UK’s First Commercial Scale Offshore Wind Farm 26th March 2003 NWP Offshore Ltd.

25
UK’s First Commercial Scale Offshore Wind Farm 26th March 2003 NWP Offshore Ltd

Transcript of UK’s First Commercial Scale Offshore Wind Farm 26th March 2003 NWP Offshore Ltd.

UK’s First Commercial Scale

Offshore Wind Farm

26th March 2003

NWP Offshore Ltd

Presentation

• Project Overview

• Construction Process

• Progress to Date

• Marking of Wind Farm on Admiralty Charts

• Stakeholder Involvement in Construction Process

Project Overview

• 30 wind turbines, Vestas V-80 2MW • 4-5 miles off Prestatyn / Rhyl •Rectangular Turbine Array

• 800m Separation E-W• 350m Separation N-S

• Cable landfall /grid connection at Rhyl• Output equivalent to annual demand of approximately 50,000 homes

North Hoyle - Main Parameters

Project History• Summer 1999 - Install Monitoring Mast

• December 2000 - Crown Estate Invitation to Bid

• Spring 2001 - Awarded Licence to Develop

• August 2001 - Launch of “Juice”

• February 2002 - Submit Consents Application

• August 2002 - Obtain Consents

• October 2002 - Commence Onshore Works

• Summer 2003 - Offshore Construction

• Late 2003 - First Generation

Wind Farm Construction

Turnkey Contract

• Turnkey contractor is consortium of Vestas Celtic Wind Technology and Mayflower Energy

• Includes 5 year Warranty, Operations and Maintenance provision

Turnkey Contract - Major Suppliers

Wind Turbines - Vestas

Wind Turbine Installation - Mayflower

Monopile Supply - Rheden Steel

Monopile Installation - Seacore

Subsea Cables - AEI Cables

Foundations

• 4m diameter, 275t (max), stored at Mostyn

• Installation by Seacore using Jack-up Barge “Excalibur”

• Pile towed out from Mostyn, lifted to vertical

• Hammer installed, drive to rockhead (10-15m below mudline)

• 3.7m hole drilled through pile, through overburden to required penetration

• Pile driven to required penetration

Photo of Horns Rev Foundation

Progress Update

Progress to Date• Construction plans (Environmental Management

System, Oil Spill Contingency Plan etc) in place for construction phase

• Site establishment at Mostyn

• Onshore Works - Majority Complete

– Sub-station, some cable laying still to be performed

– Directional drill to be performed under sea-wall

Progress to Date• Offshore Works

– Modifications to Seacore installation vessel (in Liverpool) almost complete

– Monopile supply on schedule, currently 8 piles stored at Mostyn

– Piling about to begin

• Project “On Track” for commissioning in late Autumn

Marking of Wind Farm on Admiralty Charts

Construction Phase

Operations Phase

Stakeholder Involvement

• “Safety at Sea” Seminar

– Inform stakeholders of forthcoming activities

– Methods of communication

– Establish points of contact

– Effect of wind farm on aids to navigation

– Safety

– Invite feedback

Stakeholder Involvement

• Invitees included

– Port Authorities

– Commercial vessel operators

– RYA, RNLI, MCA,

– Local councils

– Sailing clubs

– Fisheries consultees

Stakeholder Involvement

• Fisheries Liaison Officer

• Email

– Notice of forthcoming activities

• Web Site

– Progress Updates

Stakeholder Involvement

[email protected]

• www.northhoyle.co.uk

Points of Contact