UK Power Networks · Page 5 1.2 The benefits we have already delivered UK Power Networks was...
Transcript of UK Power Networks · Page 5 1.2 The benefits we have already delivered UK Power Networks was...
ukpowernetworks.co.uk
UK Power Networks
2015 to 2023 Business Plan Update
Incorporating stakeholder feedback April 2013
Page 2
Foreword
“I am delighted to introduce our updated business plan for 2015 to 2023. Back in November 2012 we were the
first DNO group to publish a detailed business plan including prices for customers over the RIIO-ED1 period. The
detailed feedback we have received from stakeholders together with continued internal development has allowed
us to present this updated plan which delivers an even better deal for our customers and stakeholders. Again, we
are the first DNO group to publish an updated plan following stakeholder engagement, and this puts us in an
excellent position to submit a well-justified plan to our regulator, Ofgem in July this year.
I am pleased that we have continued to build on our track record of performance improvement since we became
UK Power Networks two and a half years ago. Customer interruptions and customer minutes lost continue to fall
(down 27 per cent and 31 per cent cumulatively over the last three years), we are ahead of plan on network
investment as measured by all indicators, customer service is improving, we are making cost savings that we will
pass on to customers, and most importantly the safety of our network continues to improve. We have also made
significant improvements in connections customer service, and in facilitating competition in connections services
provision.
Innovation is at the core of our culture of continuous improvement, and our plan fully embraces the transition to a
smart grid over the next two price control periods. We already use many ‘smart’ techniques as evidenced by the
high asset utilisation relatively low cost of our services and high network reliability and our RIIO-ED1 plan
incorporates significant savings from smart network operations.
Our updated plan shows lower costs and improved outputs when compared to our first draft plan. In today’s
tough economic climate demands on customers are increasing and we are very conscious that whilst electricity
distribution costs represent only around 18% of the electricity bill, we have our part to play in making electricity
affordable. Therefore I am pleased that our updated plan offers upfront price cuts in 2015 of 8% in real terms on
average across our three networks. This maintains UK Power Networks’ prices as significantly below the national
average of all network operators.
Please do give us feedback on our updated plan so that we can address any remaining concerns that you may
have before we submit our final plan to Ofgem in July this year. Importantly, thank you for the contribution you
have already made.”
Basil Scarsella
Chief Executive
Page 3
Contents
1 Executive summary 4 1.1 The purpose of this document 4 1.2 The benefits we have already delivered 5 1.3 Outcomes from UK Power Networks’ stakeholder engagement programme 5 1.4 The outputs delivered by our updated plan 6 1.5 Our focus on innovation 7 1.6 Expenditure required to deliver these outputs in the 2015 to 2023 planning period 8 1.7 Next steps 8
2 Introduction 9 2.1 Purpose of the 2015 to 2023 Business Plan Update 9 2.2 Structure of this document 9
3 Stakeholder engagement 10 3.1 Stakeholder engagement framework 10 3.2 Our stakeholder engagement objectives and principles 10 3.3 Our stakeholders 10 3.4 Our stakeholder engagement programme 11 3.5 How stakeholder feedback has influenced our plans 21 3.6 Stakeholder feedback about our engagement 24 3.7 Future consultation 25
4 The outputs we will deliver 27 4.1 Introduction 27 4.2 Outputs for the 2015 to 2023 planning period 27 4.3 Stakeholder feedback on our proposed outputs 28 4.4 Our proposed output targets and incentives - including historical performance 28 4.5 Innovation 39
5 Expenditure requirements 42 5.1 Revisions to our proposed expenditure 42 5.2 Impact of changes on 2015 to 2023 proposed capital and operating expenditure forecast 49
6 Financing 52 6.1 Impact of changes on our revenue requirement and customers’ bills 52
7 Finalising our business plans 55 7.1 Remaining steps and timeframes for finalising our business plan 55 7.2 Questions on the business plan update 55
8 Glossary 56
Page 4
1 Executive summary
1.1 The purpose of this document
In November 2012, UK Power Networks’ licence holding companies, Eastern Power Networks (EPN), London
Power Networks (LPN) and South Eastern Power Networks (SPN), were the first of the fourteen UK distribution
network operators (DNOs) to publish detailed draft business plans for the next planning period (RIIO-ED1, 2015
to 2023) for consultation with stakeholders (Consultation Draft Business Plans). UK Power Networks has received
important feedback from stakeholders on its Consultation Draft Business Plans and has also undertaken further
significant internal work to improve the benefits and costs of its draft plans for customers.
This Business Plan Update sets out, for final consultation, changes to key aspects of UK Power Networks'
Consultation Draft Business Plans before it finalises its business plans for submission to the regulator, the Office
of Gas and Electricity Markets (Ofgem), on 1 July 2013. We would like to thank our stakeholders for their input so
far and welcome further comments on this document. We propose the following questions to facilitate feedback:
1. Is this Business Plan Update useful?
2. How could UK Power Networks improve its final business plans?
3. Do you have any comments about the proposed outputs and price impacts?
4. Are there any areas that you would like to see more information on in our final business plans?
5. Do you have any general comments on this Business Plan Update?
6. How do you rate UK Power Networks’ stakeholder engagement on its business plans?
7. How does this plan compare with those of other electricity distribution networks?
Please log on to our consultation website to submit your feedback by 31 May 2013:
http://www.ukpowernetworks.co.uk/internet/en/have-your-say/business-plan/
Alternatively, you can reply by post. Please send your comments to:
Dr Nazrin Mehdiyeva
Head of Stakeholder Engagement
UK Power Networks
Newington House
237 Southwark Bridge Road
London, SE1 6NP
Page 5
1.2 The benefits we have already delivered
UK Power Networks was created in October 2010 and since then has transformed its business strategy and
performance, with significant benefits for customers. In the first three years of the current price control period
(2010-2015):
Our operational focus has delivered a step change in Customer Interruptions (EPN 25 per cent, LPN 25
per cent and SPN 34 per cent better than target) and Customer Minutes Lost (EPN 28 per cent, LPN 17
per cent and SPN 40 per cent better than target)
Our investment programme has exceeded the agreed targets for network health (EPN 93 per cent, LPN
60 per cent and SPN 82 per cent delivered after only 60 per cent of the period)
We have optimised our network reinforcement programme for the impact on demand of the global
economic crisis to both exceed targets and reduce expenditure to achieve cost savings which will be
shared with customers. The number of heavily loaded sites are as follows: EPN: 41 compared to a
target of 66; LPN: 23 compared to a target of 25; SPN: 32 compared to a target of 50. UK Power
Networks never automatically executes its investment plans as approved by the regulator, we always
update them for changing economic conditions to make sure we are only doing work that is really
necessary for the benefit of customers
Our refocusing of the business on customer service has improved our average customer satisfaction
score for faults, connections and general enquiries from 7.13 to 7.63 – although we recognise our
customer service performance still requires further improvement. We have launched a business
transformation programme at considerable expense to our shareholders to modernise our processes and
systems to allow us to realise these gains
We believe that we are the most innovative DNO group. Our London network already utilises many
‘smart grid’ techniques on a business-as-usual basis, including meshed networks, high levels of
automation and control, and contracted demand side reduction. We have the largest portfolio of major
innovation projects of any DNO group
We have delivered this improved performance at significant cost savings, which will be shared with
customers at the beginning of the next price control period in 2015/16. These savings are a direct result
of: UK Power Networks’ innovative asset management strategy; the already high level of smart network
solutions we use on our networks; and our relentless focus on driving down support costs including
reducing our office based staff by around 25per cent in 2011/12.
This track record of improvement is second to no other UK DNO, particularly considering that UK Power Networks
operates in the most challenging, fastest growing, and highest cost part of the country, including London.
1.3 Outcomes from UK Power Networks’ stakeholder engagement programme
UK Power Networks has undertaken a most comprehensive and inclusive stakeholder engagement programme
right from the commencement of its RIIO-ED1 planning in early 2011. This engagement has been fully integrated
with our business-as-usual stakeholder engagement, being managed within UK Power Networks’ customer
services directorate and through our CEO reporting to our Board.
To support the development of our Business Plans we have undertaken:
Nine Critical Friends Panel sessions
14 focus groups with domestic customers
21 telephony interviews with LPN business customers to test their Willingness to Pay (WTP) for certain
services
1,200 WTP interviews with domestic customers
300 WTP interviews with business customers
200 WTP interviews with central London business customers
22 customer connections stakeholder forums
Four priority issue topic specific stakeholder panels (vulnerable consumers & fuel poor customers, storm
performance, metal theft and street works)
Page 6
Two distributed generation customer stakeholder forums and a customer service survey
Targeted stakeholder feedback
Bilateral engagement with suppliers and large business customers
Consultation on the November 2012 Consultation Business Plan. This set out UK Power Networks’
proposed outputs, forecast expenditure, revenue and prices for the next planning period. UK Power
Networks was the first UK DNO to publish a Draft Business Plan containing this level of information in
response to stakeholder feedback
This Business Plan Update provides stakeholders with a further opportunity to make any final comments before
the Business Plans are submitted to Ofgem on 1 July 2013. UK Power Networks has made the following changes
to its 2015 to 2023 Business Plans on the basis of feedback received to date from stakeholders:
Introduced additional secondary deliverables to support primary outputs. UK Power Networks has also
identified programs of work or activities to support these commitments
Refined certain inputs to its planning scenario including forecast household growth and the domestic
uptake rate of heat pumps and electric vehicles. UK Power Networks has however, retained the core
planning scenario underpinning its Consultation Draft Business Plans
Refined the scope of investment required to respond to the decarbonisation of the UK economy
particularly through the connection of new low carbon technologies
Refined the scope of the Distributed Generation (DG) Infrastructure required to allow the timely and
efficient connection of the increase in medium to large scale generation
Refined the scope of investment in the London Infrastructure Plan to ensure that the network serving
London has capacity and resilience comparable to other world cities
Further developed its innovation strategy through expert panel review
Included greater investment to improve the end-to-end customer connections process. Further
improvements will be delivered as part transformation project over the next planning period
Targeted improvements to the quality of electricity supply through greater investment in automation and
remote control and changes to inspection and fault processes
Further reviewed and revised its procurement, work delivery, training and contractor strategy
Expanded the initiatives that it will undertake to support community engagement and the services that it
will provide to vulnerable and fuel poor customers
Amended the way that our distribution use of system prices (DUoS) will be set to reduce price volatility
1.4 The outputs delivered by our updated plan
UK Power Networks will continue to deliver improved outputs for its customers and stakeholders in the next
planning period. Table 1 sets out the outputs and associated performance measures that UK Power Networks is
proposing to deliver over the 2015 to 2023 planning period.
Table 1 UK Power Networks’ 2015 to 2023 output performance measures
Output 2015-2023 performance measures
Safety Achieve zero public and staff harm
No formal notices or prosecutions by the HSE under applicable legislation
Reduce total recordable injury rate by more than 10 per cent
Engage with 1.8 million children, either through face to face or via on-line interaction, on
public safety issues over the planning period
Customer satisfaction Achieve top third performance in all components of the Broad Measure of Customer Service
(BMoCS)
o Customer service (target an overall score of 8.3 in EPN and SPN and 8.1 in LPN
reflecting the larger proportion of underground low voltage networks)
Page 7
Output 2015-2023 performance measures
o Customer complaints
o Stakeholder engagement
Enhance stakeholder engagement to ensure the service provided to customers meets their
expectations
Continue to expand the contact channels customers can use to talk to UK Power Networks
Network Reliability Maintain LPN as having the lowest level of customer interruptions (CIs) and customer
minutes lost (CMLs) in the UK
Reduce EPN and SPN CIs by more than 8 per cent
Reduce EPN and SPN CMLs by more than 10 per cent
Maintain the health of the network during RIIO-ED1
Continue to improve the load index (LI) of the networks by reducing the number of sites
classified as LI 4 and LI5 during RIIO-ED1
Protect 98 substation sites from the risk of flooding
Reduce the number of 12 hour failures per year on average by more than 30 per cent
Environment Continue to recycle 70 per cent of office and depot waste and 98 per cent of street works
spoil
Maintain SF6 leakage as a proportion of installed mass
Reduce oil leakage by 2 per cent year on year
Undertake undergrounding in Areas of Outstanding Natural Beauty (AONB) and national
parks
Investigate all noise issues and address all non-compliant sites
Connections Facilitate a competitive connections environment in our three networks
Achieve upper quartile performance in average time to quote
Achieve upper quartile performance in average time to connect
Provide on-line instant quotations
Meet our improvement commitments to major connections customers
Deliver 100 per cent Guaranteed Standards of Performance compliance
Social Obligations Continue to improve the service provided to vulnerable customers
Maintain community engagement during RIIO-ED1
Work proactively with third parties to reduce the level of fuel poverty in our three networks
1.5 Our focus on innovation
In the next planning period, UK Power Networks will continue to build on the leadership role established in respect
of innovation over the current period. We propose to spend only 0.5 per cent of revenues a year under the
Network Innovation Allowance (NIA) because we believe it is better for customers if the networks compete for
funding under the independently scrutinised Network Innovation Competition (NIC). The Business Plans
demonstrate that UK Power Networks has fully embraced the transition to a smart grid over the next two price
control periods. Our updated plan reflects around £135 million of savings to our investment programme from the
use of smart techniques. This is in line with UK Power Networks’ implied share of the total £500 million of savings
for Great Britain estimated by the Department for Energy and Climate Change (DECC) and Ofgem’s Smart Grid
Forum.
Page 8
1.6 Expenditure required to deliver these outputs in the 2015 to 2023 planning period
UK Power Networks will deliver its output commitments to its customers at a total cost of £7.3 billion, a decrease
of £0.2 billion or three per cent compared to the forecast cost in the November 2012 Consultation Draft Business
Plan (Initial Forecast). This decrease in required expenditure is driven by savings from smart interventions,
changes in the scope of major projects including the London Infrastructure Plan and DG Infrastructure investment,
a decrease in unit costs and further assessment of the volumes of work underpinning the business plan. These
changes are discussed in detail in section 5.1 of this Business Plan Update.
Table 2 below sets out UK Power Networks’ forecast costs, by building block, for the next planning period
compared to actual expenditure over the current period and UK Power Networks’ Initial Forecast. Compared to
the current period we are increasing our investment in network reinforcement for load growth and in asset
replacement (but reducing unit costs), whilst decreasing the cost of network operations and ‘indirect’ overhead
costs.
Table 2 Summary of changes in total UK Power Networks capital and operating expenditure
£ billion DPCR-5
expenditure
(adjusted to eight
years)
Initial 2015-23
expenditure
forecast
Revised 2015-23
expenditure
forecast
% difference:
DPCR-5 expenditure
and revised 2015-23
expenditure forecast
Load related capex 1.30 1.70 1.47 +13%
Non load related capex 1.80 2.10 2.21 +23%
Network operating costs 1.30 1.30 1.20 -8%
Indirect costs 2.00 1.80 1.90 -5%
Non-operational capex 0.20 0.40 0.32 +60%
RPEs - 0.20 0.21 -
Total 6.60 7.50 7.31 +11%
The November Consultation Draft Business Plans included forecast revenues and prices post-2015 that were
broadly flat in real terms. The cost reductions in this Business Plan Update enable us to offer a price cut for
customers in 2015, the first year of the next planning period. UK Power Networks will deliver an initial real terms
price cut of 4 per cent in EPN, 10 per cent in LPN and 12 per cent in SPN respectively, or 8 per cent on average,
with some modest real growth thereafter to allow us to maintain appropriate financial ratios.
UK Power Networks is pleased to continue to ensure that DUoS prices for EPN, LPN and SPN will continue to be
lower than the UK average for both domestic and non-domestic network customers. This is an excellent outcome
for our customers given the challenges we face during the upcoming planning period such as the decarbonisation
of the UK economy and an ageing asset base.
1.7 Next steps
This Business Plan Update is the result of two years of extensive preparation by UK Power Networks and builds
on the stakeholder feedback received following publication of the November 2012 Consultation Draft Business
Plans. Our impressive track record of performance improvement over the last three years has positioned us to
offer a plan to customers that will deliver improved outputs, higher quality networks and lower prices. We hope
that our stakeholders will support us to refine key elements of this Business Plan Update further ahead of
submission of our final business plans to Ofgem in July 2013.
Page 9
2 Introduction
2.1 Purpose of the 2015 to 2023 Business Plan Update
In November 2012, UK Power Networks' licence holding companies EPN, LPN and SPN (collectively referred to
as the Networks) published and invited customers and other stakeholders to comment on their 2015 to 2023
Consultation Draft Business Plans:
EPN’s Consultation Draft 2015 to 2023 Business Plan
LPN’s Consultation Draft 2015 to 2023 Business Plan
SPN’s Consultation Draft 2015 to 2023 Business Plan
UK Power Networks has also widely consulted on key issues relating to the development of its business plans for
the upcoming planning period through a variety of other engagement pathways.
UK Power Networks has listened to, and understood, what its customers and other stakeholders have said and
has acted on this by incorporating their feedback into the further development of its business plans. UK Power
Networks has also undertaken further internal and external reviews of the key aspects of its business plans to
ensure that they are well justified and will deliver value for money over the long term, having regard for what
customers and other stakeholders have said that they value.
This document provides an overview of the changes to key aspects of UK Power Networks' Consultation Draft
Business Plans. In particular, it sets out what stakeholders have said, and on this basis the changes made to:
The outputs that will be delivered
The projects that will be undertaken
It also explains the processes that have been applied to further test, challenge and verify the proposed
expenditure forecasts to ensure that they are prudent and efficient. These changes directly influence the required
revenues over the 2015 to 2023 planning period, which in turn impact customers' electricity bills.
We welcome your views on this Business Plan Update and have included questions in section 7 to facilitate
stakeholder discussion and feedback. We will incorporate this feedback in our final business plans which are due
to be submitted to Ofgem on 1 July 2013.
2.2 Structure of this document
The remainder of this document is structured as follows:
Section 3 sets out the nature, scope and outcomes of UK Power Networks' stakeholder engagement
programme
Section 4 sets out the outputs that UK Power Networks will deliver in 2015 to 2023
Section 5 sets out UK Power Networks' revised expenditure requirements
Section 6 sets out the financing arrangements, including the impact of these changes on UK Power
Networks' required revenue and customers' bills
Page 10
3 Stakeholder engagement
3.1 Stakeholder engagement framework
UK Power Networks recognises the importance of stakeholder views to the future development of its distribution
networks. In order to build on this, UK Power Networks established a Customer Service Directorate in 2011. This
was implemented as part of the drive to transform UK Power Networks from an engineering-led to a customer
focused business. Prior to this, responsibility for customer service was at best not clear and at worst not satisfied.
Since 2011, UK Power Networks has undertaken an extensive programme of consultation on all aspects of its
2015 to 2023 Business Plans to ensure that they meet the expectations of customers and other stakeholders and
deliver value for money over the long term. The Business Plan consultation is the most extensive stakeholder
engagement programme undertaken by UK Power Networks to date and has been facilitated by the changes to
the focus of stakeholder engagement within UK Power Networks since acquisition by its current owners.
This section explains how UK Power Networks has gathered stakeholders’ views from 2011 for the purposes of
developing and informing the Network's 2015 to 2023 Business Plans which has been monitored by the Board of
Directors through the CEO.
3.2 Our stakeholder engagement objectives and principles
UK Power Networks' stakeholder engagement objective is to ‘develop arrangements that will provide meaningful
opportunities to a range of its stakeholders to influence the direction of UK Power Networks' thinking on network
development and business operations on an on-going basis'.
UK Power Networks' stakeholder engagement objective is supported by its stakeholder engagement strategy,
which is underpinned by the AA1000 Stakeholder Engagement Standard (2011 (as amended)). This is a leading
international standard which sets out the following principles:
Materiality: engaging with stakeholders on issues that they have a material interest in and that are within
UK Power Networks' control or influence
Inclusivity: involving stakeholders in the internal decision making process
Responsiveness: committing to act and respond to stakeholders’ views and opinions
UK Power Networks has developed company policies, procedures and activities to align with AA1000 and the
principles which underpin it. UK Power Networks' stakeholder engagement team has been trained in the AA1000
Stakeholder Engagement Standard.
3.3 Our stakeholders
UK Power Networks' stakeholders include any individual, groups of individuals or organisations that affect, or
could be affected by its activities, services or associated performance. UK Power Networks' diverse list of
stakeholders comprises domestic customers, commercial and industrial customers, local governments, major
energy users, customer organisations and those representing the community sector as shown in Figure 1 below.
Page 11
Figure 1 UK Power Networks' stakeholders
UK Power Networks has established a stakeholder register which records a range of relevant information on its
stakeholders including their location and areas of interest to ensure that all interested individuals, groups and
organisations are continually informed about relevant upcoming consultation pathways.
3.4 Our stakeholder engagement programme
In accordance with its stakeholder engagement principles, UK Power Networks has developed a comprehensive
programme of events for its three networks that will ensure all stakeholders have the opportunity to put forward
their views and get involved in the development of each Network’s future plans in an efficient and inclusive way.
We are committed to ensuring that all stakeholders have the opportunity - and multiple opportunities where
required - to be heard. UK Power Networks recognises that, in order to cultivate more equitable decision-making,
it is necessary to listen to and understand stakeholders' views. We also recognise that this is key to informing the
development of our 2015 to 2023 Business Plans.
UK Power Networks' stakeholder engagement programme:
Adopts a diverse range of engagement pathways including workshops, forums, online consultation,
targeted interviews, letters, telephone and face-to-face meetings. It recognises that different stakeholder
groups have different levels of interest and knowledge. Therefore we tailor engagement to meet
different stakeholder needs
Covers a wide range of business areas and issues that affect stakeholders
Takes every opportunity to raise stakeholder awareness to encourage participation in the engagement
process. UK Power Networks recognises the significant efforts made by its stakeholders participating in
the engagement processes
UK Power Networks' approach to stakeholder engagement on the development of its Business Plans comprised
three key stages:
1. Stage 1: Research
This involved the qualitative and quantitative WTP Research, undertaken in 2011 and 2012 as well as
targeted discussions and interviews with business and domestic customers. It also involved
Consumers
Domestic
Industrial &
commercial
Small and
medium
enterprises
Environmental groups
Renewable energy advocates
Landscape focused organisations
Organisations focused on carbon
Government interests
Ofgem
Central
government
Local
authorities
Health and
safety
Education and
skills
Members of
parliament
Investors
Debt and equity
investors
Credit rating agencies
Innovative industry parties
Energy service
companies (ESCos)
Electric vehicle (EV)
developers
Developers and engineers
Engineering institutions and boards
Construction Streetworks
Utilities
Gas Telecoms Water/sewerage
Local interest groups
Local community groups
Chambers of commerce
Parish councils
Industry parties
Other DNOs /
IDNOs
Distributed
generators
Suppliers
Generator
developers
Transmission owners
Page 12
consultation, via regional workshops, on the Networks' planning scenarios.
2. Stage 2: Targeted Engagement
This involved the Critical Friends Stakeholder Engagement Panel Sessions (panel sessions) undertaken
by the Networks in the second half of 2012. The panel sessions were held after the publication of the
WTP results in June 2012. The panel sessions formed the core of UK Power Networks' consultation
programme for the development of the Networks' 2015 to 2023 Business Plans. The discussions and
feedback from the panel sessions led to new engagement sessions, such as metal theft and vulnerable
customers.
3. Stage 3: Feedback Implementation
This involved UK Power Networks developing an internal actions log for each Network which recorded
the issues, views, positions and actions raised at each engagement session. The issue logs assist the
Networks to record, assess and respond to all issues raised by stakeholders and track their assessment
of, and response to, these issues over time.
Importantly, there was some overlap between the three phases which created a ‘virtuous cycle’ of addressing and
responding to issues. For example, implementation of feedback from panel sessions one and two was being
finalised at the same time that panel session three was being scoped and developed. This overlap ensured that
the issues raised in panel sessions one and two were further consulted on, as appropriate, in panel session three.
A high level overview of the programme of stakeholder events is shown in Figure 2 below.
Figure 2 Stakeholder Engagement Programme
Strategy, Preparation,
Planning, Issue
Identification
Developing Issues,
Testing Issues,
Delivering Actions &
Outcomes
Key Outcomes Ongoing Engagement
Strategy Development Stakeholder
Categorisation
Outputs
Development &
Consultation
Planning
Scenarios
Willingness to Pay
Early
Development Draft
Business Plan
Critical Friends
Panels
London
Infrastructure
Forum
Priority / Specific
Issues
Low Carbon
Whole of Business
Engagement
Future
Engagement
Final, well-
justified
Business Plan
Critical Friends
Priority Issues
London
Infrastructure
Forum
Competition in
Connections Ongoing
Stage 1: ResearchStage 2: Targeted
Engagement
Stage 3: Feedback on
Implementation
November draft
consultation
Business Plan
April Business
Plan update
Page 13
The time-table for these events is shown in Figure 3 below:
Figure 3 Timing of Stakeholder Engagement Programme
A short summary of each of the key stakeholder consultation programmes is set out below.
3.4.1 Output development consultation
UK Power Networks recognise that agreement on the outputs, being the products or services that the Networks
will deliver to their customers, is central to the Networks' future planning requirements. To this end, UK Power
Networks commenced consultation on outputs early in its business planning process in 2011, to ensure that it
understood what its stakeholders consider to be meaningful outputs for each Network. This information was then
reflected into the development of the Networks' future plans including their investment requirements.
There were four key engagement pathways:
Workshops - 62 attendees, comprising targeted organisations and individuals, from across all three
Networks participated in the workshop which was held in Central London
Online consultation - 21 participants, who attended the workshop and undertook the online consultation
established via UK Power Network's online stakeholder engagement website
Targeted telephone interviews - Ten stakeholders, who were not able to attend the workshop,
participated in the telephone interviews
Domestic customer focus groups - The objective of these focus groups was to identify activities that
domestic customers regarded as being important
Stakeholders were asked to express their views on the outputs they want the Networks to deliver. Stakeholders
confirmed that the six primary output categories as defined by Ofgem were the most important:
Safety
Conditions for connection
Customer services
Environmental performance
Network reliability and availability
Social obligations
Stakeholders also suggested that Environmental performance should be split between a DNOs direct impact on
the environment and a DNOs contribution and support of the decarbonisation of the UK economy. This change
was rejected within the development of Ofgem’s RIIO-ED1 strategy framework.
2012 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2011 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2013 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Focus Group:
Performance
during storms
Focus Group:
Street works
Critical Friends
panel 4
Regional
Residential
Forums
Stakeholder
Engagement
Solution live
Scenario Planning
Regional
Workshops
Focus Group:
Metal theft
Critical Friends panels
1 & 2
Critical Friends
panels 3
Full day outputs
workshop -
London
Embracing
Competition
workshop 2
Embracing
Competition
workshop 3
Embracing
Competition
workshop 7
Embracing
Competition
workshop 10
Willingness to
Pay Seminar
Embracing
Competition
workshop 8
Ongoing Engagement
Focus Group:
Vulnerable
customers
Embracing
Competition
workshop 9
Publication of Nov
Consultation draft
Business Plan
Focus Group:
Distribution
Generation
Page 14
3.4.2 Planning scenarios
One of the key challenges facing UK Power Networks over the 2015 to 2023 planning period is the need to adapt
to the requirements of a low carbon environment. The UK Government has committed to reducing carbon
emissions by 80 per cent by 2050 with medium term goals set for 2020.
There is significant uncertainty about the rate of consumer uptake of Low Carbon Technologies (LCT), such as
electric vehicles, solar panels and heat pumps, to support the Government’s objective of reducing greenhouse
gases. UK Power Networks is also expecting growth in a range of distributed generation technologies, including
onshore wind farms, to impact its Networks. Depending on the rate of uptake, these LCT could significantly
impact the future capacity requirement the Networks' distribution systems.
UK Power Networks consulted extensively with its stakeholders in 2011 to understand their views on the likely
scale and uptake of these LCT (referred to as 'planning scenarios') on each Network to assist it develop a "best
view", being the most likely planning scenario for the 2015 to 2023 period. UK Power Networks sought
stakeholder views on the following scenarios for each Network:
Scenario 1 - Economic concern
Scenario 2 - Engaged green
Scenario 3 - Green stimulus
Scenario 4 - Green technology
Scenario 5 - Business as usual
Each of these scenarios was considered in light of the following three key drivers of growth in demand for
electricity:
Rate of economic growth including population growth, economic growth, domestic cooking, lighting and
appliances
Deployment of LCT including heat pumps and electric vehicles
Changes in electricity market mechanisms such as the increase in demand-side response, roll out of
smart meters and the introduction of time of use tariffs
Each of the drivers was considered in the context of a high, medium or low outcome for each Network as shown
in Table 3 below.
Table 3 Possible planning scenarios 2015 to 2023
Scenario Rate of economic growth Impact of low carbon
technologies
Impact of electricity
market reform
Economic Concern Low Low High
Engaged Green Society High High High
Green Stimulus Low High High
Green Technology Revolution High High Low
Business as Usual High Low Low
UK Power Networks sought stakeholder views on the planning scenarios including through:
Regional workshops
Each Network held focused workshops which explained the alternative possible planning scenarios
relevant to them. Key differences in the location of the Networks means that regionally-specific scenarios
are required for all three Networks. Stakeholders were provided with the opportunity to discuss, review
and challenge each of the scenarios presented
Online forum
This was established via UK Power Networks' online stakeholder engagement website and provided
stakeholders with a further opportunity to provide feedback on alternative possible planning scenarios.
Over 50 people visited the web site, 11 of whom offered feedback on one or more of the scenarios.
Key stakeholder feedback included that:
Page 15
Further consideration should be given to the potential differences in views of business and domestic
customers
The Department for Energy and Climate Change’s (DECC) onshore wind forecasts are overly optimistic
given, amongst other things, public opposition and planning constraints
Further consideration should be given to emerging energy technologies including Combined Heat and
Power (CHP) and energy from waste
Drawing on stakeholder feedback and the original planning scenarios, UK Power Networks developed a ‘hybrid’
scenario which takes a more conservative approach in a number of areas including assumptions around the take-
up of green technology. This hybrid scenario underpinned UK Power Networks’ 2012 Consultation Draft Business
Plans.
UK Power Networks has continued to review and refine the planning scenario inputs and has made some
modifications including to:
Forecast household growth
UK Power Networks has revised its forecast having regard for historical actual information published by
the Department of Communities and Local Government (DCLG). Based on this analysis, UK Power
Networks has assumed that the yearly level of household formation in the next planning period will be
equal to the historic long run average shown below for each of its distribution areas
The domestic uptake rate of heat pumps
Originally UK Power Networks based its assumption on housing formation data from the English House
Condition Survey, however as part of the development of its modelling approach UK Power Networks
has used a more detailed analysis of the housing stock based on Experian data. This has resulted in an
increase in the heat pump penetration in EPN and a reduction in both SPN and LPN.
The uptake rate of electric vehicles
UK Power Networks agreed with its Stakeholders that its assumptions were optimistic given purchase
prices and concerns regarding the ease of re-charging and speed. On this basis, UK Power Networks
reduced its assumptions regarding the rate of uptake of electric vehicles
Commercial heat pumps
These were not included in UK Power Networks original scenario forecasts, however stakeholder
feedback was supportive of its inclusion and has now been included in the planning assumptions.
Domestic lighting and appliances
UK Power Networks improved its forecasts by using more recently available information released by the
Department for Environment Food and Rural Affairs (DEFRA) in its Market Transformation Programme.
The impact of these changes is shown in Table 4 below.
Table 4 Modifications to planning inputs and assumptions (as at March 2023)
November 2012 Consultation Business Plan Business Plan Update
LPN EPN SPN LPN EPN SPN
Heat pumps –
Domestic
61k 233k 121k 44k 262k 100k
Heat pumps – Non
domestic (MW)
Not included Not included Not included 70MW 176MW 94MW
Electric vehicles 130k 243k 156k 50k 156k 134k
FIT eligible
generation
93k 290k 167k 72k 207k 121k
Onshore wind
(MW)
10MW 724MW 214MW 10MW 655MW 152MW
Offshore wind
(MW)
N/A Beyond 2015
assumed to
connect to
offshore grid
Beyond 2015
assumed to
connect to
offshore grid
Not
applicable
Beyond 2015
assumed to
connect to
offshore grid
Beyond 2015
assumed to
connect to
offshore grid
Page 16
3.4.3 Willingness to pay
UK Power Networks recognises the importance of understanding its customers' WTP for the provision of different
or additional services, activities or service levels in developing its Business Plans for the 2015 to 2023 period. UK
Power Networks therefore invited stakeholders to participate in WTP studies specific to each of its Networks.
These studies comprised two elements:
Qualitative research
This was concerned with identifying the services, activities and service standards that stakeholders
considered should be reviewed in the study
Quantitative research
This was a statistical exercise involving customers and other stakeholders assigning a numerical value,
representative of a financial value, to the provision of certain services, activities or service standards.
Breaking the survey into the two phases was important to ensure that stakeholders defined the nature and scope
of the quantitative phase.
Table 5 below summarises the initiatives that customers have said they value most, ordered in terms of the
customers' WTP, over the RIIO-ED1 period.
Table 5 UK Power Networks’ WTP results (cumulative over the eight years of the RIIO-ED1 period)
Services, activities, service levels LPN
WTP (£m)
SPN
WTP (£m)
EPN
WTP (£m)
Undertake infrastructure investment required to detect loss of supply
from individual or small groups of premises
28 41 52
Undertake investment in network technologies to allow cheaper and
quicker connection of new commercial low carbon electricity generators
26 38 52
Undertake investment to support and facilitate the uptake of domestic
micro-generation such as solar panels
25 28 34
Undertake infrastructure investment required to support the take up of
low carbon electric heating technologies
21 26 28
Provide customers with confirmation around the likely timeframes
(morning, afternoon, evening) for new connections being undertaken.
16 15 25
Provide customers with information on the timeframes for undertaking
simple low voltage new connections work, for example - within 15 days
12 20 21
Provide customers with information on the expected timescale for the
provision of quotations for simple, low voltage new connections work
13 17 22
Restore supply to 80% of rural customers off supply for more than 3
minutes within 60 minutes
- 18 28
Undertake new connection during normal business hours, in the
evenings and at weekends
7 10 22
UK Power Networks to undertake all elements of the new connections
service offered
6 9 20
Limit the frequency of power cuts over 3 min to an average of one every
two years
- 13 20
Provide more information to customers during power cuts by improving
the information provided by the call centre and provision of real-time
information via the internet, social media & staff proactively contacting
customers.
5 11 15
Provide electricity back-up services to customers including regular
testing of customer-owned generators and systems
8 11 12
Provide customers with quotations for simple, low voltage new
connections work within 7 working days
8 14 -
Page 17
Services, activities, service levels LPN
WTP (£m)
SPN
WTP (£m)
EPN
WTP (£m)
Reduce the timeframes for completing simple, low voltage new
connections from 90 to 60 days.
- 11 -
Provide a single point of contact for customers seeking a new
connection work.
- 8 -
UK Power Networks also commissioned a further complementary WTP study focused on small and large London
central business district customers (City of London, West End and the Docklands). This study was concerned
with identifying any differences in the priorities and value for these customers, as compared to the wider LPN
customer base.
The results of this study highlight the subtle but important differences in the priorities of LPN Central Business
District (CBD) business customers, being that they were more concerned with network reliability and connections
and are willing to pay an additional £26 million over the RIIO-ED1 period, for services that they value. The results
of this study are summarised in Table 6 below:
Table 6 UK Power Networks’ WTP results - CBD Business Customers only (cumulative over the RIIO-ED1
period)
Services, activities, service levels WTP Value (£m)
Restore supply to 80 per cent of urban customers off supply for more than 3 minutes within 5 minutes 6
Undertake investment in infrastructure required to enable the Networks to detect loss of supply from
individual or small groups of premises 5
Provide customers with information on the expected timescale for the provision of quotations for high
voltage new connections work: within jointly agreed timeframes 3
Restore supply to 80 per cent of urban customers off supply for more than 3 minutes within 10 minutes 3
Limit the frequency of power cuts over 3 minutes to an average of one every four years 3
Provide customers with quotations for high voltage new connections work within 20 working days 3
Commence providing contingency, back-up services, to customers e.g. regular testing of customer-
owned generators and systems 2
Provide customers with confirmation around the likely timeframes (morning, afternoon, evening) for
new connections being undertaken. 2
Total 26
Based on this information, we have included the following in the 2015 to 2023 Business Plans:
£50.7 million to support targeted quality of service improvements
Delivery of a wide range of improvements to the end-to-end connections process. This investment will
be self-funded (by UK Power Networks shareholders).
£106.5 million to support process and system changes required to accommodate data from smart
meters, establish a suitably skilled workforce and carry out 160,000 metering interventions
£15 million of network reinforcement investment, predominately in the EPN, to provide additional network
capacity required to accommodate the connection of renewable generation. This investment
incorporates new 'smart' techniques which will enhance UK Power Networks' network performance,
therefore reducing the need for expensive traditional reinforcement investment
Improvements to UK Power Networks' customer service operations. This investment forms part of the
business transformation project and will be self-funded (by UK Power Networks shareholders).
3.4.4 Critical friends panel sessions
UK Power Networks organised critical friends panel sessions, for each Network, to consult with stakeholders on
the key targeted issues shown in Figure 4 below. These issues are closely related to the key output categories
identified by Ofgem in its RIIO consultation documents:
Page 18
Figure 4 Critical friends panel sessions
The panels comprised representatives from major energy users, industry participants, consumer groups, and
developers, the low carbon energy sector, local authorities and community organisations. The purpose of
establishing the panels was to ensure that the output and feedback generated through the panel sessions was
comprehensive and representative of all of the Networks' stakeholders. UK Power Networks considers that this is
important for developing robust and well justified business plans that will deliver customers value for money over
the long term. The panel was established by drawing on the Networks' internal stakeholder engagement
database, which contains key information on stakeholders, including their areas of interest.
UK Power Networks also actively encouraged additional stakeholders who were not` on the panels to attend the
panel sessions of specific interest to them. Again, these stakeholders were identified though their internal
databases and relevant UK Power Networks' managers identifying relevant contacts. The panel rounds and
session timetable are shown in Figure 5 below:
Figure 5 Critical friends panel session rounds
Figure 5 shows that in the past eight months, UK Power Networks has conducted three rounds of critical friends
panels being each involving three sessions – one session for each Network. Accordingly, to date the Networks
have held nine critical friends panel sessions.
A fourth round of panel sessions will be held in May 2013 and will focus on reviewing the progress that the
Networks have made in implementing stakeholder feedback from the previous rounds of panel sessions
highlighting where feedback has resulted in changes to their policies and processes. For feedback not yet
Customer satisfaction
Low carbon targets & transition
Low carbon technologies
Network reliability & availability
Social obligations
Safety Environment Connections
Expected Outcomes
Engagement topics and timetable
Purpose of Engagement
Priority Issue Sessions and
Planning Future Panels
Changes to Existing Business
Processes and Actions Update
Panel 1 Panel 2 Panel 3
Low Carbon Economy:
Our Path to Innovation
Overview of the RIIO
Framework
Quality of Supply
Low Carbon Challenges &
Our Innovative Solutions
Network Investment
Social Obligations, Safety
and the Environment
Customer
Services
Connections
LPN: 4 Oct, SPN: 18 Oct,
EPN 1 Nov
LPN: 15 Nov, SPN: 29
Nov, 13 Dec
LPN: 10 Jan, SPN: 24
Jan, EPN: 7 Feb
LPN: 2 May, SPN: 9
May, EPN: 16 May
Panel 4
Business Plan
engagement feedback
and update
To Test and Shape Our Business
Plan 2015-23
To Capture and Act on Your Priority
Issues
Robust Business Plan with a Clear
Sense of Direction
To Include Your Views in Our
Improvement Plans to 2015
Page 19
implemented, the Networks will provide a timeline within which stakeholders can expect to have their feedback
actioned.
Each of the panel sessions involved the Networks conducting short presentations on specific topics with the
opportunity for stakeholders to ask questions or make comments both during and after the presentations. The
presentations were followed by a dedicated open forum to facilitate discussion and further clarify key aspects of
the issues being discussed.
3.4.5 London infrastructure forum
At the commencement of its planning process, UK Power Networks sought stakeholders' views to inform the
development of its central London investment strategy to ensure that London Power Networks' distribution
system, particularly the segment serving the central business district (CBD), has capacity and resilience that is
comparable with other world cities.
Given the importance of this issue, particularly for the economic growth and prosperity of the wider UK economy
over the long term, a separate forum and working party was established to ensure that LPN's Business Plan for
the next eight years supports this growth. The working party comprised representatives from the City of London,
the City of Westminster, London First, the City Property Association, Westminster Property Association and the
Greater London Authority as well as representatives from UK Power Networks. The objective of the working party
was to challenge the infrastructure plans in LPNs business plan to ensure they will result in sufficient and timely
investment required to meet capacity growth and network resilience requirements in London over the 2015 to
2023 period. This working party met on a monthly basis from April 2012 chaired by the Corporation of London.
Importantly, this forum also contains organisations which represent business and commercial enterprises in
London. The participation and input from these organisations has added a practical perspective to what may
otherwise have been aspirational, planning-led discussions.
The London Infrastructure Forum has greatly assisted the LPN to develop an investment plan for London which is
supportive of the Government's aspirations and also reflects the needs of the wider business community. LPN will
continue to meet with the London Infrastructure Panel to obtain valuable feedback from stakeholders.
3.4.6 Priority and specific issues
Over the past 18 months UK Power Networks has conducted a number of stakeholder events focused on specific
issues identified as important by customers and other stakeholders, including:
Network performance during and after storms
Vulnerable customers
Distributed generation
Metal theft
Street works
Low carbon innovation
Competition in connections
Topics for future engagement
Consulting on these issues has been important in order to connect with specific customers and ensuring that their
needs and requirements on these matters are fully understood and reflected in the development of the Networks'
2015 to 2023 Business Plans.
3.4.7 Our consultation draft business plans
In November 2012, UK Power Networks published Consultation Draft Business Plans for each of its Networks,
which set out their proposed:
Outputs for the 2015 to 2023 period
Expenditure forecasts for each year of the 2015 to 2023 period
Revenue requirements for each year of the 2015 to 2023 period
Prices for the for the 2015 to 2023 period
UK Power Networks is pleased to advise that EPN, LPN and SPN were the first of the fourteen UK DNOs to
Page 20
publish draft business plans containing this level of detail. To date, no other DNO has published annual revenue
requirements or prices for the upcoming planning period.
Stakeholders were invited to comment on all aspects of the Consultation Draft Business Plans and the questions
included throughout were designed to assist stakeholders challenge, and apply a robust review of the key issues.
There was a two month consultation period, ending 4 February 2013, and a variety of consultation pathways were
available to facilitate stakeholders providing feedback via an online survey.
UK Power Networks considered that publishing and inviting feedback on its Consultation Draft Business Plans,
eight months prior to them being finalised for submission to Ofgem, was important to provide sufficient time to:
Assess and incorporate feedback so as to further the develop its business plans
Ensure a strong understanding of the services, and service standards, that customers and other
stakeholders want in the next planning period
Publish this document, the Business Plan Update, to explain the key changes to the business plans
before they are finalised for submission to Ofgem. UK Power Networks considers that this is important
to ensure that customers and other stakeholders have the opportunity to understand how their feedback
has been incorporated into the development of the business plans, and how the changes will impact
them in terms of prices over the next planning period
Ten stakeholder groups provided their views on the Consultation Draft Business Plans. Key areas of focus were:
Investment in infrastructure and how the associated costs are recovered from different groups of
customers
Improving the process and timeliness for connecting customers to the distribution network
Network reliability
This feedback was considered within the context of all stakeholder feedback received on the Business Plan as
well as the outcomes from internal analysis and review.
3.4.8 Supplier and large customer engagement
UK Power Networks recognises the importance of the unique relationship it has with electricity retail suppliers. To
this end, UK Power Networks has developed a substantial consultation programme focused on developing a
working understanding of the expectations and needs of suppliers over the next ten years focusing on how it can
better work with them to ensure that customers receive value for money over the long term. UK Power Networks
has therefore proactively sought bilateral meetings with all of the major suppliers and has actively attended
forums representing the smaller suppliers. These efforts have proved successful - to date there have been five
bilateral meetings focused on understanding retail suppliers' views on the Networks' Business Plans. Further,
supplier feedback on the nature and scope of these meetings has been extremely positive. Key feedback from
suppliers through this engagement relates to the impact of DUoS price volatility on their customers. Suppliers
highlighted that a significant proportion of their customer contracts are based on fixed prices or are set
significantly in advance. Sudden and large changes to prices therefore disproportionately impact suppliers’ cash-
flow risk and customer's final bills. For customers deciding to choose a pass through contract this adds to the
uncertainty inherent in the electricity market.
UK Power Networks recognises that DUoS price volatility is driven by a combination of:
A lack of sufficient advanced visibility of DUoS price changes
The revised DUoS Common Changing Methodology
UK Power Networks will continue to actively seek to resolve these issues through industry forums. It will assist in
promoting transparency of indicative changes to its DUoS charges for the 2015 to 2023 period by outlining these
in its 2015 to 2023 Business Plan - this is discussed further in section 6.1.
A number of suppliers have also proposed further changes to the current industry arrangements, including EDF
Energy who's consultants, CEPA, published a paper in September 2012 examining the impact of DUoS price
volatility. In this paper it was proposed that "a more comprehensive approach would instead be to fix the DNOs
DUoS charges much earlier than at present by providing the notice period of future changes in tariffs and
introducing a DNO smoothing mechanism for the 2015 to 2023 period that would allow for DNO: revenue profiling;
certainty of recovering revenue; net present value (NPV) neutrality; and overall financeability.
UK Power Networks supports an approach whereby the industry fixes its DUoS prices 15 months in advance of
Page 21
price application. This approach will require further changes to the industry framework, will need to allow for any
Ofgem changes to incentive mechanisms design and for UK Power Networks to amend its charging methodology.
UK Power Networks believes there is sufficient time to introduce these changes prior to commencement of the
next planning period.
UK Power Networks is planning further rounds of meetings with suppliers on its Business Plans before they are
finalised for submission to Ofgem. This consultation programme is additional and separate to the on-going
engagement with suppliers that is undertaken through the Energy Network Association (ENA).
3.5 How stakeholder feedback has influenced our plans
Through the programme of engagement described above, UK Power Networks has gathered important feedback
and information on stakeholders' views and priorities so as to understand what they want the Networks to deliver
in the 2015 to 2023 period.
The seven most important issues for our customers and other stakeholders are set out in Table 7 below. These
issues were repeatedly raised during the engagement programme.
Table 7 Stakeholder feedback - the seven most important issues
Top seven issues Feedback Incorporating stakeholder feedback
Transparency across
the board
Requested greater transparency around
reporting, decisions and business processes
particularly in connections.
We were the first of the UK DNOs to publish
information on our annual revenue requirements
and prices for the upcoming planning period.
We will undertake further focused improvement
to our external web-site including providing
improved information on our connections
process and network availability.
Path to a DSO Support for the planning to meet the challenges
arising from the transition to a low carbon
economy, which will drive changes in the
Networks' role and responsibilities.
We are committed to the UK’s transition to a low
carbon economy and to a ‘smart grid’ and have
reflected investment to support our transition to a
DSO in our business plans. Further detail is
provided in our Smart Grid Strategy.
Choice in customer
services and
connections
Support the development of a contestable
customer connections market to foster greater
choice in service provider and in improvements
in service outcomes.
We have already significantly improved our
customer connection services by listening to and
acting on feedback from customers. We are
committed to introducing further improvements
over the next planning period as part of the
transformation project.
Vulnerable
customers
Support for even more investment in initiatives
to assist vulnerable customers.
We have established a project specifically
focused on identifying how we can better assist
vulnerable customers.
Customer
connections portal
Support for the introduction of an end-to-end
customer self-service connection portal. This
will provide customers with greater transparency
about the connection process including
timeframes, alternative service providers,
information requirements and cost.
We will introduce an end-to-end customer self-
service connection portal in the first year of the
next planning period.
Infrastructure
development
Questioned whether the Networks' investment
plans will be sufficient to accommodate future
customer connection requests in certain areas
of the network and how the cost of network
investment, required to accommodate future
connections, should be recovered from
customers.
We have revised our business plans to reflect
stakeholder feedback. In particular:
LPN’s Business Plan includes £100million to
undertake the London Infrastructure Plan.
This investment is supported by the existing
planning standards. The investment costs will
be recovered from customers in accordance
with the existing statutory connection charges
methodology
EPN has included £15 million to undertake the
Page 22
Top seven issues Feedback Incorporating stakeholder feedback
Distributed Generation (DG) Infrastructure
Investment, which is required to support the
increased level of DG seeking connection to its
distribution system. This investment is
supported by WTP and cost benefit
assessments.
Efficiency of cost
delivery
Support for more comparative information on
the relative efficiency of the Networks in
delivering their outputs compared to other
DNOs.
UK Power Networks is working with Ofgem to
develop industry annual output report, which will
contain comparative DNO information.
Table 8 below summarises feedback from customers and other stakeholders gathered through UK Power
Networks’ stakeholder engagement process. UK Power Networks has assessed this feedback and where
possible, incorporated it into its future plans. While all the feedback received has been considered, it was not
possible or feasible to incorporate all the feedback received.
Table 8 Stakeholder feedback by output category
Stakeholder Feedback Actions taken Further action to be taken
ENVIRONMENT
UK Power Networks should benchmark
its BCF against companies outside the
electricity distribution sector
We have commenced broadening the
benchmarking approach to include
other utilities sectors
We will report back to the Critical
Friends Panel on the results of the
broader benchmarking approach
What is UK Power Networks doing to
minimise losses?
We are working with Ofgem on this
issue. Ofgem has recently introduced
new annual reporting requirements that
will require us to identify the actions we
have taken to reduce losses
We will submit our first report to Ofgem
in mid- 2014 and will provide this report
to our Critical Friends Panel
SAFETY
Safety should be an essential
component of a DNO’s function
Our Public Safety Team has been
developing and implementing a
broader, more pro-active public safety
strategy
We are working with local communities,
councils, businesses and schools to
improve safety awareness and
understanding and are developing a
number of short safety films to assist in
this process
RELIABILITY AND AVAILABILITY
Can you publish maps of load pinch
points?
We are currently developing a
Geographic Information System (GIS)
which will assist in identifying the
geographic location of load and
capacity requirements
An industry approach to automatic
customer compensation payments in
accordance with the Energy
Guaranteed Standards (EGS)
requirements
We are currently reviewing the
approach applied by gas businesses
We will directly engage with Ofgem and
the other DNOs to jointly develop a
common approach to automatic
customer payments - similar to the
approach applied by gas businesses
Support more onerous reliability and
availability standard compensation
payments
We have commenced paying higher
amounts than required by the relevant
industry regulations and we proactively
contact customers advising them of
their entitlement to receive a payment
The triggers under the relevant industry
regulations are currently being
reviewed with a view to agreeing more
challenging targets. It is anticipated
that any changes to the targets will be
finalised by mid-2014
UK Power Networks should explain We are on track to deliver all our Our final business plans will set out:
Page 23
Stakeholder Feedback Actions taken Further action to be taken
and justify why it is seeking a higher
expenditure allowance in RIIO-ED1
(compared to DPCR-5) when it
underspend its DPCR-5 allowance
outputs for the current period and have
sought to achieve this as efficiently as
possible
Why our proposed RIIO-ED1
expenditure is prudent and efficient
Key drivers for any under
expenditure in DPCR-5
CONNECTIONS
UK Power Networks should improve
transparency around how it calculates
customer connection charges -
particularly where upfront customer
contributions are required
We have recently commenced directly
contacting customers to explain how
connection charges and quotes have
been developed
Further work in this area will be
undertaken as part of our business
transformation project. We are
committed to improving visibility of how
connection charges are calculated
UK Power Networks should provide
more information on the process for
new connections
We recently launched a service called
‘Ask the Expert’ which provides
information on the connection process
and assistance with new connection
applications
We will monitor the outcomes from ‘Ask
the Expert’ and introduce further
changes as required to ensure that it
meets customers’ needs
UK Power Networks should improve
resourcing in connections to reduce
long lead-times
We are currently reviewing our
processes to identify how they can be
improved
We will introduce changes on the basis
of the outcomes of our review
CUSTOMER SERVICES
UK Power Networks should develop a
customer database during 2013
We will develop a customer data base
as part of the overall business
transformation programme
As a minimum, we will implement a
temporary solution for faults by the end
of 2013
UK Power Networks should keep us
better informed during and after power
cuts
We have recently commenced
providing text updates - 24 hours a day
seven days a week - to keep
customers better informed during and
after power cuts
We are assessing how to improve the
customer friendliness of the letters we
send to customers explaining the
cause of outages. We will continue to
seek stakeholder feedback on how we
can improve in this area
UK Power Networks should advise
Stakeholders on whether a single
national DNO contact number is
feasible, as well as providing a cheaper
number from mobiles
UK Power Networks has now assessed
the technical aspects of the challenge
and has agreed to explore the concept
at a whole of industry level
We are currently reviewing whether to
replace our existing contact numbers
(there are currently multiple ) with a
single contact number for all customer
queries
UK Power Networks should develop a
Customer Portal.
This idea features heavily in the
Customer Services journey, which is
developing within the IT infrastructure
as part of the business transformation
initiative
We anticipate that we will test, if not
launch, the Customer Portal by mid
2014
UK Power Networks should publish a
staff directory for its customers and
other stakeholders
We have introduced a number of
improvements to our website during
2012 to facilitate customers contacting
us, including providing business area
contact numbers
UK Power Networks has commenced
developing a staff directory that will be
published on its website
UK Power Networks should review its
telephony service to ensure that
customers ringing in relation to a fault
are not automatically redirected to
another DNO when they are ringing
from a location outside of UK Power
Networks distribution area
We have commenced developing a
new telephony platform
We expect our new telephony platform
to be installed in the second quarter of
2013. This will ensure that our
customers will not be redirected even
when they contact us from outside our
distribution area
UK Power Networks should look at
offering an account manager service
for larger customers
Our connections team currently
operates an account approach in
dealing with specific infrastructure
We will update our approach on the
basis of the outcomes of our current
review
Page 24
Stakeholder Feedback Actions taken Further action to be taken
projects and companies. We are
currently assessing how this approach
could be extended to large customers
and those that have frequent
interactions with us
ENCOURAGING INNOVATION
UK Power Networks should provide a
clear rationale for any strategy to move
from a network operation to a system
operation (or Distributions System
Operator) (DSO) role
Our final business plan sets out how
we intend to transition to a DSO role in
the next planning period
We will commence a gradual transition
to becoming a DSO in accordance with
the investment proposal set out in our
final business plan. We recognise that
the transition will be influenced by the
rate of uptake of low carbon technology
UK Power Networks should provide
further supporting evidence for its
forecasts concerning the projected up-
take of low carbon technologies such
as EVs, heat pumps and solar panels
Our low carbon technology uptake
forecasts have been updated to reflect
expert advice from Element Energy
and stakeholder feedback - particularly
on the rate of uptake of EV. This is
discussed in section 3.4.2
We plan to continually engage with
stakeholders on this topic and use their
input to help shape our assumptions
and forecasts in the future
UK Power Networks should explain
whether it is able to use Energy
Storage on its network and if so how
this would operate in practice
We are currently working on a number
of energy storage initiatives (including
Leighton Buzzard), which have been
awarded funding by Ofgem under the
Low Carbon Network Fund.
We are also trialling a short term
energy storage solution at Hemsby.
The results are positive and our
learning are reflected in our business
plan
Owning and running this ‘proof of
concept’ facility, will allow the business
to learn valuable lessons for future
energy storage projects and facilitate
embedding similar technology across
other constrained parts of our network.
We will regularly update stakeholders
on progress, including through the
Critical Friends Panel sessions
3.6 Stakeholder feedback about our engagement
UK Power Networks has sought on-going feedback from stakeholders about the nature and structure of its
engagement pathways to ensure that it is meeting their expectations as well as satisfying UK Power Networks'
stakeholder engagement principles being:
Materiality: Engaging with stakeholders on issues that they have a material interest in and that are within
UK Power Networks' control or influence
Inclusivity: Involving stakeholders in the internal decision making process
Responsiveness: Committing to act and respond to stakeholders’ views and opinions.
The following tables summarise stakeholder feedback on the Critical Friends Stakeholder Engagement Panel
sessions undertaken in the second half of 2012. These panel sessions formed the core of our consultation
programme for the 2015 to 2023 Business Plan. The feedback is extremely positive.
Page 25
Figure 6 About the Event
Figure 7 About UK Power Networks
3.7 Future consultation
UK Power Networks is committed to on-going and regular stakeholder engagement over the course of the 2015 to
2023 planning period. The submission of UK Power Networks' Business Plans to Ofgem on 1 July 2013 will not
mark the end of its stakeholder engagement programme. The future engagement programme will build on the
benefits derived from consultation since 2011 and ensure the continued involvement of stakeholders through the
Critical Friends Panels, specific issue engagement and a range of other stakeholder engagement pathways. UK
Power Networks is committed to continuing to evaluate the effectiveness of these engagement pathways and
adapt them as required over time to ensure that they remain relevant and meaningful to stakeholders.
Key aspects of UK Power Networks’ future consultation programme for April and May 2013 include:
Street works – 29 April 2013
The City of London – 15 May 2013
The fourth Critical Friends Panel session – which are scheduled for 2, 9 and 16 May 2013.
The calendar of events until the end of 2013, as it currently stands, is shown below and the calendar of events
beyond the end of 2013 will evolve and be informed by issues that are important to customers and other
stakeholders as they arise. UK Power Networks expects stakeholders will be interested in engaging on key issues
such as, amongst other things, the transition to a low carbon economy, smart networks and the evolution to a
DSO.
0% 20% 40% 60% 80% 100%
Was useful
Easy to understand
Improved my understanding
Coverage of relevant material
Clear presentations
Engaging
Opportunity for questions
Further information sources provided
Strongly Agree Agree Disagree Strongly Disagree
0% 20% 40% 60% 80% 100%
Confidence in UKPN's investment direction
Confidence in UKPN's business plan engagement
Understanding of UKPN's low carbon technologyinnovation
Confidence in UKPN's environment & communitycommitments
Confidence in UKPN's network investment
I want to receive more information from UKPN
Confidence that my questions will be answered
Strongly Agree Agree Disagree Strongly Disagree
Page 26
Figure 8 Overview of our stakeholder engagement programme until end 2013
Session 7: TBC
Page 27
4 The outputs we will deliver
4.1 Introduction
This chapter provides an overview of:
The outputs UK Power Networks proposes to deliver over the 2015 to 2023 planning period, together
with the proposed targets against which its output delivery performance will be measured and the
associated incentives
How UK Power Networks will use innovation to deliver its outputs to ensure customers receive value for
money over the next planning period
4.2 Outputs for the 2015 to 2023 planning period
Table 9 below summarises the key output measures against which UK Power Networks will target and measure
its performance delivery in the 2015 to 2023 planning period.
Table 9 UK Power Networks' proposed output measures
Output category Definition Primary output Secondary deliverable
Safety
Minimise the risk associated
with operating distribution
networks to achieve zero harm
to customers, contractors and
staff
Compliance with HSE legislation
and directives
Asset Health, Criticality and Risk
Index – see Network Reliability.
This provides a framework for
managing risk including safety
Number of fatal major and lost
time contractor accidents
Number of public injuries
(resulting from our activities)
Customer
satisfaction
Ensure a high level of customer
satisfaction and service and
undertake effective engagement
with our customers and other
stakeholders
Customer Satisfaction Survey
Complaints Metric
Not applicable
Reliability and
availability
Promote the long term condition
and resilience of the networks,
provide customers with long
term reliability and minimise the
number and duration of supply
Customer interruptions (CI) -
planned
Customer interruptions (CI) -
unplanned
Customer Minutes Lost (CML) -
planned
Customer Minutes Lost (CML) -
unplanned
Health Index (HI)
HI Criticality and Risk Index (RI)
Load Index
Resilience
Worst served customers
Guaranteed Standards of
Performance
Environment
Reduce the environmental
impacts of our electricity
network
Business Carbon Footprint
(BCF)
Innovation Funding
Management of equipment
containing SF6 (i.e. switch gear
and transformers)
Page 28
Output category Definition Primary output Secondary deliverable
Management of oil leakage
Noise reduction
Undergrounding in Areas of
Outstanding Natural Beauty and
National Parks
Minimising landfill
Recycling spoilage waste from
street works
Connections
Ensure the provision of
information around the process
and cost of connecting, the
information required, timeliness
of connections and third party
service
Time to connect
Major connections stakeholder
engagement
Social
Ensuring all customers have
access to affordable electricity
including those that are
vulnerable to supply
interruptions (vulnerable
customers) and / or are fuel
poor
Zero harm
Public safety awareness
Provision of the priority services
register (PSR) and fuel poor
customers
UK Power Networks' proposed outputs align with the six categories defined by Ofgem in its March 2013 RIIO -
ED1 Strategy Decision.
4.3 Stakeholder feedback on our proposed outputs
As discussed in section 3.2 above, UK Power Networks has consulted extensively with its customers and other
stakeholders on the outputs, being the products or services provided to customers, in the 2015 to 2023 planning
period. Sections 3.3 and 3.4 of this Business Plan Update, respectively discuss:
The nature of UK Power Networks' stakeholder consultation on its outputs
Stakeholder feedback received through consultation pathways on its proposed outputs.
In summary stakeholders:
Supported the output categories defined in Ofgem's RIIO-ED1 Draft Strategy Decision.
Supported the primary outputs under each of the six output categories albeit requested more detail in
some areas
Supported the proposed secondary deliverables, albeit some suggestions for additional secondary
deliverables were made. In particular they requested that the secondary deliverables supporting the
environmental output should distinguish between UK Power Networks’ response to the low carbon
economy and its services or activities, over which it has direct control (i.e. services which involve the use
of fluid filled cables), which impact negatively on the environment
4.4 Our proposed output targets and incentives - including historical performance
4.4.1 Safety
We are committed to ensuring safety and minimising the risks associated with operating our Networks to achieve
zero harm to customers, contractors and staff.
Safety relates to the physical, mechanical and electrical safety of network assets. UK Power Networks is bound
by the framework and obligations set out in the Health and Safety Legislation to ensure its network assets do not
present a safety risk to the public or its employees and contractors. This is enforced through the Health and
Safety Executive (HSE), the national safety regulator.
Page 29
2015-23 performance measures
Targeted zero public and staff harm
No formal notices or prosecutions by the HSE under applicable legislation
Reduction in total recordable injury rate by more than 10 per cent
Engage with 1.8 million children, either through face to face or via or on line interaction, on public safety issues over the
planning period
Zero harm
UK Power Networks’ vision is to deliver top third industry performance in the area of safety. Our safety
performance is our highest priority – UK Power Networks recognises the potential safety risk associated with
electricity assets if they are not appropriately managed. UK Power Networks is committed to identifying ways to
eliminate risk to achieve zero harm to customers, contractors and staff.
Loss Time Injuries (LTI) and Total Recordable Injuries (TRI)
Since acquisition by our current owners, we have been on a journey to improve our safety performance. This has
resulted in significant improvement in our accident rate and injuries.
Table 10 UK Power Networks’ actual and forecast safety performance
DPCR-5 Average - EPN DPCR-5 Average - LPN DPCR-5 Average - SPN UKPN’s RIIO ED1
forecast performance
LTIs 14 8 9
Zero harm TRIs 109 39 63
Public safety
UK Power Networks will continue to actively promote public safety including by:
Actively managing our network including through rapid resolution of potential safety issues such as low
conductors and poor condition street furniture (such as link-boxes and streetlights).
Managing the security of our substations to through passive security features, active monitoring and
patrols aw well as maintaining a high level of engagement with the police and other authorities. This will
minimise theft of earthing metalwork may create safety risks for customers
Education programs including at county shows and schools. Our schools program will include both face
to face sessions or line interaction via our interactive website ‘powerup’ and will target 1.8 million
interactions in RIIO-ED1.
Asset Health and Risk
The overall health and condition of UK Power Networks’ assets is an important contributor to staff and public
safety. UK Power Networks has well developed maintenance, refurbishment and replacement activities and
programmes of work which ensure the overall condition of its network assets, the overall health of which is
measured through the Health Index (HI).
In particular, the RIIO Strategy Decision introduces a criticality component which is incorporated into the risk
index. Asset criticality is concerned with the consequence of failure and specifically has regard for safety,
reliability and environmental issues.
The risk index is a secondary deliverable for the network reliability and availability output and is discussed in
detail in section 31 of this document.
General Safety
UK Power Networks’ approach to safety is wider than solely reducing LTIs. We have put significant effort into
promoting the health of those who work for us. We have published an Occupational Health and Wellbeing
Strategy and have launched Fitness to Work assessments for all of our operational staff. Other preventative
measures include a flu vaccination programme that is available to all staff. We have also arranged ‘office walk-
Page 30
arounds’ by physiotherapists to promote good posture. These improvements have been achieved through
continued communication efforts and incentive.
4.4.2 Customer satisfaction
UK Power Networks is committed to being a customer-driven business. We are committed to monitoring and
improving the service we deliver to achieve a high level of customer satisfaction on everything that we do. As
discussed in section 3 we are also concerned with ensuring effective stakeholder engagement across a range of
services and activities which directly impact our customers.
Customer satisfaction with our performance is measured through the broad measure of customer satisfaction
(BMoCS), which is intended to replicate the sorts of measures typically used by customer-facing businesses in
competitive markets. The BMoCS comprises the following three components:
Customer satisfaction survey
Complaints metric
Stakeholder engagement
2015-23 performance measures
Improve performance to top third in all components of the BMoCS including
Customer satisfaction survey
Complaints metric
Stakeholder engagement
Further enhance stakeholder engagement to ensure the service provided to customers meets their expectations during RIIO-
ED1
Continue to expand the contact channels customers can use to talk to us
Broad Measure of Customer Service
Table 11 below shows the BMoCS for each Network for the current and next planning periods.
UK Power Networks' BMoCS targets for the next period highlight its commitment to significantly improve its
performance, particularly in the area of connections and for LPN, general enquiries. In 2012/13, SPN and EPN’s
general enquires performance improved providing confidence that the measures implemented will enable them to
meet the challenging 2015 to 2023 targets. Efficiencies arising from the implementation of best practice systems
and processes as part of the transformation process will also facilitate UK Power Networks achievement of these
targets.
Table 11 UK Power Networks' overall customer satisfaction survey scores
DNO BMoCS component DPCR-5 (Feb. 2012-2013)
UKPN’s forecast performance
for RIIO ED1
EPN Interruptions 8.11 8.55
Connections (minor) 7.20 8.09
General Enquiries 8.18 8.44
LPN Interruptions 7.55 8.05
Connections (minor) 7.19 8.09
General Enquiries 6.80 8.44
SPN Interruptions 7.91 8.55
Connections (minor) 7.25 8.09
General Enquiries 8.04 8.44
Page 31
UK Power Networks will introduce a glide path approach to achieving the RIIO-ED1 targets which will involve
setting increasingly higher targets for the remainder of the planning period to incentivise continual improvement in
its performance.
Resolving customer complaints is important to us. We are committed to getting the job right first time, every time
which is reflected in our commitment to eliminate repeat complaints and complaints awarded to the ombudsman
in the 2015 to 2023 planning period as shown in Table 12 below.
Table 12 Complaints metric
DPCR-5
Average - EPN
DPCR-5
Average - LPN
DPCR-5
Average- SPN
UKPN’s
forecast
performance
for RIIO ED1
Complaints not resolved within 1 Day (%) 67 69 62 40
Complaints not resolved within 31 Days (%) 9 9 9 5
Repeat Complaints (%) 12 13 12 0
Ombudsman Complaints awarded to the
customer (%) 0 1 1 0
Overall Complaints Metric Score (%) 15 16 15 6
4.4.3 Network reliability and availability
UK Power Networks is committed to ensuring the long term condition and resilience of its Networks to ensure that
the number and duration of customer supply interruptions are minimised.
2015-23 performance measures
Maintain LPN having the lowest level of customer interruptions and customer minutes lost in the UK
Reduce EPN and SPN customer interruptions by more than 8 per cent
Reduce EPN and SPN customer minutes lost by more than 10 per cent
Maintain the health of the network during RIIO-ED1
Continue to improve the load index of the networks by reducing the number of LI 4/5 sites
Protect 98 substations sites from the risk of flooding
Reduce the number of 12 hour failures per year on average by more than 30 per cent
Customer Interruptions (CI) and Customer Minutes Lost (CML)
Table 13 below summarises UK Power Networks' actual performance over the current period (2011 and 2012)
and target performance for the next planning period which commit it to deliver further improvements in relation to:
CIs, which refer to the number of customers whose supplies have been interrupted per 100 customers
each year and
CMLs, which refer to the duration of unplanned interruptions to supply each year, measured by average
customer minutes lost per customer where an interruption of supply to the customer lasts three minutes
or longer
This commitment is underpinned by UK Power Networks' Quality of Supply Strategy, which is focused on
achieving:
Greater network automation and remote control to increase its ability to remotely restore loss of supply
Improvements to inspections and faults processes across the Networks including through changes to
working patterns that better align with the volume and timing of fault calls
Page 32
Table 13 Unplanned interruptions performance - current period performance and RIIO ED1 targets
DNO CI and CML's DPCR-5 average
performance
UKPN revised forecast
2015-23 performance
% reduction from
DPCR-5 average
EPN CIs 62.5 57.3 8%
CMLs 45.9 41.2 10%
LPN CIs 24.9 25.1 -1%
CMLs 33.0 31.0 6%
SPN CIs 56.4 52.0 8%
CMLs 45.0 39.7 12%
The improvements in EPN's, LPN's and SPN's CI and CML performance during the current period is shown in
Figure 9 to Figure 11. In particular, they show that the Networks are expected to outperform the CI and CML
targets set by Ofgem for the current period, thereby delivering a more reliable service to customers. This
improvement has largely been driven by recent investment which has focused on the efficient and innovative use
of the existing network assets.
This performance improvement has enabled UK Power Networks to achieve the third lowest CI performance of all
fourteen DNOs and the lowest proportion of customer interruptions lasting more than 12 hours as a percentage of
the number of customers interrupted.
EPN has the fourth lowest average restoration time of all 14 UK DNOs reflecting the significant improvements in
restoration performance over the current period. EPN's average restoration time per customer improved by 26
minutes between 2008/09 and 2011/12 (reducing from an average of 101 to 75 minutes).
Figure 9 EPN’s unplanned interruptions performance
Figure 10 shows that LPN has consistently delivered high levels of network reliability as reflected in its CI and
CML targets set by Ofgem for the current period. LPN has outperformed these targets with outperformance being
most pronounced in 2010 and 2011 due to the mild weather. LPN's RIIO-ED1 targets commitment to improved
reliability and availability of supply, notwithstanding growth in demand on its network.
Figure 10 LPN’s unplanned interruption performance
0
50
100
07/08 09/10 11/12 13/14 15/16 17/18 19/20 21/22
EPN CI - UKPN Initial forecast performance
EPN CI - Actual performance
EPN CI - UKPN Revised forecast performance
EPN CI Ofgem Target
0
50
100
07/08 09/10 11/12 13/14 15/16 17/18 19/20 21/22
EPN CML - UKPN Initial forecast performance
EPN CML - Actual performance
EPN CML - UKPN Revised forecast performance
EPN CML - Ofgem Target
0
50
07/08 09/10 11/12 13/14 15/16 17/18 19/20 21/22
LPN CI - UKPN Initial forecast performance
LPN CI Actual performance
LPN CI - UKPN Revised forecast performance
LPN CI Ofgem Target
0
50
07/08 09/10 11/12 13/14 15/16 17/18 19/20 21/22
LPN CML - UKPN Initial forecast performance
LPN CML Actual performance
LPN CML - UKPN Revised forecast performance
LPN CML Ofgem Target
Page 33
SPN has the fifth lowest average restoration time of all 14 UK DNOs reflecting the significant improvements in
restoration performance over the current period. SPNs average restoration time per customer has improved by
34 minutes between 2008/09 and 2011/12 (reducing from an average of 114 to 80 minutes).
Figure 11 SPN’s unplanned interruption performance
Network health index (HI)
The HI framework is concerned with asset condition. In particular is a framework collating information on the
health (i.e. condition) of distribution assets and for tracking changes in condition over time. The index is based on
the following five categories:
HI1: new or as new
HI2: good or serviceable condition
HI3: deterioration requires assessment and monitoring
HI4: material deterioration, intervention requires consideration
HI5: end of serviceable life, intervention required
UK Power Networks has been reporting against HIs since 2010. By the end of the 2012/13, UK Power Networks
will be ahead of its agreed HI output delivery for all three of its Networks. This is highlighted in Figure 12 to
Figure 14, which also show EPN’s, LPN’s and SPN’s progress against HI output scores monitored by Ofgem over
the current period and the forecast performance HI targets for RIIO-ED1.
Figure 12 EPN’s performance against Ofgem’s DPCR-5 HI scores
0
50
100
07/08 09/10 11/12 13/14 15/16 17/18 19/20 21/22
SPN CI - UKPN Initial forecast performance
SPN CI Actual performance
SPN CI - UKPN Revised forecast performance
SPN CI Ofgem Target
0
50
100
07/08 09/10 11/12 13/14 15/16 17/18 19/20 21/22
SPN CML - UKPN Initial forecast performance
SPN CML Actual performance
SPN CML - UKPN Revised forecast performance
SPN CML Ofgem Target
0%
50%
100%
150%
200%
2011 2012 2013 2014 2015Impro
vem
ent as %
of
HI
targ
et*
EPN Actual
EPN Forecast
Agreed HI Improvement
* HI improvement as agreed with Ofgem
0%
10%
20%
30%
40%
50%
60%
70%
80%
End of DPCR5 End of ED1
Axis
title
HI 1 HI 2 HI 3 HI 4 HI 5
Page 34
Figure 13 LPN’s performance against Ofgem’s DPCR-5 HI scores
Figure 14 SPN’s performance against Ofgem’s DPCR-5 HI scores
UK Power Networks will maintain the profile of its asset health risk for each Network broadly consistent over the
upcoming period. This will involve maintaining the number of assets in each index category broadly consistent.
Load Index (LI)
UK Power Networks is committed to maintaining its LI at current levels in the RIIO-ED1. The LI framework relates
to the utilisation of the assets supplying a demand group and therefore involves assigning each primary or grid
substation a load index number from 1 to 5, representing an increasing level of utilisation or loading.
Table 14 shows EPN’s, LPN’s and SPN’s progress against the LI scores monitored by Ofgem over the current
period and forecast performance for the next planning period.
Table 14 UK Power Networks’ LI performance and forecast future performance
UK Power
Networks
Initial LI
performance at
commencement
of DPCR-5
Revised (as of
2012) LI
performance
forecast at end
of DPCR-5
Forecast LI
performance for
end of RIIO ED1
EPN 87 38 30
LPN 28 27 15
SPN 59 31 25
0%
50%
100%
150%
2011 2012 2013 2014 2015Impro
vem
ent as %
of
HI
targ
et*
LPN Actual
LPN Forecast
Agreed HI Improvement
* HI improvement as agreed with Ofgem
0%
10%
20%
30%
40%
50%
60%
70%
80%
End of DPCR5 End of ED1
Axis
title
HI 1 HI 2 HI 3 HI 4 HI 5
0%
50%
100%
150%
2011 2012 2013 2014 2015Impro
vem
ent as %
of
HI
targ
et*
SPN Actual
SPN Forecast
Agreed HI Improvement
* HI improvement as agreed with Ofgem
0%
10%
20%
30%
40%
50%
60%
70%
80%
End of DPCR5 End of ED1
Axis
title
HI 1 HI 2 HI 3 HI 4 HI 5
Page 35
Figure 15 EPN performance
(number of LI 4&5s)
Figure 16 LPN performance
(number of LI 4&5s)
Figure 17 SPN performance
(number of LI 4&5s)
At the start of DPCR-5 our networks had considerably more heavily loaded sites than other DNOs. Table 14
above shows that over the current period the Networks have outperformed the target number of LI4 and LI5,
meaning that that there are fewer assets in these categories than forecast at the start of the current period. This
means that overall, assets have more headroom capacity (or less loading). Figure 15 to Figure 17 show that UK
Power Networks’ 2015 to 2023 load related investment plans will continue to reduce the number of heavily loaded
sites over the period, ensuring that our load index profile comes more in line with other DNOs. This will be
achieved through a combination of traditional reinforcement and investment in smart network solutions (discussed
in section 5.1.5) and are supported by the assumptions relating to the growth in forecast demand over the
upcoming planning period.
Resilience
Resilience is the ability of the distribution system to continue to supply electricity during a disruptive event (such
as flooding or severe storms) and the speed of recovery to resume normal operations after the event. UK Power
Networks applies a proactive approach to improving its network resilience and in RIIO ED1 will undertake:
Flooding resilience for a further 40 substations in EPN, 18 substations in LPN and 40 substations in SPN
Black start resilience by ensuring all UK Power Networks’ sites meet the 72 hour resilience standards
within the RIIO-ED1 periods
UK Power Networks is committed to maintaining average fault rates on overhead lines in RIIO-ED1 at the current
period average rate.
Worst Served Customers
UK Power Networks supports investment to improve service quality to the worst served customers, and has
undertaken investment in the current period where it is funded to do so under the regulatory arrangements. UK
Power Networks will continue to make such investments in the next planning period.
Guaranteed Standards of Performance
Where customers experience an electricity supply interruption lasting more than 18 hours, they are entitled to a
compensation payment under the Electricity (Standards of Performance) Regulations 2010. Domestic customers
receive a payment of £54 and non-domestic customers receive a payment of £108, and both receive a further £27
payment for every additional 12 hours off supply. UK Power Networks has voluntarily increased the payments it
makes to domestic customers to £100. The standards under the Regulations will become more challenging in the
2015 to 2023 period. Customers will be entitled to compensation following 12 hour supply interruptions and
compensation payments will increase to £75 for domestic customers and £150 for non-domestic customers, with
a further £35 payment for every additional £12 hours off supply.
UK Power Networks welcomes this change and will focus on ensuring that the Networks outperform the new
restoration standard to minimise the number of these incidents, so that long duration outages become
increasingly rare for all customers. In particular, UK Power Networks will aim to restore all customers in under 12
hours and 98 per cent of customers in under 8 hours.
0
50
100
EPN
2010 DPCR5 Start2010 DPCR5 Forecast for 2015Actual 2011/122012 forecast for 2015RIIO ED1 End
0
20
40
LPN
2010 DPCR5 Start2010 DPCR5 Forecast for 2015Actual 2011/122012 forecast for 2015RIIO ED1 End
0
50
100
SPN
2010 DPCR5 Start2010 DPCR5 Forecast for 2015Actual 2011/122012 forecast for 2015RIIO ED1 End
Page 36
4.4.4 Environmental performance
2015-23 performance measures
Top third BCF performance
Continue to recycle 70 per cent of office and depot waste and 98 per cent of street works spoil
Maintain SF6 leakage as a proportion of installed mass
Reduce oil leakage by 2 per cent year on year.
Use allowance for undergrounding in Areas of Outstanding Natural Beauty (AONB) and National Parks
Investigate all noise issues and address all non-compliant sites
Business Carbon Footprint
UK Power Networks is committed to the low carbon transition. In addition to playing a key role in facilitating a low
carbon economy through the connection of low carbon generation, it is also concerned with reducing its own CO2
emissions. Over the current period UK Power Networks has reduced its business footprint by 24 per cent. UK
Power Networks is committed to achieving further reductions including by reviewing the operational areas of its
business that create CO2 emissions.
Table 15 UK Power Networks actual and forecast BCF performance (excluding electricity line losses)
Tonnes CO2
equivalent
DPCR-5 Average
- EPN
DPCR-5 Average
- LPN
DPCR-5 Average
- SPN
DPCR-5 Average
- UKPN
UKPN’s RIIO ED1
forecast
performance
BCF 36,495 18,630 22,687 77,812 76,273
The largest contributors to UK Power Networks’ BCF arise from its transport and fuel usage. Some activities such
as use of temporary generation to restore customers can directly increase UK Power Networks’ carbon footprint.
UK Power Networks’ current forecast BCF performance in the next planning period is based on the average
performance over the current period. UK Power Networks is signing up to the global reporting initiative and is
committed to achieve upper third performance amongst comparable industries.
Innovation to meet decarbonisation
Over the current period, UK Power Networks has significantly increased expenditure on innovation investment
related to low carbon initiatives. In particular, UK Power Networks’ expenditure under the Low Carbon Network
Fund (LCNF) in 2011/12 was £78.2 million or around 0.72 per cent of revenue and increased to £12.7 million
which is around 0.98 per cent of revenue in 2012/13. Further information is provided in section 4.5.
UK Power Networks also monitors a number of environmental indicators including:
Management of equipment containing SF6 (i.e. switch gear and transformers)
Management of oil leakage
Noise reduction
Undergrounding in AONB and national parks
Minimising landfill
Recycling spoilage waste from street works
Over the 2015 to 2023 planning period, UK Power Networks is committed to:
Reducing the impact of our street works through the current on-going program of work
Recycling 98 per cent of its street-works spoil from its term contractors, and is committed to exploring
new ways of treating the remaining waste so that it is re-usable. The learnings from street-works spoil
recycling will be applied to maximise the recycling of waste from major construction projects
A two per cent per annum reduction in the oil loses from pressurised cables and will seek further
reductions through the asset replacement program
Maintaining its SF6 gas leakage at 0.2 per cent of the installed mass by focussing on older items of
switchgear which is designed to lower standards
Page 37
Undertaking undergrounding of overhead lines in AONB.
4.4.5 Connections
UK Power Networks is committed to facilitating competition in the connections market and making it easier for
customers seeking connection by ensuring:
Customers receive high quality information on the process and cost of connecting to our networks
Customer connection are completed in reasonable timeframes that meet customers’ expectations
2015-23 performance measures
Ensure UK Power Networks facilitates a competitive connections environment in its three networks
Achieve upper quartile performance in average time to quote
Achieve upper quartile performance in average time to connect
Provide on-line instant quotations
Meet our improvement commitments to major connections customers
Deliver 100 per cent Guaranteed Standards of Performance compliance
Since formation in 2010, UK Power Networks has focused on improving connection services by undertaking a
number of improvement initiatives including:
The redesign of its website to include improved information on the connection process including in
relation to: connection timeframes; customer information requirements; and third party providers. This
will assist customers understand the choices they have, the information we need from them and our
commitments to them
The introduction of a web based self-service system designed to improve the process for less complex
connection enquiries by enabling customers to create an illustrative quotation
Stakeholder engagement to understand what our stakeholders and customers, including third party
providers, consider to be the priority areas for improvement in the areas of connection services.
Customers and other stakeholders have told us that this is an area in which we could improve further. UK Power
Networks agrees with stakeholders and is committed to undertaking further improvements over the next planning
period. In particular, UK Power Network is committed to implementing an End-to-End Connection Project, as part
of its business transformation project, which will lead to further improvements.
To this end, UK Power Networks’ performance targets for the next planning period as shown in Table 16 and
Table 17 commit it to delivering even further performance improvements that would enable it to reach top-third
performance amongst the 14 UK DNOs.
Table 16 Average time to quote (days)
DPCR-5 Average -
EPN
DPCR-5 Average -
LPN
DPCR-5 Average -
SPN
UKPN’s RIIO ED1
forecast
performance
Low voltage single services 2.4 2.5 2.7 2.4
Low voltage multiple services 6.6 6.6 8.2 5.2
Table 17 Average time to connect (days)
DPCR-5 Average -
EPN
DPCR-5 Average -
LPN
DPCR-5 Average -
SPN
UKPN’s RIIO ED1
forecast
performance
Low voltage single services 42 49 49 42
Low voltage multiple services 53 70 63 53
Page 38
4.4.6 Social commitments
UK Power Networks understands that electricity is an essential service which is important to its customers. UK
Power Networks considers that a basic customer requirement for all its customer groups, especially those that are
vulnerable to supply interruptions, is an affordable price and dependable electricity service.
2015-23 performance measures
Continue to improve the service provided to vulnerable customers
Maintain community engagement during RIIO-ED1
Work proactively with third parties to reduce the level of fuel poor in our three networks
Priority Services Register (PSR) for vulnerable consumers
UK Power Networks maintains a PSR which captures important information on its vulnerable customers in order
to assist it in providing services to these customers. There are currently around 280,000 vulnerable customers on
its PSR. As a respected corporate citizen, UK Power Networks is committed to doing everything possible to
identify and support vulnerable customers. Over the current period, UK Power Networks has improved its service
offerings to vulnerable customers including by introducing:
A welcome pack including luminous stickers with UK Power Networks’ contact details and practical
advice on preparing for a power cut
A priority number enabling an immediate point of contact
Real-time updates offered by way of call backs or SMS messages
Mobile generators to care homes, critically ill customers and those with a medical dependency
Hotel and meal allowances in certain circumstances
Home visits from an engineer before leaving the site
An electronic flagging system was also introduced which enables UK Power Networks to easily identify vulnerable
customers in its database and on its fault management system.
Over the next planning period, UK Power Networks will continue to build on these recent improvements. In
particular, it is committed to, amongst other things:
Developing new, and strengthen existing, partnerships with suppliers, local government authorities and
community organisations to improve services to vulnerable consumers
Assessing how vulnerable and fuel poor customers can benefit from the introduction of smart meters
including through the introduction of innovative tariff structures
Using all available channels to promote the PSR and clearly and simply explain our priority service
offerings. For instance, UK Power Networks will seek to do this during calls with customers, in SMS
correspondence, via its website and via twitter
Where practical, enhance its service offerings to:
Offer notices in braille, for visually impaired customers
Simplify telephone options, so it is simpler and quicker to contact a customer advisor
More simply explain to customers our pricing methodology.
Fuel poor
Fuel poor customers are those who would need to spend 10 per cent of their income on fuel to maintain an
adequate level of warmth (21 degrees in the main living area, and 18 degrees for other occupied rooms). It is
estimated that approximately five million households in the UK are fuel poor and a large percentage of these
customers (around 80 per cent) are also vulnerable.
UK Power Networks is committed to undertaking initiatives to reduce fuel poverty. Key areas of focus in the next
planning period include:
Assessing how smart meters can be used to reduce fuel poverty. UK Power Networks will seek to work
jointly with suppliers, local government authorities and community organisations on this matter
Providing greater targeted information on how energy efficiency and demand side activity can be used by
these customers to better manage their energy consumption and thereby reduce their electricity bill.
Page 39
Community engagement
As an essential service provider, UK Power Networks is committed to helping sustain livelihoods and lifestyles for
many people in the East and South East of England and London. UK Power Networks strengthens local
economies and communities through infrastructure investment, as well as through everyday actions including
supporting:
The British Red Cross assistance for vulnerable customers
Wildlife trusts in our distributions area
Public safety education in schools and county shows
Charity aid foundations
UK Power Networks is pleased to advise that it has recently established a community grant program that provides
funding (from shareholder returns) for community based projects relating to low carbon projects, vulnerable
customers and communities. Quarterly grants of £1,000 to £10,000 are available under the scheme depending
on the project’s size and merit with a total of £100,000 available for each Network in the first year of the scheme.
The grant program is about bringing ideas to life and the possibilities are endless.
4.5 Innovation
UK Power Networks has a strong track record of network innovation and has made extensive use of incentives
such as the Innovation Funding Incentive, Registered Power Zone and Low Carbon Network Fund to develop
bespoke demonstration projects and selectively participate in major European research programmes. UK Power
Networks is committed to continually implementing new ideas or methods that improve the way it operates its
networks and transports electricity. UK Power Networks uses innovation to deliver its vision, improve its customer
satisfaction, deliver cost efficiencies, optimise investment and network planning and meet the challenges of the
low carbon economy and keep customers’ bills down. UK Power Networks has been successful in winning
funding in each year of the first three years of the Low Carbon Network Fund Tier 2 competition. The three
projects for which it has been awarded funding: Low Carbon London; Flexible Plug & Play Networks; and Smarter
Network Storage, explore the scope for both technological and commercial innovation to enhance the capability of
electricity distribution networks and the wider system to accommodate new low carbon technologies such as
electric vehicles, heat pumps and renewable generation.
4.5.1 Innovation investment over the current period
Over the current period, UK Power Networks has significantly increased expenditure on innovation. Total
innovation expenditure (LCNF tier 1 and 2 and IFI) has increased from £3.3 million in 2008/09 (or 0.5 per cent of
allowed revenue) to £15.8 million in 2012/13 (or to 1.2 per cent of allowed revenue). IFI and LCNF Tier 1
expenditure has increased from £3.9 million in 2010/11 to £5.4 million in 2012/13. The remaining expenditure
relates to LCNF Tier 2 and has risen from £1.1 million to £10.4 million over the same period. The efficiency and
value of this expenditure was tested through the LCNF Tier 2 competitive bidding process. This shown by Figure
18.
Figure 18 UK Power Networks’ innovation related expenditure
A short summary of UK Power Networks' investments under the LCN fund and IFI is provided below:
0
5
10
15
20
25
Ea
rly S
tart
05/0
6
06/0
7
07/0
8
08/0
9
09/1
0
10/1
1
11/1
2
12/1
3
13/1
4
14/1
5Innovation S
pend (
£m
)
IFI LCNF Tier 1 LCNF Tier 2
Page 40
UK Power Networks' current period LCNF tier 1 investments
To date, the following five projects have been registered:
Short-term energy storage on the distribution network (June 2010). The focus of this project is
investigating the use of storage, as an alternative to traditional network reinforcement, to provide
additional network capacity (thermal or voltage support) for limited periods where the demand is
uncertain.
Distribution network visibility (September 2010). The focus of this project is assessing the benefits of
collecting, utilising and visualising available network data to improve our operational and investment
decisions e.g. to improve time required to connect new customers.
LV current sensor technology evaluation (December 2011). This is a joint UK Power Networks' and
Western Power Distribution project - and UK Power Netwroks' first joint project. It evaluates a range of
network monitoring solutions that assist in understanding the available network capacity, thereby
minimising customer disruption or delay when low-carbon technologies are deployed in the future.
Validation of Photovoltaic (PV) connection assessment tool (January 2012). This project tests the
validity of UK Power Networks' new planning tool, which assesses the impact of concentrations of small
scale generation on its distribution networks e.g. solar panels, which enable it to provide improved
services to customers.
Smart urban low voltage network (July 2012). This is a joint project with TE Connectivity, to develop a
new solid-state switching technology. This project will increase flexibility with respect to remote switching
and re-configuration of the LV network. Solid-state switching technology provides greater visibility of
power flows on the network, using the near real-time communications and built in sensors. This enables
extensive load monitoring so as to better understand the live state of the LV network.
UK Power Networks' current period LCNF tier 2 investments
To date, Ofgem has awarded UK Power Networks funding for the projects under the LCNF Tier 2 scheme:
Low Carbon London (October 2010) – This was UK Power Networks' first flagship project. Ofgem
awarded UK Power Networks £24.9 million of the available £64 million (to all DNOs) to purse smart
network initiatives which focused on innovative ways to deliver sustainable electricity to businesses and
communities in a low carbon future UK Power Networks has contributed an additional £5 million to
support this project
Flexible Plug and Play (November 2011) - This was UK Power Networks' second flagship project. Ofgem
awarded UK Power Networks £6.8 million to trial innovative technical and commercial solutions in order
to provide cheaper and faster connections of renewable generation, such as wind power, to the
electricity distribution network
Smarter Network Storage – (November 2012). This project involves the installation of a larger scale
storage plant to solve a network constraint. Electricity storage could provide value for customers by
reducing the need for network reinforcement and has wider system benefits such as providing network
services such as reserve and response to help balance electricity supply and demand
UK Power Networks will continue to bid for expenditure to be approved under the LCNF where it identified
projects which will deliver long term benefits to customers.
UK Power Networks' current period IFI projects
UK Power Networks expenditure on approved IFI projects falls into three high level areas:
Innovation and current assets
Managing customer demand through innovation
Using innovation to release extra capacity in our networks.
Further information on UK Power Networks’ innovation expenditure in the current period is set out in:
UK Power Networks' Innovation Strategy, which will also be published on 1 July 2013
UK Power Networks IFI / LCNF Annual Report April 2011 to March 2012.
Page 41
4.5.2 Innovation investment in the 2015 to 2023 planning period
UK Power Networks is seeking a regulated Network Innovation Allowance of 0.5 per cent of total regulated
revenue over the upcoming planning period. As noted, UK Power Networks is forecasting to spend around 0.5
per cent of its total regulated revenue over the current 2010 to 2015 period and has spent around 0.4 per cent in
2010/11 and 2012/13.
The innovation mechanisms that will apply in the 2015 to 2023 period are different to the mechanisms applied by
Ofgem in the current period and include:
The Network Innovation Competition (NIC). This will replace tier two of the LCN Fund. The NIC will
provide competitive funding for large scale low carbon and environmental projects
The Network Innovation Allowance (NIA). This will replace the IFI programme and tier one of the LCN
Fund. This will provide a fixed annual regulatory allowance of between 0.5 and 1.0 per cent of allowed
annual revenue for each year of the 2015 to 2023 planning period
The Innovation Roll out Mechanism (IRM). This will provide funding for business as usual innovative
projects that are not funded under either the NIC or NIA. Funding is provided under a revenue
adjustment mechanism whereby DNOs will be able to apply for funding at specified times (application
windows) during the price control where the costs are material (proposed expenditure multiplied by the
DNOs efficiency rate is greater or equal to one per cent of revenue base) and satisfy defined criteria
including supporting the delivery of outputs.
UK Power Networks is only seeking 0.5 per cent under the NIA and will actively bid for funding for specific
projects available annually on competitive basis via the NIC where it identifies projects that satisfy the required
criteria and that will assist it to deliver its outputs in a manner that provides long term benefits for customers. UK
Power Networks considers that having a low regulated allowance under the NIC will deliver the best value for
customers.
UK Power Networks considers that this level of funding will support it achieve its vision of delivering top-third
performance amongst the 14 UK DNOs in the area of safety, network reliability, customer service, cost efficiency
and employee engagement. It will also strongly position UK Power Networks to address the challenges, changes
and opportunities that lie ahead over the next ten years whilst continuing to deliver long term benefits for
customers.
Further information on UK Power Networks’ innovation strategy for the next period is set out in UK Power
Networks' Innovation Strategy, which will be published, together with the Business Plans, on 1 July 2013.
Page 42
5 Expenditure requirements
5.1 Revisions to our proposed expenditure
Based on stakeholder feedback and our own further reviews, UK Power Networks has revised the capital and
operating expenditure forecasts in the 2015 to 2023 Business Plans to reflect the following:
Changes to major projects
Revised unit costs
Network regional characteristics
Revised volumes
Each of these is discussed below.
5.1.1 Major projects and investments
UK Power Networks has listened to its customers and other stakeholders and has undertaken further internal
analysis of its key reinforcement projects. This has resulted in material changes to the proposed expenditure for
the following projects
London Infrastructure Plan - LPN is proposing to only include three of the six projects previously
proposed in its Consultation Draft Business Plan. The impact of this is to reduce expenditure from £170
million to around £100 million (excluding land purchase and other associated costs)
Distributed Generation (DG) Infrastructure - EPN is proposing a reduction in expenditure from £50 million
to £15 million
The nature and results of the assessment undertaken of each of the following projects is discussed below:
London Infrastructure Plan
The London Infrastructure Plan project is our central London investment strategy to ensure that the London
network, particularly the central business district (CBD), has capacity and resilience that is comparable with other
world cities. There are currently concerns relating to:
Faults with long restoration times primarily due to the complexity of the LV interconnected network
Available capacity required to cater for load growth
LPN’s Consultation Draft Business Plan included a draft plan to enhance network resilience, network capacity and
customer service for London by:
Increasing capacity at six main substations (Vauxhall Nine Elms, White City, West End, City of London,
West Ferry Road, Calshot Street) at an estimated cost of around £170 million
Increasing network automation and remote control to improve the quality of supply and network
resilience at an estimated cost of around £42 million.
LPN has revised the scope of the proposed investment required for the London Infrastructure Plan based on
outcomes and advice from:
WTP studies - There was strong support from the London Infrastructure Forum for this investment given
the importance of this investment for the economic growth and prosperity of the wider UK economy over
the long term. The nature, scope and outcomes of this consultation is discussed in sections 3.3 and 3.4
above
Page 43
Network options analysis – UK Power Networks has assessed different investment options to improve
the resilience – performance and capacity – of LPN’s network assets. It engaged an independent
engineering consultant, Sinclair Knight Merz (SKM), to provide an expert review of the possible
investment options for addressing the issues. SKM identified and reviewed the costs versus the benefits
of the available options which were categorised as short, medium and long terms solutions
Stakeholder engagement – UK Power Networks extensively engaged with its stakeholders, including
through the London Infrastructure Forum which is discussed in section 3.3 above on an appropriate
investment solution. UK Power Networks recognises that any investment solutions must be line with
requirements of customers and key stakeholders
As a result of these outcomes UK Power Networks has revised its investment strategy by removing three projects
from this updated business plan. In the case of the City of London project UK Power Networks is able to extend
an existing network primary substation, reducing the expected time to connect once a customer has made a
formal connection request. The proposed investments are summarised in Table 18 below.
Table 18 London infrastructure development revised plan
Project name Initial firm capacity
to be installed (n-1)
Latest status in
UKPN business plan
Costs to DUoS
customers
(£ million)
Cost to connection
customer(s)
(£ million)
Vauxhall Nine Elms 66 MVA Included in RIIO-ED1 33.0 TBC
White City 66 MVA Included in RIIO-ED1 27.5 2.5
West End 60 MVA Included in RIIO-ED1 32.0 0
City of London 33 MVA
Waiting for initial
customer enquiry
before agreeing
funding allocation
Not applicable Not applicable
West Ferry Road 66 MVA
Waiting for initial
customer enquiry
before agreeing
funding allocation
Not applicable Not applicable
Calshot Street 66 MVA
Included in DPCR-5/
RIIO-ED1 Business
Plan
8.0 0
Total 423 MVA 100.5 TBC
Earls Court 66 MVA
Waiting for initial
customer enquiry
before agreeing
funding allocation
Not applicable Not applicable
DG infrastructure investment
This project is intended to address existing network constraints in the East of England where there has been a
high number of renewable generation developments. While UK Power Networks supports the timely and efficient
connection of these medium to large scale generation proponents to its network, it emphasises that significant
network investment is required to ensure the maintenance of the quality and reliability of supply and network
safety standards for existing customers.
UK Power Networks reviewed 16 investment projects ranging in capacity to be installed between 90MVA and
7MVA. UK Power Networks has revised the size of the investment based on outcomes and advice from:
WTP studies - There was clear support from customers for network investment to provide additional
infrastructure to support the network against LCT growth. Customers indicated that they were willing to
pay an additional £116 million across our three networks, and for EPN alone they were prepared to pay
an additional £52 million, over the 2015 to 2023 planning period.
Page 44
Cost-benefit / options analysis – UK Power Networks undertook an internal cost benefit assessment of
the different investment options. This assessment involved:
Determining the cost of each network investment project and assumed that the costs would be incurred
in a single year
Determining the benefits associated with each project, being the reduction in carbon emissions from
the connection of low carbon generation enabled by the network extension. UK Power Networks
assessed the benefits using both the DECC energy market traded and non-traded carbon values (high-
low scenarios in both cases) over a period of 16 and 24 years
Assuming phased use (over several years) of the additional network investment
Further stakeholder engagement at two UK Power Networks’ DG forums
Technical expert review – UK Power Networks is finalising an external technical review by SKM of the
four proposed projects to ensure best value for customers is achieved in RIIO-ED1. This review will be
completed for the final July business plan
Our Business Plan Update proposes four projects should be developed during RIIO-ED1 installing a further
187MVA of capacity at a total cost to consumers of £15.35 million. These projects represent best value for money
realising a positive return using the DECC non-traded carbon values.
5.1.2 Unit costs
UK Power Networks has reviewed the unit costs underpinning its 2015 to 2023 expenditure forecasts to ensure
that they are the most efficient achievable costs. The unit costs underpin both the capital and operating
expenditure as follows:
Capital expenditure – network replacement, network refurbishment and network reinforcement
expenditure
Operating expenditure – day to day costs of running the network including faults, tree cutting and
inspection and maintenance
The review involved a:
Top-down assessment of the efficient industry costs for network activities, as reported annually by DNOs
A detailed review of all cost components (i.e. a bottom-up cost build-up) for 22 network services and
activities, which represent around 80 per cent of UK Power Networks’ total expenditure for the next
planning period. This involved assessing and comparing the costs incurred across the Networks for
these activities as well as average industry costs
Importantly, the review highlighted differences between the costs calculated using the detailed bottom-up
approach compared to the top-down approach, with the top-down approach resulting in a lower cost outcome.
UK Power Networks has therefore adopted these costs in developing its expenditure forecast for the 2015 to 2023
period and these will provide better value for money (through costs savings) for its customers.
UK Power Networks’ 2015 to 2023 expenditure is based on unit costs that represent the upper quartile industry
targets adjusted for regional cost impacts (which apply only to LPN and SPN). UK Power Networks is continuing
to review these target unit costs together with its stakeholders and consultants and any revisions will be
incorporated in its final 2015 to 2023 business plans.
5.1.3 Regional differences impacting costs
UK Power Networks has updated its expenditure forecasts to reflect the regional differences that impact the cost
of undertaking the work required to deliver its outputs. These differences influence the level and type of required
activities and associated costs associated with:
Transport and travel – increased costs associated with working in narrow streets, traffic congestion, and
parking restrictions
Excavation – increased costs associated with working in high density urban areas, and increased cable
installation depth
Operations – increased costs associated with scheduling work, accessing sites, and gaining consent
from multiple interested parties such as property owners and local authorities
Resources – increased costs associated with higher labour rates
Page 45
Security – increased costs associated with higher network asset security requirements
Cable routes – increased costs associated with building tunnels to allow the installation of, and access
to, underground cables
Properties – increased costs associated with land and buildings
Contractors – increased costs associated with higher labour rates (due to shortage of skilled labour)
To calculate the cost impact associated with regional factors, UK Power Networks has applied the same top down
approach applied by Ofgem in its recent gas distribution determination. This approach is set out in Ofgem's
"RIIO-GD1: Initial Proposals – Step-by-step guide for the cost efficiency assessment methodology". This
approach was chosen as it provides a straightforward, robust and transparent approach for calculating regional
cost differences.
5.1.4 Revised volumes
UK Power Networks has revised the volumes underpinning its expenditure forecast to reflect outcomes from:
CBA analysis
Options analysis
External review and assurance
Benchmarking of asset life duration
UK Power Networks has worked extensively with consultants to review both its network asset management
strategy and its forecasting models to ensure they support robust and efficient forecast volumes of work to be
undertaken over the upcoming planning period.
5.1.5 Incorporation of smart metering
Since UK Power Networks published its Consultation Draft Business Plans there has been further clarification on
the services that DNOs will need to provide as a result of the implementation of the smart metering programme in
the first half of RIIO-ED1. UK Power Networks has adopted the following key principles in determining its smart
metering strategy:
The interests and experience of the customer are paramount. Work undertaken during RIIO-ED1 must
create a good customer experience and customer benefits must be realised early where possible, to help
encourage positive adoption of smart metering
Smart metering will yield data and functionality that provides a significant opportunity for business
benefits and these opportunities must be seized
Smart metering provides the vanguard in moving the UK distribution networks towards a smart grid,
capable of supporting load shifting, pervasive LCTs and active network management. Investment must
be made to take advantage of these opportunities in RIIO-ED1 and provide a sustainable platform to
maximise opportunities in RIIO-ED2
Smart metering provides a new infrastructure that benefits not just DNOs, but customers, suppliers and
other participants
To measure these principles, we have included benefits in our business plan in excess of those set out in
the ENA’s paper ‘Analysis of Network Benefits from Smart Meter Message Flows Interim Review
(Phasing and Categorisation)’ and seek wherever possible to meet the benefits that can be distilled from
the Department of Energy and Climate Change (DECC) Impact Assessment (IA)
During the rollout, it is expected that there will be an additional 20,000+ interventions per year. These must be
carried out efficiently and effectively with trained staff who deliver a good customer experience and in a safe
manner. A dedicated unit will be established to manage this work for the rollout period. Staff will be transferred
from existing units to provide business knowledge, mentoring and leadership to new staff. A mix of direct and
contractor labour, broadly 60 to 40 per cent, will initially be developed to match a two per cent intervention rate.
UK Power Networks has assessed each area of cost and sought ways to optimise spend, consistent with
delivering a quality consumer experience and the overall benefits. The main cost drivers in RIIO-ED1 are
summarised in Table 19 below.
Page 46
Table 19 Smart metering investment requirements
Area DPCR-5
total (£m)
ED1
total (£m)
Comment
Interventions 7.7 60.2 Establish a workforce and carry out 160,000 additional
interventions
Indirects (Inc. training) 8.0 14.1 Dedicated Interventions team and the recruitment,
training of the direct workforce
Industry interface and income
management
1.0 0.5 Support additional data queries and the Smart Energy
Code (SEC)
Call centre 0.1 1.0 Temporary additional agents to manage interventions
Network Condition and Planning - -
DCC Fixed charge 0.3 6.6 Based on 7.7m meters at bands of 2p, 5p, 10p until
2020, then 20p post 2020
DCC transaction costs 0.1 2.3 Energisation checks and asset data
IT Costs 7.5 21.0 Mandated change and building a platform to support
smarter networks
Total 24.7 105.7
UK Power Networks has applied a rigorous approach to identifying and quantifying potential benefits. We have
reviewed the benefits in the DECC IA and in the ENA submissions to the programme to identify the applicability
and value to UK Power Networks. We have further sought to identify additional benefits and to ensure smart
meter opportunities are fully fed into our other corporate initiatives. We have assessed the benefits to other
parties, for example consumers and suppliers, as well as to ourselves. We estimate that during the ED1 period
we can deliver the following benefits:
A total of £97.1 million of benefits for all parties against the DECC IA estimate of £107million and the
ENA paper ‘Analysis of Network Benefits from Smart Meter Message Flows Interim Review (Phasing and
Categorisation)’ estimate of £67 million
This includes benefits of £42.5m to the UK Power Networks’ business
In addition to these financial benefits, we believe we can deliver substantial qualitative benefits to consumers, in
particular proactive targeted messaging in fault situations. We can also position the business to address the
opportunities of the network of the future at the start of RIIO-ED2.
5.1.6 Implementing a smart grid strategy to reduce network investment
Within the business, UK Power Networks has developed a comprehensive Future Network Development Plan
which provides the overall framework for our Smart Grid Innovation Strategy. This plan, which we referred to in
our November 2012 Consultation Draft Business Plans, comprises a suite of documents which collectively map
out our priorities for smart grid implementation and further research and development over the RIIO-ED1 period.
Importantly, given the inherent uncertainty as to the rate of adoption of low carbon technologies over the medium
term, the plan identifies how our priorities would flex to deal with varying future energy scenarios and so ensure
an optimal level of investment in smart grid solutions.
Complementary to our Future Network Development Plan is UK Power Networks’ approach to future load
forecasting. We have worked with acknowledged experts in this field to develop our forecasts at a granular level
thereby enabling us to identify those particular parts of our network which, under varying future energy scenarios,
will more quickly come under pressure as both low carbon technologies and wider economic drivers of load
growth eat into currently available network capacity headroom.
Collaboration with Smart Grid Forum and Development of Models
As well as being represented on the joint Ofgem / DECC chaired Smart Grid Forum, UK Power Networks has
engaged fully with its various workstreams. This has included developing future energy scenarios; examining the
Page 47
overall business case for smart grids; identifying potential regulatory and market barriers, and solutions; and
assessing the scope for smart grid investment strategies to reduce overall requirements for network expenditure,
both in the longer term and over the RIIO ED1 and ED2 periods. Our Low Carbon Network Fund projects continue
to provide a valuable source of experience which we are able to share with the Smart Grid Forum workstreams
and so ensure that the industry as a whole benefits from our work.
Whilst all of the Smart Grid Forum workstreams are important, and indeed interdependent to some extent, of
particular importance has been the development of a parametric model of the GB distribution networks to provide
a high-level assessment of the impact of low carbon technologies, and the relative cost-effectiveness of a range
of both conventional and smart network investment options to manage that impact. The model, known as
‘Transform’, can be used to compare the relative benefits of alternative smart interventions under varying future
energy scenarios. Whilst it can provide an indicative level of investment over a given period of time (such as
RIIO-ED1) the parametric nature of model means that it is better utilised in its design context – namely as a
means of comparing longer-term investment strategies.
Notwithstanding its longer-term horizon, UK Power Networks has carefully studied the outputs of Transform from
a RIIO-ED1 perspective in order to compare its predicted savings over conventional investment compared with
those of our own smart grid strategy. Our analysis shows that UK Power Networks anticipates similar savings to
those predicted by the Transform model over the RIIO ED1 period, albeit our solutions are more appropriate to
our networks and the RIIO-ED1 timeframe than those promoted by the model.
UK Power Networks’ RIIO ED1 Smart Grid Strategy
Solutions which are of particular importance to our network over the RIIO-ED1 period include: Demand Side
Response with Industrial and Commercial Consumers (incorporating Generator Network Support); Real Time
Thermal Ratings of Overhead Lines; Real Time Thermal Ratings of System Transformers; Fault Current Limiters;
Enhanced Network Meshing; and Voltage Optimisation. Complementary to these smart grid solutions, UK Power
Networks will invest in appropriate enabling technologies over the RIIO-ED1 period to ensure that our smart grid
strategy remains optimal over the RIIO-ED2 period when low carbon technologies are expected to have a much
greater impact. A priority over RIIO-ED1 will be to increase visibility of network load flows and voltage levels
through advanced monitoring and communications systems so that emerging network constraints can be
foreseen and addressed in good time. UK Power Networks will make full use of data emanating from smart
meters, the rollout of which should be completed during 2019, as part of its enhanced network visibility strategy.
Over the RIIO-ED1 period, by investing in smart grid alternatives, UK Power Networks anticipates savings across
its three licensed distribution networks of around £125 million compared with a conventional approach to network
reinforcement. UK Power Networks also anticipates that it will benefit from £10 million of smart savings on non-
load related expenditure through the use of partial discharge, giving a total saving of c. £135 million.
Benefits from Existing Smart Solutions
As one of GB’s leading exponents of smart grids, UK Power Networks has already established a baseline of
smart network solutions which have provided, and will continue to deliver, significant network investment
efficiencies. Two particular examples which will be of particular relevance and further developed over the RIIO-
ED1 period are Enhanced Network Meshing and Transformer Thermal Modelling.
The former is being continuously developed as a means of maintaining the unique benefits of LV interconnected
HV feeder groups in Central London. This arrangement is a specific form of network meshing that combines the
benefits of high HV and LV network utilisation, and no-break supplies under single HV circuit fault conditions. As
such the system provides similar levels of service to unit-protected circuits but without the redundant network
capacity inherent in unit-protected schemes. Systems are developed which combine extensive automation and
simplified interconnection which enable high utilisation levels to be maintained along with rapid post-fault
restoration of supplies.
5.1.7 Real price effects
Key elements of UK Power Networks’ cost base for the next planning period will increase at a greater rate than
the retail price index (RPI), which measures general prices in the economy, due to the specialist labour and
materials required to operate our Networks. UK Power Networks engaged NERA Economic Consulting (NERA) to
independently estimate the real price effects (RPEs), being the real price movements, relative to RPI for the next
planning period for:
Page 48
Labour
Materials
Plant and equipment
NERA’s analysis (methodology and data sources) is consistent with the approach applied by Ofgem in the recent
RIIO electricity transmission and gas distribution price reviews. NERA developed a range of scenarios: midpoint
and upper and lower bounds. Separate RPEs were calculated for network investment expenditure and operational
expenditure reflecting the different composition of inputs required to undertake activities relating to this
expenditure.
UK Power Networks has adopted NERA’s mid-point RPE estimates as shown in Table 20 below. These RPEs
have been reflected in UK Power Networks’ capital and operating expenditure forecasts, which are separately
detailed in section 5.2. The RPE impact is offset, in part, by efficiency savings also independently calculated by
NERA. The RPEs applied by UK Power Networks are lower than those applied by Ofgem in its RIIO electricity
and gas transmission Decision (on a consistent weighting of activity).
Table 20 RPEs for the 2015 to 2023 planning period
Operational activities (%) Network investment (%)
RPE applied by UKPN (NERA) 1.2 1.0
Page 49
5.2 Impact of changes on 2015 to 2023 proposed capital and operating expenditure forecast
Sections 5.2.1 to 5.2.3 set out EPN’s, LPN’s and SPN’s total forecast expenditure requirements (capital
expenditure (capex) and operating expenditure (opex)) for the next planning period which reflect the changes
discussed in section 5.1.
5.2.1 EPN’s 2015 to 2023 proposed expenditure forecasts
EPN’s total proposed expenditure for the next planning period is £3.09 billion. This is:
An increase of £0.29 billion or ten per cent compared to the current 2010 to 2015 period expenditure,
adjusting for the difference in the length of the planning period. The increase is primarily driven by the
DG Infrastructure investment, increased work volumes and smart meter readiness including interventions
A decrease of £0.01 billion compared to UK Power Networks’ Initial Forecast. This decrease in required
expenditure is largely driven by a change in scope of the DG Infrastructure investment, a revision of unit
costs and further assessment of the volumes of work underpinning the business plan. These changes
are discussed in detail in section 5.1 of this Business Plan.
Table 21 below sets out EPN’s forecast capex, by building block, for the next planning period compared to actual
expenditure over the current period and its initial forecast (set out in its Consultation Draft Business Plan).
Table 21 EPN: Revised capital expenditure requirement 2015 to 2023 - by building blocks
£ billion DPCR-5
expenditure
Initial 2015-23
expenditure
forecast
Revised 2015-23
expenditure
forecast
% difference:
DPCR-5 expenditure
and revised 2015-23
expenditure forecast
Load related capex 0.40 0.60 0.59 +46%
Non load related capex 0.80 0.90 0.91 +14%
Network operating costs 0.70 0.60 0.55 -22%
Indirect costs 0.80 0.80 0.82 +3%
Non-operational capex 0.10 0.10 0.13 +27%
RPEs - 0.10 0.09 -
Total 2.80 3.10 3.09 +10%
Figure 19 EPN Initial 2015 to 2023 forecast (£3.10
billion)
Figure 20 EPN Revised 2015 to 2023 forecast
(£3.09 billion)
0.6
0.9
0.6
0.8
0.10.1
Load related capex
Non load relatedcapexNetwork operatingcostsIndirect costs
Non operational capex
RPEs
0.6
0.9
0.5
0.8
0.10.1
Load related capex
Non load relatedcapexNetwork operatingcostsIndirect costs
Non operational capex
RPEs
Page 50
5.2.2 LPN’s 2015 to 2023 proposed expenditure forecasts
LPN’s total proposed expenditure for the next planning period is £2.14 billion. This is:
An increase of £0.34 billion or 19 per cent compared to the current 2010 to 2015 period expenditure,
accounting for the difference in the length of the planning period. The increase is primarily driven by the
London Infrastructure Plan, increased work volumes and smart meter readiness including interventions.
A decrease of £0.16 billion or seven per cent compared to UK Power Networks’ Initial Forecast. This
decrease in required expenditure is largely driven by a change in scope of the London Infrastructure
Plan, a revision of unit costs and further assessment of the volumes of work underpinning the business
plan. These changes are discussed in detail in section 5.1 of this Business Plan.
Table 22 below sets out LPN’s forecast capex, by building block, for the next planning period compared to actual
expenditure over the current period and its initial forecast (set out in its Consultation Draft Business Plan).
Table 22 LPN: Revised capital expenditure requirement 2015 to 2023 - by building blocks
£ billion DPCR-5
expenditure
Initial 2015-23
expenditure
forecast
Revised 2015-23
expenditure
forecast
% difference:
DPCR-5 expenditure
and revised 2015-23
expenditure forecast
Load related capex 0.40 0.70 0.49 +23%
Non load related capex 0.50 0.60 0.64 +29%
Network operating costs 0.30 0.30 0.30 +1%
Indirect costs 0.50 0.50 0.55 +10%
Non-operational capex 0.10 0.10 0.09 -9%
RPEs - 0.10 0.06 -
Total 1.80 2.30 2.14 +19%
Figure 21 LPN Initial 2015 to 2023 forecast (£2.30
billion)
Figure 22 LPN Revised 2015 to 2023 forecast (£2.14
billion)
0.7
0.6
0.3
0.5
0.10.1
Load related capex
Non load relatedcapexNetwork operatingcostsIndirect costs
Non operational capex
RPEs
0.5
0.60.3
0.6
0.1
0.1
Load related capex
Non load relatedcapexNetwork operatingcostsIndirect costs
Non operational capex
RPEs
Page 51
5.2.3 SPN’s 2015 to 2023 proposed expenditure forecasts
SPN’s total proposed expenditure for the next planning period is £2.08 billion. This is:
An increase of £0.18 billion or nine per cent compared to the current 2010 to 2015 period expenditure,
accounting for the difference in the length of the planning period. The increase is primarily driven
increased work volumes and smart meter readiness including interventions.
An increase of £0.08 billion or four per cent compared to UK Power Networks’ Initial Forecast. This
increase in required expenditure is largely driven by further assessment of the volumes of work
underpinning the business plan, offset by a revision of unit costs. These changes are discussed in detail
in section 5.1 of this Business Plan.
Table 23 below sets out SPN’s forecast capex, by building block, for the next planning period compared to actual
expenditure over the current period and its initial forecast (set out in its Consultation Draft Business Plan).
Table 23 SPN: Revised capital expenditure requirement 2015 to 2023 - by building blocks
£ billion DPCR-5
expenditure
Initial 2015-23
expenditure
forecast
Revised 2015-23
expenditure
forecast
% difference:
DPCR-5
expenditure and
revised 2015-23
expenditure
forecast
Load related capex 0.20 0.40 0.39 +96%
Non load related capex 0.60 0.60 0.66 +9%
Network operating costs 0.40 0.40 0.35 -13%
Indirect costs 0.60 0.50 0.52 -13%
Non-operational capex 0.10 0.10 0.10 +2%
RPEs - 0.10 0.06 -
Total 1.90 2.00 2.08 +9%
Figure 23 SPN Initial 2015 to 2023 forecast
(£ 2.00 billion)
Figure 24 SPN Revised 2015 to 2023 forecast
(£ 2.08 billion)
0.4
0.6
0.4
0.5
0.10.1
Load related capex
Non load relatedcapexNetwork operatingcostsIndirect costs
Non operational capex
RPEs
0.4
0.7
0.3
0.5
0.1
0.1
Load related capex
Non load relatedcapexNetwork operatingcostsIndirect costs
Non operational capex
RPEs
Page 52
6 Financing
6.1 Impact of changes on our revenue requirement and customers’ bills
6.1.1 Cost of capital and financial requirements
UK Power Networks has not amended any of the financial assumptions made in its November 2012 Consultation
Draft Business Plan set out below. We are still reviewing these assumptions for our Final Business Plans,
including the cost of equity. UK Power Networks’ financial assumptions reflect what is required to attract essential
investment required to finance the Networks over the 2015 to 2023 planning period and long term value for
money for consumers.
Table 24 Financing parameters
Parameter Current period (DPCR-5) 2015 to 2023 planning period
Cost of equity 6.73% 7.00%
Notional gearing 65.0% 65.0%
Cost of debt 3.6% Rolling 10 year average
Vanilla WACC 4.69% 4.24% to 4.17% (estimated)
Totex split (fast / slow) 15/85 (business support + non-
operational capital expenditure 100%
fast)
30/70 on all expenditure categories
RAV depreciation 20 years Single period transition to 45 years
Ofgem target dividend yield 5% on regulated equity 5% on regulated equity
6.1.2 Revenue requirement
In order for UK Power Networks to continue to operate safe and secure distribution networks it needs levels of
revenue to match its expenditure plans. Figure 25 to Figure 27 show EPN’s, LPN’s and SPN’s annual revenue
requirements for the 2015 to 2023 planning period. The revenue requirements cover the cost of operating the
Networks, financing capital investments, tax expenses and other liabilities incurred such as employee pensions.
UK Power Networks will recover this revenue from customers through the charges discussed in section 6.1.3
below.
We are pleased that the cost savings in our Business Plan Update allow us to offer real term price cuts in 2015,
followed by some modest real term growth in line with our asset base in order to maintain appropriate credit
ratios.
Page 53
Figure 25 EPN’s annual revenue requirement Figure 26 LPN’s annual revenue requirement
Figure 27 SPN’s annual revenue requirement
6.1.3 The impact on our customers
UK Power Networks has estimated the impact on domestic and non-domestic customers using the same
methodology applied in its November 2012 Consultation Draft Business Plan. This involved applying the
percentage change in forecast revenue required to finance UK Power Networks in the next planning period to the
current charges.
Figure 28 to Figure 33 show that in real terms LPN and SPN’s prices will remain relatively constant with current
price levels over the next planning period and that there will be a relatively modest increase in EPN’s prices but
they will flatten from 2019.
UK Power Networks’ 2015 to 2023 Business Plans should see each of the Networks remain amongst the lowest
cost UK DNOs.
Figure 28 EPN: projected change in average annual
domestic bill (real £2010/11)
Figure 29 LPN projected change in average annual
domestic bill (real £2010/11)
0
100
200
300
400
500
60013/1
4
14/1
5
15/1
6
16/1
7
17/1
8
18/1
9
19/2
0
20/2
1
21/2
2
22/2
3£m
(2010/1
1 p
rices)
Profiled revenue Profiled revenue (Nov '12)
CAGR: 1.3%
Po: (4%)CAGR: 2.3%
0
100
200
300
400
500
600
13/1
4
14/1
5
15/1
6
16/1
7
17/1
8
18/1
9
19/2
0
20/2
1
21/2
2
22/2
3£m
(2010/1
1 p
rices)
Profiled revenue Profiled revenue (Nov '12)
CAGR: 0%
Po: (10%)CAGR: 1.7%
0
100
200
300
400
500
600
13/1
4
14/1
5
15/1
6
16/1
7
17/1
8
18/1
9
19/2
0
20/2
1
21/2
2
22/2
3£m
(2010/1
1 p
rices)
Profiled revenue Profiled revenue (Nov '12)
CAGR: 0%
Po: (12%)CAGR: 1.9%
76.289.3
60.5
79.488.3
0
50
100
150
2009
2010
2011
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
EPN EPN - NOV '12
DNO average DNO average forecast
Highest cost DNO
60.4
77.0 86.6
85.5 85.5
0
50
100
150
2009
2010
2011
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
LPN LPN - NOV '12
DNO average DNO average forecast
Highest cost DNO
Page 54
Figure 30 SPN: projected change in average
annual domestic bill (real £2010/11)
Figure 31 EPN: projected change in average annual
non-domestic bill (real £2010/11)
Figure 32 LPN: projected change in average annual
non-domestic bill (real £2010/11)
Figure 33 SPN: projected change in average annual
non-domestic bill (real £2010/11)
56.0
95.2
83.895.6
95.2
0
50
100
150
2009
2010
2011
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
SPN SPN - NOV '12
DNO average DNO average forecast
Highest cost DNO
174.3204.4
151.5
181.6 202.1
0
100
200
300
400
500
2009
2010
2011
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
EPN EPN - NOV '12
DNO average DNO average forecast
Highest cost DNO
164.0
156.5
140.9 158.5
156.5
0
100
200
300
400
500
2009
2010
2011
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
LPN LPN - NOV '12
DNO average DNO average forecast
Highest cost DNO
183.2209.0
130.1
208.2 208.2
0
100
200
300
400
500
2009
2010
2011
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
SPN SPN - NOV '12
DNO average DNO average forecast
Highest cost DNO
Page 55
7 Finalising our business plans
7.1 Remaining steps and timeframes for finalising our business plan
UK Power Networks is currently in the last stages of finalising its business plans for submission to Ofgem on 1
July 2013. UK Power Networks is keen that stakeholders have an explicit opportunity to comment on the updated
proposed business plan. UK Power Networks has therefore built into its engagement process these remaining
key steps:
Incorporate feedback from stakeholders on this Business Plan Update in the Final Business Plans
Conduct further stakeholder consultation and engagement:
The Central London Update – 15 May 2013
The fourth Critical Friends Panel sessions in EPN, LPN & SPN (May 2013)
Supplier bilateral meetings
Evaluate feedback received from the above consultations and incorporate in the final Business Plans.
7.2 Questions on the business plan update
UK Power Networks welcomes your feedback on all aspects of this Business Plan Update. The following
questions are intended to assist stakeholders in providing feedback:
1. Is this Business Plan Update useful?
2. How could UK Power Networks improve its Business Plan Update?
3. Do you have any comments about the proposed outputs, costs or price impacts?
4. Are there any areas that you would like to see more information on in our Final Business Plan?
5. Do you have any general comments on this Business Plan Update?
6. How do you rate UK Power Networks’ stakeholder engagement on its business plan?
7. How does this plan compare with those of other electricity distribution networks?
Please logon to our consultation website to submit your feedback by 31 May 2013:
http://www.ukpowernetworks.co.uk/internet/en/have-your-say/business-plan/
Alternatively, you can reply by post. Please send your comments to:
Dr Nazrin Mehdiyeva
Head of Stakeholder Engagement
UK Power Networks
Newington House
237 Southwark Bridge Road
London, SE1 6NP
Page 56
8 Glossary
A
Asset risk and prioritisation (ARP)
Models for establishing and forecasting the health of
network assets. The ARP models use a combination
of information relating to an asset’s age,
environment, duty and specific condition and
performance information to derive a health score for
each asset, underpinned by proximity to end of life
and probability of failure
B
Business carbon footprint (BCF)
The BCF scheme was introduced as a reputational
incentive in DPCR-5 to encourage DNOs to
consider the direct carbon impact of conducting their
operations and to be proactive in the reduction of
emissions
Broad measure of customer satisfaction
(BMoCS)
A composite incentive consisting of a customer
satisfaction survey, a complaints metric and
stakeholder engagement. It was introduced for
DPCR-5 and is designed to drive improvements in
the quality of the overall customer experience by
capturing and measuring customers’ experiences of
contact with their DNO across the range of services
and activities the DNOs provide
C
Capital expenditure (Capex)
Expenditure on investment in long-lived distribution
assets, such as underground cables, overhead
electricity lines and substations
Combined heat and power (CHP)
The simultaneous generation of usable heat and
electricity in a single process, thereby discarding
less wasted heat
Compound annual growth rate (CAGR)
Average annual growth rate over a defined period of
time
Customer interruptions (CIs)
The number of customers whose supplies have
been interrupted per 100 customers per year over
all incidents, where an interruption of supply lasts
for three minutes or longer, excluding re-
interruptions to the supply of customers previously
interrupted during the same incident.
Customer minutes lost (CMLs)
The duration of interruptions to supply per year –
average customer minutes lost per customer per
year, where an interruption of supply to customer(s)
lasts for three minutes or longer
D
DCLG
Department for Communities and Local Government
DECC
Department of Energy and Climate Change
DEFRA
Department for Environment, Food and Rural Affairs
(DEFRA)
Page 57
Distributed generation (DG)
Distributed generation (also known as embedded or
dispersed generation) refers to an electricity
generating plant connected to the distribution
network . There are many types and sizes of
distributed generation facilities. These include
Combined Heat and Power (CHP), wind farms,
hydro-electric power or one of the new smaller
generation technologies such as photo-voltaic cells
Distribution network operators (DNOs)
A DNO is a company which operates the electricity
distribution network which includes all parts of the
network from 132kV down to 230V in England and
Wales. In Scotland 132kV is considered to be a part
of transmission rather than distribution so their
operation is not included in the DNOs’ activities.
There are 14 DNOs in the UK which are owned by
six different groups
Distribution price control review 5 (DPCR-5)
Distribution price control review 5. This price control
runs from 1 April 2010 until 31 March 2015
Distribution system operator (DSO)
As DNOs actively manage the local levels of
demand, whilst at the same time accommodating
varying amounts of generation onto the network,
they will start to behave like system operators (ie
locally balancing demand and supply on their
networks), known as the DSO
E
EA
Environment Agency
Eastern Power Networks (EPN)
One of the three distribution network licence areas
owned and operated by UK Power Networks. The
EPN network covers the East of England
Element Energy (EE)
Element Energy, a strategic energy consultancy,
have provided economic analysis to inform the 2013
forecast business plan
Electricity Guaranteed Standards Electric
vehicle (EV)
Vehicles that utilise electric motor(s) or traction
motor(s) and are powered by either an external
power station, on-board electrical generators, or
stored electricity
Electricity, safety, quality and continuity
regulations 2002 (ESQCR)
The ESQCR specify safety standards, which are
aimed at protecting the general public and
customers from danger. In addition, the regulations
specify power quality and supply continuity
requirements to ensure an efficient and economic
electricity supply service to customers
Extra high voltage (EHV)
Voltages over 20kV up to, but not including, 132kV
F
Fast money
Fast money is the revenue that is matched to the
year of expenditure
Feed in tariff (FIT)
The price per unit of electricity that a utility or
supplier has to pay for renewable electricity from
private generators. These are used to encourage
distributed renewable generation through private
generators
Forecast business plan questionnaire
(FBPQ)
Questionnaire through which data is submitted to
Ofgem to help form Ofgem’s initial views on the
revenue requirements for price control reviews
G
Gigawatt (GW)
Measure of power equal to one billion watts
Guaranteed standards of performance
(GSOPs)
Guaranteed Standards set service levels to be met
in each individual case and are established by a
Statutory Instrument. If the licence holder fails to
provide the level of service required, it must make a
payment to the customer affected subject to certain
exemptions
Page 58
H
Health index (HI)
Framework for collating information on the health (or
condition) of distribution assets and for tracking
changes in their condition over time. The HI will be
used by Ofgem to inform an assessment of the
efficacy of the DNOs’ asset management decisions
over the price control period. Health index
arrangements were introduced as a part of DPCR-5
High voltage (HV)
Voltages over 1kV up to, but not including, 22kV
I
Indirect cost efficiency (ICE)
The ICE programme was launched in 2011 in order
to close the gap with the benchmark distribution
companies in relation to indirect costs
Information technology (IT)
Technology systems used to manage information. In
UK Power Networks this includes our management
information systems, asset information systems and
operational IT
Inspections and maintenance (I&M)
The activities of both:
Inspections – the visual checking of the
external condition of assets
Maintenance – the invasive (‘hands on’)
examination of plant and equipment
Innovation funding incentive (IFI)
The IFI is intended to encourage DNOs to invest in
appropriate research and development activities
that are designed to enhance the technical
development of distribution networks (up to and
including 132 kV) and to deliver value (ie financial,
supply quality, environmental, safety) to end
customers
Interruption incentive scheme (IIS)
The interruption incentive scheme is a symmetric
annual rewards and penalties scheme based on
each DNO’s performance against their targets for
the number of customers interrupted per 100
customers (CI) and the number of customer minutes
lost (CML)
K
KiloWatt hour revenue driver (kWh)
A revenue allowance based on units distributed
(kWh)
L
Load index (LI)
Framework for collating information on the utilisation
of individual substations or groups of interconnected
substations and for tracking changes in their
utilisation over time. The LI will be used by Ofgem to
inform an assessment of the efficacy of the DNOs’
general reinforcement decisions over the price
control period. The Load Index was introduced as a
part of DPCR-5
Load related expenditure (LRE)
The installation of new assets to accommodate
changes in the level or pattern of electricity or gas
supply and demand
London Power Networks (LPN)
One of the three distribution network licence areas
owned and operated by UK Power Networks. The
LPN network covers Greater London
Low Carbon Networks Fund (LCNF)
A mechanism introduced under the fifth distribution
price control review to encourage the DNOs to use
the forthcoming price control period to prepare for
the role they will have to play as GB moves to a low
carbon economy. The fund will see up to £500
million made available for DNOs and partners to
innovate and trial new technologies, commercial
arrangements and ways of operating their networks
Low voltage (LV)
This refers to voltages up to, but not including, 1kV
M
Megawatt (MW)
Measure of power equal to one million watts
Megawatt-hour (MWh)
A measure of energy production or consumption
equal to one million watts produced or consumed for
one hour
Page 59
N
Non load related expenditure (NLRE)
The replacement or refurbishment of assets which
are either at the end of their useful life due to their
age or condition, or need to be replaced on safety or
environmental grounds
O
Office of gas and electricity markets
(Ofgem)
Responsible for regulating the gas and electricity
markets in the UK to ensure consumers’ needs are
protected, including their interests in the reduction of
greenhouse gases and in the security of the supply
of gas and electricity. This involves promoting
competition, wherever appropriate, and regulating
the monopoly companies which run the gas and
electricity networks
P
Photovoltaic (PV) connection assessment
tool
Planning tool which assesses the impact of
concentrations of small scale generation on our
networks e.g. solar panels, enabling us to provide a
better and faster service to our customers
R
Real price effects (RPE)
Increase in prices over and above increases in the
Retail Price Index (RPI). For example, increases in
the cost of copper, steel, direct or contract labour
over and above increases in RPI.
Regulatory asset value (RAV)
The value ascribed by Ofgem to the capital
employed in the licensee’s regulated distribution or
(as the case may be) transmission business (the
‘regulated asset base’). The RAV is calculated by
summing an estimate of the initial market value of
each licensee’s regulated asset base at privatisation
and all subsequent allowed additions to it at
historical cost, and deducting annual depreciation
amounts calculated in accordance with established
regulatory methods. These vary between classes of
licensee. A deduction is also made in certain cases
to reflect the value realised from the disposal of
assets comprised in the regulatory asset base. The
RAV is indexed to RPI in order to allow for the
effects of inflation on the licensee’s capital stock.
The revenues licensees are allowed to earn under
their price controls include allowances for the
regulatory depreciation and also for the return
investors are estimated to require to provide the
capital
RPI-X
The form of price control currently applied to
network monopolies. Each company is given a
revenue allowance in the first year of each control
period. The price control then specifies that in each
subsequent year the allowance will move by ‘X’ per
cent in real terms
Revenue = incentives + innovation +
outputs (RIIO)
Ofgem’s new regulatory framework, stemming from
the conclusions of the RPI-X@20 project, to be
implemented in forthcoming price controls. It builds
on the success of the previous RPI-X regime, but
better meets the investment and innovation
challenge by placing much more emphasis on
incentives to drive the innovation needed to deliver
a sustainable energy network at value for money to
existing and future consumers
RIIO electricity distribution 1 (RIIO-ED1)
The first RIIO price control review to be applied to
the electricity distribution network operators,
following DPCR-5. This price control will run from 1
April 2015 to 31 March 2023.
Remote terminal unit (RTU)
Communications device that transmits readings and
information about the status of the network back to
the control centre.
Page 60
Renewable heat incentives (RHI)
Financial incentive scheme for renewable heat
generation thatwill help the UK reduce carbon
emissions and hit its European Union renewable
energy targets
Ring main unit (RMU)
A HV switchgear arrangement for the connection
and protection of distribution transformers
S
Slow money
Slow money is where costs are added to the RAV
and revenues allow recovery of the costs over time
together with the cost of financing this expenditure
in the interim
South Eastern Power Networks (SPN)
One of the three distribution network licence areas
owned and operated by UK Power Networks. The
SPN network covers the South East of England
Site of Special Scientific Interest (SSSI)
Sites of Special Scientific Interest give legal
protection to wildlife, geological and physiographical
heritage under the Wildlife and Countryside Act
1981 There are over 4000 SSSIs in England,
covering around 8 per cent of the country
Sulphur Hexafluoride (SF6)
One of the most potent greenhouse gases and is
widely used in transmission and distribution
equipment
System operator (SO)
National Grid Electricity Transmission is the
electricity system operator, responsible for
managing the operation of the electricity
transmission system. They balance supply and
demand ensuring the stability and security of the
power system and the maintenance of satisfactory
voltage and frequency
T
Tonnes of carbon dioxide equivalent
(tCO2e)
Unit of measurement that allows global warming
potential of different greenhouse gases to be
compared
Total operating and capital expenditure
(totex)
Total of capital expenditure (capex) plus operational
expenditure (opex)
W
Weighted average cost of capital (WACC)
This is the weighted average of the expected cost of
equity and the expected cost of debt
Page 61