UNIVERSIDAD NACIONAL AUTÓNOMA DE MÉXICO · 2020. 9. 9. · The Charterparty comprised a fixture...
Transcript of UNIVERSIDAD NACIONAL AUTÓNOMA DE MÉXICO · 2020. 9. 9. · The Charterparty comprised a fixture...
INTERNATIONAL MARITIME LAW ARBITRATION MOOT
ROTTERDAM, 2019
MEMORANDUM FOR RESPONDENT
UNIVERSIDAD NACIONAL AUTÓNOMA DE MÉXICO
ON BEHALF OF: AGAINST:
Omega Chartering Ltd. Panther Shipping Inc.
Respondent Claimant
GEMMA NAVEJA • MARÍA JOSÉ GONZÁLEZ •
BRENDA VALTIERRA • FRIDA CRUZ
TEAM 27
TABLE OF CONTENTS
TABLE OF ABBREVIATIONS……………………………………………...………………………..…I
TABLE OF LITERATURE…………………………………………………………………………….III
TABLE OF CASES……………………………………………………………...………………………IV
STATEMENT OF FACTS…………………………………………………...………………………...…1
ARGUMENT………………………………………………………………...…………………………….4
PART I: THE RESPONDENT IS RELIEVED OF THE OBLIGATION TO PERFORM
UNDERWATER CLEANING……………………………………………………………………………4
A. RESPONDENT WAS PREVENTED FROM CARRYING OUT UNDERWATER CLEANING….4
1. THE CLAIMANT WAS UNWILLING TO AGREE A LUMP SUM…………………………......…...4
2. THE CLAIMANT UNREASONABLY REJECTED THE UNDERWATER CLEANING AT PORT
NORTH …………………………………………………………………………………………………….5
3. RESPONDENT SHALL NOT PAY THE COST OF THE VOYAGE TO SOUTH ISLAND……….......6
PART II: THE CLAIMANT IS NOT ENTITLED TO LOSS OF PROFITS…………….…………….6
A. THE RESPONDENT IS NOT LIABLE FOR THE CLAIMANT’S LOSS OF FIXTURE…………...6
i) APPLICABLE TEST FOR RECOVERABILITY OF DAMAGES………………………………………...7
COUNTERCLAIMS DEFENSE……………………………………………………………………..…..9
PART I: THE RESPONDENT SUBMITTED THE CARGO CLAIM WITHIN THE TIME
LIMIT…………………………………………………………………………………………...……….9
A. THE RESPONDENT NOTICE OF CARGO DAMAGE CONSTITUTES A CARGO
CLAIM……………………………………………………………………….…………………………..9
i) IN THE ALTERNATIVE, RESPONDENT'S SUBMISSION WAS MADE WITHIN THE SIX
YEARS PROVIDED BY THE ICA………………………………………………...……………………..10
B. THE CLAIMANT IS RESPONSIBLE FOR CARGO DAMAGE……………..………………….11
1. THE CLAIMANT IS RESPONSIBLE FOR CARGO DAMAGE ARISING FROM CREW
NEGLIGENCE…………………………………………………………………………..………………11
2. THE CLAIMANT IS RESPONSIBLE FOR CARGO DAMAGE IN ACCORDANCE WITH THE
ICA………………………………………………………………………………………………………..12
i) THE CLAIMANT IS 100% LIABLE FOR THE CARGO DAMAGE……...............................................12
ii) ALTERNATIVELY, THE CLAIMANT IS 50% RESPONSIBLE FOR THE CARGO
CLAIM……………………………………………………………………………………………………13
PART II: THE VESSEL WAS OFF-HIRE……………………………………………………………..14
A. THE OFF-HIRE WAS CAUSED BY THE CLAIMANT’S LACK OF DUE DILIGENCE……….14
1. THE MASTER’S DECISION TO SAIL FROM WEST COAST WAS CONTRARY TO THE
NAVIGATION OBLIGATION………………...……………………………………………………….14
B. THE PORT STATE DETENTION IS ENVISAGED IN THE CLAUSE 17 OF THE
CHARTERPARTY…………………………..…………………………………………………………..15
i) THE DETENTION WAS DERIVED FROM THE MASTER’S LACK OF DUE
DILIGENCE……………………………………………………………………………………..………..16
ii) THE RESPONDENT IS ENTITLED TO THE RESTITUTION OF THE OVERPAID HIRE…………18
PRAYER FOR RELIEF……………………………………………………………….………19
I
TABLE OF ABBREVIATIONS
Abbreviation Explanation
Art. Article
Arbitration
Act 1996
English Arbitration Act 1996
Cargo 2,000 mt of cargo of loose-leaf English Breakfast Tea with a value of
US$50 per kg
Corp. Corporation
Crew Crew of the Motor Vessel Thanos Quest
English Court of
Appeal
Court of Appeal of England and Wales
ICA Inter-Club New York Produce Exchange Agreement 1996 (As
Amended September 2011)
Inc. Incorporated
Limitation Act Limitation Act 1980
Ltd. Limited Company
Moot Scenario International Maritime Law Arbitration Moot 2019 ‘Moot Scenario’
No. 20, Version 3.
Mt. Metric Tonne
New Fixture Fixture between Panther Shipping Inc. and Fairwind International, BVI
Next Fixture Fixture between Panther Shipping Inc. and Champion Chartering Corp.
for a period of two years, plus a further two years in charters’ option
North Port Titan Shipbuilders, North Titan Port
NYPE 2015 New York Produce Exchange Charterparty 2015
Preliminary
Survey Report
Preliminary Survey Report of Mekon Surveyors Inc., dated 30 June
2016
South Island South Island Port Agency Co. Ltd
TCP Time charterparty (between Panther Shipping Inc. and Omega
Chartering Ltd.) including the Rider Clauses
Underwater
Cleaning
Underwater Hull Cleaning Obligation pursuant clause 83 of the TCP.
II
USD United States Dollar
V. Versus
Vessel Motor Vessel Thanos Quest
III
TABLE OF LITERATURE
Cited as Citation ALIZADEH, Amir/
NOMIKOS, Nikos
ALIZADEH, Amir/ NOMIKOS, Nikos
Shipping derivatives and risk management,
Springer, [2009] ATHERTON, Laura ATHERTON, Laura
Protecting time under the ICA [2015]
BACHXEVANIS,
Konstantinos
BACHXEVANIS, Konstantinos
The distinction between ‘crew negligence’ and ‘crew
incompetence’ and the consequence thereof
Journal of International Maritime Law [2010] COGHLIN, Terence, et al.
COGHLIN, Terence, et al.
Time charters
Informa Law from Routledge [2014]
https://www.i-
law.com/ilaw/doc/view.htm?queryString=%22cleaning%22+%22
prior%22+%22redeliver*%22&sort=date&querySector=Maritime
+and+Commercial&practiceArea=Maritime+and+Commercial&s
ort=date&searchType=advanced-
search&se=27&id=173284&searched=true
MCINNES David/
CHISHOLM Alex
MCINNES David/ CHISHOLM Alex
UK: Protecting Time In Claims Under The NYPE Inter-
Club Agreement [2012] NYPE Inter-Club
Agreement
NYPE Inter-Club Agreement
English court decision on time bar issue Gard News 206
[2012] Steamship Mutual
Steamship Mutual, Comprehensive Cover
Time Charter – Charterers' Orders to Proceed by a
Specified Route – Whether Navigation or Employment?
[2000] TETLEY, William
TETLEY, William
Marine cargo claims, 4th edition, Thomson Carswell
[2008]
The Inter- Club Agreement The Inter- Club Agreement
Standard Club, Limited Cargo [2018]
IV
TABLE OF CASES
Cited as
Citation
Agile Holdings
Corporation v Essar
Shipping Ltd
Agile Holdings Corporation v Essar Shipping Ltd
Queen's Bench División
[2018] EWHC 1055
Blyth v Birmingham
Waterworks Co
Blyth v Birmingham Waterworks Co
Court of Exchequer
[1856] WLUK 25
CC Award No. 2291 CC Award No. 2291, Clunet 1976, at 990
Hardely v. Baxender Hardley v Baxendale
Court of Exchequer
[1854] WLUK 132;
The Maestro Bulk Ltd v
Cosco Bulk Carrier Co Ltd
Great Creation
The Maestro Bulk Ltd v Cosco Bulk Carrier Co Ltd Great
Creation
Queen's Bench Division
[2014] EWHC 3978
https://www.bailii.org/cgi-
bin/format.cgi?doc=%2Few%2Fcases%2FEWHC%2FComm%2F201
4%2F3978.html&query=(delay)%20AND%20(redelivery)&fbclid=I
wAR0B4pn3FozjV6tLl6gyb1ceNHTxRk-
pobsSa7oJYT7GF0ckEXfIQG7dwLc;
Metall Market 000 v
Vitorio Shipping Company
Limited, The Lehmann
Timber
Metall Market 000 v Vitorio Shipping Company Limited,
The Lehmann Timber
Court of Appeal
[2013] WLUK 133
P v Q, Q v R, R v S P v Q, Q v R, R v S,
Court of Justice Business and Property Courts of England
and Wales
[2018] EWHC 1399
Scheepvaartonderneming
Flintermar v Sea Malta Co
Ltd (The Flintermar)
CV Scheepvaartonderneming Flintermar v Sea Malta Co
Ltd (The Flintermar) Flintermar
[2005] WLUK 396
V
Transfield Shipping Inc v
Mercator Shipping Inc (The
Achilleas)
Transfield Shipping Inc v Mercator Shipping Inc (The
Achilleas)
House of Lords
[2008] Lloyd's Rep 275
1
STATEMENT OF FACTS
18 March 2016 The Claimant time chartered the Vessel to Respondent for about 50-
55 days from West Coast to Wahanda pursuant to a time charterparty
(hereafter the “Charterparty”).
The Charterparty comprised a fixture recap incorporating the
NYPE 2015 form and additional rider clauses.
29 March 2016 The Vessel was delivered into the Charterparty.
18 April 2016 It was published that it was a serious concern in relation to an
outbreak of Ebola virus in West Coast.
20 April 2016 The vessel sailed from the loading port
21 April 2016 West Coast authorities confirmed the outbreak of Ebola and
quarantine surrounding areas.
07 May 2016 The Vessel arrived at the discharge port of Wahanda. She waited at
the anchorage due to the impossibility to berth immediately due to
the fact that the Port Authority feared that the crew had Ebola,
charterers informed that the Vessel is off hire.
2
08 May 2016 Owners noted the decision to detain the vessel due to Port
Authorities orders.
11 May 2016 Charterers informed that the vessel have quarantine for a minimum
period of 28 days affirming that the vessel was off-hire
8 June 2016 Charterers offered USD 15,000 due to the impossibilities to
perform underwater cleaning.
9 June 2016 Owners rejected the Charterer’s proposal.
23 June 2016 Port North Titan sent the invoice of underwater cleaning
performance to Charterers.
27 June 2016 Discharge began
Charterers noted that it was a clear substantial damage in the cargo
for possible negligence of the crew and found the owners fully
liable for it.
Charterers offered to perform the cleaning in North Port or a lump
sum in lieu.
29 June 2016 Charterers notified to the Owners that receivers told them that the
cargo is severely damage.
3
30 June 2016 Charterers informed to Owners that the voyage of South Island will
not be contractual. Charterers offered a lump sum of USD 30,000.
30 June 2016 It is submitted the Preliminary Survey Report.
4 July 2016 Owners chartered the vessel to Fairwind International for 50-55
days.
7 July 2016 Charterers sent to Owners the Preliminary damage report.
23 May 2017 Charterers requested to Owners a 3 months’ time extension in
relation to claim for cargo damage.
29 May 2017 Owners approved the extension.
23 August 2017 Charterers asked for another 3 months’ time extension regarding
cargo claim.
28 August 2017 Owners approved the extension.
4
ARGUMENT
PART I: THE RESPONDENT IS RELIEVED OF THE OBLIGATION TO PERFORM
UNDERWATER CLEANING
A. RESPONDENT WAS PREVENTED FROM CARRYING OUT UNDERWATER
CLEANING
1. On 24 May 2016, the Respondent sent an email to Wahanda Port requesting relevant
information regarding cleaning of the Vessel, in order to comply with the clause 83 of the
TCP.1 However, Wahanda Port Authority held that the underwater cleaning was not
suitable due to the fact that the visibility was below the standard.2
1. THE CLAIMANT WAS UNWILLING TO AGREE A LUMP SUM
2. The impossibility to perform the underwater cleaning was beyond Respondent’s control.
The clause 83 (d) of the TCP contemplates this scenario by establishing that in such cases
in which the Charterer is prevented for cleaning before redelivery, the parties shall agree on
a lump sum payment.3
3. There is an implied duty to cooperate in the performance of the contract4[3] by acting
in a way non prejudicial for the other party, therefore, reasonable renegotiations are usual
in international economic contracts.5 And as was established in the clause 83 (d), the
parties had the contractual obligation to cooperate for agree on a lump sum payment.
4. On 8 June 2016 the Respondent offered to pay a lump sum of USD15,0006in order to
comply with the underwater cleaning obligation, however the Claimant denied this
1 Moot Scenario, 27 2 Moot Scenario, 26 3 Moot Scenario, 16-17 4 COGHLIN, Terence, et al. 5 ICC Award No. 2291 6 Moot Scenario, 29
5
proposal. Then, on 27 June 2016 the Respondent tried again to comply with said obligation
by offering USD20,000.7 Finally, the Respondent tried to reach a solution by offering
USD30,000 as a lump sum payment.8 Nevertheless the Claimant did not even try to
negotiate said offers, showing Claimant’s unwillingness to cooperate.
2. THE CLAIMANT UNREASONABLY REJECTED THE UNDERWATER
CLEANING AT NORTH PORT
5. Regardless Claimant’s unwillingness to reach an agreement on the lump sum payment,
the Respondent was still trying to comply with the underwater cleaning obligation and
looked for a Porth to perform the underwater cleaning.
6. On 26 June 2016, the Claimant requested to the Respondent for the details of the
arrangement for vessel’s cleaning.9 The day after that, it was notified to the Claimant that
Respondent could arrange the cleaning at North Port.10 However, the 29 June 2016, the
Claimant denied Respondent’s offer by calling upon Respondent to arrange inspection and
cleaning in South Island without giving any reasons for the denial of the proposal for
performing the cleaning at North Port.11
7. The Respondent tried in several occasions to reach an agreement for the performance of
the underwater cleaning obligation, but as was set out above, the Claimant unreasonable
denied every Respondent’s proposal breaching the cooperation duty, thus, the Respondent
was relieved of the cleaning obligation.
8. Alternatively, if it is consider that the Respondent is not relieved of the underwater
cleaning obligation, the Respondent is not liable for more than the payment of USD33,000,
7 Moot Scenario, 39 8 Moot Scenario, 42-43 9 Moot Scenario, 34 10 Moot Scenario, 39 11 Moot Scenario, 43
6
since the Respondent offered to perform the cleaning at North Port in which the cost of
said performance would be of said amount.12
9. It was Claimant’s fault to choose the most expensive Port, consequently, the Claimant
shall cover the over cost of it.
3. RESPONDENT SHALL NOT PAY THE COST OF THE VOYAGE TO SOUTH
ISLAND.
10. In the time charterparties the charterer hires the vessel for a period of time.13
Given the impossibility of perform the underwater cleaning at Wahanda, on 27 June 2016
the Respondent explicitly explained to the Claimant that it was not possible to arrange hull
cleaning before redelivery of the Vessel.14
11. On 30 June 2016, the Vessel was redelivered15 finishing the contractual relationship
between the Claimant and the Respondent, for that reason the Respondent stated on the
same day that any further voyage would not be contractual.
12. The voyage to South Island took place after the re-delivery day, thus, the Respondent
is not liable for said cost.
PART II: THE CLAIMANT IS NOT ENTITLED TO LOSS OF PROFITS
A. THE RESPONDENT IS NOT LIABLE FOR THE CLAIMANT’S LOSS OF
FIXTURE
13. On 15 June 2016 the Claimant did a fixture with Champion Chartering Corp.,16 even
when the Respondent notified to the Claimant since 7 May 2016 that the vessel had been
12 Moot Scenario, 35 13 ALIZADEH, Amir/ NOMIKOS, Nikos, 41 14 Moot Scenario, 39 15 Moot Scenario, 68 16 Moot Scenario, 30-33
7
detained by Port State Control due to the reasonable believe that the crew was infected
by Ebola,17 which was a circumstance beyond Respondent’s control and it was not
possible to know the time that would take to redeliver the vessel.
14. The Claimant’s assertion that the Respondent had special knowledge of the Next
Fixture at the moment of entering into the TCP18 was not possible due to the fact that the
TCP was celebrated on 18 March 201619 and the Claimant entered into the Next Fixture
on 15 June 2016, notifying that situation to the Claimant until 26 June 2016.20
15. Even if it is considered that the loss of fixture could have been foresee by the
Respondent, the Claimant is not entitled to loss of profits, because it has been established
in sophisticated areas of commerce, like shipping, the foreseeability test alone is too
simplistic.21
i) APPLICABLE TEST FOR RECOVERABILITY OF DAMAGES
16. The remoteness rule is used in the shipping industry for determine the extent of
recoverability of damages. Said rule states that the contract-breaker is liable for: “the
damages which … may fairly and reasonably be considered either arising naturally, ie,
according to the usual course of things, from such breach of contract itself, or such as
may reasonably be supposed to have been in the contemplation of both parties, at the time
they made the contract, as the probable result of the breach of it”.22
17 Moot Scenario, 25 18 Moot Scenario, 77 19 Moot Scenario, 2 20 Moot Scenario, 34 21 Much ado about nothing?. Mike Burns, of Weightmans LLP, considers a case of contractual damages. Maritime
Risk International , 19 may 2010
Hardely v. Baxender 22 Lloyd's Maritime and Commercial Law Quarterly. Contractual remoteness, “scope of duty” and intention. Mark
Stiggelbout (2012).
Hardely v. Baxender
8
17. In this sense, on Transfield Shipping Inc v Mercator Shipping Inc (The Achilleas)
award, the Tribunal found that the damages claimed were too remote to be recoverable
as there was no evidence establishing the contemplation of the parties at the time they
entered into the charterparty regarding said damages.23
18. The loss of a particularly lucrative fixture in a volatile market is too remote since it is
unlikely that it was contemplated for the parties as a loss arising from a breach,24 therefore
it cannot be recoverable.
19. In any case, the Claimant is not entitled to loss of profits, because it is a recognized
standard in the shipping industry that the only damages that could be asked regarding the
delay in re-delivery are those consisting in the difference between the charter rate and the
market rate.25However, as the Claimant did not provide the applicable market rate and
not did any claim in this regard, the Tribunal shall found that the Claimant is not entitled
to that.
20. In the alternative, the damages should not constitute further than 2 years period,
because to consider the optional extension of the New Fixture of other 2 years it is way
too remote.
21. On 4 July 2016 the Claimant chartered the vessel to Fairwind International for 50-55
days.26 As the Claimant is not losing any profit in that period, even if it is considered that
the Claimant is entitled to loss of profits, the amount earned for the new fixture, shall be
discounted of the period of 2 years.
23 URL: http://www.bailii.org/ew/cases/EWCA/Civ/2007/901.html
[2007] EWCA Civ 901, [2007] 2 Lloyd's Rep 555, [2007] 2 CLC 400, [2008] 1 All ER (Comm) 685 24 Much ado about nothing?. Mike Burns, of Weightmans LLP, considers a case of contractual damages. Maritime
Risk International , 19 may 2010 25 The Maestro Bulk Ltd v Cosco Bulk Carrier Co Ltd Great Creation 26 Moot Scenario, 53-54
9
COUNTERCLAIMS
PART I: THE RESPONDENT SUBMITTED THE CARGO CLAIM WITHIN THE
TIME LIMIT.
A. THE RESPONDENT NOTICE OF CARGO DAMAGE CONSTITUTES A
CARGO CLAIM.
22. On 27 June 2016, the Respondent notified to the Claimant that the cargo had been
severely damaged and found that Claimant was fully liable of that.
The clause 53 of the TCP states:
“Owners agree that liability for cargo claims, as between Owners and
Charterers, shall be apportioned as specified by the Inter-Club New York
Produce Exchange Agreement (...)”
23. The clause 6 of the ICA concerning the Time Bar establishes:
“Recovery under this Agreement by an Owner or Charterer shall be
deemed to be waived and absolutely barred unless written notification of
the Cargo Claim has been given to the other party to the charterparty
within 24 months of the date of delivery of the cargo or the date the cargo
should have been delivered, save that, where the Hamburg Rules or any
national legislation giving effect thereto are compulsorily applicable by
operation of law to the contract of carriage or to that part of the transit
that comprised carriage on the chartered vessel, the period shall be 36
months. Such notification shall if possible include details of the contract
of carriage, the nature of the claim and the amount claimed.”
24. The term if possible shall be interpreted as its ordinary meaning. In this sense, the
Cambridge dictionary define possible as “able to be done or achieved, or able to exist”.
10
25. In the case at bar, the Respondent was not able to provide the amount of the damages,
given that as it was showed by the preliminary survey report, the real extent of the
damages was unknown.
26. The purpose of the 24 months of the time bar at clause (6) ICA is for notifying owners’
or charterers’ intention to seek apportionment of the cargo claim.27 In the case at hand the
Respondent notified the intention for seeking said apportionment of the cargo claim even
before the delivery of the cargo.
27. In light of the London Arbitration 32/04, commencement of the proceeding regarding
indemnity arising from the ICA, is calculated from the date when the liability for the
cargo claim has been established.28
28. Therefore, the Respondent’s notification of the cargo shall be considered a cargo
claim in accordance with the clause 6 of the ICA
(i) IN THE ALTERNATIVE, RESPONDENT'S SUBMISSION WAS MADE
WITHIN THE SIX YEARS PROVIDED BY THE ICA.
29. The amount of the cargo claim was notified before the 15 March 2019.29
30. The time bar under English law for proceedings commencement in relation to their
claim is the same as that for breach of contract under the Limitation Act, which is six
years, as was held in the English Court decision in the Genius Star 1,30 and for that reason
in said decision was held that the charterers' claim was not time barred.31
31. Consequently, even if it is considered that the cargo claim was submitted until 15
March 2019, the Respondent has still more than 3 years for the submission of the cargo.
27 MCINNES David/ CHISHOLM Alex 28 The Inter- Club Agreement 29 Moot Scenario, 82 30 ATHERTON, Laura 31 NYPE Inter-Club Agreement
11
B. THE CLAIMANT IS RESPONSIBLE FOR CARGO DAMAGE
1. THE CLAIMANT IS RESPONSIBLE FOR CARGO DAMAGE ARISING
FROM CREW NEGLIGENCE
32. On 27 June 2016, the Respondent notified to the Claimant that the cargo was severely
damaged.32 It appears that the crew have pumped sea water into the cargo hold instead of
pumping it out. On 30 June 2016 a preliminary survey report was presented indicating
that cargo damage was caused when a crew member opened the wrong valves33. Later,
the Claimant, undertook its own investigations in that matter, which confirmed the cause
of the cargo was the one established in the preliminary survey report.34
33. In the same sense, the clause 64 of the TCP establishes that all ballasting/deballasting
shall be at the discretion of the Master having due regard to stability and seaworthiness
of the Vessel.35
34. Negligence can be defined as in Blyth v Birmingham Waterworks Co as “the omission
to do something which a reasonable man, guided upon those considerations which
ordinarily regulate the conduct of human affairs, would do, or doing something which a
prudent and reasonable man would not do”.36
35. The clause 26 of the TCP establishes that the Owner shall remain responsible for the
crew.
36. In the case Scheepvaartonderneming Flintermar v Sea Malta Co Ltd (The Flintermar)
2005, the Charterer had the responsibility for the cargo damage arising by loading of the
cargo by stevedores negligence because under its charterparty the Charterer was
32 Moot Scenario, 38 33 Moot Scenario, 46 34 Moot Scenario, 81 35 Moot Scenario, 12 36 BACHXEVANIS, Konstantinos, P.2.
12
responsible for them.37 In the Present case, the Arbitral Tribunal shall follow the same
line of reasoning by establishing that the Claimant is responsible for the cargo damage
arising from negligence of the crew.
2. THE CLAIMANT IS RESPONSIBLE FOR CARGO DAMAGE IN
ACCORDANCE WITH THE ICA
37. The clause 27 of the TCP sets out:
“Cargo claims as between the Owners and the Charterers shall be settled
in accordance with the Inter-Club NYPE Agreement 1996 (...)”
38. The present claim in within the definition of the ICA concerning cargo claims, since
they are defined as claims for loss, damage, shortage (including slackage, ullage or
pilferage), overcarriage of or delay to cargo including customs dues or fines in respect
of such loss, damage, shortage, overcarriage or delay.
i) THE CLAIMANT IS 100% LIABLE FOR THE CARGO DAMAGE.
39. The clause 53 of TCP lays down that liability for cargo claims, as between Owners
and Charterers, shall be apportioned as specified by the clause 8 of the ICA.38
Herein is established that (a) the claims arising out of unseaworthiness and/or error or
fault in navigation or management of the vessel shall be apportioned as 100% Owners.
40. Error of navigation could be defined as some mistake or negligence as to a matter of
seamanship which comprises the safety of the vessel and/ or its crew, resulting in cargo
loss or damage.
41. Error in management of the ship could be understand as some failure in the day to day
operation of the vessel, for example transferring bunkers and vessels fresh water to one
37 Scheepvaartonderneming Flintermar v Sea Malta Co Ltd (The Flintermar) 38 Moot Scenario, 10
13
bank the other with an error in valve sets causing damage to cargo(...) thereby causing
damage to cargo stowed therein (...)39
ii) ALTERNATIVELY, THE CLAIMANT IS 50% RESPONSIBLE FOR THE
CARGO CLAIM
42. According to clause 8 (a) of the ICA the Charterers are entitled to be indemnified by
Owners for the cargo claim,
“save the Owner proves that the unseaworthiness was caused by loading,
discharge or other handling of the cargo, in which case the claim shall be
apportioned under sub clause (b).
(b) claims in fact arising out of the loading, stowage, lashing, discharge,
storage or other handling of the cargo: 100% Charterers.
Unless the words “and responsibility” are added in clause 8 or there is a
similar amendments making the Master responsible for cargo handling in
which case: 50% Charterers 50 % Owners”.
43. In the case Agile Holdings Corp v Essar Shipping Ltd40, the Charterer brought a claim
against the Owner for cargo interests, the Owner argued that under the clause 8 (b) of the
ICA, he cannot be liable because under the clause 8 of the charterparty, the master was
responsible for cargo handling. The court held that as the word “and responsibility” was
not added into the TCP, the charterers were 100% liable.
39 TETLEY, William, 956
40 Agile Holdings Corporation v Essar Shipping Ltd
14
44. In the case at hand, the parties agreed to add the words “and responsibility” after
“under supervision” in clause 8 (a) of the TCP, making the Master responsible for cargo.41
PART II: THE VESSEL WAS OFF-HIRE
A. THE OFF-HIRE WAS CAUSED BY THE CLAIMANT’S LACK OF DUE
DILIGENCE.
1. THE MASTER’S DECISION TO SAIL FROM WEST COAST WAS
CONTRARY TO THE NAVIGATION OBLIGATION
45. On 18 April 2016 it was published in a widely known Newspaper that there were
several cases of Ebola at West Coast, and there was a serious concern of an outbreak of
said virus.42 Regardless that information, on 20 April 2016 the Master decided to sail
from West Coast to Wahanda.43
46. By doing a harmonic interpretation of the TCP, it is beyond cavil that the Master is
responsible for the navigation and for granting the seaworthiness of the vessel before, at
the beginning and during the voyage, and is the one that took the final decision to sail.44
47. In this sense, the clause (26) Navigation sets out:
Nothing herein stated is to be construed as a demise of the Vessel to the
Charterers. The Owners shall remain responsible for the navigation of the
Vessel, acts of pilots and tug boats, insurance, crew, and all other matters,
same as when trading for their own account.
41 Moot Scenario, 5 42 Moot Scenario, 22 43 Moot Scenario, 81 44P v Q, Q v R, R v S
15
48. On 8 May 2016 Contrary to Claimant assertion that the vessel could not be declared
off-hire by arguing that the Port State Control decision was beyond Claimant’s control.
The Port State Control declared the quarantine because of the reasonable believe that the
crew had Ebola. Since the Vessel sailed from an infected area, this situation was under
owners’ control,45 in accordance with the navigability obligation.
49. The master shall take his decisions to set and follow a course on the grounds that he
would thereby avoid the danger of bath weather and possible damage to the ship, in order
to comply with his navigability obligation. Said decisions might be made before or after
the Vessel had left the Port, or even while the Vessel was still on Port.46
50. Neither obligation displaced the responsibility of the Master in matters of
navigation.47
B. THE PORT STATE DETENTION IS ENVISAGED IN THE CLAUSE 17 OF
THE CHARTERPARTY.
51. On 11 May 2016 the Respondent informed to the Owners that the Port State Control
detained the vessel.48
52. The clause 17 of the TCP set out:
In the event of loss of time from (...) detention by the arrest of the Vessel,
or detention by Port State control or other competent authority for Vessel
deficiencies (...) or by any other similar cause preventing the full working
of the Vessel, the payment of hire and overtime, if any, shall cease for the
time thereby lost.
45 Metall Market 000 v Vitorio Shipping Company Limited, The Lehmann Timber 46 Steamship Mutual 47 Steamship Mutual 48 Moot Scenario, 24
16
53. The clause set out above, has two provisions of particular interest in the present case.
The first one is detention by Port State control or other competent authority for Vessel
deficiencies. In the present case, the Port State control detained the Vessel due to a health
issue of the crew.
54. And the second one is by any other similar cause preventing the full working of the
Vessel, which clearly is as a similar cause for detention by Port State Control for Vessel
deficiencies, due to the fact that the Port State Control detained the Vessel and that
circumstance prevented the full working of the vessel due to the impossibility of doing
anything, such as discharging, while this situation persisted, causing the unavoidable
delay of re-delivery.
(i) THE DETENTION WAS DERIVED FROM THE MASTER’S LACK OF
DUE DILIGENCE.
55. The clause 46 of the TCP establishes as following:
46. Safety and Health Regulations: Owners warrant that Vessel shall be in
possession of the necessary certificates to comply with all safety and health
regulations and all current requirements at all ports of call during the
currency of this Charter, without hindrance or delay.49
56. Wahanda Port50 is in Bao Kingdom, which laws closely resemble the laws of Hong
Kong.51
57. The International Health Regulations of the WHO are incorporated into Hong Kong
Law, in this sense, the regulations of the WHO shall be followed by the Claimant.
49 Moot Scenario, 9 50 Wahanda Port is the discharging port. 51 Moot Scenario, 81
17
58. In the art. 37 of the International Medical Guide for Ships of the World Health
Organization, it is established that the master of a ship, before arrival at its first port of
call in the territory of a State Party, shall ascertain the state of health on board.
59. The Master should have had special care in doing so due to its particular knowledge
of the outbreak of the Ebola virus in West Coast.
60. The failure of the Master to ascertain the state of health on board, had therefore the
detention of the Port State Control.
61. In the same sense, The Merchant Shipping (Seafarers) (Health and Safety: General
Duties) Regulation (Cap. 478 sub. leg. C), which is a Hong Kong regulation, establishes
as following:
12. Inspection and detention of ships which are not Hong Kong ships
(2) Where the Authority or a person referred to in subsection
(...)
(1) (b) where, in the opinion of the Authority or that person, as the case
may be, the ship does not comply with those requirements to such an extent
that conditions on board the ship are clearly hazardous to the health or
safety of persons on board the ship, the Authority or that person, as the
case may be, may detain the ship until measures are taken to rectify those
conditions, for which purpose the Authority or that person, as the case may
be, may take those measures.52
52 Emphasis added
18
62. The Wahanda Port Authority detained the Vessel because the Master did not follow
the applicable rules on the matter of health and by doing so the Claimant breached the
clause 46 of the TCP.
(ii) THE RESPONDENT IS ENTITLED TO THE RESTITUTION OF THE
OVERPAID HIRE.
63. On 07 May 2016, the Port State Control detained the vessel due to the reasonable fear
that the crew was carrying the Ebola virus.
64. Until 26 June 2016, the vessel obtained free pratique and was cleared to berth.53
65. The Respondent was obliged under the charterparty to pay hire for as long as the ship
was performing the charter service.54
66. In the case at hand, the vessel did not perform the charter service while it was detained
by the Port State Control, thus, the Vessel should have been considered off-hire from 07
May 2016 until 26 June 2016.Consequently, the Respondent payment for the overrun
period shall be reimbursed.
53 Moot Scenario, 81 54 COGHLIN, Terence, et al.
19
PRAYER FOR RELIEF
Respondent respectfully requests the Arbitral Tribunal to:
1. ORDER that:
a. Costs due by the Respondent regarding Underwater Hull Cleaning are no more
than USD33,000
b. Owners are not entitled to damages for the Next Fixture of the Vessel with
Champion Chartering Corp.
(i) Alternatively, that only the 2 years period of the Next Fixture shall
be contemplated for the calculation of damages reimbursing the
credit received under the Replacement Fixture.
c. The cargo Claim is admissible
d. 100% of the Cargo Claim is for Claimants’ account
(i) Alternatively, 50% of the Cargo Claim is for Claimants’ account.
e. The Vessel was off hire from 7/05/2016 until 26/06/2016 pursuant to Clause 17
of the TCP.
f. Claimant shall restitute the overpaid hire in amount USD 375,000.
2. AWARD interest on all sums in favor of the Respondent as the Tribunal considers
fit pursuant to section 49 of the Arbitration Act 1996.
Dated this 29th day of April 2019
Solicitors for the Respondent
Omega Chartering Ltd.