UCN Facility Working Group October 3, 2012 OverviewL.Lee MCNPX and ShieldingP.Carlson Beam...

31
UCN Facility Working Group October 3, 2012 Overview L.Lee MCNPX and Shielding P.Carlson Beam Monitors C.A.Davis / A.Konaka

Transcript of UCN Facility Working Group October 3, 2012 OverviewL.Lee MCNPX and ShieldingP.Carlson Beam...

Page 1: UCN Facility Working Group October 3, 2012 OverviewL.Lee MCNPX and ShieldingP.Carlson Beam MonitorsC.A.Davis / A.Konaka.

UCN FacilityWorking Group

October 3, 2012

Overview L.LeeMCNPX and Shielding P.CarlsonBeam Monitors C.A.Davis / A.Konaka

Page 2: UCN Facility Working Group October 3, 2012 OverviewL.Lee MCNPX and ShieldingP.Carlson Beam MonitorsC.A.Davis / A.Konaka.

UCN FacilityWorking Group

October 3, 2012

Overview L.Lee - Schedule & 2014 Shutdown - Decisions about beamline configurations - High-density shielding (Vault-1A “Plug”, UCN Pyramid) - Shielding needs (Monte Carlo studies)

MCNPX and Shielding P.CarlsonBeam Monitors C.A.Davis / A.Konaka

Page 3: UCN Facility Working Group October 3, 2012 OverviewL.Lee MCNPX and ShieldingP.Carlson Beam MonitorsC.A.Davis / A.Konaka.

2011 2015201420132012 2016 2017ACTIVITY

J A J OJ A J O J A J OJ A J O J A J OJ A J O J A

Schedule( 2010-2016 )2011 2015201420132012 2016 2017

Cleanup M11,1A/1B roof-beamDismantle PIENU & M13-DS

MESON HALL (& Vault):

Core M13 I-block

Shielding

UCN APPARATUS:Spallation Target & R/HUCN Source

BEAMLINE 1U:Kicker

SeptumDipoleBeamline (incl Quads, PS,…)

Design & Review Order/Fabricate/Deliver

Test

Test

Order/Mod

Order/Fabricate

Design & Review

Design & Review Order/Fabricate InstallTest

Specify/Conceptual design

Design/Fabricate InstallUnInstall

Procure shielding blocksDesign & Review Install

COMMISSION @ TRIUMFBeamline Commissioning

HELIUM LIQUEFIER:

Upgrade He Liquefier System

He Liquefier SystemProcure

UCN Source Commissioning

Install/Test & Run @ RCNP

Procure/Install

Install

Kicker Ceramic Beamtube InstallDesign/Order Fabricate

Install

Test

MILESTONES Shutdown Activities Activities Elsewhere(KEK, RCNP, CERN, Acsion)

Non-Shutdown Activities

Mod. 1VQ4/Q5; BL1V & Shld

InstallInstall

Install

Dismantle M13-US, Mod.Shld

UCN Schedule (Draft)

Design/Order/Fabricate Test

Install

Install

Design/Fabr

Page 4: UCN Facility Working Group October 3, 2012 OverviewL.Lee MCNPX and ShieldingP.Carlson Beam MonitorsC.A.Davis / A.Konaka.

N

Kick direction (vertical or horizontal)Shielding “Plug” will need to be reconfigured

UCN Installation 2014

Page 5: UCN Facility Working Group October 3, 2012 OverviewL.Lee MCNPX and ShieldingP.Carlson Beam MonitorsC.A.Davis / A.Konaka.

Decisions aboutbeamline configurations

Page 6: UCN Facility Working Group October 3, 2012 OverviewL.Lee MCNPX and ShieldingP.Carlson Beam MonitorsC.A.Davis / A.Konaka.

Transporting the split beam from the kicker through the existing beam apertures

Page 7: UCN Facility Working Group October 3, 2012 OverviewL.Lee MCNPX and ShieldingP.Carlson Beam MonitorsC.A.Davis / A.Konaka.
Page 8: UCN Facility Working Group October 3, 2012 OverviewL.Lee MCNPX and ShieldingP.Carlson Beam MonitorsC.A.Davis / A.Konaka.
Page 9: UCN Facility Working Group October 3, 2012 OverviewL.Lee MCNPX and ShieldingP.Carlson Beam MonitorsC.A.Davis / A.Konaka.

UCN Installation 2015 (Option 3f)

N

T1study

Page 10: UCN Facility Working Group October 3, 2012 OverviewL.Lee MCNPX and ShieldingP.Carlson Beam MonitorsC.A.Davis / A.Konaka.

UCN Installation 2015 (Option 3g)

N

T1study

Page 11: UCN Facility Working Group October 3, 2012 OverviewL.Lee MCNPX and ShieldingP.Carlson Beam MonitorsC.A.Davis / A.Konaka.

High-densityShielding

Page 12: UCN Facility Working Group October 3, 2012 OverviewL.Lee MCNPX and ShieldingP.Carlson Beam MonitorsC.A.Davis / A.Konaka.

Shielding Plug Layout: Option-1Replace some concrete with steel blocks ( ~ 3:1 thickness ratio)

“First-Pass” study using SolidWorks 3D-Model of Meson Hall West

Page 13: UCN Facility Working Group October 3, 2012 OverviewL.Lee MCNPX and ShieldingP.Carlson Beam MonitorsC.A.Davis / A.Konaka.

Higher Density Shielding Materials

Replacing some concrete blocks with higher density material

Issues/Considerations:

- Re-use existing concrete blocks, as much as possibleCosts, Storage fewer removed blocks (potentially activated)

- Combine with denser (Steel) blocks

- Combine with denser (Hematite-aggregate concrete) blocks

Concrete/Hematite aggregate shielding blocks (from NSS)Variable/Customizable density (3.8 - 5.7 g/cc)Used at reactors (Ontario – 25 yrs), SNS, TRIUMFNSS has worked with Ellis-Don, Burnco, LaFargeNSS Meeting at TRIUMF on Sep.10, 2012 (M.Chopra)

Layout Options (“First-Pass” study):(1) Replace some concrete w/ steel blocks ( ~ 3:1 thickness ratio)(2) Replace some concrete w/ aggregate blocks ( ~ 2:1 thickness ratio)

Page 14: UCN Facility Working Group October 3, 2012 OverviewL.Lee MCNPX and ShieldingP.Carlson Beam MonitorsC.A.Davis / A.Konaka.

SolidWorks 3D-Model of Meson Hall West

CYCL.VAULT

BL1ATUNNEL

Page 15: UCN Facility Working Group October 3, 2012 OverviewL.Lee MCNPX and ShieldingP.Carlson Beam MonitorsC.A.Davis / A.Konaka.

Beampipe to BL1A

ImmovableBlock East (to T1,

T2, TNF)

Existing Shielding (Layers A-D)(UPPER LAYERS E-J HIDDEN)

Vault-1A“Plug”

Page 16: UCN Facility Working Group October 3, 2012 OverviewL.Lee MCNPX and ShieldingP.Carlson Beam MonitorsC.A.Davis / A.Konaka.

List of “Removed” Concrete Blocks: List of “New” Blocks:(2) 12’ x 6’ x 4’ (Layer A, C) (5) 2’ x 3’ x 6’ steel (Layer A)(7) 2’ x 3’ x 6’ (Layer A) (1) 2’ x 3’ x 6’ steel* (Layer A)(1) 6’ x 3’ x 2’ (Layer C) (2) 2’ x 3’ x 6’ concrete* (Layer A)(5) 2’ x 3’ x 2’ (Layer D) (1) 6’ x 3’ x 2’ concrete* (Layer C)

(6) 2’ x 3’ x 2’ steel (Layer D)(38% of existing) *block with “cut-out” for 1U beampipe

Vault-1A Shielding Layout (Layers A-D)EXISTING vs “NEW” (OPTION-1, STEEL)

Page 17: UCN Facility Working Group October 3, 2012 OverviewL.Lee MCNPX and ShieldingP.Carlson Beam MonitorsC.A.Davis / A.Konaka.

List of “Removed” Concrete Blocks: List of “New” Blocks:(2) 12’ x 6’ x 4’ (Layer A, C) (7) 2’ x 3’ x 6’ aggregate (Layer A)(6) 2’ x 3’ x 6’ (Layer A) (1) 2’ x 3’ x 6’ aggregate* (Layer A)(5) 6’ x 3’ x 2’ (Layer A, B, C) (2) 2’ x 3’ x 6’ concrete* (Layer A)(4) 2’ x 3’ x 2’ (Layer D) (1) 6’ x 3’ x 2’ concrete* (Layer C)

(8) 2’ x 3’ x 2’ aggregate (Layer D)(42% of existing) *block with “cut-out” for 1U beampipe

Vault-1A Shielding Layout (Layers A-D)EXISTING vs “NEW” (OPTION-2, AGGREGATE)

Page 18: UCN Facility Working Group October 3, 2012 OverviewL.Lee MCNPX and ShieldingP.Carlson Beam MonitorsC.A.Davis / A.Konaka.

High Density Concrete w/ AggregateNuclear Shielding Supplies and Services (NSS)

Concrete/Hematite aggregate shielding blocks – HD (3.8-5.7 g/cc) - Hematite (Fe2O3): Coarse [1” 3/8”] & Fine [3/8” 100 mesh] components

Established history of use at reactors and accelerators - Ontario Hydro (20 yrs, P.Mukherjee: Study of long-term effect on HD concrete at reactors) - BNL AGS (ilmenite, roof beams: 33 ton, blocks: 21, 11, 0.5 – 2 ton) - SNS Tunnel (hematite, 3.85g/cc, poured in place, 2000 m3) - TRIUMF

NSS has worked with Ellis-Don, Burnco, LaFarge

Used in both radiation & non-radiation applications: - high density radiation shielding - linear accelerator vaults & treatment rooms - high dose rate HDR rooms - mass concrete projects - high density concrete applications columns - gravity seawall, coastal protection & breakwater structures - bridge counterweights - ballast for ocean vessels and off shore platforms - noise and vibration dampening

Coarse Hematite

Fine Hematite

Page 19: UCN Facility Working Group October 3, 2012 OverviewL.Lee MCNPX and ShieldingP.Carlson Beam MonitorsC.A.Davis / A.Konaka.

Charles River Suspension Bridge in Boston, MA

NSS HD-concrete (Non-radiation Applications)

HD-concrete Back-spans

Page 20: UCN Facility Working Group October 3, 2012 OverviewL.Lee MCNPX and ShieldingP.Carlson Beam MonitorsC.A.Davis / A.Konaka.

Breakwater Structure Utilizing High Density Concrete

NSS HD-concrete (Non-radiation Applications)

Page 21: UCN Facility Working Group October 3, 2012 OverviewL.Lee MCNPX and ShieldingP.Carlson Beam MonitorsC.A.Davis / A.Konaka.

UCN Installation 2015/2016 (Option 3f)

N

High-densityNon-magnetic

Shielding

Dose Limit: 3 Sv/h outside of shielding

Page 22: UCN Facility Working Group October 3, 2012 OverviewL.Lee MCNPX and ShieldingP.Carlson Beam MonitorsC.A.Davis / A.Konaka.

EXTRA

Page 23: UCN Facility Working Group October 3, 2012 OverviewL.Lee MCNPX and ShieldingP.Carlson Beam MonitorsC.A.Davis / A.Konaka.

UCN Installation Schedule

N

2014 Shutdown

2015 Shutdown

2015 Non-Shutdown& 2016 Shutdown

Page 24: UCN Facility Working Group October 3, 2012 OverviewL.Lee MCNPX and ShieldingP.Carlson Beam MonitorsC.A.Davis / A.Konaka.

Optics Studies

Page 25: UCN Facility Working Group October 3, 2012 OverviewL.Lee MCNPX and ShieldingP.Carlson Beam MonitorsC.A.Davis / A.Konaka.

Vault-BL1A/1U Shielding RequirementsWhat are the requirements for the shielding “plug” with BL1U installed? (Preliminary discussions with A.Trudel) - Prompt Radiation Hazard (PRH) Study - Based on occupancy in 1A/1U tunnel with beam ON in vault:

Dose rate in accessible areas < 100 Sv/hr Annual personnel dose limits from chronic losses < 1 mSv

- Dose rate constraints for various accidental full beam loss scenarios (e.g. accidental insertion of 1A stripper, failure of 2AVB1 bender) Dose rate outside shielding < 50 mSv/hr Dose limit per full loss event < 1 mSv

How thick does the “new” shielding need to be? - Based on dose rates from various scenarios mentioned above (PRH study, simulation studies, surveys/measurements) - Design to maintain overall effective thickness (t ) in shielding “plug”

Is a Shielding-Plug “Task Force” needed?

Layout Option: Maintain effective thickness of shieldingReplace some of the concrete w/ higher density mat’l

Page 26: UCN Facility Working Group October 3, 2012 OverviewL.Lee MCNPX and ShieldingP.Carlson Beam MonitorsC.A.Davis / A.Konaka.

Vault Elements

Page 27: UCN Facility Working Group October 3, 2012 OverviewL.Lee MCNPX and ShieldingP.Carlson Beam MonitorsC.A.Davis / A.Konaka.

Existing Shielding (Layer A)(LAYERS B+C+D & UPPER LAYERS E-J HIDDEN)

Page 28: UCN Facility Working Group October 3, 2012 OverviewL.Lee MCNPX and ShieldingP.Carlson Beam MonitorsC.A.Davis / A.Konaka.

“New” Shielding Layout (Layer A)“FIRST-PASS” STUDY : OPTION-1 (STEEL)

Blue – steel, newYellow – concrete, new (w/ cut-out)

Page 29: UCN Facility Working Group October 3, 2012 OverviewL.Lee MCNPX and ShieldingP.Carlson Beam MonitorsC.A.Davis / A.Konaka.

“New” Shielding Layout (Layer A+B)“FIRST-PASS” STUDY : OPTION-1 (STEEL)

Blue – steel, newYellow – concrete, new (w/ cut-out)

Page 30: UCN Facility Working Group October 3, 2012 OverviewL.Lee MCNPX and ShieldingP.Carlson Beam MonitorsC.A.Davis / A.Konaka.

“New” Shielding Layout (Layer A+B+C)“FIRST-PASS” STUDY : OPTION-1 (STEEL)

Blue – steel, newYellow – concrete, new (w/ cut-out)

Page 31: UCN Facility Working Group October 3, 2012 OverviewL.Lee MCNPX and ShieldingP.Carlson Beam MonitorsC.A.Davis / A.Konaka.

“New” Shielding Layout (Layer A+B+C+D)“FIRST-PASS” STUDY : OPTION-1 (STEEL)

Blue – steel, newYellow – concrete, new (w/ cut-out)