PLANNING OF FLOATING PRODUCTION STORAGE OFFLOADING (FPSO) FABRICATION USING
DEPENDENCY STRUCTURE MATRIX (DSM) MODEL
Presented by :
MUHAMAD FIRDAUS BIN ISMAIL
Supervised by :
Eng. Dr. JASWAR KOTO
Faculty of Mechanical EngineeringSKMO
CONTENTS
CHAPTER
CONTENTS
1 INTRODUCTION •Problem Statement •Research Objective•Research Scope•Research Significant
2 LITERATURE REVIEW
3 RESEARCH METHODOLOGY
INTRODUCTION
• Depleting oil reserves along with increasing energy consumption significantly increase the need for exploration and production in deepwater and ultra-deepwater discoveries.
• Need of great planning to complete build of FPSO along with reduction of time completion.
• Challenging in planning FPSO fabrication due to the complexity of the processes and systems.
• These project management tools such as PERT and CPM are not capable of planning the project that involves looping activities.
• Therefore, applying Dependency Structure Matrix (DSM) is the solution to address complexity and interdependency of fabrication process.
3
• These project management tools such as PERT and CPM are not capable of planning the project that involves looping activities.
• Therefore, applying Dependency Structure Matrix (DSM) is the solution to address complexity and interdependency of fabrication process.
4
LITERATURE REVIEW
FPSO vessel is designed to receive oil or gas produced from nearby
platforms or subsea template, process it, and store it until oil or gas can be
offloaded onto a shuttle tanker or transported through a pipeline said
William L.Leffler.
7
According to Professor Don Steward (1981), DSM method used to build an effective engineering plan, showing where estimates are to be used, how to handle design iterations and review, and how information flows during the design work [2].
DSMs have been developed for planning and managing projects in the building construction, photographic, semiconductor, automotive, aerospace, telecom, and electronics industries said Yassine et al., (2005) [8].
Researcher has determined DSM is powerful management tool to plan sequence activity by feedback present and can manage the exchange
8
DSM
DSM is known as design structure matrix, dependency source matrix, and dependency structure method which is a basic matrix tool approach as management tools.
Easy to identify the sequences of the process
9
Benefit of DSM
contribution of DSM in various fields such as:
Aerospace (Grose, 1994; Browning and Eppinger, 2002) Proposed DSM in design of an aircraft, assigning values of sizing to wing, body
and control surfaces is regarded as a design activity.
Construction (Austin et al., 2005) Application DSM to increase the design efficiency of a repetitive high-rise building
because of the repetition of construction and the cycle-time for the completion.
10
Flow chart
DSM THEORY
What is Dependency Structure Matrix (DSM) all about? :
DSM is known as design structure matrix, dependency source matrix, and dependency structure method.
A DSM also can be define as square matrix that have equal number of rows and columns (m x n).
12
DEPENDENCIES OF DSM
Type of dependencies of DSM:
13
Diagram Representation
Relationship Dependent ( Sequential) Independent (Parallel) Interdependent (Coupled)
Types of Dependencies
Activity 1 Activity 2 Activity 1
Activity 2
Activity 3
Activity 1
Activity 3
Activity 2
Activity 4
A BA XB
A BA XB X
A BAB
Dependencies DSM in Matrix Form
Dependent ( Sequential) Interdependent (Coupled) Independent (Parallel)
15
Figure shows the sequence of the DSM matrixFigure shows DSM matrix form
Example of relationship in DSM:
PARTITIONING OF DSM
DSM Partitioning Analysis:
Partitioning is the sequencing or reordering of the rows and columns of DSM with new arrangement which does not have feedback and looping mark at the below diagonal
The mark below diagonal is transformed into the above diagonal
Process eliminate the feedback and looping marks to move as close as the diagonal
Estimate project Duration using DSM