be occupied during December 2004, the costs for2004-2005 represent a partial year budget with the rest of the increase shown thefollowing year for a total projected increase of $345,000. A detailed operating financialanalysis for the new Library can be found in the final pages Appendix.

In general these budget increases are designed to support an enlarged number ofcomputer workstations as requested by users: 1) for planned upgrade/replacement ofequipment and provision of additional network jacks or wireless connectivity, and 2)because a larger technical staff will be required to service these machines and assist usersacross the 110 hours per week that the library is open and staffed. Additional staff arealso included to cover the opening of a secondary entrance into the library (facing South)for the greater convenience of campus users coming from that direction.

A budget is also included to maintain a small satellite operation in the existing DenisonLibrary facility at 9th Avenue and Colorado Boulevard. This satellite will provideessential direct support for students from the Schools of Nursing and Pharmacy whilethese programs remain centered on the current campus.

Projected Occupancy Date - December 1, 2004

DescriptionFTE Amount FTE Amount FTE Amount

On-Going Operations:Compensation 4.50 $97,804 $69,860 4.50 $167,664Operating $61,068 $17,906 $78,974

Total On-Going Operations 4.50 $158,872 $87,766 4.50 $246,638

Maintain Services at 9th AvenueCampus Until the Schools of Nursingand Pharmacy Relocate to Fitzsimons 2.00 $57,516 $41,082 2.00 $98,598

Total 6.50 $216,388 $128,848 6.50 $345,236

UNIVERSITY OF COLORADO HEALTH SCIENCES CENTERLibrary Program Plan

Summary of Projected Increases to Existing Library Operating Budget

04-05 Year 1 05-06 Year 2 Total

Page 83: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

Description

FTE $ FTE $ FTE $UCHSC Library - Unrestricted FundOn-Going Operating Budget:

Compensation:Circulation:

Library Tech I 1.50 $37,066 1.50 $37,066Vacancy Savings ($15,444) $15,444 $20,592 salary + 20% benefits Support for desk at second entrance to new facility

Hourly Students 0.50 $15,000 0.50 $15,000Vacancy Savings ($6,250) $6,250 Provide sick leave and vacation coverage as well as coverage during the busiest times of the day for desks at both entrances to new facility

Total 2.00 $30,372 $21,694 2.00 $52,066

Informatics/Education:Enhancement of existing EducationDepartment to support the integrationof informatics competencies into thecurriculum of the UCHSC schools.The new facility will provide space to enlarge the department.

Informatics Faculty 1.00 $72,000 1.00 $72,000Vacancy Savings ($30,000) $30,000

Library Tech II 1.00 $28,598 1.00 $28,598Vacancy Savings ($11,916) $11,916 $23,832 salary + 20% benefits Provides evening and weekend coverage for student e-mail & PDA technology

Hourly Students 0.50 $15,000 0.50 $15,000Vacancy Savings ($6,250) $6,250 Provide evening and weekend coverage to assist students with computer based instructional programs.

Total 2.50 $67,432 $48,166 2.50 $115,598

Total Compensation 4.50 $97,804 $69,860 4.50 $167,664

UNIVERSITY OF COLORADO HEALTH SCIENCES CENTERLibrary Program Plan

Projected Operating Plan - Unrestricted Fund Operations

Total

Incremental IncreaseLibrary Occupancy - December 1, 2004

04-05 05-06

1

Page 84: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

Description

FTE $ FTE $ FTE $

UNIVERSITY OF COLORADO HEALTH SCIENCES CENTERLibrary Program Plan

Projected Operating Plan - Unrestricted Fund Operations

Total

Incremental IncreaseLibrary Occupancy - December 1, 2004

04-05 05-06

Operating:General Operating:

Support for new FTE @ $2,500 per FTE $11,250 $11,250Operating Savings ($4,688) $4,688 Telephone, b-jack, supplies, etc.

Administration Support $20,000 $20,000Operating Savings ($8,333) $8,333 Printers, copier, supplies, etc. Required to support staff who are not located in adjacent areas

Total $18,229 $13,021 $31,250

Book Truck Replacement: 20 New with 20% Replaced Each Yr $2,000 $2,000

Projected $500 cost each IT Hardware & Software Replacement and Upgrade Reserve $34,000 $34,000

50 New with 1/3 Replaced Each Yr Projected $2,000 cost each

Telecommunication: Additional B-Jacks & Wireless Technology for Library Users $11,724 $11,724

Operating Savings ($4,885) $4,885 Projection: 100 b-jacks or wireless communication hub in new facility for 100 users @ $9.77 per month each. Excludes equipment or installation cost

Total Operating $61,068 $17,906 $78,974

Total On-Going Operations 4.50 $158,872 $87,766 4.50 $246,638

2

Page 85: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

Description

FTE $ FTE $ FTE $

UNIVERSITY OF COLORADO HEALTH SCIENCES CENTERLibrary Program Plan

Projected Operating Plan - Unrestricted Fund Operations

Total

Incremental IncreaseLibrary Occupancy - December 1, 2004

04-05 05-06

Cost of Maintaining Services at 9th Avenue:Costs after the Fitzsimons Library opens until the Schools of Nursing & Pharmacy relocatePlan: Maintain a satellite within Denison for24 hr study space, 9-5 reference assistance,PC access to electronic resources, small printcollection of reference materials, daily courierservice for other materials

Faculty Librarian 1.00 $60,000 1.00 $60,000Vacancy Savings ($25,000) $25,000 $50,000 salary + 20% benefits

Library Tech II 1.00 $28,598 1.00 $28,598Vacancy Savings ($11,916) $11,916 $23,832 salary + 20% benefits

Print Materials $5,000 $5,000Operating Savings ($2,083) $2,083

General Operating $5,000 $5,000Operating Savings ($2,083) $2,083

Total Satellite Facility 2.00 $57,516 $41,082 2.00 $98,598

GRAND TOTAL 6.50 $216,388 $128,848 6.50 $345,236

3

Page 86: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

Projected Occupancy Date - December 1, 2004

DescriptionFTE Amount FTE Amount FTE Amount

On-Going Operations:Compensation 4.50 $97,804 $69,860 4.50 $167,664Operating $61,068 $17,906 $78,974

Total On-Going Operations 4.50 $158,872 $87,766 4.50 $246,638

Maintain Services at 9th AvenueCampus Until the Schools of Nursingand Pharmacy Relocate to Fitzsimons 2.00 $57,516 $41,082 2.00 $98,598

Total 6.50 $216,388 $128,848 6.50 $345,236

UNIVERSITY OF COLORADO HEALTH SCIENCES CENTERLibrary Program Plan

Summary of Projected Increases to Existing Library Operating Budget

04-05 Year 1 05-06 Year 2 Total

Page 87: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

Projected Occupancy Date - December 1, 2004

COFRS Fund 04-05 05-06 06-07 TotalYear 1 Year 2 Year 3

310 - Unrestricted Fund Non-Exempt $115,000 $115,000Allocation of New Resources

310 - Unrestricted Fund Non-Exempt $101,388 $128,848 $230,236Reallocation of Existing Resources

Total $216,388 $128,848 $345,236

UNIVERSITY OF COLORADO HEALTH SCIENCES CENTERLibrary Program Plan

Funding Sources for Projected Operating Increases

Page 88: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

Projected Occupancy Date - December 1, 2004

DescriptionFTE Amount FTE Amount FTE Amount

On-Going Operations:Compensation 4.50 $97,804 $69,860 4.50 $167,664Operating $61,068 $17,906 $78,974

Total On-Going Operations 4.50 $158,872 $87,766 4.50 $246,638

Maintain Services at 9th AvenueCampus Until the Schools of Nursingand Pharmacy Relocate to Fitzsimons 2.00 $57,516 $41,082 2.00 $98,598

Total 6.50 $216,388 $128,848 6.50 $345,236

UNIVERSITY OF COLORADO HEALTH SCIENCES CENTERLibrary Program Plan

Summary of Projected Increases to Existing Library Operating Budget

04-05 Year 1 05-06 Year 2 Total

Page 89: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

Description Amount Per GSF

Housekeeping $0.77Building Maintenance & Repair $1.80Utilities $4.04Grounds $0.26Environmental Health & Safety $0.25Police $0.72Insurance $0.22

Total $8.06

UNIVERSITY OF COLORADO HEALTH SCIENCES CENTERLibrary Program Plan

Projected Facility Operating Costs

Page 90: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

Fitzsimons Library Program Plan University of Colorado Health Sciences Center

June 1, 2001

Appendix Section 7.07

IS DesignRequirements

Page 91: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

UCHSC Telecommunications Cost Estimating Guidelines

As of: 9/22/00 1 of 8 UCHSC IS

The following elements of telecommunications infrastructure shall be addressed whenpreparing telecommunications cost estimates for new UCHSC construction. Additionalinformation, standards, recommendations, and guidelines for intra-building infrastructuredesign may be found in the BICSI Telecommunications Distribution Methods Manual(TDMM), 9th Ed. For outside plant design, please consult BICSI’s Customer-OwnedOutside Plant Design Manual.

Other relevant references include the Section 16470 Telecommunications Voice and DataSystems document and UCHSC IS Schematic Design Criteria document. Both arereadily available from UCHSC IS.

Each element of telecommunications infrastructure is broken out in subsequent tables.Specific guidance is given, where available, on how we do cost estimating by rules ofthumb (ROT).

Elements of Telecommunications Infrastructure Table.

Element ComponentsSpaces Service Entrance (SE); Equipment Room (ER);

Telecommunications Room (TR); Work area (WA)Pathways Horizontal distribution; building backbone (riser)

distribution; campus backbone distributionMedia Horizontal media; building backbone (riser) media;

campus backbone mediaData Network Equipment Horizontal distribution hardware; Building backbone

hardware; Communications Center hardwareVoice Equipment Telephone sets at the WA; PBX or RTU;

Communications Center equipmentConnecting Hardware Racks; patch panels; connecting blocks; jacks; transition

points; consolidation pointsGrounding System Telecommunications Main Grounding Busbar (TMGB);

Telecommunications Grounding Busbar (TGB);Telecommunications Bonding Backbone (TBB);Grounding Electrode Conductor (GEC); Equipment Bonding Conductor (EBC); Primary protectors at SE

Fire Systems FM�200; Preaction Systems; Firestopping

Page 92: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

UCHSC Telecommunications Cost Estimating Guidelines

As of: 9/22/00 2 of 8 UCHSC IS

Telecommunications Spaces Table.

Spaces DescriptionSE A SE serves as the building’s entry point for campus backbone media.

The size of a SE is a minimum of 10’ by 12’. A larger SE may berequired depending on the size of building and the amount ofinfrastructure entering the building from the campus backbone.Significant wall space may be required for primary protection of coppercircuits. A SE may also serve as an ER or TR. Contact Rob Lee,Manager of Telephony, (303) 724-0443, for questions.

ER The minimum size is 150 ft2. An ER normally holds a PBX and anintermediate cross-connect (IC). ERs are usually collocated with a TR.ERs require strict environmentals, fire suppression, etc. Contact RobLee, Manager of Telephony, (303) 724-0443, for questions.

TR The size of a TR depends on floor space being served. The typical sizeof a TR is 10’ x 12’. TRs serve as the cross-connect location forhorizontal cabling and building backbone media. TRs requireenvironmentals, fire suppression, etc. Contact Rob Lee, Manager ofTelephony, (303) 724-0443, for questions.

WA WAs require telecommunications space for faceplates, jacks, WA cables(station cords), etc. Contact Rob Lee, Manager of Telephony, (303)724-0443, for questions.

Telecommunications Pathways Table.

Pathways DescriptionHorizontal Horizontal pathways consist of cellular floors, access (raised) floors,

ceiling zones and grids, underfloor ducts, cellular floors, conduit,raceway, tray, etc from TR to WA. Horizontal pathways shall provide atechnology independent distribution system. Contact Rob Lee, Managerof Telephony, (303) 724-0443, for questions.

Buildingbackbone

The building backbone pathway consists of sleeves, slots, conduit, trays,and other pathways that vertically interconnect floors (via TRs). Thebuilding backbone is also used to provide pathways between TRs on thesame floor. Contact Rob Lee, Manager of Telephony, (303) 724-0443,for questions.

Campusbackbone

The campus backbone pathway is typically provided. Each building isresponsible for providing a service entrance pathway (number ofconduits and sized per UCHSC IS Schematic Design Criteria) from thebuilding backbone (via the SE) to the nearest campus backbonemanhole. Contact Rob Lee, Manager of Telephony, (303) 724-0443, forspecifics on campus backbone manhole locations.

Page 93: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

UCHSC Telecommunications Cost Estimating Guidelines

As of: 9/22/00 3 of 8 UCHSC IS

Telecommunications Media Table.

Media DescriptionHorizontal Category 6 (or Category 5E, as specified by IS) cable is the standard for

horizontal media. Each WA typically requires four (4) 8-pin modularjacks (RJ-45 in the vernacular) housed in two faceplates. That is, twojacks are contained per faceplate. Each faceplate will contain one A-jack (to support telephony) and one B-jack (to support data networking).This requirement necessitates placing four Category 6 (or Category 5E,as specified by IS) UTP cables per WA. The campus rule of thumb(ROT) cost model for horizontal media is $300 per faceplate or $600per WA. Additional jacks and faceplates may be required to supportother applications as dictated by the building’s occupants. Contact RobLee, Manager of Telephony, (303) 724-0443, for questions.

Buildingbackbone

The building backbone media is generally 50/125 �m (or 62.5/125 �m,as specified by IS) fiber for data networking applications and UTP fortelephony applications. Building dimensions and the applications beingsupported will determine the amount of building backbone media to beplaced. Contact Rob Lee, Manager of Telephony, (303) 724-0443, forquestions.

Campusbackbone

Each building must provide campus backbone media back to theCommunications Center in Building 500. Sufficient fiber optic mediamust be placed to support data networking; CATV; CCTV and securitysystems; video (MPEG2, H.320, and H.323); fire, life, and safetysystems; HVAC; and building management systems (BMS). The rule ofthumb (ROT) is to allocate 48 strands of 50/125 �m (or 62.5/125 �m asspecified by IS) multimode fiber and 24 strands of single mode fiber perbuilding. Additionally, copper media must be placed to support NEC voicecommunications. The number of pairs of copper to be placed dependson the type of building, the number of users, and the distance from theCommunications Center. The distance we can drive digital dial tonedepends upon the gauge of the copper, whether an AC long line adapter(LLA) is used, and the distance from the Communications Center inBuilding 500. Use the following data to determine the American WireGauge (AWG) of the copper to be placed :26 AWG (0.40 mm): 1700’ without LLA; 2300’ with LLA24 AWG (0.50 mm): 2800’ without LLA; 4000’ with LLA22 AWG (0.64 mm): 4600’ without LLA; 6000’ with LLAYou should note that use of a LLA is not desired because telephonyservice would depend on reliable, uninterruptible AC power beingavailable. Contact Rob Lee, Manager of Telephony, (303) 724-0443,for guidance on estimating the number of pairs of copper to run back tothe PBX in the Communications Center located in Building 500. Thecost of these media will be influenced by the building’s distance fromBuilding 500 and the amount of media placed.

Page 94: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

UCHSC Telecommunications Cost Estimating Guidelines

As of: 9/22/00 4 of 8 UCHSC IS

Data Networking Equipment Table.

Data NetworkingEquipment Description

Horizontaldistributionhardware

We use Cisco Catalyst 3524-PWR-XL Enterprise Edition (WS-C3524-PWR-XL-EN) switches for horizontal distributionhardware. These are 24-port 10/100 Mb/s switches, with twoslots for Gigabit Ethernet (GbE) GBICs (Gigabit InterfaceConverter) as down links to the Communications Center.Additionally, these switches are capable of providing power toVoIP IP Telephones. In general, each Catalyst 3524 costs$3000, installed. The uplink to the building backbone network(see below) is a GbE GBIC interface that costs $350 each. Two(2) GBICs are typically required per TR to ensure redundantaccess to the backbone network. In the event that two or moreswitches (maximum of 4 per stack, additional stacks can becreated as necessary) are used in the same TR, we connect themtogether via daisy-chained GBICs. Fiber patch cables areneeded to connect the GBICs together. Fiber optic patch cablescost $50 per patch cable. The cost per station cable to connect tothe horizontal media in the work area is $15 per cable assembly.

Finally, each TR requires a UPS capable of powering theCatalyst 3524s for 4 hours to ensure reliable telephony power.The size and capacity of the UPS depends on the number ofswitches supported. For planning purposes, an UPS to support 3Catalyst 3524s costs $2500, installed.

The ROT for provisioning horizontal distribution hardware is todivide the number of required data ports by 23 (reserve one portfor UPS and operations maintenance) and round the resultingnumber up. This gives you the number of Catalyst 3524switches required if you could assign exactly 23 users to eachswitch. This typically doesn’t happen. So you need to multiplynumber of switches by 20 percent. This number reflects the totalnumber of switches needed by assuming you can’t supportexactly 23 users per switch. You should note that this 20 percentdesign rule might not accurately reflect your building’s footprint,design, or inherent needs.

Contact Dick Kovach, Data Network Manager (303) 724-0484,for questions.

Page 95: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

UCHSC Telecommunications Cost Estimating Guidelines

As of: 9/22/00 5 of 8 UCHSC IS

Data Networking Equipment Table (continued).

Data NetworkingEquipment Description

Building backbonehardware

Gigabit Ethernet (GbE) Solution. This solution will use eithermultimode fiber (MMF) or single mode fiber (SMF) dependingon the building’s distance from the Communications Center inBuilding 500. 62.5/125 �m MMF, with a modal bandwidth of500 MHz�km, supports connectivity up to 550 m at the longwavelength (LX) of 1300 nm and 220 m at the short wavelength.SMF supports connectivity to 10,000 m at the long wavelength.For large building, we will employ the Cisco Catalyst 4006 (5slots) with GBIC interfaces (30 maximum if a second SupervisorEngine isn’t specified). This concentrator costs $30,000.Several concentrators may be required for large buildings. Forsmaller buildings, the Cisco Catalyst 4908G-L3 Layer 3 switchmay be used. It has 8 GBIC interfaces and costs $15,000.

Contact Dick Kovach, Data Network Manager (303) 724-0484,for specific configuration and costing guidance.

Data Networking Equipment Table (continued).

Data NetworkingEquipment Description

CommunicationsCenter Hardware

As a general ROT, specify a Gigabit Ethernet (GbE) interface atcost of $2,500 per port, installed. Two ports are required perbuilding, as a minimum. The per port charges include access tothe Internet for all building jacks, firewall security, andmaintenance.

Contact Dick Kovach, Data Network Manager (303) 724-0484,for specific guidance.

Page 96: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

UCHSC Telecommunications Cost Estimating Guidelines

As of: 9/22/00 6 of 8 UCHSC IS

Voice Equipment Table.

Voice Equipment DescriptionTelephones WA telephone handsets cost $265 each, installed. Contact Rob

Lee, Manager of Telephony, (303) 724-0443, for questions.PBX; RTUs Buildings located too far from the Communications Center in

Building 500 may require a private branch exchange (PBX) or aremote terminal unit (RTU) for telephony. Contact Rob Lee,Manager of Telephony, (303) 724-0443, for guidance inestimating the cost of these requirements.

CommunicationsCenter Equipment

Individual voice ports on the NEC PBX cost $188, with 16 portsper card, installed. Voice cards also require housing in a PortInterface Module (PIM). Each voice port required shouldcontribute $59 per port for procuring PIM space. The PIMincludes power supply, TDM cards, cables, and installation. Forcosting of voice mail accounts, additional telephonycomponents, etc. please contact Rob Lee, Manager ofTelephony, (303) 724-0443.

Connecting Hardware Table.

ConnectingHardware Description

Racks; patchpanels; jacks;connectingblocks

Typically, each TR costs $4500 for connecting hardware. Thisincludes 3 Chatworth racks (19” by 84”) and a 12” Chatworth ladderrack. Other components include: Panduit wire management, 4Chatworth vertical double-sided wire management, and 2 Chatworth90� sweeps. ERs require more comprehensive connecting hardware. Contact Rob Lee, Manager of Telephony, (303) 724-0443, for designquestions.

TransitionPoints (TP);ConsolidationPoints (CP)

TPs and CPs are not generally deployed at UCHSC. They may berequired if the user is employing modular furniture. Contact Rob Lee, Manager of Telephony, (303) 724-0443, forquestions.

Page 97: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

UCHSC Telecommunications Cost Estimating Guidelines

As of: 9/22/00 7 of 8 UCHSC IS

Grounding System Table.

GroundingSystem Description

TMGB;TGB; TBB; GEC; EBC

Typically, major portions of the Grounding System are provided in theelectrical design. The telecom piece of the Grounding System willrequire close coordination with the electrical designer.

Contact Rob Lee, Manager of Telephony, (303) 724-0443, for guidanceon designing and costing the telecom portion of the grounding system.

PrimaryProtection

All media that contain conductors must be protected in the SE or as nearas possible to the point at which the exposed cables enter the building.As a general guideline, plan for 5 in2 per circuit pair of wall space forprimary protectors.

Contact Rob Lee, Manager of Telephony, (303) 724-0443, forquestions.

Fire Systems Tables.

Fire Systems DescriptionFM-200 Because of their size, cost, nature, and complexity, ERs require

advanced fire suppression. FM-200 shall be used to protect all ERs.Contact Rob Lee, Manager of Telephony, (303) 724-0443, forquestions.

Preaction Preaction fire suppression systems � instead of wet pipe or dry pipesystems � are recommended for use in TRs. Contact Rob Lee,Manager of Telephony, (303) 724-0443, for questions.

Firestopping Approved firestopping materials and procedures are required toreestablish the integrity of any fire barrier breached bytelecommunications pathways or media. Firestopping is required forany membrane or through penetration. Firestops may be mechanicalor nonmechanical systems (putties, caulk, cementitious materials,intumescent sheets or wraps, silicon foam, and pillows or collars).Contact Rob Lee, Manager of Telephony, (303) 724-0443, forquestions.

Page 98: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

UCHSC Telecommunications Cost Estimating Guidelines

As of: 9/22/00 8 of 8 UCHSC IS

8

7

6

5

4

3

2

1

A B C D

8

7

6

5

4

3

2

1

UNIVERSITY of COLORADO HEALTH SCIENCES CENTEROffice of Information Systems

MS# F408, P. O. Box 6508 Aurora, CO 80045-0508PROJECT Information Systems

Element of Telecommunications

Infrastructure

SHEET 1 of 1 SCHEMATIC DESIGN.DSFNONE

D

DON GALAROWICZ

29 DEC 1999SCALE: DRAWING FILE:

REVAPPROVED

CHECKED

SIZE:

DRAWN

FILE No. DRAWING No.

DON GALAROWICZ

DR-ELEMENTS

Fitzsimons Build Out

BILL FREUD

Building 500Communications Center

Firewall

Internet

Manhole

Manhole

TR TR

ER TRSE

Campus Backbone Pathway(provided by IS)

Cam

pus B

ackb

one

Path

way

(pro

vide

d by

IS)

Service Entrance Pathway(provided by building)

Firewall(provided by IS)

Internet Access(provided by IS)

Campus Backbone Mediaprovided by building

New Building

nth Floor

Ground Floor

2 Drops per WA provided by buildingWA

Horizontal distribution and media,building backbone distribution and media

provided by building

New construction responsible for: spaces, pathways, media, data network and voice equipment, connecting hardware, grounding system, and firestopping.

Page 99: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

UCHSC Telecommunications Responsibilities

Work Program Plan Cost Estimate Design Responsibility Design Cost Construction

Responsibility Construction Cost

1.0 Trunk

1.1 Conduit Facilities Projects - Coordination w/ HSC IS

1. HSC IS Completes Capacity Planning and

SD

Campus Infrastructure Project Professional

Service's Budget

Campus Infrastructure Project Contractor

Campus Infrastructure Project Construction

Budget2. Campus

Infrastructure Project A/E Completes DD

through CA2.0 In Tract

2.1Campus Backbone Distribution - Conduit from Building to Trunk

Institutional Planning - Coordination w/ HSC IS

Building Project Architect/Engineer

Building Project Professional Service's

Budget

Building Project Contractor

Building Project Construction Budget

2.2

Campus Backbone Media - Media from Building Project to Building 500

Institutional Planning - Coordination w/ HSC IS HSC IS Designer No charge HSC IS Contractor

Building Project Equipment/Furnishings

Budget - Communications

3.0 Building3.1 Spaces

3.11 Service Entrance (SE) Institutional Planning - Coordination w/ HSC IS

Building Project Architect/Engineer

Building Project Professional Service's

Budget

Building Project Contractor

Building Project Construction Budget

3.12 Equipment Room (ER) Institutional Planning - Coordination w/ HSC IS

Building Project Architect/Engineer

Building Project Professional Service's

Budget

Building Project Contractor

Building Project Construction Budget

3.13 Telecommunications Room (TR)

Institutional Planning - Coordination w/ HSC IS

ESS, and University Police

Building Project Architect/Engineer

Building Project Professional Service's

Budget

Building Project Contractor

Building Project Construction Budget

3.14 Work Area (WA) {Voice, Data, and Video Layout)

Institutional Planning - Coordination w/ HSC IS

and ESS

Building Project Architect/Engineer

Building Project Professional Service's

Budget

Building Project Contractor

Building Project Construction Budget

As of: 1/4/011 of 7 IS requirements.xls

Page 100: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

UCHSC Telecommunications Responsibilities

Work Program Plan Cost Estimate Design Responsibility Design Cost Construction

Responsibility Construction Cost

3.2 Pathways

3.21 Horizontal Distribution Institutional Planning - Coordination w/ HSC IS

Building Project Architect/Engineer

Building Project Professional Service's

Budget

Building Project Contractor

Building Project Construction Budget

3.22 Building Backbone (Riser) Distribution

Institutional Planning - Coordination w/ HSC IS

Building Project Architect/Engineer

Building Project Professional Service's

Budget

Building Project Contractor

Building Project Construction Budget

3.23

Campus Backbone Distribution - see Section 2.1, Conduit from Building to Trunk

Institutional Planning - Coordination w/ HSC IS

Building Project Architect/Engineer

Building Project Professional Service's

Budget

Building Project Contractor

Building Project Construction Budget

3.3 Media

3.31 Horizontal Media

Institutional Planning - Coordination w/ HSC

IS, ESS, and University Police

HSC IS Designer/ HSC Technology Consultant

HSC IS Designer - no charge/Technology

Consultant - Building Project Professional

Service's Budget

HSC IS Contractor

Building Project Equipment/ Furnishings

Budget - Communications

3.32 Building Backbone (Riser) Media

Institutional Planning - Coordination w/ HSC IS HSC IS Designer No charge HSC IS Contractor

Building Project Equipment/Furnishings

Budget - Communications

3.33

Campus Backbone Media - see Section 2.2, Media from Building Project to Building 500

Institutional Planning - Coordination w/ HSC IS HSC IS Designer No charge HSC IS Contractor

Building Project Equipment/Furnishings

Budget - Communications

3.4 Data Networking Equipment

3.41 Horizontal Distribution Hardware

Institutional Planning - Coordination w/ HSC IS HSC IS Designer No charge HSC IS Contractor

Building Project Equipment/Furnishings

Budget - Communications

3.42 Building Backbone Hardware

Institutional Planning - Coordination w/ HSC IS HSC IS Designer No charge HSC IS Contractor

Building Project Equipment/Furnishings

Budget - Communications

3.43 Communications Center Hardware

Institutional Planning - Coordination w/ HSC IS HSC IS Designer No charge HSC IS Contractor

Building Project Equipment/Furnishings

Budget - Communications

As of: 1/4/012 of 7 IS requirements.xls

Page 101: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

UCHSC Telecommunications Responsibilities

Work Program Plan Cost Estimate Design Responsibility Design Cost Construction

Responsibility Construction Cost

3.5 Voice Equipment

3.51 Telephone handsets at the WA

Institutional Planning - Coordination w/ HSC IS HSC IS Designer No charge HSC IS Contractor

Building Project Equipment/ Furnishings

Budget - Communications

3.52 PBX or RTU Institutional Planning - Coordination w/ HSC IS HSC IS Designer No charge HSC IS Contractor

Building Project Equipment/ Furnishings

Budget - Communications

3.53 Communications Center Equipment

Institutional Planning - Coordination w/ HSC IS HSC IS Designer No charge HSC IS Contractor

Building Project Equipment/Furnishings

Budget - Communications

3.6

Connecting Hardware (racks, patch panels, connecting blocks, jacks, TP, and CP)

Institutional Planning - Coordination w/ HSC IS HSC IS Designer No charge HSC IS Contractor

Building Project Equipment/Furnishings

Budget - Communications

3.7

Grounding System (TMGB, TGB, TBB, GEC,EBC, and primary protectors)

Institutional Planning - Coordination w/ HSC IS

Building Project Architect/Engineer

Building Project Professional Service's

Budget

Building Project Contractor

Building Project Construction Budget

3.8Fire Systems (FM-200, preaction systems, firestopping)

Institutional Planning - Coordination w/ HSC IS

Building Project Architect/Engineer

Building Project Professional Service's

Budget

Building Project Contractor

Building Project Construction Budget

As of: 1/4/013 of 7 IS requirements.xls

Page 102: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

UCHSC Telecommunications Responsibilities

Work Program Plan Cost Estimate Design Responsibility Design Cost Construction

Responsibility Construction Cost

4.0 ESS4.1 ESS Spaces

4.11 ESS Central Control Room

Institutional Planning - Coordination w/ HSC

ESS

Building Project Architect/Engineer

Building Project Professional Service's

Budget

Building Project Contractor

Building Project Construction Budget

4.12

Telecommunications Room (TR) (ESS coordinates requirements with IS)

Institutional Planning - Coordination w/ HSC IS

ESS, and University Police

Building Project Architect/Engineer

Building Project Professional Service's

Budget

Building Project Contractor

Building Project Construction Budget

4.13 Work Area (WA) {Voice, Data, and Video Layout)

Institutional Planning - Coordination w/ HSC

ESS

Building Project Architect/Engineer

Building Project Professional Service's

Budget

Building Project Contractor

Building Project Construction Budget

4.2 ESS Pathways

4.21 Horizontal Distribution (see IS pathways 3.21)

Institutional Planning - Coordination w/ HSC IS

Building Project Architect/Engineer

Building Project Professional Service's

Budget

Building Project Contractor

Building Project Construction Budget

4.22Building Backbone (Riser) Distribution (see IS pathways, 3.22)

Institutional Planning - Coordination w/ HSC IS

Building Project Architect/Engineer

Building Project Professional Service's

Budget

Building Project Contractor

Building Project Construction Budget

4.23

Campus Backbone Distribution - see Section 2.1, Conduit from Building to Trunk

Institutional Planning - Coordination w/ HSC IS

Building Project Architect/Engineer

Building Project Professional Service's

Budget

Building Project Contractor

Building Project Construction Budget

4.3 ESS Media

4.31

Use IS Horizontal Media where possible, otherwise deploy own media

Institutional Planning - Coordination w/ HSC IS

and ESS

HSC IS Designer/ HSC Technology Consultant

HSC IS Designer - no charge/Technology

Consultant - Building Project Professional

Service's Budget

HSC IS Contractor

Building Project Equipment/ Furnishings

Budget - Communications

4.32Building Backbone (Riser) Media (provided by IS, 3.32)

Institutional Planning - Coordination w/ HSC IS HSC IS Designer No charge HSC IS Contractor

Building Project Equipment/Furnishings

Budget - Communications

4.33

Campus Backbone Media - see Section 2.2, Media from Building Project to Building 500

Institutional Planning - Coordination w/ HSC IS HSC IS Designer No charge HSC IS Contractor

Building Project Equipment/Furnishings

Budget - Communications

As of: 1/4/014 of 7 IS requirements.xls

Page 103: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

UCHSC Telecommunications Responsibilities

Work Program Plan Cost Estimate Design Responsibility Design Cost Construction

Responsibility Construction Cost

4.4 ESS Video Equipment

4.41

WA Equipment (video cameras, microphones, speakers, LCD projectors)

Institutional Planning - Coordination w/ HSC

ESS

HSC Technology Consultant as directed

by IS and ESS

Building Project Professional Service's

BudgetAV Contractor

Building Project Equipment/Furnishings

Budget - Equipment

4.42

Central Control Room Equipment (serial digital routers, cross point switch, distribution amplifiers, FOT)

Institutional Planning - Coordination w/ HSC

ESS

HSC Technology Consultant as directed

by IS and ESS

Building Project Professional Service's

BudgetAV Contractor

Building Project Equipment/Furnishings

Budget - Equipment

4.5

Connecting Hardware (racks, patch panels, connecting blocks, jacks, TP, and CP)

Institutional Planning - Coordination w/ HSC

ESS

HSC Technology Consultant as directed

by IS and ESS

Building Project Professional Service's

BudgetAV Contractor

Building Project Equipment/Furnishings

Budget - Equipment

4.6

Grounding System (TMGB, TGB, TBB, GEC,EBC, and primary protectors)

Institutional Planning - Coordination w/ HSC IS

and ESS

Building Project Architect/Engineer

Building Project Professional Service's

Budget

Building Project Contractor

Building Project Construction Budget

4.7Fire Systems (FM-200, preaction systems, firestopping)

Institutional Planning - Coordination w/ HSC IS

and ESS

Building Project Architect/Engineer

Building Project Professional Service's

Budget

Building Project Contractor

Building Project Construction Budget

As of: 1/4/015 of 7 IS requirements.xls

Page 104: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

UCHSC Telecommunications Responsibilities

Work Program Plan Cost Estimate Design Responsibility Design Cost Construction

Responsibility Construction Cost

5.0 University Police5.1 University Police Spaces

5.11 Control RoomInstitutional Planning -

Coordination w/ University Police

Building Project Architect/Engineer

Building Project Professional Service's

Budget

Building Project Contractor

Building Project Construction Budget

5.12

Telecommunications Room (TR) - Coordinate space requirements with IS, See 3.13

Institutional Planning - Coordination w/ HSC IS

and University Police

Building Project Architect/Engineer

Building Project Professional Service's

Budget

Building Project Contractor

Building Project Construction Budget

5.13 Work Area (WA) Institutional Planning -

Coordination w/ University Police

Building Project Architect/Engineer

Building Project Professional Service's

Budget

Building Project Contractor

Building Project Construction Budget

5.2 University Police Pathways

5.21

Use IS Horizontal Distribution where practical, otherwise specify own pathway

Institutional Planning - Coordination w/ HSC IS

Building Project Architect/Engineer

Building Project Professional Service's

Budget

Building Project Contractor

Building Project Construction Budget

5.22

Building Backbone Distribution (Coordinate with IS -see IS pathways, 3.22)

Institutional Planning - Coordination w/ HSC IS

Building Project Architect/Engineer

Building Project Professional Service's

Budget

Building Project Contractor

Building Project Construction Budget

5.23

Campus Backbone Distribution - Coordinate with IS - see Section 2.1, Conduit from Building to Trunk

Institutional Planning - Coordination w/ HSC IS

Building Project Architect/Engineer

Building Project Professional Service's

Budget

Building Project Contractor

Building Project Construction Budget

5.3 University Police Media

5.31

Use IS Horizontal Media where possible, otherwise deploy own media

Institutional Planning - Coordination w/ HSC IS

and University Police

HSC IS Designer/ HSC Technology Consultant

HSC IS Designer - no charge/Technology

Consultant - Building Project Professional

Service's Budget

Security ContractorBuilding Project

Equipment/ Furnishings Budget - Security

5.32Building Backbone Media (coordinate with IS, see, 3.32)

Institutional Planning - Coordination w/ HSC IS HSC IS Designer No charge HSC IS Contractor

Building Project Equipment/Furnishings

Budget - Communications

As of: 1/4/016 of 7 IS requirements.xls

Page 105: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

UCHSC Telecommunications Responsibilities

Work Program Plan Cost Estimate Design Responsibility Design Cost Construction

Responsibility Construction Cost

5.33

Campus Backbone Media - coordinated with IS, see Section 2.2, Media from Building Project to Building 500

Institutional Planning - Coordination w/ HSC IS HSC IS Designer No charge HSC IS Contractor

Building Project Equipment/Furnishings

Budget - Communications

5.4 University Police Equipment

5.41

University Police Equipment (Code Blue phones, security cameras, access phones, etc.)

Institutional Planning - Coordination w/ HSC

University Police

HSC Technology Consultant as directed

by IS and University Police

Building Project Professional Service's

BudgetSecurity Contractor

Building Project Equipment/ Furnishings

Budget - Security

5.42

Telecommunications Room Equipment (concentrators, hubs, servers)

Institutional Planning - Coordination w/ HSC

University Police

HSC Technology Consultant as directed

by IS and University Police

Building Project Professional Service's

BudgetSecurity Contractor

Building Project Equipment/ Furnishings

Budget - Security

5.43

Connecting Hardware (racks, patch panels, connecting blocks, jacks, TP, and CP)

Institutional Planning - Coordination w/ HSC

University Police

HSC Technology Consultant as directed

by IS and University Police

Building Project Professional Service's

BudgetSecurity Contractor

Building Project Equipment/ Furnishings

Budget - Security

As of: 1/4/017 of 7 IS requirements.xls

Page 106: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

Fitzsimons Library Program Plan University of Colorado Health Sciences Center

June 1, 2001

Appendix Section 7.08

Program PlanRegulatory

CodeAnalysis

Page 107: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

PROGRAM PLAN - REGULATORY CODE ANALYSIS

1. PROJECT

Project Name: UCHSC Library Location: UCHSC Campus at Fitzsimons, Aurora, COOwner: State of Colorado

2. GENERAL REQUIREMENTS

Applicable Building Code: Uniform Building Code (IBCO) Year: 1997Applicable Local Code: UCHSC Campus Standards Year:Applicable Fire Code: Uniform Fire Code (IBCO) Year: 1997Zoning Code: N/A Year:Zone District: R-3 Year:Fire Zone: Year:Restrictions in Fire Zone:

3. OCCUPANCY REQUIREMENTS - GENERAL

Table 1. Occupancy Classification: Gross Area3-A

A. Primary Occupancy B Library 113,467SF

Table 2. Occupancy Separations(s) Required:3-B

A. None.

3. Occupancy Requirements - By Group:

A. Chapter 3 - Group B, Library:304.3 Location on property - Main entrance shall be located on a public street or on min. 20' exit discharge.304.4 Access and exit tacilities - refer to chapter 10 and chapter 11.304.5 Light, ventilation and sanitation - refer to chapter 12, plumbing fixtures per section 2902.2.304.6 Shafts and exit enclosures - refer to chapter 10.304.7 Sprinklers and standpipes - refer to chapter 9.304.8 Special hazards - refer to section 405.3.3, 302.5 heat equipment. Rooms to have 1-Hour separation.

4. GENERAL BUILDING LIMITATIONS

1. Proposed Building:

A. Basement Unlimited AreaB. First Floor Unlimited AreaC. Second Floor Unlimited AreaD. Third Floor Unlimited AreaE. Fourth Floor Unlimited AreaF. Penthouse Roof Unlimited Area

2. Proposed Building Height:

A. Number of stories: 5 StoriesB. Height in feet: 75 Feet

REGULATORY CODE ANALYSISUCHSC Library at Fitzsimons 215.04

Page 1 of 6printed 6/5/01

Page 108: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

Table 3. Exterior Wall Opening Protection:5-A

A. Group BType 1-FR: Bearing walls - 4-Hour N/C <5' from property line, 2-Hour N/C elsewhere.

Nonbearing walls - 4-Hour less than 5'. 2-Hour less than 2". 1-Hour less than 40". NR, N/C elsewhere.Openings - Not permitted less than 5'. Protected less than 20'.

Table 4. Basic Allowable Height and Area:5-B

A. Group BType I-FR: Unlimited height

Unlimited areaB. Group S-3

Type I-FR: Unlimited heightUnlimited area

5. Premises Identification:

502 Provide address numbers on building.

6. Location on Property:

503.3 When a new building is erected on the same property as an existing building, the assumed property line location shall be such that the wall opening protection of the existing buildings comply with table 5-Aand chapter 6.

5. FIRE RESISTIVE REQUIREMENTS

Table 6-A 1. Construction Element: Type I Construction:

Exterior bearing walls 2-HourInterior bearing walls 3-HourExterior non-bearing walls N/RStructural frame 3-Hour

302.3 Partitions - permanent 1-HourShaft enclosures 2-Hour *see section 711Floors and floor/ceiling 2-Hour Roofs and roof/ceiling 2-Hour Exterior door and windows N/R

601.5.2.1 Non-corridor partitions Non-combustible, 1-Hour or F>T. woodTable 15A Roof coverings Minimum class B

302.5 Boiler room enclosure 1-Hour, openings 1-Hour rated

*711.2 Shafts shall be enclosed at the bottom or protected with fire damper.*711.3 Openings made through floors for cables, tubes, pipes, etc. need not be enclosed provided they are

fire stopped to the same fire-resistance as the floor/ceiling construction.*711.4 Openings into shaft enclosures shall be protected 1 1/2-Hour for 2-Hour shaft.

6. STRUCTURAL REQUIREMENTS - BY CONSTRUCTION TYPE

602 1. Construction Elements:A. Framework: Steel - chapter 22, Concrete - chapter 19, Masonry - chapter 21.B. Stairs: Steel or reinforced concrete. Refer to chapter 10.C. Roofs: Structural frame rated per Table 6-A.

REGULATORY CODE ANALYSISUCHSC Library at Fitzsimons 215.04

Page 2 of 6printed 6/5/01

Page 109: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

7. EXIT REQUIREMENTS

104.2.2.4 TABLE 10-A Occupant Load and Exit Required 1004.2.3.4FLOOR USE LOAD GROSS # OCC. TOTAL ADJACENT TOTAL #

FACTOR S.F.* OCC. FLOOR OF EXITSBasement storage 300 3,500 12

utilities 300 3,000 1022

First study 50 9,450 189Floor office 100 11,400 114

utilities 300 1,000 3306

Second study 50 9,450 189Floor office 100 10,200 102

utilities 300 120 0classroom 50 5,400 108

399

Third stacks 100 18,600 186Floor study 50 5,500 110

utilities 300 120 0296

Fourth stacks 100 14,600 146Floor study 50 2,300 46

office 100 3,100 31assembly 15 3,600 240utilities 300 120 0

463

Penthouse utilities 300 6,530 2222

TOTAL 2,865 107,990 1,509 1,509 2*Note: Gross area excludes toilets, custodial closets and vertical circulation such as shafts, stairs and elevators.

1. Arrangement and Distance to Exits:1004.2.4. A. Half diagonal distance overall for building:1004.2.5.1 B. Maximum allowable travel distance: 200 feet, 250 feet if sprinkled.1004.2.6 C. Dead end corridors allowed? Yes, 20' - 0" maximum length.

2. Exit Doors:1003.3.1.3 A. Minimum width allowed: 3'-0" with 32" clear.1003.3.3.3.1 B. Maximum leaf witdth allowed: 4'-0"

C. Width required for No. of occupants: See table, Table 10-B all doors 3'-0".

3. Exit Corridors:1004.3.4.2 A. Minimum allowable width: 44"

B. Exit required at each end of corridor? YesC. Wall fire resistance required: 1-Hour for Type I construction.

1004.3.4.3.2 D. Doors and frames fire resistance required: 20-min. self-closing.E. Other openings fire resistance required: 3/4-Hour rated and not more than 25% of the wall

of the room separated by the corridor.F. Ceiling Fire Resistance required 1-Hour for Type I construction.

REGULATORY CODE ANALYSISUCHSC Library at Fitzsimons 215.04

Page 3 of 6printed 6/5/01

Page 110: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

4. Stairs:1003.3.3.3.2 A. Minimum. Width: 44" (36" for less than 50 occupants).

B. Stairs and ladders used to attend equipment are exempt

5. Rise/Run:1003.3.3.3 A. Minimum and Maximum riser allowed: 4" minimum, 7" maximum

B. Stairs and ladders used to attend equipment are exempt.

6. Landings:1003.3.3.5 A. Minimum length: Not less than the stair width, but need not be more

than 44" for a straight run stair.B. Basement stairs: No storage below stairs.C. Max. vertical distance between landings: 12'-0"

7. Handrails:1003.3.3.6 A. Required at each side? Yes, and must be continuous for > 44" stairs.

B. Intermediate rails required at stairs? If more than 88 inches wide.C. Height above nosing: Not less than 34", not more than 38".D. Handrails return to wall at ends? Yes, or terminate in newel posts.E Handrails extend beyond end? Minimum 12" beyond top riser and 12" beyond the bottom riser.F. Handrail diameter: Not less than 1 - 1/2" dia., to more than 2" dia.

8. Roof access:1003.3.3.11 A. Stair to roof required? Yes, required for 4 or more stories.

9. Stair required to continue to basement? Provide barrier at first floor.

1003.3.3.12 10. Stair hatchway access to roof required? Yes, required for 4 or more stories.

11. Ladder access to roof high point required? No

1003.3.3.4 12. Stair Head Room: Not less than 6 feet, 8 inches.

13. Ramps:1003.3.4 A. Maximum slope to use as exit: Maximum 1 vertical to 8 horizontal. If on an accessible

route, 1 vertical to 12 horizontal.B. Handrails required? Yes, but if less than 88 inches wide, no intermediates required.C. Width and Landings: 44: minimum width. Landing at top and bottom

with intermediate at each 5' of vertical rise.

14. Horizontal Exit:1005.3.5 A. Where permitted may not serve as the only exit. Where more than two exits required, not more than 1/2

may be horizontal exit.B. Openings: Rating of wall is 2-Hour minimum.C. Area of Refuge: Must lead to a floor area with an occupant capacity of 3 SF per occupant sufficient to

accept the occupant load of the exit.

15. Exit Enclosures:1005.3.3 A. Where required: At all exit stairs and ramps except where serving only one adjacent floor and not

connected with corridors or stairs serving other floors.B. Construction: Not less than 1-Hour construction for building less than four floors in height, 2-Hour for four.C. Openings: Only openings necessary for exiting are permitted. Rating of fire assembly at opening is

minimum one hour. 1 1/-Hour for 2-Hour enclosures.

16. Pressurized Enclosure:1005.3.3.7 A. Where required: An occupied floor that is more than 75' above fire department vehicle access (N/A).

REGULATORY CODE ANALYSISUCHSC Library at Fitzsimons 215.04

Page 4 of 6printed 6/5/01

Page 111: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

17. Exit Passageways:1002.3.4 A. Requirements: Shall discharge into public ways or exit passage ways.

B. Openings: 1-Hour for 1-Hour enclosure. 1 1/2-Hour for 2-Hour enclosures. C. Width: Not less than 44".

1003.2.8 18. Exit signs required: Where two or more exits are required. No point more than 100' from sign.

19. Guard Rails:A. Where required: Landings, etc. more than 30" above grade or floor below. B. Height required: Not less than 42".C. Intermediate rail dimension

or pattern: Such that 4" sphere cannot pass.

8. ROOF STRUCTURES

1511 1. Penthouses:A. Area limitations: Maximum 33-1/3 percent of the roof.B. Height limitations: 28 feet above roof.C. Use limitations: Only for mechanical equipment and shafts.D. Construction requirements: Same as floors, walls and roof of the main building.

Table 5-A 2. Minimum roof class for type B occupancy is "B."

709.4.1 3. Parapet Walls:A. Not required where wall, due to location from property line, may have unprotected openings.

9. FIRE PROTECTION SYSTEM REQUIREMENTS

904 1. Fire extinguishing systems:A. Sprinklers required: In any story or basement where floor area exceeds 1,500 S.F. and there is

not at least 20 S.F. of opening in each 50 lineal feet of wall.904.5 2. Standpipes:Table 9-A A. Standpipe class I required.

10. FIRE-RESISTANT MATERIALS AND CONSTRUCTION

708.1 1. Fire Blocking:A. Where required: In combustible construction at all concealed vertical and horizontal space at 10' intervals.B. Construction: Nominal 2" lumber or gypsum board.

2. Draft Stops:A. Where required: In combustible construction at floor/ceiling assemblies with concealed spaces.B. Area limitations: Concealed spaces not to exceed 1000 S.F. with maximum dimension of 60' (3000 S.F.

and 100' if sprinkled).C. Attics: Area between attic draft stops is not to exceed 3000 S.F. with maximum dimension of 60'

(9000 S.F. and 100' if sprinkled).D. Construction: Nominal 2" lumber or gypsum board.E. Openings: In draft stops, self closing with automatic latches.

712 3. Usable Space Under Floors:A. Protection: Usable space below the first story shall be enclosed and protected on the usable side

with one-hour fire-resistive construction.B. Openings: 20-minute, self-closing.

REGULATORY CODE ANALYSISUCHSC Library at Fitzsimons 215.04

Page 5 of 6printed 6/5/01

Page 112: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

UNIFORM FIRE CODE

1. FIRE DEPARTMENT ACCESS AND WATER SUPPLY

901.2.2.1 1. Fire apparatus access to be approved prior to construction.

902.2.1 2. Access roads to be provided when any portion of the building is in excess of 150' from access point on public street. (Exception 1. Roads may be waived by fire chief if building is fully protected.)

902.4 3. Key boxes to be provided for access to secured buildings.

903.2 4. Fire hydrants to be installed on site such that no portion of the building is in excess of 150'.

2. FIRE PROTECTION SYSTEMS AND EQUIPMENT

1002.1 1. Provide portable extinguishers as required by the Chief and UFC Standard 10-1.

Table 2. Standpipes are required for buildings four stories or higher.1004-A

REGULATORY CODE ANALYSISUCHSC Library at Fitzsimons 215.04

Page 6 of 6printed 6/5/01

Page 113: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

Fitzsimons Library Program Plan University of Colorado Health Sciences Center

June 1, 2001

Appendix Section 7.09

IndependentThird-Party

Review

Page 114: University of Colorado Health Sciences Center...Fitzsimons Library Program Plan University of Colorado Health Sciences Center June 1, 2001 4 Following receipt of the DEGW strategic

Fitzsimons Library Program Plan University of Colorado Health Sciences Center

June 1, 2001

The Third Party Review will be performed prior to review by the

University of Colorado Board of Regents