Unit-IV-3-PM

download Unit-IV-3-PM

of 17

Transcript of Unit-IV-3-PM

  • 8/9/2019 Unit-IV-3-PM

    1/17

    Operations Research

    MBA-024

  • 8/9/2019 Unit-IV-3-PM

    2/17

    PROJECT MANAGEMENT

    UNITIV

  • 8/9/2019 Unit-IV-3-PM

    3/17

    Basic Concepts

    Activity (arc): All projects are composed of

    operations or tasks called activities.

    Predecessor activity: Activity that must becompleted immediately prior to the start of

    another activity.

    Successor activity: Activity that cannot be

    started until one or more of the other

    activities are completed.

  • 8/9/2019 Unit-IV-3-PM

    4/17

    Basic Concepts

    Concurrent activities: activities which can be

    accomplished concurrently.

    Event (node): A specific accomplishment inthe project; takes place at a particular instant

    of time; does not consume any time or

    resource.

    Merge event: The event at which more than

    one activity end.

  • 8/9/2019 Unit-IV-3-PM

    5/17

    Basic Concepts

    Burst event: The event from where more than

    one activity start.

    Merge and Burst event: A combination of theabove two.

    Dummy activity: A fictitious activity used to

    fulfill some specific purpose in a network.

  • 8/9/2019 Unit-IV-3-PM

    6/17

    Rules for Drawing Network

    Diagram Each activity is represented by one and only

    one arrow.

    No two activities can be identified by thesame beginning and end events.

    Before an activity is undertaken, all preceding

    activities must be completed.

  • 8/9/2019 Unit-IV-3-PM

    7/17

    Rules for Drawing Network

    Diagram The arrows depicting various activities are

    indicative of the logical precedence only. The

    length and bearing of the arrows are of no

    significance.

    The flow of the diagram should be from left to

    right.

    Arrows should be kept straight.

  • 8/9/2019 Unit-IV-3-PM

    8/17

    Rules for Drawing Network

    Diagram Angles between the arrows should be as large

    as possible.

    Each activity must have a tail and a headevent.

    Dangling must be avoided.

    Fulkersons rule should be followed for

    numbering the nodes. The interdependence of activities must not be

    violated.

  • 8/9/2019 Unit-IV-3-PM

    9/17

    Common Errors

    Dangling.

    Looping.

    Redundancy.

  • 8/9/2019 Unit-IV-3-PM

    10/17

    Critical Path Method (CPM)

    Developed by M. R. Walker.

    Uses single time estimate, unlike PERT.

    The amount of time required for completingvarious activities is assumed to be known with

    certainty.

    Emphasizes the relationship between applying

    more men and/or other resources to shorten

    the duration of project; in the process, the

    cost increases.

  • 8/9/2019 Unit-IV-3-PM

    11/17

    Programme Evaluation and Review

    Technique (PERT) Developed by a (American) Navy sponsored

    research team in 1950s.

    Helpful in planning and controlling projects. Designed for scheduling complex projects that

    involve many inter-related tasks.

    Uses three time estimates normal,

    optimistic, pessimistic.

    Identifies likely trouble spots in advance.

  • 8/9/2019 Unit-IV-3-PM

    12/17

    Applications of PERT and CPM

    To plan, schedule, monitor and control projects

    such as:

    Construction of buildings, bridges, factories,highways, stadiums, irrigation projects, etc.

    Budget and auditing procedures.

    Missile development programmes.

    Installation of a complex new equipment such

    as computers or large machinery.

  • 8/9/2019 Unit-IV-3-PM

    13/17

    Applications of PERT and CPM

    To plan, schedule, monitor and control projects

    such as:

    Advertising programmes and for developmentand launching of new products.

    Planning of political campaigns.

    Strategic and tactical military planning.

    Research and development of new products.

  • 8/9/2019 Unit-IV-3-PM

    14/17

    Applications of PERT and CPM

    To plan, schedule, monitor and control projects

    such as:

    Finding the best traffic flow pattern in a largecity.

    Maintenance and overhauling complicated

    equipment in the chemical, power plants,

    steel and petroleum industries.

  • 8/9/2019 Unit-IV-3-PM

    15/17

    Applications of PERT and CPM

    To plan, schedule, monitor and control projects

    such as:

    Long-range planning and developing staffingplans.

    Organisation of big conferences, public works,

    etc.

    Shifting of manufacturing plant from one site

    to another.

  • 8/9/2019 Unit-IV-3-PM

    16/17

    Applications of PERT and CPM

    To plan, schedule, monitor and control projects

    such as:

    Preparation of bids and proposals for projectsof large size.

    Launching space programmes.

  • 8/9/2019 Unit-IV-3-PM

    17/17

    Crashing

    The project completion time can be reduced

    by reducing (crashing) the normal completion

    time of critical activities.

    The reduction in normal time of completion

    will increase the total budget of the project.

    The decision-maker will have to look at the

    time-cost trade-off for the various activities of

    the project.