Unit 3 RIGID AND FLEXIBLE PAVEMENTS
-
Upload
anonymous-sedun6pw -
Category
Documents
-
view
303 -
download
6
Transcript of Unit 3 RIGID AND FLEXIBLE PAVEMENTS
-
8/12/2019 Unit 3 RIGID AND FLEXIBLE PAVEMENTS
1/33
Basically, all hard surfaced pavement types can be categorized
into two groups, flexible and rigid. Flexible pavements arethose which are surfaced with bituminous (or asphalt)
materials. Rigid pavements are composed of a PCC surface
course. Such pavements are substantially "stiffer" than flexible
pavements due to the high modulus of elasticity of the PCC
material. Further, these pavements can have reinforcing steel,which is generally used to reduce or eliminate joints.
INTRODUCTION
-
8/12/2019 Unit 3 RIGID AND FLEXIBLE PAVEMENTS
2/33
Flexible Pavement Basics
Flexible pavements are so named
because the total pavement structure
deflects, or flexes, under loading. A
flexible pavement structure istypically composed of several layers
of material. Each layer receives the
loads from the above layer, spreads
them out, then passes on these loads
to the next layer below.
-
8/12/2019 Unit 3 RIGID AND FLEXIBLE PAVEMENTS
3/33
The typical flexible pavement structure consist of:Surface course. This is the top layer and the layer that
comes in contact with traffic.
Base course. This is the layer directly below the HMA
layer and generally consists of aggregate (either stabilizedor un stabilized).
Sub base course. This is the layer (or layers) under the
base layer. A sub base is not always needed.
-
8/12/2019 Unit 3 RIGID AND FLEXIBLE PAVEMENTS
4/33
Typical layers of a conventional flexible pavement includes seal
coat, surface course, tack coat, binder course, prime coat, base
course, sub-base course, compacted sub-grade, and natural sub-grade .
Seal Coat: Seal coat is a thin surface treatment used to water-proof
the surface and to provide skid resistance.
Tack Coat: Tack coat is a very light application of asphalt, usuallyasphalt emulsion diluted with water. It provides proper bonding
between two layer of binder course and must be thin, uniformly
cover the entire surface, and set very fast.
Prime Coat: Prime coat is an application of low viscous cutback
bitumen to an absorbent surface like granular bases on which binder
layer is placed. It provides bonding between two layers. Unlike tack
coat, prime coat penetrates into the layer below, plugs the voids, and
forms a water tight surface.
Typical layers of a flexible pavement
-
8/12/2019 Unit 3 RIGID AND FLEXIBLE PAVEMENTS
5/33
-
8/12/2019 Unit 3 RIGID AND FLEXIBLE PAVEMENTS
6/33
Surface course
Surface course is the layer directly in contact with traffic
loads and generally contains superior quality materials. Theyare usually constructed with dense graded asphalt concrete
(AC). The functions and requirements of this layer are:
It provides characteristics such as friction, smoothness,
drainage, etc. Also it will prevent the entrance of excessivequantities of surface water into the underlying base, sub-base
and sub-grade,
It must be tough to resist the distortion under traffic and
provide a smooth and skid- resistant riding surface,
It must be water proof to protect the entire base and sub-
grade from the weakening effect of water.
-
8/12/2019 Unit 3 RIGID AND FLEXIBLE PAVEMENTS
7/33
Binder course
This layer provides the bulk of the asphalt concrete structure. It's chief
purpose is to distribute load to the base course The binder course
generally consists of aggregates having less asphalt and doesn't requirequality as high as the surface course, so replacing a part of the surface
course by the binder course results in more economical design.
Base course
The base course is the layer of material immediately beneath the
surface of binder course and it provides additional load distribution and
contributes to the sub-surface drainage It may be composed of crushed
stone, crushed slag, and other untreated or stabilized materials.
-
8/12/2019 Unit 3 RIGID AND FLEXIBLE PAVEMENTS
8/33
Sub-Base course
The sub-base course is the layer of material beneath the base course
and the primary functions are to provide structural support, improvedrainage, and reduce the intrusion of fines from the sub-grade in the
pavement structure If the base course is open graded, then the sub-
base course with more fines can serve as a filler between sub-grade
and the base course A sub-base course is not always needed or used.For example, a pavement constructed over a high quality, stiff sub-
grade may not need the additional features offered by a sub-base
course. In such situations, sub-base course may not be provided.
Sub-grade
The top soil or sub-grade is a layer of natural soil prepared toreceive the stresses from the layers above. It is essential that at no
time soil sub-grade is overstressed. It should be compacted to the
desirable density, near the optimum moisture content.
-
8/12/2019 Unit 3 RIGID AND FLEXIBLE PAVEMENTS
9/33
There are many factors that affect pavement design which can be
classified into four categories as traffic and loading, structuralmodels, material characterization, environment.
Traffic and loading
Traffic is the most important factor in the pavement design. The
key factors include contact pressure, wheel load, axle
configuration, moving loads, load, and load repetitions.
Contact pressure:
The tyre pressure is an important factor, as it determine the contact
area and the contact pressure between the wheel and the pavement
surface. Even though the shape of the contact area is elliptical, forsake of simplicity in analysis, a circular area is often considered..
FACTORS AFFECTING PAVEMENT DESIGN
-
8/12/2019 Unit 3 RIGID AND FLEXIBLE PAVEMENTS
10/33
Wheel load:
The next important factor is the wheel load which determines the
depth of the pavement required to ensure that the sub grade soil isnot failed. Wheel configuration affect the stress distribution and
deflection within a pavement. Many commercial vehicles have
dual rear wheels which ensure that the contact pressure is within
the limits. The normal practice is to convert dual wheel into anequivalent single wheel load so that the analysis is made simpler.
Axle configuration:
The load carrying capacity of the commercial vehicle is further
enhanced by the introduction of multiple axles.
Moving loads:The damage to the pavement is much higher if the vehicle is
moving at creep speed. Many studies show that when the speed is
increased from 2 km/hr to 24 km/hr, the stresses and deflection
reduced by 40 per cent.
-
8/12/2019 Unit 3 RIGID AND FLEXIBLE PAVEMENTS
11/33
Repetition of Loads:
The influence of traffic on pavement not only depend on themagnitude of the wheel load, but also on the frequency of the load
applications. Each load application causes some deformation and
the total deformation is the summation of all these. Although the
pavement deformation due to single axle load is very small, thecumulative effect of number of load repetition is significant.
Therefore, modern design is based on total number of standard
axle load (usually 80 kN single axle).
-
8/12/2019 Unit 3 RIGID AND FLEXIBLE PAVEMENTS
12/33
Structural models
The structural models are various analysis approaches to determine
the pavement responses (stresses, strains, and deflections) at various
locations in a pavement due to the application of wheel load. Themost common structural models are layered elastic model and visco-
elastic models.
Layered elastic model:
A layered elastic model can compute stresses, strains, and
deflections at any point in a pavement structure resulting from the
application of a surface load. Layered elastic models assume that
each pavement structural layer is homogeneous, isotropic, and
linearly elastic. In other words, the material properties are same at
every point in a given layer and the layer will rebound to its originalform once the load is removed. The layered elastic approach works
with relatively simple mathematical models that relates stress,
strain, and deformation with wheel loading and material properties
like modulus of elasticity and poissons ratio.
-
8/12/2019 Unit 3 RIGID AND FLEXIBLE PAVEMENTS
13/33
Material characterization
The following material properties are important for bothflexible and rigid pavements.
When pavements are considered as linear elastic, the elastic
moduli and poisson ratio of subgrade and each component
layer must be specified.If the elastic modulus of a material varies with the time of
loading, then the resilient modulus, which is elastic modulus
under repeated loads, must be selected in accordance with a
load duration corresponding to the vehicle speed.
When a material is considered non-linear elastic, theconstitutive equation relating the resilient modulus to the state
of the stress must be provided.
-
8/12/2019 Unit 3 RIGID AND FLEXIBLE PAVEMENTS
14/33
-
8/12/2019 Unit 3 RIGID AND FLEXIBLE PAVEMENTS
15/33
Basic Structural Elements
A typical flexible pavement structure consists of the surface
course and the underlying base and sub base courses. Each of
these layers contributes to structural support anddrainage. The surface course is the stiffest and contributes
the most to pavement strength. The underlying layers are less
stiff but are still important to pavement strength as well as
drainage and frost protection. A typical structural design
results in a series of layers that gradually decrease in material
quality with depth.
-
8/12/2019 Unit 3 RIGID AND FLEXIBLE PAVEMENTS
16/33
The surface course is the layer in contact with traffic loadsand normally contains the highest quality materials. It
provides characteristics such as friction, smoothness, noise
control, rut and shoving resistance and drainage. In
addition, it serves to prevent the entrance of excessivequantities of surface water into the underlying base, sub
base and sub grade.
Wearing Course. This is the layer in direct contact with
traffic loads. It is meant to take the brunt of traffic wear
and can be removed and replaced as it becomes worn.
Intermediate/Binder Course. It's chief purpose is to
distribute load.
Surface Course
-
8/12/2019 Unit 3 RIGID AND FLEXIBLE PAVEMENTS
17/33
The base course is immediately beneath the surface course. Itprovides additional load distribution and contributes to drainage
and frost resistance. Base courses are usually constructed out of:
Aggregate. Base courses are most typically constructed from
durable aggregates that will not be damaged by moisture or frost
action. Aggregates can be either stabilized or un stabilized.
Base Course
-
8/12/2019 Unit 3 RIGID AND FLEXIBLE PAVEMENTS
18/33
The sub base course is between the base course and the sub
grade. It functions primarily as structural support but it can also:Minimize the intrusion of fines from the sub grade into the
pavement structure.
Improve drainage.
Minimize frost action damage.Provide a working platform for construction.
The sub base generally consists of lower quality materials than the
base course but better than the sub grade soils. A sub base course
is not always needed or used. For example, a pavement
constructed over a high quality, stiff sub grade may not need the
additional features offered by a sub base course so it may be
omitted from design. However, a pavement constructed over a
low quality soil such as a swelling clay may require the additional
load distribution characteristic that a sub base course can offer.
Sub base Course
-
8/12/2019 Unit 3 RIGID AND FLEXIBLE PAVEMENTS
19/33
Design criteria
The flexible pavements has been modeled as a three layer
structure and stresses and strains at critical locations have
been computed using the linear elastic model. To giveproper consideration to the aspects of performance, the
following three types of pavement distress resulting from
repeated (cyclic) application of traffic loads are
considered:
vertical compressive strain at the top of the sub-grade
which can cause sub-grade deformation resulting in
permanent deformation at the pavement surface.
horizontal tensile strain or stress at the bottom of the
bituminous layer which can cause fracture of thebituminous layer. pavement deformation within the
bituminous layer.
-
8/12/2019 Unit 3 RIGID AND FLEXIBLE PAVEMENTS
20/33
Design procedure
Based on the performance of existing designs and using analytical
approach, simple design charts and a catalogue of pavement
designs are added in the code. The pavement designs are given for
subgrade CBR values ranging from 2% to 10% and design traffic
ranging from 1 msa to 150 msa for an average annual pavement
temperature of 35 C. The later thicknesses obtained from the
analysis have been slightly modified to adapt the designs to stageconstruction. Using the following simple input parameters,
appropriate designs could be chosen for the given traffic and soil
strength:
Design traffic in terms of cumulative number of standard axles;and
CBR value of sub grade
-
8/12/2019 Unit 3 RIGID AND FLEXIBLE PAVEMENTS
21/33
To carry maximum load with in the specified limit and to carry greater load, dual
wheel, or dual tandem assembly is often used. Equivalent single wheel load (ESWL)
is the single wheel load having the same contact pressure, which produces same value
of maximum stress, deflection, tensile stress or contact pressure at the desired depth.
The procedure of finding the ESWL for equal stress criteria is provided below. This is
a semi-rational method, known as Boyd and Foster method, based on the following
assumptions:
equalancy concept is based on equal stress; contact area is circular;influence angle is 45o; and
soil medium is elastic, homogeneous, and isotropic half space.
The ESWL is given by:
where P is the wheel load, S is the center to center distance between the two
wheels, d is the clear distance between two wheels, and z is the desired depth.
ESWL
-
8/12/2019 Unit 3 RIGID AND FLEXIBLE PAVEMENTS
22/33
Rigid Pavement Basics
Rigid pavements are so named because the pavement structure
deflects very little under loading due to the high modulus of
elasticity of their surface course. A rigid pavement structure istypically composed of a PCC surface course built on top of either (1)
the sub grade or (2) an underlying base course. Because of its
relative rigidity, the pavement structure distributes loads over a wide
area with only one, or at most two, structural layers
The typical rigid pavement structure consist of:
Surface course. This is the top layer, which consists of the PCC
slab.
Base course. This is the layer directly below the PCC layer and
generally consists of aggregate or stabilized sub grade.
Sub base course. This is the layer (or layers) under the base
layer. A sub base is not always needed and therefore may often be
omitted.
-
8/12/2019 Unit 3 RIGID AND FLEXIBLE PAVEMENTS
23/33
Basic Structural Elements
A typical rigid pavement structure consists of the surface
course and the underlying base and sub base courses (ifused). The surface course (made of PCC) is the stiffest and
provides the majority of strength. The underlying layers are
orders of magnitude less stiff but still make important
contributions to pavement strength as well as drainage andfrost protection.
-
8/12/2019 Unit 3 RIGID AND FLEXIBLE PAVEMENTS
24/33
Surface Course
The surface course is the layer in contact with traffic loads and is
made of PCC. It provides characteristics such as friction,smoothness, noise control and drainage. In addition, it serves as
a waterproofing layer to the underlying base, sub base and sub
grade. The surface course can vary in thickness but is usually
between 150 mm (for light loading) and 300 mm (for heavy loads
and high traffic).
PCC Surface Rigid Pavement Slab
(Surface Course) Thickness
B C
-
8/12/2019 Unit 3 RIGID AND FLEXIBLE PAVEMENTS
25/33
Base Course
The base course is immediately beneath the surface course. It provides (1)
additional load distribution, (2) contributes to drainage and frost resistance,
(3) uniform support to the pavement and (4) a stable platform forconstruction equipment. Bases also help prevent sub grade soil movement
due to slab pumping. Base courses are usually constructed out of:
Aggregate base. A simple base course of crushed aggregate has been a
common option since the early 1900s and is still appropriate in many
situations today.Stabilized aggregate or soil. Stabilizing agents are used to bind Cement
treated bases (CTBs) can be built to as much as 20 - 25 percent of the
surface course strength.
Lean concrete. Contains less Portland cement paste than a typical PCC
and is stronger than a stabilized aggregate. A lean concrete base functionsmuch like a regular PCC surface course and therefore, it requires
construction joints and will crack over time. These joints and cracks can
potentially cause reflection cracking in the surface course if they are not
carefully matched.
-
8/12/2019 Unit 3 RIGID AND FLEXIBLE PAVEMENTS
26/33
Sub base Course
The sub base course is the portion of the pavement structure
between the base course and the sub grade. It functionsprimarily as structural support but it can also:
Minimize the intrusion of fines from the sub grade into the
pavement structure.
Improve drainage.
Minimize frost action damage.
Provide a working platform for construction.
The sub base generally consists of lower quality materials
than the base course but better than the sub grade
soils. Appropriate materials are aggregate and high qualitystructural fill. A sub base course is not always needed or
used.
-
8/12/2019 Unit 3 RIGID AND FLEXIBLE PAVEMENTS
27/33
Joints
Joints are purposefully placed discontinuities in a rigid pavement
surface course. The most common types of pavement joints,defined by their function, are: contraction, expansion and
construction.
Contraction Joints
A contraction joint is a sawed, formed, or tooled groove in a
concrete slab that creates a weakened vertical plane. It regulates
the location of the cracking caused by dimensional changes in the
slab. Unregulated cracks can grow and result in an unacceptablyrough surface as well as water infiltration into the base, sub base
and sub grade, which can enable other types of pavement
distress. Contraction joints are the most common type of joint in
concrete pavements.
-
8/12/2019 Unit 3 RIGID AND FLEXIBLE PAVEMENTS
28/33
Contraction joints are chiefly defined by their spacing and their
method of load transfer. They are generally between 1/4 - 1/3
the depth of the slab and typically spaced every 3.1 - 15 m withthinner slabs having shorter spacing. These patterns typically
use a repeating sequence of joint spacing (for example: 2.7 m
then 3.0 m then 4.3 m then 4.0 m . Transverse contraction joints
can be cut at right angles to the direction of traffic flow.
Rigid Pavement Showing
Contraction Joints
-
8/12/2019 Unit 3 RIGID AND FLEXIBLE PAVEMENTS
29/33
Expansion Joints
An expansion joint is placed at a specific location to
allow the pavement to expand without damaging
adjacent structures or the pavement itself. However,
expansion joint are not typically used today because
their progressive closure tends to cause contractionjoints to progressively open. Progressive or even
large seasonal contraction joint openings cause a loss
of load transferparticularly so for joints without
dowel bars.
-
8/12/2019 Unit 3 RIGID AND FLEXIBLE PAVEMENTS
30/33
Construction Joints
A construction joint is a joint between slabs that results whenconcrete is placed at different times. This type of joint can be
further broken down into transverse and longitudinal
construction joints . Longitudinal construction joints also allow
slab warping without appreciable separation or cracking of the
slabs.
Longitudinal and Transverse Construction Joints
-
8/12/2019 Unit 3 RIGID AND FLEXIBLE PAVEMENTS
31/33
Dowel Bars
Dowel bars are short steel bars that provide a mechanical
connection between slabs without restricting horizontal jointmovement. They increase load transfer efficiency by allowing
the leave slab to assume some of the load before the load is
actually over it. Dowel bars are typically 32 to 38 mm in
diameter, 460 mm long and spaced 305 mm apart. In order toprevent corrosion, dowel bars are either coated with stainless
steel or epoxy. Dowel bars are usually inserted at mid-slab
depth and coated with a bond-breaking substance to prevent
bonding to the PCC. Thus, the dowels help transfer load but
allow adjacent slabs to expand and contract independent ofone another.
-
8/12/2019 Unit 3 RIGID AND FLEXIBLE PAVEMENTS
32/33
Dowel Bars in Place at a
Construction Joint- the GreenColor is from the Epoxy
Coating
-
8/12/2019 Unit 3 RIGID AND FLEXIBLE PAVEMENTS
33/33