UCSB College of Creative Studies Proposal
-
Upload
christina-hackett -
Category
Documents
-
view
219 -
download
3
description
Transcript of UCSB College of Creative Studies Proposal
request for proposalAlese Ashuckian_Gilbert Bastidas_Ryan Burger_Emmanuel Gomez_Christina Hackett_Alexson Lim_Tony Rosemann
EMIDESIGN.ENGINEERING.CONSTRUCTION
UCSB_College of Creative Studies
INTEGRATED FIRMEMI, Inc.
Christina B. Hackett, Principal ArchitectRyan Burger, Urban Designer
Emmanuel Gomez, Landscape ArchitectAlese Ashuckian, Structural EngineerTony Rosemann, Structural Engineer
Alex Lim, Preconstruction Manager Gilbert Bastidas, Project Manager
CLIENTSUniversity of California, Santa Barbara
College of Creative StudiesDean: Dr. Bruce Tiffney
Senior Campus Planner: Mr. Dennis Whelan
1
June 3rd, 2011
Alexson LimEMI Design-Build, Inc.
123 Canyon Circle, Suite #1114San Luis Obispo, CA 93410
Dr. Bruce TiffneyMr. Dennis Whelan
College of Creative StudiesUniversity of California, Santa Barbara
552 University RoadGoleta, CA 93106
To: Dr. Tiffney and Mr. Whelan
EMI, Inc. is pleased to respond to your request for proposal for the reconstruction of the College of Creative Studies (CCS) at the University of California, Santa Barbara. As the
principal preconstruction manager at EMI, Inc. I am authorized to submit this proposal on our behalf. We certify that our team has reviewed the RFP revisions 1 and 2 and agree that
this response complies with all requirements specified. We look forward to developing a project to become an integral core of the university campus and meet the objectives of the
college’s mission.
EMI is a group of design and construction professionals collaborating together to deliver superior products and services to its clients. For the CCS, we have centered our design
and focus around the idea of “a reciprical exchange of knowledge” between students and faculty. Our team worked to create a project that not only provides innovative, integrated
learning spaces, but also allows the CCS to showcase its many disciplines and curriculum to the surrounding university. We consistently utilize the most sustainable building methods
and provide energy-efficient structures that improve indoor enviornments. EMI utilizes a design-build construction approach, which allows our team to collaborate with your
representatives to address your needs, while reducing construction time.
Our team feels confident that the design proposed meets the vision of the college while delivering the most value possible. Thank you once again for the chance to work with the
College of Creative Studies and the opportunity to bring a truly unique building experience to UCSB. Please contact me at (562)726-2663 for further correspondence and notifications.
Sincerely,
Alexson LimPreconstruction Manager
EMI, Inc.
SECTION 1.1 TRANSMITTAL LETTER
CONTENTSSECTION 1.2
2
SECTION 1.0 PREFACE 1 1.1 TRANSMITTAL LETTER 1 1.2 CONTENTS 2 1.3 EXECUTIVE SUMMARY 3SECTION 2.0 QUALIFICATIONS 4 2.1 KEY ELEMENTS OF THE DESIGN 4 2.2 OUR RESUME 5 2.3 OUR TEAM - PRINCIPAL OFFICERS 6 2.4a OUR ORGANIZATION CHART 7 2.4b PROJECT DELIVERY METHOD 7 2.5 OUR MISSION 8 2.6 EXEMPLARY PROJECTS 8SECTION 3.0 PROJECT OVERVIEW 9 3.1 PROJECT VISION 9 3.2 PROJECT GOALS 9 3.3 PROGRAM SUMMARY 10SECTION 4.0 CONCEPT DESCRIPTION 11SECTION 5.0 CONCEPTUAL DESIGN 12 5.1 BUILDING CIRCULATION 12 5.2 FLOOR PLANS 13 5.3 SECTIONS 15 5.4 PERSPECTIVES 16 5.5 STRUCTURAL DESIGN 23 5.6 STRUCTURAL FRAMING PLANS 24 5.7 STRUCTURAL DETAILS 27 5.8 STRUCTURAL PERSPECTIVES & ELEVATIONS 29 5.9 LANDSCAPE MASTER PLAN 30 5.10 LANDSCAPE LIGHTING PLAN 32 5.11 LANDSCAPE DETAILS 33 5.12 ENERGY-EFFICIENCY ANALYSIS 34SECTION 6.0 CONSTRUCTION MANAGEMENT 35 6.1 PROJECT COSTS 35 6.2 PROJECT SCHEDULE 36 6.3 CONSTRUCTION LOGISTICS 37
PRODUCED BY AN AUTODESK STUDENT PRODUCT
PR
OD
UC
ED
BY
AN
AU
TOD
ES
K S
TUD
EN
T PR
OD
UC
T
PRODUCED BY AN AUTODESK STUDENT PRODUCT
PR
OD
UC
ED
BY
AN
AU
TOD
ES
K S
TUD
EN
T P
RO
DU
CT
PRODUCED BY AN AUTODESK STUDENT PRODUCT
PR
OD
UC
ED
BY
AN
AU
TOD
ES
K S
TUD
EN
T PR
OD
UC
T
PRODUCED BY AN AUTODESK STUDENT PRODUCT
PR
OD
UC
ED
BY
AN
AU
TOD
ES
K S
TUD
EN
T P
RO
DU
CT
“EXECUTIVE SUMMARY
3
For the College of Creative Studies, our biggest goals are to:• Foster the reciprical exchange of ideas between CCS faculty and students
through integrated learning spaces.• Integrate the various disciplines in the CCS through porous, interactive interiors.• Create a cost-effective and energy-efficient structure modeling sustainable
long-range development
In all of our decisions, we kept these and other goals in mind to meet your college’s requests and the university’s long-range development plan.
Success is meeting your goals and objectives. ”
Our design proposes 3 structures connected by terraces on the site south of Ucen Road. These structures will house approximately 39,000 sq. ft. of classrooms, faculty offices, studios, labs, administration, and public spaces dedicated to showcasing the College of Creative Studies and student work. The college will also provide about 2,500 sq. ft. of housing to accommodate 42 beds.
We go beyond the IBC and ADA codes to provide a comfort and safety. This site will utilize energy-efficient HVAC systems, take advatange of natural ventilation, and be partially covered by photovoltaic panels. These innovations reduce building energy use and will improve occupancy health with higher-quality indoor environments.
In addition to the CCS, we will resurface the parking lot north of Ucen Road to accomodate 144 vehicles. This reduction in vehicles emphasizes the university’s LRDP of creating a more pedestrian-friendly campus. The parking lot will be framed with a plaza that connects the CCS with the university library.
The project will run on a 36 month schedule that includes predesign, criteria development, RFP response period, design, construction, and postconstruction. Construction will take 20 months to complete.
SUSTAINABILITY & ENERGY-EFFICIENCY
OUR PROPOSAL FOR THE CCS
THE EMI ADVANTAGE
• 53,000 GSF, 39,000 ASF• Includes housng for 42-beds• $36,540,000 budget• 36 month schedule (20 months construction)
PROPOSAL SUMMARY
This team has experience developing educational buildings and residential complexes similar to the College of Creative Studies at UCSB, including:
• UNLV Greenspun Hall• UCSD Rady School of Management• UCI E. Campus Housing
We also take the time to research precedent structures and see how we can incorporate unique designs with the state-of-the-art facilities we create. This dedication to research and experience-building is what makes EMI a leader in innovation.
Our initial analysis concludes that we can achieve LEED Gold for the CCS project with smart planning and little additional cost. Many sustainable decisions were made in the early selection of materials, facades, and roof system. In addition to visible energy-efficient components of the structure, such as photovoltaic panels, our design incorporates native plants to Santa Barbara, vegetative roofs, recycled or readily available materials, and low-solar-gaining surfaces. With these premium additions and energy-efficient solutions, we propose a budget of $35,000,000 that includes building costs, general requirements, landscaping, and design.
Our design proposal for the College of Creative Studies will become a key component of the campus core and become a model of sustainable, value-engineered construction that future UCSB buildings will follow.
SECTION 1.3
CALIFORNIA SCIENCE CENTERLOS ANGELES, CA
UT TYLER PERFORMING ARTS CENTERTYLER, TX
UNLV GREENSPUN HALLLAS VEGAS, NV
EMI, Inc. was created with one goal in mind: to provide professional interdisciplinary and design-build services to clients seeking energy-efficiency, value, and innovation. We pride ourselves with integrity in business, safety in construction, and ambition in design.
Our design-build project delivery method contracts consultants (architects, engineers, facility planners, etc.) and constructors together to develop a project through near-continuous design. This collaboration allows opinions and ideas to be made with the consultation of all parties involved in the project to mitigate conflicts. To qualify for public projects, our design-build project delivery hires subcontractors based on qualifications, lowest cost, and availability. In practice, design-build is one of the fastest project delivery methods because there are no change orders to go through between the architect and constructor. In addition, the owner, like the College of Creative Studies, will only have one contract to deal with.
PRODUCED BY AN AUTODESK STUDENT PRODUCTP
RO
DU
CE
D B
Y A
N A
UTO
DE
SK
STU
DE
NT P
RO
DU
CT
PRODUCED BY AN AUTODESK STUDENT PRODUCT
PR
OD
UC
ED
BY
AN
AU
TOD
ES
K S
TUD
EN
T P
RO
DU
CT
SECTION 2.0 QUALIFICATIONS
4
2.1 KEY ELEMENTS OF THE DESIGN
From even our earliest schematic designs, we wanted to incorporate these elements into the College of Creative Studies:
• Exterior building circulation• Enclosures that sustain porosity to connect the CCS to the university• Architectural bio-mimicry• Integrated classrooms with faculty offices• Natural lighting and ventilation• Vegetative or photovoltaic roof systems
With these design goals in mind and constant collaboration between our interdisciplinary team and the CCS, we achieved a design that fulfill the requirements of this RFP, while responding to specific requests and suggestions from our clients. The proposed project will provide a combination of administration, classrooms, labs, studios, music facilities, student housing, a gallery, theaters, and excellent indoor and outdoor spaces to enjoy the Santa Barbara lifestyle. The entire team at EMI is excited to produce this cost-effective, high-quality project for the College of Creative Studies to boost the integrated education of highly motivated students.
N
WEST-FACING SECTION PERSPECTIVE
DESIGN DEVELOPMENT OF INTERIOR COURTYARDLANDSCAPING INTEGRATED INTO THE STRUCTURE
Like all the work we have completed in the past, EMI emphasizes on quality and value in our designs and during construction. Our team starts all projects by first understanding our client’s goals and expectations and use them to foster our own vision and objectives for the designs. The most important aspect to this project, is ensuring that our client receives the project they envision while providing alternatives and solutions that go beyond the College of Creative Studies expectations.
OBJECTIVE-DRIVEN DESIGN
5
EMI is an integrated team of designers and constructors with expertise in the entire lifecycle of construction. We have the knowledge and experience that allows us to provide customized solutions to your specific needs and desires. Allow us to provide preconstruction, design, and construction services tailored to give you value engineered cost estimates, accurate scheduling, and realistic proposals for your project. We strive to exceed your expectations with services guided by innovation and value.
We carry a team of professionals from some of the top schools in the nation, with up-to-date expertise in energy-efficient buildings, building information modeling, and integrated project delivery. Each member of our team has had a least 3 years experience in industry, designing and managing buildings ranging from commercial retail plazas, to complex apartment communities, to integrated university learning spaces.
COMPLETED PROJECTS
SUMMARY OF QUALIFICATIONS
CALIFORNIA POLYTECHNIC STATE UNIVERSITYCONSTRUCTION INNOVATIONS CENTERMARCH 2006- JUNE 2008
In addition to the projects below, EMI has also provided construction management, preconstruction, general contracting, or design consultation services for these projects:
• University of Nevada, Las Vegas, NV - Greenspun Hall• University of California, San Diego, CA - Rady School of Management• University of California, Irvine, CA - E. Campus Housing• City Heights Urban Village Townhomes & Office Center - San Diego, CA• Metlox Town Center - Manhattan Beach, CA• University of Texas, Tyler, TX - Performing Arts Center• Harvard University NW Science - Cambridge, MA
These projects all have elements similar to the CCS with integrated uses of spaces, similar size of developments, modern student housing, and sustainable building methods. This extensive resume of complete projects allows us to share with the College of Creative Studies our experiences while constantly trying to improve on our previous work.
CALIFORNIA SCIENCE CENTERLOS ANGELES, CAJANUARY 2002 - MARCH 2004
SANTA MONICA PUBLIC LIBRARYSANTA MONICA, CAJANUARY 2002 - MARCH 2004
MILLER CHILDREN’S HOSPITALLONG BEACH, CAFEBRUARY 2007 - JULY 2009
The EMI team boasts a roster of experienced and licensed professionals with advanced degrees and specialized certifications from a variety of industry agencies. Our work is backed by our constant training in the classroom and in the industry to provide reputable service, integrity, and professionalism.
Work at EMI is performed using cutting edge technology with an old-fashioned, yet efficient hands-on approach. In addition to our highly collaborative fieldwork, our professionals have a broad software base to use in their project development such as:
• Adobe Creative Suite• Autodesk AutoCAD & Revit• Navisworks• Primavera• Rhino 3-D• Vico Virtual Construction
Advanced design software and building information modeling allows our integrated team to propose designs that any subcontractor can review and understand. Designers can visualize how their building feels and looks with digial walkthroughs, while engineers can see how structural and auxilary components fit into the project, and constructors can provide constructability reviews detailing how workflows can be accomplished and anticipate what challenges may arise in the field. The end result is a streamlined project delivery that saves our clients time and money.
SECTION 2.0 QUALIFICATIONS2.2 OUR RESUME
TONY ROSEMANN, S.E., P.E., DBIASTRUCTURAL ENGINEER
University of California, San Diego, CAMasters in Structural Engineering, 2005
California Polytechnic University,San Luis Obispo, CABachelors in Architectural Engineering, 2004
References: John Lawson, S.E.Cal Poly San Luis Obispo
Architectural Engineering [email protected]
Richard RathckeSenior Project Manager
McCormick [email protected]
6
2.3 OUR TEAM - PRINCIPAL OFFICERS
ALESE ASUCKIAN, S.E., P.E., LEED APPRINCIPAL STRUCTURAL ENGINEER
University of California, Berkeley, CAMasters in Earthquake Engineering, 2007
California Polytechnic University, San Luis Obispo, CABachelors in Architectural Engineering, 2006
References: Abe Lynn, Ph.D., P.E.Cal Poly San Luis Obispo
Architectural Engineering [email protected]
Barry HooperProject Manager
SF Dept. of Environment Green [email protected]
RYAN BURGER, ASLA, LEED APPRINCIPAL LANDSCAPE ARCHITECT
Harvard School of Design, Cambridge, MAMasters in Urban Design, 2008
California Polytechnic University, San Luis Obispo, CABachelors in Landscape Architecture, 2006
References: Omar FaruqueLandscape Architecture Professor
Cal Poly San Luis [email protected]
CHRISTINA HACKETT, AIA, LEED APPRINCIPAL ARCHITECT
Mass. Institute of Technology, Cambridge, MAMasters in Architecture, 2008
California Polytechnic University, San Luis Obispo, CABachelors in Architecture, 2006
References: Denis Townsend, AIAPrincipal Architect
Townsend Architectural [email protected]
Tom ThomasChief Information Officer
GILBERT BASTIDAS, CMAA, LEED APPROJECT MANAGER
University of Southern California, Los Angeles, CAMasters in Real Estate Development and Sustainable Design, 2005
California Polytechnic University, San Luis Obispo, CABachelors in Construction Management, 2002
References: Grant RobbinsPresident
Robbins | Reed [email protected]
Brent SpiegelProject Manager
Robbins | Reed [email protected]
EMMANUEL GOMEZ, ASLA, DBIALANDSCAPE ARCHITECT
University of California, Berkeley, CAMasters in Landscape Architecture, 2008
California Polytechnic University, San Luis Obispo, CABachelors in Landscape Architecture, 2006
References:Richard SullivanLandscape Contractor
Enchanting [email protected]
ALEXSON LIM, CMAA, LEED AP, DBIAPRECONSTRUCTION MANAGER
Stanford University, Menlo Park, CAMasters in Construction Engineering Management, 2007
California Polytechnic University, San Luis Obispo, CABachelors in Construction Management, 2005
References: Scott Kelting, LEED AP, CGPCal Poly San Luis Obispo
Construction Management [email protected]
SECTION 2.0 QUALIFICATIONS
7
THE TRADITIONAL DESIGN-BID-BUILD PROCESSThe design-bid-build project delivery method accounts for 3/4 of all projects developed in the U.S. It is the traditional delivery method and is the required method to qualify for public projects.
In this method, the owner contracts the architect and constructor separately. The architect and constructor then subcontract any work necessary to deliver the project for the owner.
Subsequently, the architects and constructor are forced to work together but do not have a direct contractural relationship to each other - resulting in a conflict of interests.
We do not recommend this delivery method because it involves:• Least opportunity for quality• Slow development process• Heavy owner management
The figure to the left represents the contractural organization of the traditional design-bid-build process.
2.4a OUR ORGANIZATION
ADVANTAGES OF THE DESIGN-BUILD PROCESSThe figure to the right highlights the key advantages of design-build project delivery versus traditional design-bid-build. This delivery method provides the CCS with only one contract to EMI, Inc., which will provide construction management, design services, and postconstruction analysis.
In practice, design-build is the fastest delivery method, allowing us to devlop your project within 3 years, with less than 2 years of that time entailing actual construction. Essentially, design-build project delivery enables EMI, Inc. to delivery the highest quality structure that fits your budget without sacrificing your goals and needs.
DESIGN-BUILDFor this project, we recommend utilizing design-build project delivery. Design-build is an innovative delivery method that offers clients the opportunity to collaborate with an integrated design and construction team to achieve their visions. WIth design-build, you will only have one contract that creates a contractural relationship between an architect and contractor to deliver your project. In our organization, we provide in-house design from architects and engineers, as well as construction management from experienced professionals.
We propose for the College of Creative Studies to contract EMI, Inc. to act as the designer/contractor for the proposed project at UCSB. Subcontractors will then be selected based on lowest cost to qualify for a public project contract. In addition to cost, subcontractors will also be selected on qualifications and availability as necessary. This organization will allow us to provide the design-build services we specialize in while ensuring that you receive the best value for the subcontracted consultants and constructors.
DESIGNDesign will be spearheaded by our principal architect, Chistina Hackett. Christina and her team of architects consult with the entire EMI team at weekly meetings to establish communication between design, engineering, and construction. In addition to buiding design, we have an in-house landscape and urban design team to integrate the site with the building and further achieve the visual and spatial objectives of the CCS.
ENGINEERSThroughout design, engineers will consult with designers to achieve the most efficient and buildable structure possible. We have in-house structural engineers and will subcontract mechanical and civil engineers to help plan site development, coordinate MEP designs, and successfully incorporate auxillary systems into the building design.
CONSTRUCTIONConstruction will be managed by our preconstruction manager and coordinated by our project manager and superintendents. These professionals will provide constructability reviews and overall input into the design. As progress of the project proceeds beyond design, specialties and trade subcontractors will be selected and managed by this branch of our team.
SECTION 2.0 QUALIFICATIONS2.4b PROJECT DELIVERY METHOD
UNIVERSITY OF SAN DIEGORADY SCHOOL OF MANAGEMENTCONSTRUCTION: March 2006 - September 2006PROJECT BUDGET: $38,900,000SIZE: 65,000 SF TYPE: Steel frame, metal panels
8
2.6 EXEMPLARY PROJECTS
The Rady building is home to a new management school for UCSD which includes multiple tiered classrooms, administrative offices, Dean’s Suite, Executive Education/EMBA offices, and other support areas. The University is planning to move forward with the design for a Phase II building that will tie in with this project.
EMI, Inc. provided design consultation and preconstruction services for UCSD. We utilized building information modelling to mitigate mechanical system clashes with architectural and structural elements throughout the building. We remained as partners throughout the development of the site, overseeing construction as well as coordinating with overseas suppliers for the exterior cladding.
UNIVERSITY OF NEVADA, LAS VEGASGREENSPUN HALLCONSTRUCTION: January 2007 - December 2008PROJECT BUDGET: $93,700,000SIZE: 120,000 SF, 5 floorsTYPE: Steel-frame, concrete panels
Acting as a CM-at-risk, EMI, Inc. teamed up with the design team at HKS Architects, consulting with the owner throughout preconstruction stages. This process allowed us to meet and exceed the objectives of the Green Spun Hall Project by implementing cost-effective solutions. We coordinated with subcontractors to value-engineer and to address architectural and engineering constructability challenges before the actual construction occurred.
The Greenspun Hall has similarities to the CCS and is comprised of energy-efficient building products we would like to use at UCSB, such as unobtrusive photovoltaics and horizontal louvers.
EMI manifests our clients’ visions while redefining the built and natural environment, through design, engineering, and construction in a design-build approach, guided by integrity, innovation, and the pursuit of building excellence. ”
“
The Greenspun hall houses six of the seven academic units that comprise the Greenspun College of Urban Affairs. For the first time in the college’s history, the College of Urban Affairs are now integrated into spaces conducive to collaboration and innovation.
Greenspun Hall was designed, in part, to help foster closer collaboration among department faculty and to encourage interdisciplinary academic efforts. The Greenspun Hall houses the following spaces:
•MediaFacility(1stfloor)•StudentAdvisingCenter(2ndfloor)•HankGreenspunSchoolofJournalismandMediaStudies(2ndFloor)•EnvironmentalStudies(3rdFloor)•SchoolofSocialWork(3rdFloor)•CommunicationStudies(4thFloor)•PublicAdministration(4thFloor)•CriminalJustice(5thFloor)•OfficeoftheDeanoftheCollegeofUrbanAffairs(5thFloor)
The building has approximately 63,000 SF of conditioned space and 101,000 SF of new construction. The project also includes associated sitework, including landscaping, utilities, and tie-ins to existing parking areas.
The building is four stories with a portion of the first floor below grade. The exterior skin consists of a combination of composite (phenolic) panels, stone composite panels, aluminum curtain/window walls, and plaster. The main mechanical systems are fed by a campus hot and chilled water system that was extended to serve the building. The project also included associated sitework, including landscaping, utilities, and tie-ins to existing parking areas.
The Rady School of Management offers high-quality design elements and energy-efficient solutions within an affordable budget. Similar to the CCS, the site was located directly adjacent to student housing facilities and located on major pedestrian pathways making the project limited in construction hours, material laydown availability, and involved heavy traffic control planning.
SECTION 2.0 QUALIFICATIONS2.5 OUR MISSION
EMI, Inc. is dedicated to employing cutting edge technology and eco-responsive building methods to develop an intellectual environment conducive to creative
and collaborative learning that embodies the College of Creative Studies. ”3.2 PROJECT GOALS & OBJECTIVES
1. Foster a reciprocal exchange of ideas between CCS students and faculty through a design of integrated learning spaces.
2. Bridge a connection between the CCS and the University.
3. Integrate the various disciplines in the CCS through porous, interactive spaces that reflect the unique curriculum of the CCS.
4. Coalesce the fundamentals of sustainable building, design, and bio-mimicry to create an exemplary structure for future UCSB buildings to model after.
5. Create a energy-efficient building that is accessible to all members of the university and adaptive to the ever-changing campus.
“
9
3.1 PROJECT VISION
SECTION 3.0 PROJECT OVERVIEW
1.Reduce building energy consumption by at least 25% in comparison to standard buildings of similar size and occupancy.
2. Connect the CCS to the University with glazing that works with daylight to achieve passive heating and cooling.
3. Program spaces that allow faculty and students to interact and mingle in spaces adjacent to one another.
4.Provide structural elements, such as dendritic columns, that incorporate bio-mimicry and add value to the design of the CCS.
5. Establish a site that follows the Campus 2025 vision and LRDP by integrating the concept of large roads that will run directly adjacent to the college.
GOALS
OBJECTIVES
10
3.3 PROGRAM SUMMARY
SECTION 3.0 PROJECT OVERVIEW
UCen
Library
To UCen
Legend Cirrculation Views Wind Shade Vegetation
UCen
Library
To UCen
Legend Cirrculation Views Wind Shade Vegetation
Potential views of the lagoon and the ocean according to the Vision 2025
Important circulation intersection and node
Problematic circulation path through parking lot
- Site will be greatly affected by the new proposed Master Plan for 2025.
- Site is neighbored by buildings of many different uses (residential, classrooms, library and public spaces).
- Many opportunities to take advantage of vistas
View to the mountains and link to existing campus corridor
Node
N
11
SECTION 4.0 CONCEPT DESCRIPTION
Our structural design is based on a simple grid system that reflects the building’s linear form. The structural system is integrated with the architectural design intent and space programs; maximizing beam spans allow for open floor plans and avoiding the use of load-bearing walls allows for program changes based on the College of Creative Studies’ future development.
Steel is the project’s structural framing material. Comprised of recycled content, steel is an appropriate choice for an environmentally-conscious project, is readily available, and allows for a relatively fast construction process. The structure was designed to frame vistas and view corridors from the site; a steel structural system consisting of moment frames and braced frames will be used to resist lateral forces in our building. This will allow for an open and inviting space that isn’t constricted by shear walls. Moment frames will resist the longitudinal lateral loads of each building, while braced frames will resist the transverse lateral loads.
The lateral force-resisting system consists of Buckling-Restrained Braced Frames (BRBF’s) and Reduced Beam Section (RBS) Moment Frames. BRBF’s are an ideal lateral force resisting system for high seismic areas like California. The main component of BRBF’s is the brace, which is braced against buckling under compressive loads by a concrete casing that surrounds the brace’s inner steel core plates. This buckling-restraining system limits out-of-plane movements and allows the braced frame to sustain large compressive strains. RBS Moment Frames are designed to have a ductile response to seismic forces. The reduced beam improves the beam-to-column connection design; the beam of an RBS moment frame is weakened when portions of the beam flanges are trimmed away in the region adjacent to the beam-to-column connection. This causes yielding to occur within the reduced section of the beam, which is an area that can sustain large strains, and avoids potentially catastrophic damage in the column.
Our design team has decided to exceed the minimum seismic code requirements of life safety and design for immediate occupancy. Structural damage in the event of an earthquake will be minimized, reducing the amount of repair necessary to restore the building to an operational level. As part of the university’s academic core, a more sustainable and long-lasting design will ensure the building’s resilience in the event of an earthquake.
A STRUCTURAL SYSTEM THAT BUILDS ON DESIGNCONTRASTING GEOMETRIC ARCHITECTURE WITH ENTICING LANDSCAPING
INNOVATIVE DESIGN PAIRS QUALITY WITH CONSTRUCTABILITY
The landscape design is focused on attracting people to the site, taking advantage of scenic views and contrasting the geometric properties of the building. Sweeping curves tie the existing and proposed circulation paths, through the building, to the interior courtyard. This creates a site that is very porous and well connected to the rest of the campus. Although the interior courtyard is openly connected to the surrounding campus ,it still achieves an intimate and inward focused feel through the use of wrapping seat walls and sheltering plant material.
The proposed design for the College of Creative Studies at UC Santa Barbara embodies the organic nature of art and music with the geometrical essence of math and science. The contrasting landscape and building design work together to create an environment that symbolizes the diversity of the CCS. With energy-efficiency in mind, the building integrates sustainability features, such as solar panels and horizontal louvered wood paneling, as a key feature of the architectural aesthetics.
All buildings are designed to be one classroom wide to create narrow spaces that will allow controlled, natural light to penetrate all rooms. Exterior circulation influenced the form of the buildings, which are three separate structures connected with terraces and catwalks. The use of exterior circulation reduces heating/cooling of non-assignable spaces to save energy and also acts as shading devices for lower levels. Exterior circulation is a cost-effective feature of the building that allows exterior lighting systems to serve for site security and circulation illumination.
Terraces are used primarily to bridge the structures together, but also framing the interior courtyard. These terraces, located on each floor level of the structure, allows students, faculty, and visitors to enjoy the outdoor environment and the views of the surrounding university and lagoon.
Our designers programmed spaces to take advantage of daylighting schemes and to create a functional flow of learning spaces. Studios on the northern part of the site take advantage of indirect daylighting for unobstrusive natrual lighting and ventilation.
Site visits and Google Earth imaging revealed the opportunity for unobstructed views of the ocean from the 2nd and 3rd of the CCS. Thus, residential housing on the south part of the site provides beautiful views of the ocean. These south-facing spaces will have insulated windows in combination with horizontal louvers to control sunlight and allow for natural heating or passive cooling.
Integration of the staff office, classrooms, and labs were also important in the design of the CCS. Staff offices are flanked by classrooms, allowing students and faculty to intermingle and communicate openly among the college. The varying spaces from studios, to computer labs, to science labs and classrooms are spread out among the buildings to effectively integrate the majors of the CCS without compromising functionality of learning spaces.
The structure is also an integral part of the design, which is seen by the exposed moment and braced frames in not only the buildings, but also the solar panel canopy and the shading devices. The modulated design not only brings costs down, but it also allows for different functions to be placed within the spaces.
GROUND LEVEL
The three buildings are placed in a position to create an interior courtyard for the College of Creative Studies. The courtyard is par-tially shaded by a solar panel shading canopy that integrates the panels as a part of the architectural aesthetics. Placed on the southern part of the site, the buildings draw pedestrians into the courtyard coming from the core of campus to housing, and on campus residents walking onto campus.
LANDSCAPE DESIGN
The organic landscape, is designed to contradict the geometrical design, which brings the arts and maths and sciences together. The sculpture garden is placed outside of the gallery and near the theater lobby, creating strong indoor and outdoor relationships among all the di�erent spaces called for in the program. The site is also designed to allow for easy accessibility to all interior and exterior spaces from the interior courtyard.
STUDIOS/LABS/OFFICES
The design incorporates full integration of sta� o�ces and classrooms/labs, allowing for interaction between students and professors on a daily basis when walking around the site. All buildings are one classroom wide to allow for all interior spaces to have natural lighting and ventilation. The design also incudes all exterior circulation among catwalks to ensure that no energy is wasted heating and cooling unnecessary spaces.
Executive Conference with views facing south, looking over at the ocean
The Sculpture garden con-sists of raised planter beds to display student sculptures
Catwalks allow for exterior circulation, ensuring conser-vation of energy so that heating and cooling is not wasted on hallways. Both the second and third level have terraces, so the stu-dents and faculty can enjoy the nice Santa Barbara weather and the views.
The working sculpture yard is located near both the wood/metal shop and the sculpture studio to allow for closeness in proximity
The working sculpture yard is located near both the wood/metal shop and the sculpture studio to allow for closeness in proximity
UCenn road will be paved to create a more pedestrian walk way that is safer for occupants. The paving will also still allow for service and emergency vehicles to access other parts of the sites.
Service vehicle parking is located on the west side of the site where it is currently located. The location of the parking is near the theaters and administration for con-venience.
12
SECTION 4.0 CONCEPTUAL DESIGN
5.1 BUILDING CIRCULATION
DN
DN
DN
UP
UP
DNUP
DNUP
ART STUDIO ART STUDIO ART FACULTY
STAFF STAFF STAFFSTAFF STAFF STAFF
STAFF
40 PERSON
25 PERSON LAB
25 PERSON LAB
15 PERSON LAB
15 PERSON LAB
25 PERSON LAB
25 PERSON LABKITCHEN
STUDENTLOUNGE
BATHROOM
STAFF
STAFF
STAFF
STAFF
STAFF
UP
UPUP
GALLERY SCULPTURESTUDIO
WOOD/METAL SHOP
STORAGE
THEATER 1
COMPUTER SCIENCE LAB
FAB LAB STUDENT COMPUTER LAB
15 PERSON LAB
15 PERSON LAB
COMMON SCIENCE LAB
STAFF
STAFF
STAFF
STAFF
STAFF
STAFF
STAFF
RECORD STORAGE
ASS. DEAN STORAGE
ASS. DEAN
ASS. DEAN
BREAK ROOM
DEAN
RECEPTION
DOASS.
DOUNDER-GRAD
OFFICE
UNDER-GRAD
OFFICE
UNDER-GRAD
OFFICE
LOBBY
THEATER 2
13
SECTION 4.0 CONCEPTUAL DESIGN
5.2 FLOOR PLANS
SECOND LEVELFIRST LEVEL
NN
DN
DN
DNUP
DN
20 PERSON STUDIO ART FACULTY
MUSIC STUDIO
MUSIC RECORDING
STUDIO
STORAGE
STAFF
STAFF
STAFF
STAFF
STAFFSTAFF
STAFF
STAFF
BOOK ROOM
STAFF
MUSIC PRACTICE
MUSIC PRACTICE
MUSIC PRACTICE
MUSIC PRACTICE
MUSIC COMPOSITION
STUDIO
KITCHEN
STUDENTLOUNGE
BATHROOM
CONFERENCE ROOM
DN
14
SECTION 4.0 CONCEPTUAL DESIGN
5.2 FLOOR PLANS
FOURTH LEVELTHIRD LEVEL
NN
15
SECTION 4.0 CONCEPTUAL DESIGN
5.3 SECTIONS
2
1
N
N
16
SECTION 4.0 CONCEPTUAL DESIGN
5.4 PERSPECTIVESAERIAL PERSPECTIVE OF SITE FACING SOUTHEAST
N
17
SECTION 4.0 CONCEPTUAL DESIGN
5.4 PERSPECTIVESENTRANCE VIEW FROM GROUND LEVEL
N
18
SECTION 4.0 CONCEPTUAL DESIGN
5.4 PERSPECTIVESNORTHWEST APPROACH
19
SECTION 4.0 CONCEPTUAL DESIGN
5.4 PERSPECTIVESINTERIOR COURTYARD FACING SOUTHWEST
20
SECTION 4.0 CONCEPTUAL DESIGN
5.4 PERSPECTIVESSOUTHEAST APPROACH
21
SECTION 4.0 CONCEPTUAL DESIGN
5.4 PERSPECTIVESINTERIOR COURTYARD VIEW FROM THIRD FLOOR TERRACE
22
SECTION 4.0 CONCEPTUAL DESIGN
5.4 PERSPECTIVESSECOND FLOOR MEZZANINE IN THEATER LOBBY
23
SECTION 4.0 CONCEPTUAL DESIGN
EXPLODED PERSPECTIVE OF STRUCTURAL ELEMENTS5.5 STRUCTURAL DESIGN
Buckling restrained brace frame and moment frame compose the lateral force resistance systems throughout the structure
Beam and joist system supporting concrete decks and roof systems
Horizontal louvers supported by columns extending from ground level to photovoltaic panels
Photovoltaic panels supported by beams connected to roof of east structure. Cantilever achieved by columns extending to ground level
Dendritic columns support terraces to achieve architectrual bio-mimicry
6” concrete composite decks comprise levels. Floors will have finished concrete topping or carpetting depending on spaces
22-27’ drilled caissons will be drilled into bedrock to provide a foundation that allows the CCS to achieve immediate occupancy following earthquakes
Grade beams will mount caissons to a 6”- deep slab on grade to top off the substructure
UP
UP
UP
1
3
2
A B C F
18
19
20
21
22
23
24
1.1
26
N
17
25
O
D E G
4
5
H
P R S T U V
I J L MK
6
7
8
9
10
11
12
13
14
15
16
Q
27
28
29
30
31
32
33
64 65 66 6768 69
R.1
21.1
7.1
W10x49 W10x49 W10x49 W10x49
W14x53 W14x90 W14x53W14x90
W14x53 W14x90 W14x53W14x90
W14x90
W14x90
W14x90
W14x90
W14x90
W14x53
W14x90
W14x53
W14x90
W14x90
W14x90
W10x33
W10x45
W10x45
W10x45
W10x45
W10x45W10x45
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER27' LONG
3' DIA. DRILLED PIER27' LONG
3' DIA. DRILLED PIER27' LONG
3' DIA. DRILLED PIER18' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER18' LONG
3' DIA. DRILLED PIER18' LONG
3' DIA. DRILLED PIER18' LONG
3' DIA. DRILLED PIER18' LONG
3' DIA. DRILLED PIER18' LONG
3' DIA. DRILLED PIER18' LONG
3' DIA. DRILLED PIER18' LONG
3' DIA. DRILLED PIER18' LONG
3' DIA. DRILLED PIER18' LONG
3' DIA. DRILLED PIER18' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER18' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER18' LONG
3' DIA. DRILLED PIER18' LONG
3' DIA. DRILLED PIER18' LONG
3' DIA. DRILLED PIER18' LONG
3' DIA. DRILLED PIER18' LONG
3' DIA. DRILLED PIER18' LONG
6" THICKSLAB-ON-
GRADE
6" THICKSLAB-ON-
GRADE
6" THICKSLAB-ON-
GRADE
W14x53
W10x49
3' DIA. DRILLED PIER22' LONG
37' - 6" 31' - 10" 10' - 10" 7' - 2" 21' - 0" 6' - 0" 11' - 6"
39' - 0" 17' - 6"
125' - 10"
11' -
10
1/2"
11' -
10
1/2"
16' -
3"
6' -
0 3/
32"
23' -
9"
46' -
0 3
/32"
K.1
25' - 10 7/16" 13' - 7 7/8" 7' - 5" 10' - 10" 22' - 6" 11' - 1 7/16"
39' - 6 9/32" 44' - 5 7/16"
91' - 4 23/32"
29' -
10
3/4"
17' -
4 1
/4"
4' -
8"18
' - 5
"10
' - 8
"21
' - 6
3/4
"26
' - 1
0 1/
4"17
' - 8
"10
' - 6
"19
' - 0
"5'
- 6"
35' -
0"
81' -
0"
182'
- 1"
13' - 7 7/16" 5' - 8" 7' - 11 23/32" 7' - 0 9/32" 8' - 2 19/32" 4' - 3 13/32" 13' - 7 1/2"
15' - 0" 26' - 1 1/2"
60' - 4 15/16"
26' -
6"
24' -
2 3
/4"
25' -
8"
22' -
11
7/8"
25' -
8 1
/8"
29' -
11
1/4"
9' -
8 17
/32"
155'
- 0"
26' - 10 5/32"
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER27' LONG
3' DIA. DRILLED PIER27' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER22' LONG3' DIA. DRILLED PIER
22' LONG3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER27' LONG3' DIA. DRILLED PIER
27' LONG
3' DIA. DRILLED PIER27' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER22' LONG
W10x49
W10x49W10x49
W10x49 W10x49
W10x49 W10x49
W10x49
W10x49 W10x49 W10x49
W10x49W10x49
W10x49
W10x49
W10x49
W10x49 W10x49 W10x49 W10x49
W10x49
W10x49
W10x49
W10x49
3' DIA. DRILLED PIER22' LONG
W10x49
W10x49
3' DIA. DRILLED PIER22' LONG3' DIA. DRILLED PIER
22' LONG
W10x49
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER22' LONG
24"x24" GRADE BEAM, TYP.
24"x24" GRADE BEAM, TYP.
24"x24" GRADE BEAM, TYP.
DENDRITIC STRUCTURE BASE, TYP.
W30x261W30x261
W30x261 W30x261
W30x261W30x261
W30x261
W30x261W30x261
W30x261
W30x261
W30x261
W30x261
W30x261
W30x261
W30x261
FIRST LEVEL / FOUNDATION PLANSCALE: 1/8" = 1' - 0"
1
DN
DN
UP
UP
DNUP
1
3
2
A B C F
18
19
20
21
22
23
24
1.1
26
N
17
25
O
D E G
4
5
H
P R S T U V
I J L MK
6
7
8
9
10
11
12
13
14
15
16
Q
27
28
29
30
31
32
33
64 65 66 6768 69
R.1
21.1
7.1
W14
W14
W14
W14
W14
W14
W14
W14
W14
W27
W27
W27
W27
W27
W27
W27
W27
W16
W16
W16
W16
W16
W16
W16
W16
W16
W16
W16
W16
W16
W10
W10
W10
W10
W10
W10
W10
W10
W10
W10
W10
W10
W27W10
W14
W21
W21
W21
W21
W21
W21
W21
W21
W21
W21
W12
W12
W12
W12
W12
W12
W12
W12
W12
W12
W12
W12
W12
W12
W12
W12W12
W14
W14
W14
W14
W14
W14
W14
W14
W14
W14
W14
W14
W14
W14
W14
W14
W14
W12 W14
W21
W21
W21
W21
W21
W21
W21
W21
W21
W21
W21
W21
W21
W21
W21
W21
W21
W21
W12
W12
W12
W12
W12
W12
W12
W12
W12
W12
W12
W12
W12
W12
W12
W12
W12
W12W12
W14
W14
W14
W14
W14
W14
W14
W14
W14
W14
W14
W14
W14
W14
W14
W14
W14
W14
W27
W27
W27
W27
W27
W27
W27
W27
W27
W16
W16
W16
W16
W16
W16
W16
W16
W16
W16
W16
W16
W16
W10
W10
W10
W10
W10
W10
W10
W10
W10
W10
W10
W10
W10
W27
K.1
37' - 6" 31' - 10" 10' - 10" 7' - 2" 21' - 0" 6' - 0" 11' - 6"
39' - 0" 17' - 6"
125' - 10"
11' -
10
1/2"
11' -
10
1/2"
16' -
3"
6' -
0 3/
32"
23' -
9"
46' -
0 3
/32"
25' - 10 7/16" 13' - 7 7/8" 7' - 5" 10' - 10" 22' - 6" 11' - 1 7/16"
39' - 6 9/32" 44' - 5 7/16"
91' - 4 23/32"
29' -
10
3/4"
17' -
4 1
/4"
4' -
8"18
' - 5
"10
' - 8
"21
' - 6
3/4
"26
' - 1
0 1/
4"17
' - 8
"10
' - 6
"19
' - 0
"5'
- 6"
35' -
0"
81' -
0"
182'
- 1"
13' - 7 7/16" 5' - 8" 7' - 11 23/32" 7' - 0 9/32" 8' - 2 19/32" 4' - 3 13/32" 13' - 7 1/2"
15' - 0" 26' - 1 1/2"
60' - 4 15/16"
26' -
6"
24' -
2 3
/4"
25' -
8"
22' -
11
7/8"
25' -
8 1
/8"
29' -
11
1/4"
9' -
8 17
/32"
155'
- 0"
26' - 10 5/32"
-
-Moment FrameElevation
-
SEISMIC JOINT
SEISMIC JOINT
SEISMIC JOINT
7" THICK CONCRETEDECK SLAB
7" THICK CONCRETEDECK SLAB
-
-BRBF Elevation
KEY
MOMENT CONNECTION
CANTILEVER CONNECTION
BRACED FRAME
W21
W24
W24
W24
W24
W24
W24
W24
W24
W24
W24
W24
W24
W24
W24
W24
W24 W
24
W24
W24
W24
W24
W24
W24
W24
W24
W24
W24
W24 W24
W24
W24
W24
W24
W24
W24
W24
W24
W30 W30
W30
W30
W30
W30 W30
W30W30
W30 W30W30 W30
W24
W24
W14
W14
W14
W14
W14
W14
W16
W16
W16
W30
W30
W30
W30
W24
W24
SECOND LEVEL FRAMING PLANSCALE: 1/8" = 1' - 0"
2
24
SECTION 4.0 CONCEPTUAL DESIGN
5.6 STRUCTURAL FRAMING PLANSFIRST LEVEL FRAMING/FOUNDATION PLAN SECOND LEVEL FRAMING PLAN
NN
1
3
2
A B C F
18
19
20
21
22
23
24
1.1
26
N
17
25
O
D E G
4
5
H
P R S T U V
I J L MK
6
7
8
9
10
11
12
13
14
15
16
Q
27
28
29
30
31
32
33
64 65 66 6768 69
R.1
21.1
7.1
restroom
W14
W14
W14
W14
W14
W14
W14
W14
W14
W14
W14
W14
W14
W14
W14
W14
W14
W14
W14
W8
W8
W8
W8
W8
W8
W8
W8
W8
W8
W8
W8
W8
W8
W8
W8
W16
W16
W14
W8
W16 W16
W16 W16 W16
W16 W16 W16
W14
W8
W14
W8
W14
W8
W14
W8
W14
W8
W14
W8
W14
W8
W14
W8
W14
W8
W14
W8
W14
W8
W14
W8
W30
W24
W24
W24
W24
W24
W24
W24
W24
W24
W24
W24
W24
W24
W24
W24
W24
W24
W24
W24
W8
W8
W8
W8
W16
W16
W16
W16
K.1
37' - 6" 31' - 10" 10' - 10" 7' - 2" 21' - 0" 6' - 0" 11' - 6"
39' - 0" 17' - 6"
125' - 10"
11' -
10
1/2"
11' -
10
1/2"
16' -
3"
6' -
0 3/
32"
23' -
9"
46' -
0 3
/32"
25' - 10 7/16" 13' - 7 7/8" 7' - 5" 10' - 10" 22' - 6" 11' - 1 7/16"
39' - 6 9/32" 44' - 5 7/16"
91' - 4 23/32"
29' -
10
3/4"
17' -
4 1
/4"
4' -
8"18
' - 5
"10
' - 8
"21
' - 6
3/4
"26
' - 1
0 1/
4"17
' - 8
"10
' - 6
"19
' - 0
"5'
- 6"
35' -
0"
81' -
0"
182'
- 1"
13' - 7 7/16" 5' - 8" 7' - 11 23/32" 7' - 0 9/32" 8' - 2 19/32" 4' - 3 13/32" 13' - 7 1/2"
15' - 0" 26' - 1 1/2"
60' - 4 15/16"
26' -
6"
24' -
2 3
/4"
25' -
8"
22' -
11
7/8"
25' -
8 1
/8"
29' -
11
1/4"
9' -
8 17
/32"
155'
- 0"
26' - 10 5/32"
-
-Moment FrameElevation
-
-
-BRBF Elevation
KEY
MOMENT CONNECTION
CANTILEVER CONNECTION
BRACED FRAME
W12W12
W24
W24
W24
W24
W24
W24
W24
W24
W24
W24
W24
W24 W
24
W24
W24
W24
W24
W24
W24
W24
W24
W24
W30 W30
W30
W30
W30
W30 W30
W30W30
W30 W30 W30
W24
W24
W30
W30
W30
FOURTH LEVEL FRAMING PLANSCALE: 1/8" = 1' - 0"
4
W30
W24
W24
W24
W14
W16
W14
W14
W14
W14
W16
DN
DN
DN
1
3
2
A B C F
18
19
20
21
22
23
24
1.1
26
N
17
25
O
D E G
4
5
H
P R S T U V
I J L MK
6
7
8
9
10
11
12
13
14
15
16
Q
27
28
29
30
31
32
33
64 65 66 6768 69
R.1
21.1
7.1
W27
W27
W27
W27
W27
W27
W10
W10
W10
W10
W10
W10
W10
W10
W10
W10
W10
W10
W10
W27
W27
W27
W27
W27
W27
W27
W27
W16
W16
W16
W16
W16
W16
W16
W16
W16
W16
W16
W16
W16
W10
W10
W10
W10
W10
W10
W10
W10
W10
W10
W10
W10
W27
W21
W21
W21
W21
W21
W21
W21
W21
W21
W21
W21
W21
W12
W12
W12
W12
W12
W12
W12
W12
W12W12
W14
W14
W14
W14
W14
W14
W14
W14
W14
W12
W12
W12
W12
W12
W12
W12
W12
W12
W12
W14
W14
W14
W14
W14
W14
W14
W14
W14
W14
W21
W21
W21
W21
W21
W21
K.1
37' - 6" 31' - 10" 10' - 10" 7' - 2" 21' - 0" 6' - 0" 11' - 6"
39' - 0" 17' - 6"
125' - 10"
11' -
10
1/2"
11' -
10
1/2"
16' -
3"
6' -
0 3/
32"
23' -
9"
46' -
0 3
/32"
25' - 10 7/16" 13' - 7 7/8" 7' - 5" 10' - 10" 22' - 6" 11' - 1 7/16"
39' - 6 9/32" 44' - 5 7/16"
91' - 4 23/32"
29' -
10
3/4"
17' -
4 1
/4"
4' -
8"18
' - 5
"10
' - 8
"21
' - 6
3/4
"26
' - 1
0 1/
4"17
' - 8
"10
' - 6
"19
' - 0
"5'
- 6"
35' -
0"
81' -
0"
182'
- 1"
13' - 7 7/16" 5' - 8" 7' - 11 23/32" 7' - 0 9/32" 8' - 2 19/32" 4' - 3 13/32" 13' - 7 1/2"
15' - 0" 26' - 1 1/2"
60' - 4 15/16"
26' -
6"
24' -
2 3
/4"
25' -
8"
22' -
11
7/8"
25' -
8 1
/8"
29' -
11
1/4"
9' -
8 17
/32"
155'
- 0"
26' - 10 5/32"
-
SEISMIC JOINT
SEISMIC JOINT
7" THICK CONCRETEDECK SLAB
7" THICK CONCRETEDECK SLAB
-
-BRBF Elevation
KEY
MOMENT CONNECTION
CANTILEVER CONNECTION
BRACED FRAME
W12W12
W24
W24
W24
W24
W24
W24
W24
W24
W24
W24
W24
W24
W24
W24
W24
W24 W
24
W24
W24
W24
W24
W24
W24
W24
W24
W24
W24 W24
W24
W24
W24
W24
W24
W24
W24
W24
W30 W30
W30
W30
W30
W30 W30
W30W30
W30 W30 W30
W24
W24
W30
W30
W30
W30
W24
W24
W24
THIRD LEVEL FRAMING PLANSCALE: 1/8" = 1' - 0"
3
W30
W24
W30
W30
W30
W30
W30
W30
W30
W30
W30
W30
W30
W30
X10
8
W24
W24
W24
W24
W24
W24
W24
W24
W24
W24
W24 W24
W24
W24
W24
W24
W24
W30
25
SECTION 4.0 CONCEPTUAL DESIGN
THIRD LEVEL FRAMING PLAN FOURTH LEVEL FRAMING PLAN
NN
5.6 STRUCTURAL FRAMING PLANS
UP
UP
UP
1
3
2
A B C F
18
19
20
21
22
23
24
1.1
26
N
17
25
O
D E G
4
5
H
P R S T U V
I J L MK
6
7
8
9
10
11
12
13
14
15
16
Q
27
28
29
30
31
32
33
64 65 66 6768 69
R.1
21.1
7.1
W10x49 W10x49 W10x49 W10x49
W14x53 W14x90 W14x53W14x90
W14x53 W14x90 W14x53W14x90
W14x90
W14x90
W14x90
W14x90
W14x90
W14x53
W14x90
W14x53
W14x90
W14x90
W14x90
W10x33
W10x45
W10x45
W10x45
W10x45
W10x45W10x45
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER27' LONG
3' DIA. DRILLED PIER27' LONG
3' DIA. DRILLED PIER27' LONG
3' DIA. DRILLED PIER18' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER18' LONG
3' DIA. DRILLED PIER18' LONG
3' DIA. DRILLED PIER18' LONG
3' DIA. DRILLED PIER18' LONG
3' DIA. DRILLED PIER18' LONG
3' DIA. DRILLED PIER18' LONG
3' DIA. DRILLED PIER18' LONG
3' DIA. DRILLED PIER18' LONG
3' DIA. DRILLED PIER18' LONG
3' DIA. DRILLED PIER18' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER18' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER18' LONG
3' DIA. DRILLED PIER18' LONG
3' DIA. DRILLED PIER18' LONG
3' DIA. DRILLED PIER18' LONG
3' DIA. DRILLED PIER18' LONG
3' DIA. DRILLED PIER18' LONG
6" THICKSLAB-ON-
GRADE
6" THICKSLAB-ON-
GRADE
6" THICKSLAB-ON-
GRADE
W14x53
W10x49
3' DIA. DRILLED PIER22' LONG
37' - 6" 31' - 10" 10' - 10" 7' - 2" 21' - 0" 6' - 0" 11' - 6"
39' - 0" 17' - 6"
125' - 10"
11' -
10
1/2"
11' -
10
1/2"
16' -
3"
6' -
0 3/
32"
23' -
9"
46' -
0 3
/32"
K.1
25' - 10 7/16" 13' - 7 7/8" 7' - 5" 10' - 10" 22' - 6" 11' - 1 7/16"
39' - 6 9/32" 44' - 5 7/16"
91' - 4 23/32"
29' -
10
3/4"
17' -
4 1
/4"
4' -
8"18
' - 5
"10
' - 8
"21
' - 6
3/4
"26
' - 1
0 1/
4"17
' - 8
"10
' - 6
"19
' - 0
"5'
- 6"
35' -
0"
81' -
0"
182'
- 1"
13' - 7 7/16" 5' - 8" 7' - 11 23/32" 7' - 0 9/32" 8' - 2 19/32" 4' - 3 13/32" 13' - 7 1/2"
15' - 0" 26' - 1 1/2"
60' - 4 15/16"
26' -
6"
24' -
2 3
/4"
25' -
8"
22' -
11
7/8"
25' -
8 1
/8"
29' -
11
1/4"
9' -
8 17
/32"
155'
- 0"
26' - 10 5/32"
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER27' LONG
3' DIA. DRILLED PIER27' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER22' LONG3' DIA. DRILLED PIER
22' LONG3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER27' LONG3' DIA. DRILLED PIER
27' LONG
3' DIA. DRILLED PIER27' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER22' LONG
W10x49
W10x49W10x49
W10x49 W10x49
W10x49 W10x49
W10x49
W10x49 W10x49 W10x49
W10x49W10x49
W10x49
W10x49
W10x49
W10x49 W10x49 W10x49 W10x49
W10x49
W10x49
W10x49
W10x49
3' DIA. DRILLED PIER22' LONG
W10x49
W10x49
3' DIA. DRILLED PIER22' LONG3' DIA. DRILLED PIER
22' LONG
W10x49
3' DIA. DRILLED PIER22' LONG
3' DIA. DRILLED PIER22' LONG
24"x24" GRADE BEAM, TYP.
24"x24" GRADE BEAM, TYP.
24"x24" GRADE BEAM, TYP.
DENDRITIC STRUCTURE BASE, TYP.
W30x261W30x261
W30x261 W30x261
W30x261W30x261
W30x261
W30x261W30x261
W30x261
W30x261
W30x261
W30x261
W30x261
W30x261
W30x261
FIRST LEVEL / FOUNDATION PLANSCALE: 1/8" = 1' - 0"
1
26
SECTION 4.0 CONCEPTUAL DESIGN
NORTH SECTION FIRST LEVEL / FOUNDATION
N
5.6 STRUCTURAL FRAMING PLANS
Level 10' - 0"
Level 214' - 0"
Level 328' - 0"
Level 442' - 0"
RUREQUIRED
STEEL
5.7 SQ. IN.
REQUIREDSTEEL
10.3 SQ. IN.
REQUIREDSTEEL
12.6 SQ. IN.
REQUIRED
STEEL
5.7SQ. IN
.
REQUIRED
STEEL
10.3
SQ. IN.
REQUIRED
STEEL
12.6
SQ. IN.
W30
x261
W30
x261
W14
W14
W14
DRILLEDPIER FOUNDATION, TYP.
24"x24" GRADE BEAM
6" SLAB-ON-GRADE
ABCF
W14x38 W14x38 W14x38
W21x111 W21x111 W21x111
W21x122 W21x122 W21x122
W14
x53
W14
x53
W14
x90
W14
x90
24"x24" GRADE BEAM 24"x24" GRADE BEAM 24"x24" GRADE BEAM
6" THICK SLAB-ON-GRADE
DRILLED PIERFOUNDATION, TYP.
27
SECTION 4.0 CONCEPTUAL DESIGN
5.7 STRUCTURAL DETAILS
BUCKLING RESTRAINED BRACE FRAME ELEVATION
Level 10' - 0"
Level 214' - 0"
Level 328' - 0"
Level 442' - 0"
RUREQUIRED
STEEL
5.7 SQ. IN.
REQUIREDSTEEL
10.3 SQ. IN.
REQUIREDSTEEL
12.6 SQ. IN.
REQUIRED
STEEL
5.7SQ. IN
.
REQUIRED
STEEL
10.3
SQ. IN.
REQUIRED
STEEL
12.6
SQ. IN.
W30
x261
W30
x261
W14
W14
W14
DRILLEDPIER FOUNDATION, TYP.
24"x24" GRADE BEAM
6" SLAB-ON-GRADE
REDUCED BEAM SECTION MOMENT FRAME ELEVATION
DRAWINGS NOT TO SCALE
28
SECTION 4.0 CONCEPTUAL DESIGN
5.7 STRUCTURAL DETAILS
SPIDER GLAZINGDENDRITIC STRUCTURE
The columns that support the terraces that connect the buildings within our project are designed after a natural dendritic form, which develops with multi-branching tree-like extensions. Dendritic crystal growth, illustrated by snowflake formation and frost patterns on a window, forms a natural fractal pattern. This bio-mimicry technique provides gravity support of the concrete terrace slabs through axial compression and bridges the organic flow of our landscape design to the linear architectural form of our structure.
A spider glazing curtain wall system provides the building façade with an “all-glass” appearance and consists of frameless toughened glass assemblies which are bolted together at their corners by means of metal patch fittings.
Glass panel joints are sealed with silicone, and tension cables provide lateral stability against wind loading. The final glass assembly is suspended from the building structure by hangers bolted to its top edge, and is sealed into channels.
29
SECTION 4.0 CONCEPTUAL DESIGN
5.8 STRUCTURAL PERSPECTIVES & ELEVATIONSEAST ELEVATION
PERSPECTIVE - NORTHEAST APPROACH
PERSPECTIVE - NORTHWEST APPROACH
WEST ELEVATION
SOUTH ELEVATIONNORTH ELEVATION
N
30
SECTION 4.0 CONCEPTUAL DESIGN
ALLEE OF TREES TO FRAME VIEWS OF THE LAGOON
PARKING LOT ENTRANCE
20’ STREET LIGHTING
SCUPTURE YARD
MAIN ENTRANCE
THEATER PLAZA
SERVICE PARKING
SCUPTURE GARDEN
INTERIOR COURTYARD
SCALE 1” = 50’
N
SOUTH SITE - CCS BUILDING REDESIGN
POROUS PAVERS
STAMPED CONCRETE PAVING
CONCRETE PAVING
5.9 LANDSCAPE MASTER PLAN
4’ o EVERGREENSHRUB
4’ o FLAXSHRUB
6’ o BORDERSHRUB
25’ o DECIDUOUSTREE
20’ o ACCENTTREE
35’ o SHADETREE
/
/
/
/
/
/
BENCHES ALONG CATWALK
BICYCLE RACKS
The design development of the this project is a direct response to the existing site and the goals for the future of the campus. With the college being at the crossroads of the university, both physically and academically, cohesive integration was a key concept for the design.
Not only did the site plan need to coalesce with and complement the building, it was important that it responded positively to the
surrounding campus to intrigue visitors and create a sense of belonging.
Our design strives to reach out to the core of campus and bring that energy into the new heart of the College of Creative Studies. Curvilinear
paths, accentuated by plant material, paving patterns, lighting and glimpses of students’ artwork will draw people from the significant
pedestrian corridors into interior courtyard.
N
31
SECTION 4.0 CONCEPTUAL DESIGN
UCEN ROAD
TWO-WAY SHARED BICYCLE AND PEDESTRIAN PATHWAY
PARKING LOT ENTRANCE
BICYCLE RACKS
BICYCLE AND PEDESTRIAN PATHWAYS
RAISED PLANTERS TO SCREEN PARKING LOT
SCALE 1” = 50’
N
DECOMPOSED GRANITE
CONCRETE PAVING
POROUS PAVERS
NORTH SITE - PARKING LOT REDESIGN
5.9 LANDSCAPE MASTER PLAN
4’ o EVERGREENSHRUB
4’ o FLAXSHRUB
6’ o BORDERSHRUB
25’ o DECIDUOUSTREE
20’ o ACCENTTREE
35’ o SHADETREE
/
/
/
/
/
/
VEGETATED DRAINAGE SWALE
32
SECTION 4.0 CONCEPTUAL DESIGN
5.10 LANDSCAPE LIGHTING PLAN
SCALE 1” = 50’
N
SCALE 1” = 50’
NNORTH SITE - PARKING LOT LIGHTING
SOUTH SITE - CCS BUILDING LIGHTING
20’ HALIDE STREET LIGHTING 3’ BOLLARD LIGHTING WALL & PLANT LIGHTS
33
SECTION 4.0 CONCEPTUAL DESIGN
5.11 LANDSCAPING DETAILS
SCALE 1” = 20’
NSCALE 1” = 20’
N
THEATER PLAZA - LANDSCAPINGTHEATER PLAZA - LIGHTING
DOUBLE SEAT WALL WITH RAISED PLANTER
LOBBY WITH ENTRANCE TO THEATERS
WALL LIGHTS @ 12’ o.c.
MOUNDING GRASS
FLOWERING PERENNIAL
BRICK EDGING
35’ o SHADE TREE
20’ o FLOWERING ACCENT TREE/
/
THE EXTENSIVE GREEN ROOF• Theextensivesystemwillbeusedoverthetheaterstoprovidesoundandthermalinsulationas well as an aesthetic view from 3rd and 4th floors.• Littletonomaintenancewillbeprovidedtothisareaandtherewillbenoneedforirrigation.• Recommendedplantswillincludesucculents,grasses,andherbsinasoilmixtureofminerals and organic matter about 3” thick.
THE INTENSIVE GREEN ROOF• Theintensivegardenwillbeincorporatedontopofthe3rdflooroftheresidenceswithexclusive access to the college (i.e. special events, conferences, parties).• Thegardenwillserveasanoutdoorpedestrianrecreationalareawithbenches,butlittlespacefor
circulation due to live load constraints.• Thesoildepthwillrangefrom6”to12”withthepossibilityofplantersforlargershrubs.• Thistypeofgardenroofrequiresconsiderablemaintenanceandirrigation
GREEN ROOFS & TERRACESGarden Roof Assemblies allow for a low profile and lightweight system that incorporates a monolithic membrane to assure a water-tight structure. Advantages of a Garden Roof Assembly include:
• Buildingappearanceenhancement• Addeduseablespacefortenants• Mitigatestheheatislandeffect• Retainsupto90%ofrainwater• Improvesenergyefficiencyofbuilding• Reducesnoisetointeriorandfiltersoutdoorsoundpollution• Providestherapeuticandpeacefulenvironments• Rebuildsnaturalhabitatsremovedfromgroundlevel• Increasesthelifeexpectancyoftheroof• Incorporatingagreenroofisadisplayofenvironmentalawareness
34
SECTION 4.0 CONCEPTUAL DESIGN
At EMI, we feel sustainability is a mandatory social responsibility we owe to our clients and building occupants. It is proven that green building contributes to higher student attendance rates, less faculty sick days, and more productivity when working. A facility such as the College of Creative Studies, that inspires to be conducive to advanced and collaborative learning should consider as many sustainable building practices as possible. We believe LEED Gold should be the minimum certification for the CCS.
The table below summarizes our LEED analysis for this site. Conservatively, we are looking at 62 LEED credits we will definitely acquire with smart, basic design decisions that already adhere to the client’s expectations and UCSB Sustainability Plan. Another 41 points are available to the CCS, while 7 points cannot be acquired due to site applicability. LEED Gold certification only requires 60 points, which we believe we will acquire through sustainable sites, improved water & efficiency, and increasing our use of recyclable materials and resources.
This project will earn a minimum of 15/26 credits in Sustainable Sites (SS). Many of these points are earned from the existing site, which is in close proximity to basic services and easily accessable by alternative transportation. Our design will earn credits from stormwater pollution prevention, light pollution prevention, and mitigation of the heat-island effect. The heat-island effect occurs when a building acts as a solar conductor, trapping heat from the sun because of dark-colored surfaces, low-reflective materials, and extensive use of hardscapes like asphalt. By installing photovoltaic panels and vegetative roofs, we will harness solar energy rather than trap heat into the atmosphere.
We will earn 6/10 credits in Water & Efficiency (WE) with the remaining 4 credits fairly easy to acquire. We propose using vegetated roofs and native plants in our landscapes to reduce the need for irrigation water. With additional investment and development, we can take this one step further by trapping and storing rainwater. For occupant water use, low-flow, dual-flush toilets can be installed to reduce potable water usage by 50%.
Energy & Atmosphere (EA) offers the greatest opportunity to acquire credits. Our designs incorporate photovoltaic panels in our terrace/courtyard roof systems and would contribute to the projected 10-15% energy savings the CCS will achieve (in comparison to typical, comparable-sized structures). To save more electricity, occupancy sensors and timers will be installed into all rooms that will shut off lights when not in use. Additional credits can be earned based on the clients desire to invest in additional energy-reducing technologies.
Materials & Resources (MR) allows the CCS to acquire 7 more points. Our initial designs utilize glazing, concrete, architectural wood, structural steel, and masonry. From our preliminary research, we found suppliers that recycle concrete and steel, two major structural components of our site. 3 more points may be acquired with additional investment into recycled materials. Finalized designs will also contribute to the possibility of earning all 10 LEED credits in this category.
We prioritize Indoor Environmental Quality (IEQ) because it plays a major role in occupant health and happiness in a building. Poor indoor air quality is attributed to asthma, increased allergy symptoms, and mold growth. With proper ventilation to the outdoor environment, these issues can be mitigated. The CCS will be equipped with automated windows that open when the artificial ventilation system is shut off. In addition, we designed rooms to have nultiple openings via doorways and windows to allow air to flow freely through spaces. Through such techniques, the CCS will earn 10 IEQ credits from our initial designs with another 3 credits available.
Our LEED accredited professionals will acquire 1 point in Innovation & Design (ID) and we anticipate getting 3 more from our innovative designs. The final LEED inspection will determine the remaining points. According to USGBC.org, Regional Priority credits may be awarded to projects focusing on specific credits in LEED categories: Sustainable Sites, Water & Efficiency, and Energy & Atmosphere.
5.12 ENERGY-EFFICIENCY ANALYSISOur design proposal consists of programmed spaces that take into consideration daylighting, ventilation, and air temperature. These factors contribute to the building’s energy efficiency by passively cooling or heating the interior spaces.
The south-facing walls are protected by exterior horizontal louvers which block out intense summertime sunlight, which cut down on ventilation and cooling costs. Alternatively these louvers will allow winter sunlight to penetrate to the south-facing office and studio spaces, which cut down on artificial heating costs.
The section perspective below illustrates daylighting and natural ventilation of the north section of the buiding.
This portion of the CCS consists of mainly the art studios, which take advantage of the north-facing, indirect sunlight beaming through floor-to-ceiling glazing. On the north side, window treatments (horizontal louvers or vertical blinds) will allow students and instructors to control privacy and desired levels of natural lighting.
The openness of the floor-to-ceiling glazing also draws the attention of visitors and passerbys, harnessing the College of Creative Studies’ vision of porousity and connecting to the surrounding university.
A combination of open doors and windows on the south and north-facing walls will allow natural ventilation to flow smoothly through the interior spaces. Automated windows will open and close depending on thermostat controls. If the HVAC system is artificially ventilation a space, windows will automatically open.
LEED CATEGORY PROJECTED POSSIBLE
SUSTAINABLE SITES 15 10
WATER & EFFICIENCY 6 4
ENERGY & ATMOSPHERE 18 17
MATERIALS & RESOURCES 7 3
INDOOR ENVIRONMENTAL QUALITY 10 3
INNOVATION & DESIGN (LEED AP) 4 2
REGIONAL PRIORITY (SS 1, 2, 4.1, WE 1.1,3, EA 2) 2 2
TOTAL: 62 41 PROJECTED LEED GOLD CERTIFICATION (60-79 CREDITS)
Sunlight varies through seasons and with angled horizontal louvers, we can harness sunlight to warm interior spaces during the winter and block sunlight during the summer to keep spaces cool.
Open doors/windows on both sides of the building will allow cross-ventilation of clean, natural air.
DAYLIGHTING & VENTILATION STUDY
LEED ANALYSIS
LEED CREDIT SUMMARY
PRECONSTRUCTION 14%
BUILDING CONSTRUCTION 68%
LANDSCAPE/HARDSCAPE 12%
UCSB ORGANIZATION 3%
CONTINGENCY 3%
35
The proposed $37,800,000 project is broken down into subcategories to simplify cost estimates. Costs were developed from RS Means Assemblies Cost Data 2009, RS Means Green Building 2010, RS Means Heavy Civil Construction and precedent studies of similar-sized or similar-programmed projects including the UNLV Greenspun Hall, the UCSD Rady School of Management, and the Cal Poly Construction Innovations Center. We did take-offs by hand and calculated quantities using popular construction and design software.
The building proposed will consist of:• 3-4 stories in height• 39,000 assignable square feet (53,000 GSF)• 19,500 SF building footprint• 42 beds in a dormatory-style residence• 144 parking stalls
EXTERIORSThe enclosure will consist of a variety of facades - capturing a fresh, new complex to the UCSB while maintaining a connection to existing architecture. Exterior surfaces will be comprised of masonry, floor-to-floor glazing, metal doors, and concrete panels.
SCHEMATIC DESIGN: LANDSCAPEPROJECT COSTSECTION 6.1
$37,800,000PROPOSAL
INTERIORSWalls will be made with metal studs and insulated for acoustical performance. 5/8” drywall will cover most walls and ceilings. Acoustical tile ceilings will be hung in all classrooms and offices and carpet will line office and seminar room floors.
HARDSCAPE & LANDSCAPEThis portion of the estimate covers costs for demolition, earthwork, a new parking lot, landscaping, irrigation, hardscapes, vegetative roofs, and site improvements (bike racks, seating areas). Landscaping involves construction of a sculpture courtyard, terraces, and paving.
STRUCTURALThe substructure will require a slab foundation with caissons drilled into bedrock throughout the building footprint. The superstructure will consist of structural steel and composite decks, including columns, beams, dendritic columns, braced frames, and moment frames
GENERAL REQUIREMENTS & OVERHEADThis portion of the estimate accounts for site project costs to sustain construction including: rentals, the jobsite office trailer(s), contractor fees, equipment operation, etc.
Cost % of Budget
DESIGN-‐BUILD COSTSPreconstruction
Architecture/Engineering 2,537,500 6.7%Other Consultants 1,268,700 3.4%Site Investigation 300,600 0.8%Permits/Fees 601,300 1.6%Bonds/Insurance 754,000 2.0%
Subtotal Preconstruction 5,462,100 14.4%
Site Preparation 802,200 2.1%Demolition 92,700 0.2%Builiding Construction
Substructure 1,194,200 3.2%Superstructure 2,334,200 6.2%Exterior Enclosure 2,657,800 6.2%Roofing 608,200 7.0%Interior Construction 4,033,200 1.6%Conveyance 338,400 0.9%Mechanical 1,714,000 4.5%Plumbing 1,252,300 3.3%Electrical 2,082,300 5.5%Equipment & Furnishings 3,905,100 10.3%
General Requirements 3,045,000 241.1%Overhead 2,537,500 201.0%
Subtotal Building Construction 25,702,200 68.0%
Hardscape 2,407,000 6.4%Landscape 1,954,200 5.2%
Subtotal Landscape/Hardscape 4,361,200 11.5%
Subtotal Design-‐Build Costs 30,063,400 79.5%
UCSB Organization Cost Allowance 1,262,700 3.3%Project Contingency Allowance 1,015,000 2.7%
Total Project Costs $37,803,200 100.0%
TOTAL (excluding UCSB Organization Cost) $36,540,500 96.7%
36
SCHEMATIC DESIGN: LANDSCAPE
PHASE 1 CONSTRUCTIONOnce we receive our notice to proceed, we will prepare the site by installing necessary traffic and pedestrian controls, closing off the site with a dust-screen fence, and being procuring equipment. We will then demolish existing structures and excavate and grade for foundations. Once the barracks on the north site are cleared, we will being procuring materials for the building substructure.
PHASE 2 CONSTRUCTIONAfter site preparation, we will proceed with the actual construction of the CCS building. Activities will overlap if possible to allow multiple non-conflicting subcontractors to operate on different sides of the site. This procedure allows us to efficiently deliver the project within 20 months of construction.
Mechanical, Electrical, and Plumbing (MEP) will be broken into a rough-in period before interior finishes and a finishing period after interior finishes. This 2-step process will protect finished components from being damaged during construction of interior finishes.
Phase 3 may overlap with installation of equipment and furnishings because exterior work generally does not conflict with interior furnishings
PHASE 3 CONSTRUCTIONLandscaping will involve installation of vegetative roof(s), the sculpture courtyard, and construction of hardscapes. We will landscape and pave the south site before moving onto the north site. When concrete is paved on the south site, the building will achieve substantial completion.Final inspections and certifications for the building may occur during the landscaping and paving of the parking lot on the north site to allow occupancy as soon as possible.
POSTCONSTRUCTIONPostconstruction documentation and inspections will occur after sitework on the south site. Our superintendent(s) will coordinate inspections with the city, the university, and with the USGBC (for LEED certification).
DESIGNDesign will be substantially complete before we recieve our notice to proceed with construction during week 64. By this time, construction documents involving subcontractors, bids, bonds, insurance, and permits will be complete, while finalized drawings will be completed after construction begins.
Our proposed schedule represents a conservative project duration of 40 months. This duration includes the entire predesign, design, construction, and postconstruction phases of the project. The entire schedule has been limited to 5-day working weeks, with typical construction hours from 8am-5pm (in consideration of the campus environment). The schedule above represents a breakdown of milestones related to each phase of the project. These tasks closely mirror major components of the project estimate shown in Section 3.8.
We researched activity durations using computer software such as D4 cost and applied knowledge from our own completed projects to develop the proposed schedule for the College of Creative Studies. Schematic designs were presented to the client on April 18th, 2011 and conceptual designs, a narrow-scope estimate, and schedule were presented to the client on May 4th, 2011. Based on their feedback, we made adjustments to our design and construction logistics and reduced the project duration from 28 months to 27 months (construction reduced from 21 months to 20 months).
ACCURATE PLANNING FROM EXPERIENCE
PROPOSED SCHEDULE MILESTONES
PROJECT SCHEDULESECTION 6.2
ACTIVITY DURATION (Days)
DURATION (Weeks)
PROPOSED COMPLETION
Notice to Proceed with Design-Build - - Week 1
DESIGN 132 27 Week 27Schematic Design 33 7 Week 7Design Development 66 14 Week 20Construction Documents 99 20 Week 27Notice to Proceed with Construction - - Week 27
CONSTRUCTION 396 80 Week 107Phase 1 - Sitework 33 7 Week 34
Demolition 11 2 Week 29Site Preparation (Excavation, Grading, Dewatering) 22 5 Week 34
Phase 2 - Building Construction 303 61 Week 95Substructure 44 9 Week 43Superstructure 50 10 Week 53Exterior Closure 50 10 Week 59Roofing 22 5 Week 61Interior Finishes 61 12 Week 73Conveyances 11 2 Week 63Mechanical 44 9 Week 82Plumbing 66 14 Week 87Electrical 44 9 Week 86Equipment & Furnishings 22 5 Week 92
Phase 3 - Site Improvements & Landscaping 66 14 Week 104Hardscapes 22 5 Week 135Landscaping 55 11 Week 141
POSTCONSTRUCTION 66 14 Week 11727 Months for Design-Build
(20 Months of Construction)588PROJECT TOTAL
College Of Creative Studies - Site StudyUCSB Campus Planning & Design March 2011 N0 50 100 150 20025
Feet
37
CONSTRUCTION LOGISTICSSECTION 6.3
College Of Creative Studies - Site StudyUCSB Campus Planning & Design March 2011 N0 50 100 150 20025
Feet
Jobsite Trailer
Construction Parking
Material Laydown
Main Gate
Emergency Access
Site Fence
Proposed Parking
N
FIGURE 1: PHASE 1 & 2 CONSTRUCTION SITE FIGURE 2: PHASE 3 CONSTRUCTION SITEGENERAL CONCERNSThis project will be built in the core of campus. Thus, parking will need to remain available for use by adjacent building occupants. Service vehicles will also require access to all adjacent buildings. Dormitories are located to the southwest of the site, so construction will be limited to typical workdays and limited during specific campus holidays and exam days. Equipment will not be started before 8am and will be shut off before 5:30pm. Because of the high volume of pedestrian, bicycle, and vehicle traffic around the site, special considerations will have to be made to ensure construction does not impede traffic flow or endanger pedestrians.
SITE SECURITY AND PEDESTRIAN SAFETYSite fencing will be installed with dust screens and with proper traffic control and safety signage. Fencing will provide a 20-foot buffer zone between construction and pedestrian walkways. The main gates to both construction areas are marked with “light blue” arrows on the figures. Entrances will be covered with gravel to remove dirt from exiting construction vehicles. Emergency access gates are marked with “red” crosses on both figures. To keep pedestrians out of construction zones, gates will be locked at the end of the workday and a system of security cameras will be installed for further safety and security. Security cameras will feed to university police and to the jobsite trailer.
DELIVERIESMaterial deliveries will be made through Ucen Road to a designated unloading/turn around area within the material laydown zone. Material deliveries shall take place between the hours of 9:30am and 2:30pm to reduce the effect on student traffic during rush hours. From there, materials will be stored at the material laydown area(s) highlighted in “blue” on Figures 1 and 2. Construction traffic will enter and exit via Ucen Road to Lagoon Road (the same path traffic enters). Deliveries of steel, concrete and other large materials will be made with semi-trucks. Further investigation with the university may determine if oversized truckloads are permitted in the area.
PARKING ACCOMODATIONUniversity parking during construction will utilize the existing lot. After Phase 2 of construction is complete, the existing parking lot will be closed to construct the proposed parking lot shown in the highlighted “green” area on Figure 2. The proposed lot will accommodate approximately 120 vehicles. It will only take 2.5 weeks to demolish the existing lot and pave the new lot. During this time, parking will be dispursed by traffic control measures highlighted below. Construction traffic will utilize the parking areas highlighted in “lime green” on Figures 1 and 2. Separating parking lots for traffic and campus use mitigates conflicts regarding access and permission.
TRAFFIC CONTROLWe will begin Phase 1 by placing traffic control signage and barriers. The majority of signs will be posted along the site fence. A project sign will inform traffic entering the campus via Ucen road from Lagoon that construction is in progress and access may be limited during deliveries. When the new parking lot is being constructed during Phase 3, signage will be placed at the intersection of Lagoon and Ucen notifying traffic that parking on the main lot will not be available. Detour signs will direct vehicles to park at lots on nearby lots and on the west side of campus.
JOBSITE REQUIREMENTSThere will be two 10’x32’ office trailers with a 25’x40’ storage dumpster placed at the area highlighted in “white” on both figures. An 8500-watt generator will provide temporary power to the office trailers. Additional, 1500-watt generators will provide power for tools throughout the south site. A mobile crane will be set up near the center of the south site to accommodate building development in Phase 2 of construction.
There will be temporary toilets and hand wash stations on the northern section of the south site. Additional stations will be located throughout the site to fulfill code requirements for the maximum expected construction workers on site (10 toilet stations, 8 wash stations for workers, 2 toilets and 1 wash station for the office).
VERTICAL CONSTRUCTIONOur proposed structure varies from 42’ in height to 56’. Construction will require a 75’-100’ mobile crane and scaffolding. We opted for a mobile crane for the ease of making adjustments and to retain flexibility with the constraints of working on an active college campus. The mobile crane will be stationed primarily on the northern section of the south site.
We recommend scaffolding rather than man-material hoists because of the cost savings from renting hoist equipment. Hoists require specialized installation and are difficult to demobilize and reposition on different parts of the site. Scaffolding will be installed as the building construction progresses upward. Ladders will be located throughout the scaffold system as necessary for emergency exiting and convenience. All decks and scaffolds will be secured with toeboards and guardrails.
Steel will be erected with as many pre-welded components as possible during fabrication and will be bolted on site as necessary. Composite decks will be poured using a hose attached to the boom of the mobile crane and with the help of a 60-foot concrete boom pump. Concrete will be finished with plate compactors.
Traffic Flow
College Of Creative Studies - Site StudyUCSB Campus Planning & Design March 2011 N0 50 100 150 20025
Feet
38
CONSTRUCTION LOGISTICSSECTION 6.3
College Of Creative Studies - Site StudyUCSB Campus Planning & Design March 2011 N0 50 100 150 20025
Feet
Jobsite Trailer
Construction Parking
Material Laydown
Main Gate
Emergency Access
Site Fence
N
FIGURE 3: ALTERNATIVE CONSTRUCTION SITE
Traffic Flow
College Of Creative Studies - Site StudyUCSB Campus Planning & Design March 2011 N0 50 100 150 20025
Feet
ALTERNATE PROPOSALIn our previous presentation to Dennis and Bruce at UCSB, they brought up the possible need to keep the three barracks on the north site in service. In this alternate construction scheme, we eliminate all landscape and hardscape work from the north site. Thus, phase 3 will consist of less work, but may require a similar scheduled duration to accomodate site improvements and paving. This scheme also leaves the large parking lot open to the university for the entire duration of the project.
We will adjust the construction site to accommodate material laydown along the north and west sides of the site. The northeast corner of the jobsite will serve as a truck turnaround and entrance/exiting zone. Construction vehicle parking and the jobsite trailer will be located on the parking lot southwest of the CCS. Delivery trucks will use Ucen road from Lagoon road to deliver materials to the north entry gate. The south entry gate will service subcontractor vehicles, the superintendent, and other typical-sized vehicles.
This alternative will save approximately $900,000 from reduced site preparation, less demolition, less roadwork, reduced landscaping, and elimination of the parking lot.
EMI, Inc. would like to thank you for the invitation to design and build the College of Creative Studies
39