UDOT I-15 The Point Design-Build ProjectUsing an ‘Independent Quality Firm’ to Verify Conformance to
Contract Requirements
July 20, 2015
1
Tim Rose, PE – Utah Department of TransportationDavid Brown, PE – ParsonsMatt Wildauer, PE - Parsons
![Page 2: UDOT I-15 The Point Design-Build Project Using an ‘Independent Quality Firm’ to Verify Conformance to Contract Requirements July 20, 2015July 20, 2015.](https://reader036.fdocuments.in/reader036/viewer/2022062314/56649e735503460f94b72c1e/html5/thumbnails/2.jpg)
Introduction
• Project Overview• Measuring Quality and Approach to Quality Management• IQF Methodology and Reporting• Conclusions/Take-Away• Questions
2
![Page 3: UDOT I-15 The Point Design-Build Project Using an ‘Independent Quality Firm’ to Verify Conformance to Contract Requirements July 20, 2015July 20, 2015.](https://reader036.fdocuments.in/reader036/viewer/2022062314/56649e735503460f94b72c1e/html5/thumbnails/3.jpg)
Project Overview
3
![Page 4: UDOT I-15 The Point Design-Build Project Using an ‘Independent Quality Firm’ to Verify Conformance to Contract Requirements July 20, 2015July 20, 2015.](https://reader036.fdocuments.in/reader036/viewer/2022062314/56649e735503460f94b72c1e/html5/thumbnails/4.jpg)
Project scope is to reconstruct I-15 from SR-92 to 12300 South
4
![Page 5: UDOT I-15 The Point Design-Build Project Using an ‘Independent Quality Firm’ to Verify Conformance to Contract Requirements July 20, 2015July 20, 2015.](https://reader036.fdocuments.in/reader036/viewer/2022062314/56649e735503460f94b72c1e/html5/thumbnails/5.jpg)
Construction will be phased through two seasons
5
![Page 6: UDOT I-15 The Point Design-Build Project Using an ‘Independent Quality Firm’ to Verify Conformance to Contract Requirements July 20, 2015July 20, 2015.](https://reader036.fdocuments.in/reader036/viewer/2022062314/56649e735503460f94b72c1e/html5/thumbnails/6.jpg)
Complex phasing allows four lanes to be maintained in each direction
6
Phase 2 : April – June 2015 Phase 3 : June – September 2015
![Page 7: UDOT I-15 The Point Design-Build Project Using an ‘Independent Quality Firm’ to Verify Conformance to Contract Requirements July 20, 2015July 20, 2015.](https://reader036.fdocuments.in/reader036/viewer/2022062314/56649e735503460f94b72c1e/html5/thumbnails/7.jpg)
New pavement will be utilized for Phase 4 MOT
7Phase 4: September – November 2015
![Page 8: UDOT I-15 The Point Design-Build Project Using an ‘Independent Quality Firm’ to Verify Conformance to Contract Requirements July 20, 2015July 20, 2015.](https://reader036.fdocuments.in/reader036/viewer/2022062314/56649e735503460f94b72c1e/html5/thumbnails/8.jpg)
Mainline construction will extend through 2015 and 2016
8
• Independent Quality Firm is involved in the project from selection through closeout.
![Page 9: UDOT I-15 The Point Design-Build Project Using an ‘Independent Quality Firm’ to Verify Conformance to Contract Requirements July 20, 2015July 20, 2015.](https://reader036.fdocuments.in/reader036/viewer/2022062314/56649e735503460f94b72c1e/html5/thumbnails/9.jpg)
Goals and objectives provide focus to the project
9
![Page 10: UDOT I-15 The Point Design-Build Project Using an ‘Independent Quality Firm’ to Verify Conformance to Contract Requirements July 20, 2015July 20, 2015.](https://reader036.fdocuments.in/reader036/viewer/2022062314/56649e735503460f94b72c1e/html5/thumbnails/10.jpg)
Goals and objectives provide focus to the project
10
![Page 11: UDOT I-15 The Point Design-Build Project Using an ‘Independent Quality Firm’ to Verify Conformance to Contract Requirements July 20, 2015July 20, 2015.](https://reader036.fdocuments.in/reader036/viewer/2022062314/56649e735503460f94b72c1e/html5/thumbnails/11.jpg)
Goals and objectives provide focus to the project
11
![Page 12: UDOT I-15 The Point Design-Build Project Using an ‘Independent Quality Firm’ to Verify Conformance to Contract Requirements July 20, 2015July 20, 2015.](https://reader036.fdocuments.in/reader036/viewer/2022062314/56649e735503460f94b72c1e/html5/thumbnails/12.jpg)
Project Highlights
12
East Jordan Canal box culvert installation Segment 3 near Lehi
![Page 13: UDOT I-15 The Point Design-Build Project Using an ‘Independent Quality Firm’ to Verify Conformance to Contract Requirements July 20, 2015July 20, 2015.](https://reader036.fdocuments.in/reader036/viewer/2022062314/56649e735503460f94b72c1e/html5/thumbnails/13.jpg)
Project Highlights
13
Grading in Segment 3 Retaining wall along Pony Express Rd
![Page 14: UDOT I-15 The Point Design-Build Project Using an ‘Independent Quality Firm’ to Verify Conformance to Contract Requirements July 20, 2015July 20, 2015.](https://reader036.fdocuments.in/reader036/viewer/2022062314/56649e735503460f94b72c1e/html5/thumbnails/14.jpg)
Project Highlights
14
Placement of lean concrete pavement Girder setting at 14600 South bridge
![Page 15: UDOT I-15 The Point Design-Build Project Using an ‘Independent Quality Firm’ to Verify Conformance to Contract Requirements July 20, 2015July 20, 2015.](https://reader036.fdocuments.in/reader036/viewer/2022062314/56649e735503460f94b72c1e/html5/thumbnails/15.jpg)
Measuring Quality and Approach to Quality Management
15
![Page 16: UDOT I-15 The Point Design-Build Project Using an ‘Independent Quality Firm’ to Verify Conformance to Contract Requirements July 20, 2015July 20, 2015.](https://reader036.fdocuments.in/reader036/viewer/2022062314/56649e735503460f94b72c1e/html5/thumbnails/16.jpg)
Performance measurement roles depend on delivery method
16
Traditional - Project Delivery - Alternative Changing Roles & Responsibilities
DOT Maintenance
Fix the pot-hole quickly.
Ensure Quality
Design-Bid-Build
Inspect and test materials
Verify Quality
Design-Build
Design Builder follows QMP
Validate Quality
P3
Oversight of Developer
Due Diligence
![Page 17: UDOT I-15 The Point Design-Build Project Using an ‘Independent Quality Firm’ to Verify Conformance to Contract Requirements July 20, 2015July 20, 2015.](https://reader036.fdocuments.in/reader036/viewer/2022062314/56649e735503460f94b72c1e/html5/thumbnails/17.jpg)
Various projects use different measures of quality
• Set a high expectation – “We want a ‘high quality’ project.”• Inspect everything until it is right.• “If all the material tests pass then the work is good.”
17
To measure QUALITY – we need DATA
![Page 18: UDOT I-15 The Point Design-Build Project Using an ‘Independent Quality Firm’ to Verify Conformance to Contract Requirements July 20, 2015July 20, 2015.](https://reader036.fdocuments.in/reader036/viewer/2022062314/56649e735503460f94b72c1e/html5/thumbnails/18.jpg)
Quality measurement on I-15 The Point project is based on performance and conformance rates
18
# of CONFORMING observations
TOTAL # of observationsPerformance Rate =
PERFORMANCE rate CONFORMANCE rate
Conformance Rate MUST 100%
![Page 19: UDOT I-15 The Point Design-Build Project Using an ‘Independent Quality Firm’ to Verify Conformance to Contract Requirements July 20, 2015July 20, 2015.](https://reader036.fdocuments.in/reader036/viewer/2022062314/56649e735503460f94b72c1e/html5/thumbnails/19.jpg)
Requirements management uses verification to determine performance
• A way to measure PERFORMANCE• All Work is defined by distinct requirements.• Isolate KEY requirements – in a searchable database.• Apply attributes to requirements (risk, owner, phase, performance).• Verify requirements are fulfilled.• Update requirements in database as scope evolves.
19
![Page 20: UDOT I-15 The Point Design-Build Project Using an ‘Independent Quality Firm’ to Verify Conformance to Contract Requirements July 20, 2015July 20, 2015.](https://reader036.fdocuments.in/reader036/viewer/2022062314/56649e735503460f94b72c1e/html5/thumbnails/20.jpg)
The Project Management
‘Trinity’
Requirements management is a component of overall performance measurement
20
SCOPETechnical
Requirements
BUDGETDollars
SCHEDULETime
PerformanceMeasurement
![Page 21: UDOT I-15 The Point Design-Build Project Using an ‘Independent Quality Firm’ to Verify Conformance to Contract Requirements July 20, 2015July 20, 2015.](https://reader036.fdocuments.in/reader036/viewer/2022062314/56649e735503460f94b72c1e/html5/thumbnails/21.jpg)
Requirements management is a component of performance measurement
21
SCHEDULEManagement
Time Remaining 0%100%Th
e W
ork
BUDGETManagement
Dollars Remaining 0%100%
The
Wor
k
REQUIREMENTManagement
Requirements Remaining 0%100%
The
Wor
k
![Page 22: UDOT I-15 The Point Design-Build Project Using an ‘Independent Quality Firm’ to Verify Conformance to Contract Requirements July 20, 2015July 20, 2015.](https://reader036.fdocuments.in/reader036/viewer/2022062314/56649e735503460f94b72c1e/html5/thumbnails/22.jpg)
Data allows performance to be measured and reported
22
Observed Performance Rate ~97%
Acceptance Data Points
~ 1700
Similar project
in Ohio
![Page 23: UDOT I-15 The Point Design-Build Project Using an ‘Independent Quality Firm’ to Verify Conformance to Contract Requirements July 20, 2015July 20, 2015.](https://reader036.fdocuments.in/reader036/viewer/2022062314/56649e735503460f94b72c1e/html5/thumbnails/23.jpg)
IQF Methodology and Reporting
23
![Page 24: UDOT I-15 The Point Design-Build Project Using an ‘Independent Quality Firm’ to Verify Conformance to Contract Requirements July 20, 2015July 20, 2015.](https://reader036.fdocuments.in/reader036/viewer/2022062314/56649e735503460f94b72c1e/html5/thumbnails/24.jpg)
A customized database provides an efficient platform for verifying requirements
• At the beginning of the project, team will extract requirements from Contract documents, standards, and special provisions.
• This provides an organized, customizable, searchable requirement database for use by the project team.
• Requirements are updated as scope evolves.
24
![Page 25: UDOT I-15 The Point Design-Build Project Using an ‘Independent Quality Firm’ to Verify Conformance to Contract Requirements July 20, 2015July 20, 2015.](https://reader036.fdocuments.in/reader036/viewer/2022062314/56649e735503460f94b72c1e/html5/thumbnails/25.jpg)
Contract requirements are imported to the database at the beginning of the project
25
Requirement Description
![Page 26: UDOT I-15 The Point Design-Build Project Using an ‘Independent Quality Firm’ to Verify Conformance to Contract Requirements July 20, 2015July 20, 2015.](https://reader036.fdocuments.in/reader036/viewer/2022062314/56649e735503460f94b72c1e/html5/thumbnails/26.jpg)
Each applicable requirement is verified based on objective evidence
• Verifications of the design to determine conformance with Contract requirements are completed at each submittal. Requirements populated using checklists.
• Verifier provides objective evidence and location for observations on each requirement along with a result code.
26
Objective evidence is provided for each requirement verified.
Each observation is assigned a result – “C” or “RD”
![Page 27: UDOT I-15 The Point Design-Build Project Using an ‘Independent Quality Firm’ to Verify Conformance to Contract Requirements July 20, 2015July 20, 2015.](https://reader036.fdocuments.in/reader036/viewer/2022062314/56649e735503460f94b72c1e/html5/thumbnails/27.jpg)
Objective evidence for construction verifications are based on inspection and testing
• Construction verifications are based on inspection and testing – hard data from the field.
• Test results are referenced in objective evidence for verification.• Results that do not pass are marked as RD or NCR.
27Result Code
![Page 28: UDOT I-15 The Point Design-Build Project Using an ‘Independent Quality Firm’ to Verify Conformance to Contract Requirements July 20, 2015July 20, 2015.](https://reader036.fdocuments.in/reader036/viewer/2022062314/56649e735503460f94b72c1e/html5/thumbnails/28.jpg)
IQF monthly report measures and tracks project performance
• The IQF monthly report provides measurement and tracking of the design-build team’s performance on the project.
• The report presents results of verifications and tracks trends throughout the project.
• IQF staff work with the Department to capture results of Department audits in the report.
• Material testing results are gathered and summarized each month.
28
Design Discipline Latest Issue Date
RD's Opened During Reporting Period
Open RD's Carried Forward
RD's Closed During Reporting Period
RD's Remaining Open
ATMS, Lighting, Traffic Signals 5/29/2015 4 11 2 13
Drainage 5/7/2015 2 3 0 5MOT 5/14/2015 1 0 1 0
Roadway 5/20/2015 9 0 3 6Structures 5/30/2015 4 13 3 14
Utilities 5/27/2015 8 3 0 11Walls 5/20/2015 5 0 0 5TOTAL 33 30 9 54
![Page 29: UDOT I-15 The Point Design-Build Project Using an ‘Independent Quality Firm’ to Verify Conformance to Contract Requirements July 20, 2015July 20, 2015.](https://reader036.fdocuments.in/reader036/viewer/2022062314/56649e735503460f94b72c1e/html5/thumbnails/29.jpg)
Design performance is measured continuously and reported monthly
• Monthly design performance has ranged from 75%-89% conforming observations, with an average of 85% conforming observations.
• Conformance rate must equal 100% prior to RFC.
29
Design Performance
Jun-15 Project Average
0%
20%
40%
60%
80%
100%
86% 85%
Design Performance
Sep-14
Oct-14
Nov-14
Dec-14
Jan-15
Feb-15
Mar-15
Apr-15
May-15
Jun-15Jul-1
5
Aug-15
Sep-150
200
400
600
800
1000
1200
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
440
242 231
556
803
531
309 329 277
563
112
48 79
76
150
84
60 4333
891
22
80%83%
75%
88%84% 86%
83%88% 89% 86%
Monthly Design Performance Activity
Conforming Observations Requirement Deficiencies (Issued)Nonconformance (Issued) Monthly Performance Rate
Requ
irem
ents
Ver
ified Perform
ance Rate
![Page 30: UDOT I-15 The Point Design-Build Project Using an ‘Independent Quality Firm’ to Verify Conformance to Contract Requirements July 20, 2015July 20, 2015.](https://reader036.fdocuments.in/reader036/viewer/2022062314/56649e735503460f94b72c1e/html5/thumbnails/30.jpg)
Construction performance is measured and reported in a similar manner to design
• Construction performance rate is near 98% conforming.• Higher performance rate is due to larger sample size and backup of
material testing data for verifications.
30
ConstructionPerformance
Jun-15 Project Average0%
20%
40%
60%
80%
100%98% 98%
ConstructionPerformance
Sep-14
Oct-14
Nov-14
Dec-14
Jan-15
Feb-15
Mar-15
Apr-15
May-15
Jun-15Jul-1
5
Aug-15
Sep-150
200
400
600
800
1000
1200
1400
1600
1800
2000
2200
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
0 640 35
447 534 926 953 1107 17801
8
17 12
16
19
1
24
7 84
12
100%95%
100% 98% 97% 98% 98% 98%
Monthly Construction Performance Activity
Conforming Observations Requirement Deficiencies (Issued)
Nonconformance (Issued) Monthly Performance Rate
Requ
irem
ents
Ver
ified
Performance Rate
![Page 31: UDOT I-15 The Point Design-Build Project Using an ‘Independent Quality Firm’ to Verify Conformance to Contract Requirements July 20, 2015July 20, 2015.](https://reader036.fdocuments.in/reader036/viewer/2022062314/56649e735503460f94b72c1e/html5/thumbnails/31.jpg)
Observed performance rates are similar between projects
31
![Page 32: UDOT I-15 The Point Design-Build Project Using an ‘Independent Quality Firm’ to Verify Conformance to Contract Requirements July 20, 2015July 20, 2015.](https://reader036.fdocuments.in/reader036/viewer/2022062314/56649e735503460f94b72c1e/html5/thumbnails/32.jpg)
Conclusion/Take-Away
• A requirements based quality program provides a comprehensive approach to quality. The process provides an opportunity to measure performance, not just progress.
• This process collects data – from design and construction – and provides objective evidence of conformance to requirements.
• Success depends on having good people with a focus on meeting requirements the first time, allowing projects to be completed with greater speed and efficiency, and saving money.
32
![Page 33: UDOT I-15 The Point Design-Build Project Using an ‘Independent Quality Firm’ to Verify Conformance to Contract Requirements July 20, 2015July 20, 2015.](https://reader036.fdocuments.in/reader036/viewer/2022062314/56649e735503460f94b72c1e/html5/thumbnails/33.jpg)
Questions
33