Under keel clearance policy

download Under keel clearance policy

of 1

description

Company under keel clearance policy

Transcript of Under keel clearance policy

  • TSM Poster028

    Quality Assurance into the 21st Century and beyond

    CONTROLLED Revision: 01 Oct 2010Approved by DPA/DMR

    THOMESHIP MANAGEMENT PTE LTD

    Under Keel Clearance & Air Draft Policy

    1. Thome Ship managemenT UKC poliCyThome Ship Management advocates a Minimum Under-Keel Clearance policy for ocean passage, shallow water, within port limits and while alongside the berth or at SBM/CBM mooring. Thomes guideline for under keel clearance is based on the recommendations of the Society of European Pilots for vessels calling at Rotterdam, Amsterdam and Antwerp which are:

    Ocean Passage o 20% of Draft

    Fairways outside ports (Shallow waters) o 15% of Draft

    Fairways inside ports (Within Port Limits) o 10% of Draft

    Whilst alongside the berth o 10% of Draft

    Whilst at SBM/CBM moorings o 10% of Draft

    For Fairways inside Port limits, if the Port / USCG / Pilot recommended UKC required is more than 10% of the draft, Vessels are required to comply with Port / USCG / Pilot recommended UKC.

    Calculation of UKC using TSm 002

    Thome instructs that Under Keel Clearance calculations are to be done using TSM Form 002 by all ships. These forms will be filed and retained along with the passage plans. As a minimum, Under Keel Clearance Calculations must be computed for

    Each arrival and departure, for all ports.

    Any Course leg, if the depth is less than 50 mtrs

    When To inform office

    Vessels are required to inform Office if

    UKC computed is less than Thome under keel clearance criteria

    Under Keel Clearance computed is less than 2 metres (During Ocean Passage)

    Under Keel Clearance computed is less than 1 metres (During during Port approach, Pilotage / Port transit or at Anchorage / Alongside berth

    2. minimUm air-draFT ClearanCeA minimum air draft of 2 metres is required for passing under bridges or overhead cable. After calculating for all variables such as trim and tide, Thome must be consulted if calculations indicated that clearances may be less than this.