Unit-IV-3-PM
-
Upload
pravah-shukla -
Category
Documents
-
view
215 -
download
0
Transcript of Unit-IV-3-PM
-
8/9/2019 Unit-IV-3-PM
1/17
Operations Research
MBA-024
-
8/9/2019 Unit-IV-3-PM
2/17
PROJECT MANAGEMENT
UNITIV
-
8/9/2019 Unit-IV-3-PM
3/17
Basic Concepts
Activity (arc): All projects are composed of
operations or tasks called activities.
Predecessor activity: Activity that must becompleted immediately prior to the start of
another activity.
Successor activity: Activity that cannot be
started until one or more of the other
activities are completed.
-
8/9/2019 Unit-IV-3-PM
4/17
Basic Concepts
Concurrent activities: activities which can be
accomplished concurrently.
Event (node): A specific accomplishment inthe project; takes place at a particular instant
of time; does not consume any time or
resource.
Merge event: The event at which more than
one activity end.
-
8/9/2019 Unit-IV-3-PM
5/17
Basic Concepts
Burst event: The event from where more than
one activity start.
Merge and Burst event: A combination of theabove two.
Dummy activity: A fictitious activity used to
fulfill some specific purpose in a network.
-
8/9/2019 Unit-IV-3-PM
6/17
Rules for Drawing Network
Diagram Each activity is represented by one and only
one arrow.
No two activities can be identified by thesame beginning and end events.
Before an activity is undertaken, all preceding
activities must be completed.
-
8/9/2019 Unit-IV-3-PM
7/17
Rules for Drawing Network
Diagram The arrows depicting various activities are
indicative of the logical precedence only. The
length and bearing of the arrows are of no
significance.
The flow of the diagram should be from left to
right.
Arrows should be kept straight.
-
8/9/2019 Unit-IV-3-PM
8/17
Rules for Drawing Network
Diagram Angles between the arrows should be as large
as possible.
Each activity must have a tail and a headevent.
Dangling must be avoided.
Fulkersons rule should be followed for
numbering the nodes. The interdependence of activities must not be
violated.
-
8/9/2019 Unit-IV-3-PM
9/17
Common Errors
Dangling.
Looping.
Redundancy.
-
8/9/2019 Unit-IV-3-PM
10/17
Critical Path Method (CPM)
Developed by M. R. Walker.
Uses single time estimate, unlike PERT.
The amount of time required for completingvarious activities is assumed to be known with
certainty.
Emphasizes the relationship between applying
more men and/or other resources to shorten
the duration of project; in the process, the
cost increases.
-
8/9/2019 Unit-IV-3-PM
11/17
Programme Evaluation and Review
Technique (PERT) Developed by a (American) Navy sponsored
research team in 1950s.
Helpful in planning and controlling projects. Designed for scheduling complex projects that
involve many inter-related tasks.
Uses three time estimates normal,
optimistic, pessimistic.
Identifies likely trouble spots in advance.
-
8/9/2019 Unit-IV-3-PM
12/17
Applications of PERT and CPM
To plan, schedule, monitor and control projects
such as:
Construction of buildings, bridges, factories,highways, stadiums, irrigation projects, etc.
Budget and auditing procedures.
Missile development programmes.
Installation of a complex new equipment such
as computers or large machinery.
-
8/9/2019 Unit-IV-3-PM
13/17
Applications of PERT and CPM
To plan, schedule, monitor and control projects
such as:
Advertising programmes and for developmentand launching of new products.
Planning of political campaigns.
Strategic and tactical military planning.
Research and development of new products.
-
8/9/2019 Unit-IV-3-PM
14/17
Applications of PERT and CPM
To plan, schedule, monitor and control projects
such as:
Finding the best traffic flow pattern in a largecity.
Maintenance and overhauling complicated
equipment in the chemical, power plants,
steel and petroleum industries.
-
8/9/2019 Unit-IV-3-PM
15/17
Applications of PERT and CPM
To plan, schedule, monitor and control projects
such as:
Long-range planning and developing staffingplans.
Organisation of big conferences, public works,
etc.
Shifting of manufacturing plant from one site
to another.
-
8/9/2019 Unit-IV-3-PM
16/17
Applications of PERT and CPM
To plan, schedule, monitor and control projects
such as:
Preparation of bids and proposals for projectsof large size.
Launching space programmes.
-
8/9/2019 Unit-IV-3-PM
17/17
Crashing
The project completion time can be reduced
by reducing (crashing) the normal completion
time of critical activities.
The reduction in normal time of completion
will increase the total budget of the project.
The decision-maker will have to look at the
time-cost trade-off for the various activities of
the project.