U8-1 UNIT 8 Project Valuation Should we build this plant?

description

UNIT 8 Project Valuation. Should we build this plant?. What is capital budgeting?. Analysis of potential additions to fixed assets. Long-term decisions; involve large expenditures. Very important to firm’s future. Steps to capital budgeting. Estimate CFs (inflows & outflows). - PowerPoint PPT Presentation

Transcript of UNIT 8 Project Valuation

Page 1: UNIT 8 Project Valuation

U8-1

UNIT 8Project Valuation

Should we build this

plant?

Page 2: UNIT 8 Project Valuation

U8-2

What is capital budgeting? Analysis of potential additions to

fixed assets. Long-term decisions; involve

large expenditures. Very important to firm’s future.

Page 3: UNIT 8 Project Valuation

U8-3

Steps to capital budgeting

1. Estimate CFs (inflows & outflows).2. Assess riskiness of CFs.3. Determine the appropriate cost of

capital.4. Find NPV and/or IRR.5. Accept if NPV > 0 and/or IRR > WACC.

Page 4: UNIT 8 Project Valuation

U8-4

What is the difference between independent and mutually exclusive projects?

Independent projects – if the cash flows of one are unaffected by the acceptance of the other.

Mutually exclusive projects – if the cash flows of one can be adversely impacted by the acceptance of the other.

Page 5: UNIT 8 Project Valuation

U8-5

What is the difference between normal and nonnormal cash flow streams?

Normal cash flow stream – Cost (negative CF) followed by a series of positive cash inflows. One change of signs.

Nonnormal cash flow stream – Two or more changes of signs. Most common: Cost (negative CF), then string of positive CFs, then cost to close project. Nuclear power plant, strip mine, etc.

Page 6: UNIT 8 Project Valuation

U8-6

Net Present Value (NPV) Sum of the PVs of all cash inflows and

outflows of a project:

N

0tt

t

)r 1 (CF

NPV

Page 7: UNIT 8 Project Valuation

U8-7

What is Project L’s NPV?

Year CFt PV of CFt

0 -100 -$100 1 10 9.09 2 60 49.59 3 80 60.11

NPVL = $18.79

NPVS = $19.98

Page 8: UNIT 8 Project Valuation

U8-8

Excel NPV Reminder

You may use Excel’s NPV function to calculate NPV but be careful!

Use Excel’s NPV function to find NPV of CF1-n and then subtract CF0 from this result.

Page 9: UNIT 8 Project Valuation

U8-9

Rationale for the NPV methodNPV = PV of inflows – Cost

= Net gain in wealth If projects are independent, accept if

the project NPV > 0. If projects are mutually exclusive,

accept projects with the highest positive NPV, those that add the most value.

In this example, accept S if mutually exclusive (NPVs > NPVL), and accept both if independent.

Page 10: UNIT 8 Project Valuation

U8-10

Internal Rate of Return (IRR) IRR is the discount rate that forces PV of

inflows equal to cost, and the NPV = 0:

Use Excel’s IRR function.

N

0tt

t

) IRR 1 (CF

0

Page 11: UNIT 8 Project Valuation

U8-11

How is a project’s IRR similar to a bond’s YTM? They are the same thing. Think of a bond as a project. The

YTM on the bond would be the IRR of the “bond” project.

EXAMPLE: Suppose a 10-year bond with a 9% annual coupon and $1,000 par value sells for $1,134.20. Solve for IRR = YTM = 7.08%, the

annual return for this project/bond.

Page 12: UNIT 8 Project Valuation

U8-12

Rationale for the IRR method If IRR > WACC, the project’s return

exceeds its costs and there is some return left over to boost stockholders’ returns.

If IRR > WACC, accept project.If IRR < WACC, reject project.

If projects are independent, accept both projects, as both IRR > WACC = 10%.

If projects are mutually exclusive, accept S, because IRRs > IRRL.

Page 13: UNIT 8 Project Valuation

U8-13

NPV Profiles A graphical representation of project

NPVs at various different costs of capital.

WACC NPVL NPVS

0 $50 $40 5 33 2910 19 2015 7 1220 (4) 5

Page 14: UNIT 8 Project Valuation

U8-14

Drawing NPV profiles

-10

0

10

20

30

40

50

60

5 10 15 20 23.6

NPV ($)

Discount Rate (%)

IRRL = 18.1%

IRRS = 23.6%

Crossover Point = 8.7%

SL

.

.

...

.

..

.

. .

Page 15: UNIT 8 Project Valuation

U8-15

Comparing the NPV and IRR methods

If projects are independent, the two methods always lead to the same accept/reject decisions.

If projects are mutually exclusive … If WACC > crossover rate, the

methods lead to the same decision and there is no conflict.

If WACC < crossover rate, the methods lead to different accept/reject decisions.

Page 16: UNIT 8 Project Valuation

U8-16

Reasons why NPV profiles cross

Size (scale) differences – the smaller project frees up funds at t = 0 for investment. The higher the opportunity cost, the more valuable these funds, so a high WACC favors small projects.

Timing differences – the project with faster payback provides more CF in early years for reinvestment. If WACC is high, early CF especially good, NPVS > NPVL.

Page 17: UNIT 8 Project Valuation

U8-17

Reinvestment rate assumptions NPV method assumes CFs are

reinvested at the WACC. IRR method assumes CFs are reinvested

at IRR. Assuming CFs are reinvested at the

opportunity cost of capital is more realistic, so NPV method is the best. NPV method should be used to choose between mutually exclusive projects.

Perhaps a hybrid of the IRR that assumes cost of capital reinvestment is needed.

Page 18: UNIT 8 Project Valuation

U8-18

What is the payback period?

The number of years required to recover a project’s cost, or “How long does it take to get our money back?”

Calculated by adding project’s cash inflows to its cost until the cumulative cash flow for the project turns positive.

Page 19: UNIT 8 Project Valuation

U8-19

Calculating payback

PaybackL = 2 + / = 2.375 years

CFt -100 10 60Cumulative -100 -90 50

0 1 2 3

= 30 80

80

-30

Project L’s Payback Calculation

PaybackL = 2.375 years

PaybackS = 1.600 years

Page 20: UNIT 8 Project Valuation

U8-20

Strengths and weaknesses of payback

Strengths Provides an indication of a project’s

risk and liquidity. Easy to calculate and understand.

Weaknesses Ignores the time value of money. Ignores CFs occurring after the

payback period.

Page 21: UNIT 8 Project Valuation

U8-21

Proposed Project Total depreciable cost

Equipment: $200,000 Shipping: $10,000 Installation: $30,000

Changes in working capital Inventories will rise by $25,000 Accounts payable will rise by $5,000

Effect on operations New sales: 100,000 units/year @

$2/unit Variable cost: 60% of sales

Page 22: UNIT 8 Project Valuation

U8-22

Proposed Project

Life of the project Economic life: 4 years Depreciable life: MACRS 3-year class Salvage value: $25,000

Tax rate: 40% WACC: 10%

Page 23: UNIT 8 Project Valuation

U8-23

Determining project value Estimate relevant cash flows

Calculating annual operating cash flows. Identifying changes in working capital. Calculating terminal cash flows.

0 1 2 3 4

Initial OCF1 OCF2 OCF3 OCF4 Costs +

Terminal CFs

NCF0 NCF1 NCF2 NCF3 NCF4

Page 24: UNIT 8 Project Valuation

U8-24

Initial year net cash flow Find Δ NOWC.

⇧ in inventories of $25,000 Funded partly by an ⇧ in A/P of $5,000 Δ NOWC = $25,000 - $5,000 = $20,000

Combine Δ NOWC with initial costs.

Equipment -$200,000 Installation -40,000 Δ NOWC -20,000

Net CF0 -$260,000

Page 25: UNIT 8 Project Valuation

U8-25

Determining annual depreciation expense

Year Rate x Basis Depr 1 0.33 x $240 $ 79 2 0.45 x 240 108 3 0.15 x 240 36 4 0.07 x 240 17

1.00 $240

Due to the MACRS ½-year convention, a 3-year asset is depreciated over 4 years.

Page 26: UNIT 8 Project Valuation

U8-26

Annual operating cash flows

1 2 3 4

Revenues 200.0 200.0 200.0 200.0

- Op Costs -120.0

-120.0

-120.0

-120.0

- Depr’n Expense -79.2 -108.0

-36.0 -16.8

Operating Income (BT)

0.8 -28.0 44.0 63.2

- Tax (40%) 0.3 -11.2 17.6 25.3

Operating Income (AT)

0.5 -16.8 26.4 37.9

+ Depr’n Expense 79.2 108.0 36.0 16.8

Operating CF 79.7 91.2 62.4 54.7(Thousands of dollars)

Page 27: UNIT 8 Project Valuation

U8-27

Terminal net cash flow

Recovery of NOWC $20,000Salvage value 25,000Tax on SV (40%) -10,000Terminal CF $35,000

Q. How is NOWC recovered?Q. Is there always a tax on SV?Q. Is the tax on SV ever a positive cash

flow?

Page 28: UNIT 8 Project Valuation

U8-28

Should financing effects be included in cash flows? No, dividends and interest

expense should not be included in the analysis.

Financing effects have already been taken into account by discounting cash flows at the WACC of 10%.

Deducting interest expense and dividends would be “double counting” financing costs.

Page 29: UNIT 8 Project Valuation

U8-29

Should a $50,000 improvement cost from the previous year be included in the analysis?

No, the building improvement cost is a sunk cost and should not be considered.

This analysis should only include incremental investment.

Page 30: UNIT 8 Project Valuation

U8-30

If the facility could be leased out for $25,000 per year, would this affect the analysis?

Yes, by accepting the project, the firm foregoes a possible annual cash flow of $25,000, which is an opportunity cost to be charged to the project.

The relevant cash flow is the annual after-tax opportunity cost. A-T opportunity cost = $25,000 (1 – T)

= $25,000(0.6) = $15,000

Page 31: UNIT 8 Project Valuation

U8-31

If the new product line decreases the sales of the firm’s other lines, would this affect the analysis?

Yes. The effect on other projects’ CFs is an “externality.”

Net CF loss per year on other lines would be a cost to this project.

Externalities can be positive (in the case of complements) or negative (substitutes).

Page 32: UNIT 8 Project Valuation

U8-32

Proposed project’s cash flow time line0 1 2 3 4

-260 79.7 91.2 62.4 54.7 Terminal CF → 35.0

89.7

Enter CFs into calculator CFLO register and enter I/YR = 10%. NPV = -$4.03 million IRR = 9.3% Payback = 3.3 years

Page 33: UNIT 8 Project Valuation

U8-33

What is real option analysis? Real options exist when managers can

influence the size and riskiness of a project’s cash flows by taking different actions during the project’s life.

Real option analysis incorporates typical NPV budgeting analysis with an analysis for opportunities resulting from managers’ decisions.

Page 34: UNIT 8 Project Valuation

U8-34

What are some examples of real options?

Investment timing options Abandonment/shutdown

options Growth/expansion options Flexibility options