Uncertainty Management in MISO Real-Time Systems: Needs ...

17
Uncertainty Management in MISO Real-Time Systems: Needs, Opportunities and Challenges FERC Technical Conference on Increasing Real-Time and Day-Ahead Market Efficiency through Improved Software June 2017 Long Zhao, Senior R&D Analyst, Market Services, MISO Jessica Harrison, Director of R&D, Market Services, MISO Yonghong Chen, Principal Advisor, Market Services, MISO

Transcript of Uncertainty Management in MISO Real-Time Systems: Needs ...

Page 1: Uncertainty Management in MISO Real-Time Systems: Needs ...

Uncertainty Management in MISO Real-Time

Systems: Needs, Opportunities and Challenges

FERC Technical Conference on Increasing Real-Time and Day-Ahead Market

Efficiency through Improved Software

June 2017

Long Zhao, Senior R&D Analyst, Market Services, MISO

Jessica Harrison, Director of R&D, Market Services, MISO

Yonghong Chen, Principal Advisor, Market Services, MISO

Page 2: Uncertainty Management in MISO Real-Time Systems: Needs ...

• MISO is initiating exploratory R&D to evaluate and study

stochastic uses in real-time applications and processes.

• The scale and complexity of uncertainty are increasing

and opportunities exist to explore practical approaches

for stochastic techniques.

• This work will span multiple years.

– Near-term focus: out-of-market solutions

– Starting July 2017 through 2018 and Beyond

• Objective today: Seek comments and suggestions on

research focus

Study Scope & Presentation Objective

2

[Disclaimer] The views and opinions expressed in this presentation are those

of the authors and do not necessarily reflect those of MISO.

Page 3: Uncertainty Management in MISO Real-Time Systems: Needs ...

Generation and Load:

• Medium- and short-term load forecast

• (MISO) Renewable generation forecast

• Energy storage, distributed energy resources (DER), and demand response

(DR) statuses forecast

Interchange:

• Net Scheduled Interchange (NSI) forecast

Network:

• Forced outages (not in scope): Included in outage coordination study

• Grid topology, e.g., Transmission line switching or flow control devices

Uncertainty in Advisory Real-Time

Systems, Operations and Processes

3

Many types of uncertainties exist in our systems today. The

types of and complexity of uncertainty will likely grow.

Page 4: Uncertainty Management in MISO Real-Time Systems: Needs ...

Example: Load Forecast

4

Source: MISO Forecast Engineering Department, Market Evaluation and Design Department

Day-Ahead Mid-term Load Forecast

Shor-term Load Forecast

Page 5: Uncertainty Management in MISO Real-Time Systems: Needs ...

Example: Hourly Wind Forecast Accuracy

5

The 2017 accuracy data is as of June 15th.

Source: MISO Forecast Engineering Department

80%

85%

90%

95%

100%

2012 2013 2014 2015 2016 2017

94.70% 95.11% 94.99%

94.59% 94.32% 94.30%

95.60% 95.81% 95.49% 95.42%

95.81% 95.80%

Day Ahead

4-Hours Ahead

Page 6: Uncertainty Management in MISO Real-Time Systems: Needs ...

Example: Wind Forecast Error Distributions

6

-5000 -4000 -3000 -2000 -1000 0 1000 2000 3000 40000

1

2

3

4

5

x 10-4

Data

Den

sity

DA WGF error

Distribution

-4000 -3000 -2000 -1000 0 1000 2000 30000

1

2

3

4

5

6

7

x 10-4

Data

Den

sity

4H WGF error

Distribution

Mean: -20

Standard deviation: 1000

Mean: -80

Standard deviation: 760

Source: MISO Forecast Engineering Department. Normal distributions are assumed.

Page 7: Uncertainty Management in MISO Real-Time Systems: Needs ...

Engines – e.g., FRAC/IRAC, LAC

Tools – deterministic analog of stochastics

• “Most-likely” scenario

• Reserve requirement

• DA commercial flow limit

• RT peak-hour summary

Operators’ Experiences

• Override on forecasts

• Judgements in decision-making

Current Practice: Deterministic-like Engines

and Tools combined with Operators’

Experience

7

Current practices work to address uncertainties but could benefit

from more transparency into these uncertainties.

Page 8: Uncertainty Management in MISO Real-Time Systems: Needs ...

MISO’s Ramp Capability went live on 05/01/2016 and was

designed to help uncertainty management.

Ramp Capability: A Recent Market Product to

Hedge against Uncertainty

8

Simulation-based analysis indicates that Ramp Capability Product leads to *:

• Reduction in RT prices

• Reduction in RT price volatility

• Improvement in DA-RT price convergence

• Total cost savings

*Source:

https://www.misoenergy.org/Library/Repository/Meeting%20Material/Stakeholder/MSC/2016/20161129/201611

29%20MSC%20Item%2005f%20Ramp%20Capability%20Post%20Implementation%20Analysis.pdf

Page 9: Uncertainty Management in MISO Real-Time Systems: Needs ...

Key deterministic inputs that are uncertain:

• MISO 5-min STLF

• NSI forecast

• Renewable generation forecast (5-min forecasts from Participants or MISO, and SE

values)

• Topology: at “the best knowledge”

Three load forecasts scenarios are generated based on STLF input.

LAC engine is a rough “stochastic” optimization as it is a

combination of three independent deterministic approaches.

Three sets of commitment suggestions are provided to operators.

Example: LAC

9

Page 10: Uncertainty Management in MISO Real-Time Systems: Needs ...

MISO expects to see an increase in the factors that generate

uncertainty in our system today. MISO also expects that multiple

factors will contribute to certain types of uncertainty, increasing its

overall complexity.

• Renewable Generation Penetration => Increased Supply

Uncertainty

• Energy Storage, DER, and DR => Another Dimension of Complexity

• Emerging Transmission Technologies => Grid Topology Uncertainty

• New Market Products => Price/Behavior Uncertainty

Needs for More Research Questions & Efforts

10

Industry trends point to a growth in the scale and complexity

of uncertainty.

Page 11: Uncertainty Management in MISO Real-Time Systems: Needs ...

Wind Capacity Growth

11

Source: MISO Transmission

Access Management

• Around 85% of the wind resources are DIR.

0

5000

10000

15000

20000

25000

Registered Capacity (MW)

Projected (MW)

• Projections do not consider potential withdraws due to PTC expiration after 2019.

• Wind production also increases, and will likely benefit from energy storage integration.

Page 12: Uncertainty Management in MISO Real-Time Systems: Needs ...

MISO began the integration of solar in December 2016. Connecting to MISO

>=69KV facilities:

• MW Amount of Projects in Service: 180MW

• MW Amount of Projects with a GIA and under Construction: 286 MW

• MW Amount of Projects in the Queue: 8,036MW

Source: MISO GI Queue 06/16/2017; Estimation is based on Active and Done Solar Projects with GIA,

GIA in Progress or in DPP studies.

Solar Capacity Growth

12

0

500

1000

1500

2000

2500

3000

3500

Dec-2016 Dec-2017 Dec-2018 Dec-2019 Dec-2020

180

716

2282

2605

3180

Registered Max (MW)

Estimated (MW)

Page 13: Uncertainty Management in MISO Real-Time Systems: Needs ...

• Load forecast improvement

• Renewable forecast improvement

• LAC enhancement (e.g., renewable generation forecast utilization,

Regional Dispatch Transfer constraints integration, and etc.)

• DA commercial flow limits enhancement

• Constraint manager

• Reserve Procurement (e.g., Ramp Capability deliverability)

MISO’s Continuous Efforts to

Deal with Uncertainty

13

MISO is currently working on enhancements to better

address uncertainty.

Page 14: Uncertainty Management in MISO Real-Time Systems: Needs ...

• What techniques can sufficiently validate the outcome of stochastic

methodologies (operator decisions; stochastics vs. ODC, existing

issues)?

• What approaches can help overcome computational performance

limitations (IEEE 118-bus system vs. MISO system)?

• What techniques can help address combined sources of uncertainties

(e.g., renewable + energy storage)?

• What are the pricing implications of incorporating stochastic

techniques?

– e.g. CTS, emission constraints, and etc.

• What is the feasibility of applying stochastics in operating procedures?

Research Questions

14

In tandem with existing efforts, MISO will review uncertainty in our

systems and explore the viability of practical stochastic solutions.

Page 15: Uncertainty Management in MISO Real-Time Systems: Needs ...

Near-term: What are the implications of the “fixed variables” in current

designs? How might stochastic approaches help?

• Reserve requirements and deliverability (stranded MW & headroom

calculations)

• Ramp capability requirement

Long-term: What is the feasibility and value from stochastic or

stochastic-like engines?

• FRAC/IRAC: NSI forecast, MTLF, hourly renewable forecast, etc.

• LAC: NSI forecast, STLF, 5-min renewable forecast, topology

uncertainty, etc.

Proposed Applications & Focus Areas

15

Page 16: Uncertainty Management in MISO Real-Time Systems: Needs ...

• MISO is looking for feedback on its research

questions, information on relevant research

or applications to date and ideas about

potential techniques to explore further.

• MISO will begin characterizing target areas

of uncertainty and exploring near-term

applications.

16

Next steps

Page 17: Uncertainty Management in MISO Real-Time Systems: Needs ...

Comments and suggestions are welcome.

Contact Information • Jessica Harrison ([email protected])

• Yonghong Chen ([email protected])

• Long Zhao ([email protected] )

17