UDB 801 – PROJECT 1 · Figure 5 – Installation of Tank on New Tank Base . 4 . Figure 6 –...
Transcript of UDB 801 – PROJECT 1 · Figure 5 – Installation of Tank on New Tank Base . 4 . Figure 6 –...
BEB801 – PROJECT 1 PROJECT OVERVIEW
Faculty of Built Environment and Engineering
Construction Management
UDB 801 – PROJECT 1
SAMFORD ECOLOGICAL RESEARCH FACILITY STAGE 1 – PROJECT REVIEW
STUDENTS MATTHEW RODGERS N4458958 PATRICK SWEEPER N6338089 ANDREW OTTO N6408478 DAN GEORGE N5421802 The work contained in this report has not been previously submitted for a degree or diploma at any other higher education institution. To the best of our knowledge and belief, this report contains no material previously published or written by another person except where due reference is made. Signed: Date: Signed: Date: Signed: Date: Signed: Date:
i
CRICOS No. 00213J Permission has been granted by the authors to display this document and images on the SERF website.
BEB801 – PROJECT 1 PROJECT OVERVIEW
TABLE OF CONTENTS
1. Introduction 1
2. Project Overview 1
3. Conclusion 14
LIST OF FIGURES
Figure 1 – Defunct Water Tanks 1
Figure 2 – Initial Demolition of the Original Tank Base 2
Figure 3 – Continuation of Demolition 2
Figure 4 – Completion of Demolition 3
Figure 5 – Installation of Tank on New Tank Base 4
Figure 6 – Location of Tank in Relation to Existing Downpipe 5
Figure 7 – Tank Positioning Within Close Proximity of Water Supply and
Clearance for Drainage 5
Figure 8 – Connection of Downpipe to Tank 6
Figure 9 – Connection of Pump 7
Figure 10 – Installation of Water Supply 8
Figure 11 – Installation of Hot Water System 9
Figure 12 – Brazing of 20mm Copper Water Supply Line 10
Figure 13 – Installation of Toilet 11
Figure 14 – Installation of Vanity Unit 12
Figure 15 – Plumbing Connections to Vanity Unit 12
Figure 16 – Fit Off of Shower 13
Figure 17 – Running Water 14
Figure 18 – Completion of Stage 1 of SERF Water Project 15
i
CRICOS No. 00213J
BEB801 – PROJECT 1 PROJECT OVERVIEW
1. Introduction
At the commencement of semester 2 2008 the Samford Water Project Team compiled a
report specifying recommendations and desired works to be undertaken in order to provide a
sustainable and potable water supply by completion of stage one of the project. The goal of
stage one as outlined in the Samford Ecological Research Facility (SERF) Water Report, has
been achieved. The barracks situated on the SERF now has a fully functional, sustainable and
potable means of hot and cold water supply to the current functional bathroom and toilet as
well as a live water feed ready for the future kitchen. All works involved within the project
have been carried out in accordance with AS3500.
The following project overview will document the projects achievements throughout the
semester by means of photographic illustration.
2. Project Overview
Figure 1 – Defunct Water Tanks
Figure one illustrates the SERF’s redundant water facilities prior to the commencement of the
project. The original galvanised water tanks were no longer in serviceable or working order
due to extensive rust, mosquito infestation and non-potable lead contaminated roof water.
1
CRICOS No. 00213J
BEB801 – PROJECT 1 PROJECT OVERVIEW
Figure 2 – Initial Demolition of the Original Tank Base
Figure 3 – Continuation of Demolition
2
CRICOS No. 00213J
BEB801 – PROJECT 1 PROJECT OVERVIEW
Figure 4 – Completion of Demolition
Figure 2, 3 and 4 photographically illustrate the demolition process of the existing water tank
provisions which were to be the location of the new recommended water provisions. The
demolition of the original tank base required manual handling and jack hammering of the
concrete structure to clear the area ready for the instillation of the new tank and base.
3
CRICOS No. 00213J
BEB801 – PROJECT 1 PROJECT OVERVIEW
Figure 5 – Installation of Tank on New Tank Base
The newly constructed tank base was constructed with treated pine sleepers which were
bolted through galvanised steel angle brackets in each corner. The tank base was then
positioned within close proximity to the roof catchment area and existing downpipe while
allowing adequate clearance for future access to drainage provisions of the barracks. The base
was filled with crusher dust and lime and then compacted to provide a stable foundation to
support the 5,000 litre water tank. The tank was then positioned on the base centrally between
the barracks existing windows with the outlet of the tank positioned in a suitable location to
allow for the connection of the water supply.
Figures 6 and 7 illustrate the positioning of the tank in reference to the location of down
pipes, proximity of water supply and the clearance for drainage.
4
CRICOS No. 00213J
BEB801 – PROJECT 1 PROJECT OVERVIEW
Figure 6 – Location of Tank in Relation to Existing Downpipe
Figure 7 – Tank Positioning Within Close Proximity of Water Supply and Clearance for
Drainage
5
CRICOS No. 00213J
BEB801 – PROJECT 1 PROJECT OVERVIEW
Figure 8 – Connection of Downpipe to Tank
The downpipe was connected to the tank via a rainwater head. This is the fitting located
below the gutter dropper in figure 8 above. The reason for this being, that the rain water head
is designed to prevent any build up of leaves or foliage from blocking the downpipe and
stopping rainwater from entering the tank. This was necessary at the SERF due to the amount
of trees surrounding the barracks.
6
CRICOS No. 00213J
BEB801 – PROJECT 1 PROJECT OVERVIEW
Figure 9 – Connection of Pump
A gate valve was fitted between the outlet of the tank and the inlet of the pump to act as an
isolation point of the water supply.
7
CRICOS No. 00213J
BEB801 – PROJECT 1 PROJECT OVERVIEW
Figure 10 – Installation of Water Supply
The barracks water supply draws a 20mm copper water line from the pump positioned at the
tank, then through a non return pressure limiting valve before passing through the water filter
which will eliminate any sediment and unwanted odours/tastes.
8
CRICOS No. 00213J
BEB801 – PROJECT 1 PROJECT OVERVIEW
Figure 11 – Installation of Hot Water System
The water supply line branches off at the corner of the barracks. One line supplies the internal
fixtures with cold water and the other supplies the inlet of the hot water system. The hot
water line returns from the hot water system and goes on to feed the internal fixtures with hot
water.
9
CRICOS No. 00213J
BEB801 – PROJECT 1 PROJECT OVERVIEW
Figure 12 – Brazing of 20mm Copper Water Supply Line
The cold water supply line was 20mm copper and the hot water supply line was 15mm lagged
copper. Both water supply lines were installed in accordance with AS3500 requirements and
as illustrated were brazed.
10
CRICOS No. 00213J
BEB801 – PROJECT 1 PROJECT OVERVIEW
Figure 13 – Installation of Toilet
An s-trap toilet suite was fitted to the newly renovated bathroom and connected to the
existing sewerage system and new water supply.
Figures 14 and 15 below show the vanity unit fitted into the newly renovated bathroom. The
vanity unit was fixed to the stud wall and the pipe work installed during the rough in was
connected to the waste and flick mixer.
11
CRICOS No. 00213J
BEB801 – PROJECT 1 PROJECT OVERVIEW
Figure 14 – Installation of Vanity Unit
Figure 15 – Plumbing Connections to Vanity Unit
12
CRICOS No. 00213J
BEB801 – PROJECT 1 PROJECT OVERVIEW
Figure 16 – Fit Off of Shower
The newly tiled shower was fitted off with new wall stops and shower rose.
13
CRICOS No. 00213J
BEB801 – PROJECT 1 PROJECT OVERVIEW
Figure 17 – Running Water
Figure 17 illustrates the projects achieved goal of providing a sustainable, potable, running
hot and cold water supply to the SERF barracks.
3. Conclusion
As set out within the Samford Ecological Research Facility Water Report, the design and aim
of stage one has been successfully completed. Throughout semester 2, 2008 weekly working
sessions were organised in order to complete this project within the time frame set out at
commencement. At the completion of the project and semester 2, 2008 the barracks now has
a fully functional, sustainable and potable means of hot and cold water supply to the current
functional bathroom and toilet as well as a live water feed ready for the future kitchen. Figure
18 below illustrates the view of the completed external works.
14
CRICOS No. 00213J
BEB801 – PROJECT 1 PROJECT OVERVIEW
Figure 18 – Completion of Stage 1 of SERF Water Project
15
CRICOS No. 00213J