UCN Beamline Shielding, Target & Remote-Handling UCN CDR (Sept/2010) L.Lee.
-
Upload
javon-southworth -
Category
Documents
-
view
215 -
download
0
Transcript of UCN Beamline Shielding, Target & Remote-Handling UCN CDR (Sept/2010) L.Lee.
![Page 1: UCN Beamline Shielding, Target & Remote-Handling UCN CDR (Sept/2010) L.Lee.](https://reader035.fdocuments.in/reader035/viewer/2022062620/551b36e1550346dd1a8b5145/html5/thumbnails/1.jpg)
UCN Beamline
Shielding, Target & Remote-Handling
UCN CDR (Sept/2010)
L.Lee
![Page 2: UCN Beamline Shielding, Target & Remote-Handling UCN CDR (Sept/2010) L.Lee.](https://reader035.fdocuments.in/reader035/viewer/2022062620/551b36e1550346dd1a8b5145/html5/thumbnails/2.jpg)
UCN Shielding Requirements
A.Trudel calculations (TRIUMF Safety Group)
40 A, 500 MeV protons stopping in W target
Assumes 0.5 m empty space around target (no moderator)
Plot shows the shielding needed to reduce dose to 3Sv/hr outside
General Layout of Shielding Structure
Inner layer of SteelOuter layer of Concrete
![Page 3: UCN Beamline Shielding, Target & Remote-Handling UCN CDR (Sept/2010) L.Lee.](https://reader035.fdocuments.in/reader035/viewer/2022062620/551b36e1550346dd1a8b5145/html5/thumbnails/3.jpg)
Shielding Costs
Latest UCN Layout
Vendor Quotes:Concrete $1251 kSteel (radioactive) $ 360 k (66%)Steel (new) $ 480 k (33%)Staging/Installation $ 20 kTotal $2111 k
Latest UCN Layout: Concrete $ 834 kSteel (radioactive) $ 240 k (66%)Steel (new) $ 320 k (33%)Staging/Installation $ 20 kTotal $1414 k
Original Cost Estimate (CFI prop):Concrete $ 900 kSteel (radioactive) $ 200 k (66%)Steel (new) $ 700 k (33%)Staging/Installation $ 20 kTotal $1820 k
Above estimates based on bulk volume estimates+20% contingency
More detailed layoutTRIUMF Design Office (A.Prorok)
![Page 4: UCN Beamline Shielding, Target & Remote-Handling UCN CDR (Sept/2010) L.Lee.](https://reader035.fdocuments.in/reader035/viewer/2022062620/551b36e1550346dd1a8b5145/html5/thumbnails/4.jpg)
Detailed Layout of UCN Shielding (1st Iteration)
Extent of existing Shielding Wall
UCN ConcreteShielding
UCN SteelShielding
![Page 5: UCN Beamline Shielding, Target & Remote-Handling UCN CDR (Sept/2010) L.Lee.](https://reader035.fdocuments.in/reader035/viewer/2022062620/551b36e1550346dd1a8b5145/html5/thumbnails/5.jpg)
UCN Shielding – Layer 1
Concrete shielding blocks – YellowSteel shielding blocks – Black/Silver
![Page 6: UCN Beamline Shielding, Target & Remote-Handling UCN CDR (Sept/2010) L.Lee.](https://reader035.fdocuments.in/reader035/viewer/2022062620/551b36e1550346dd1a8b5145/html5/thumbnails/6.jpg)
UCN Shielding – Layer 3
![Page 7: UCN Beamline Shielding, Target & Remote-Handling UCN CDR (Sept/2010) L.Lee.](https://reader035.fdocuments.in/reader035/viewer/2022062620/551b36e1550346dd1a8b5145/html5/thumbnails/7.jpg)
UCN Shielding – Layer 5
![Page 8: UCN Beamline Shielding, Target & Remote-Handling UCN CDR (Sept/2010) L.Lee.](https://reader035.fdocuments.in/reader035/viewer/2022062620/551b36e1550346dd1a8b5145/html5/thumbnails/8.jpg)
UCN Shielding – Layer 7
![Page 9: UCN Beamline Shielding, Target & Remote-Handling UCN CDR (Sept/2010) L.Lee.](https://reader035.fdocuments.in/reader035/viewer/2022062620/551b36e1550346dd1a8b5145/html5/thumbnails/9.jpg)
UCN Shielding – Layer 9
![Page 10: UCN Beamline Shielding, Target & Remote-Handling UCN CDR (Sept/2010) L.Lee.](https://reader035.fdocuments.in/reader035/viewer/2022062620/551b36e1550346dd1a8b5145/html5/thumbnails/10.jpg)
UCN Shielding Structure
4’ x 6’ x 18’ Concrete shielding blocks(on-hand, outside “Electronics” Trailer)
Reuse existing concrete blocks from M11/M13
1836 ft3 ~50 m3
![Page 11: UCN Beamline Shielding, Target & Remote-Handling UCN CDR (Sept/2010) L.Lee.](https://reader035.fdocuments.in/reader035/viewer/2022062620/551b36e1550346dd1a8b5145/html5/thumbnails/11.jpg)
Shielding Costs from 1st Iteration Layout
Possible Cost Savings:“Skyshine” dose limits are higher remove uppermost 2 layers of shielding (?) savings of ~ 22% $225 k Reuse existing steel from magnets possible savings $ 75 k
Total savings $300 k
1st Iteration UCN Layout: Concrete $ 445 kSteel (radioactive) $ 485 k Steel (new) $ 240 k Staging/Installation $ 20 kTotal $1190 k
If above savings can be implemented, total cost for shielding $890 k
2nd Iteration Layout Possible further improvements in “blocking” efficiency
![Page 12: UCN Beamline Shielding, Target & Remote-Handling UCN CDR (Sept/2010) L.Lee.](https://reader035.fdocuments.in/reader035/viewer/2022062620/551b36e1550346dd1a8b5145/html5/thumbnails/12.jpg)
Initial startup at 2 A (500 nA time-averaged)Target cooling and residual activity not a major issue RCNP @ 1 A radiative cooling found to be adequate
residual activity very low
At higher currents 40 A (10 A time-averaged) Require Target Cooling Water-cooling vs Helium-cooling Model target after elements from existing designs at BNL, KEK, TRIUMF Budget: $30k
Residual Activity & Remote-Handling Retract target into a shielded cask TRIUMF Remote-Handling specialists consulted do-able at $100k Target failure Transfer to Horizontal transport flask (e.g. 2C-STF flask)
and crane to existing Hot Cell facility
Prior to installation at TRIUMF (recent initiative with RCNP) Spallation Target & RH system use at RCNP RCNP: 2A to 10A (instantaneous) Ideal opportunity to test system and resolve Cooling/RH issues
Spallation Target & Remote-Handling System
![Page 13: UCN Beamline Shielding, Target & Remote-Handling UCN CDR (Sept/2010) L.Lee.](https://reader035.fdocuments.in/reader035/viewer/2022062620/551b36e1550346dd1a8b5145/html5/thumbnails/13.jpg)
Target Design
BNL target
Pt target (segmented) coupled to Copper base Water-cooled base Heat load ~ 2kW (time-avg) TRIUMF people involved in design of this target
UCN target
Tungsten alloy (HeavyMet) target; d~5 cm, L~11-14 cm Coupled to water-cooled base (Cu?) Heat load ~ 5kW (time-avg) Water flow rate ~10 L/min to remove instantaneous heat load
Model target after BNL target
![Page 14: UCN Beamline Shielding, Target & Remote-Handling UCN CDR (Sept/2010) L.Lee.](https://reader035.fdocuments.in/reader035/viewer/2022062620/551b36e1550346dd1a8b5145/html5/thumbnails/14.jpg)
Beam
300K D2O
20K D2O
Target
CoolingBlockCoolant LinesRails/Bearings Bellows
Rack & PinionSystem
Driveshaft(detachable)
Pb-Shielded Cask
Pb-ShieldedShutters
Flexible Shaft(remote-control cables)
He
80 cm
Remote-Handling System (Upstream Withdrawal)
Pb-Shielded Cask and Target Mounting System
![Page 15: UCN Beamline Shielding, Target & Remote-Handling UCN CDR (Sept/2010) L.Lee.](https://reader035.fdocuments.in/reader035/viewer/2022062620/551b36e1550346dd1a8b5145/html5/thumbnails/15.jpg)
Water-Cooling Setup for 1AT1/T2 Target Ladder
Bellows & Coaxial water lines on Target Ladder
Custom sealsTRIUMF M/Shop
![Page 16: UCN Beamline Shielding, Target & Remote-Handling UCN CDR (Sept/2010) L.Lee.](https://reader035.fdocuments.in/reader035/viewer/2022062620/551b36e1550346dd1a8b5145/html5/thumbnails/16.jpg)
Target in Retracted Position
Retract Target into Cask
Access UCN cryostat OR
Prep for Target Removal
![Page 17: UCN Beamline Shielding, Target & Remote-Handling UCN CDR (Sept/2010) L.Lee.](https://reader035.fdocuments.in/reader035/viewer/2022062620/551b36e1550346dd1a8b5145/html5/thumbnails/17.jpg)
Target Removal/Disposal
External Transport Flask
(e.g. 2C-STF flask)
Relocate Target + Cask to external (horizontal) transport Flask
Crane to Meson Hall Hot-Cell facility
![Page 18: UCN Beamline Shielding, Target & Remote-Handling UCN CDR (Sept/2010) L.Lee.](https://reader035.fdocuments.in/reader035/viewer/2022062620/551b36e1550346dd1a8b5145/html5/thumbnails/18.jpg)
Accel.
& Engr Cntrls Elect Mech
1
2 30 2.5 3 5 4 2.5 2 193 04 05 06 100 1 10 4 3 4.5 13 35.57 08 09 0
10 130 3.5 13 9 7 0 4.5 15.5 2 54.511
12 2 9.5 4.5 1.5 7.5 11 3613 445 014 015 485 016 240 017 20 4 0.5 1 1 14 3 23.518 1190 6 10 5.5 1.5 0 1 21.5 14 59.519
1320.1 9.5 23 14.5 8.5 0 5.5 37 16 114Total
Preparation and InstallationSHIELDING TOTAL
(25 m3 new steel at 9.6k/m3)
Safety intelocksVacuum system
SPALLATION TARGET TOTALS
SHIELDINGConcrete shielding (160 m3 @ 2.78k/m3)
Steel shielding (160 m3)(135 m3 recycled steel @ 3.6k/m3 )
Remote handling, tranfer flask, target suspensionTargeting monitor and interlock
Water cooling (included in "Target")
Sub-projects/Work PackagesMat'l &
Supplies (K$)
Human Resource Requirements (Person Months)
Phys Design
Spallation Target & Shielding
Total
SPALLATION TARGETTarget (incl. jacket and support)
M/ShopTechnician
Outside
Costs & Human Resources Summary
More details in main Resources & Timeline Section
Possible reduction in Human Resources requirements: RCNP (Tgt), Acsion (Tgt, Shielding)
![Page 19: UCN Beamline Shielding, Target & Remote-Handling UCN CDR (Sept/2010) L.Lee.](https://reader035.fdocuments.in/reader035/viewer/2022062620/551b36e1550346dd1a8b5145/html5/thumbnails/19.jpg)
Shielding:
Final design mid-2012Procure shielding mid-2012 mid-2014Install Base layer mid-2013 Dec/2013Install remaining layers mid-2014 mid-2015
Target & RH system: Receive Target @ TRIUMF: Mar/2014Install Target @ TRIUMF: May/2014
Schedule: Shielding and Target/RH
Overview of Main Milestones (details in Resources & Timeline Section)
![Page 20: UCN Beamline Shielding, Target & Remote-Handling UCN CDR (Sept/2010) L.Lee.](https://reader035.fdocuments.in/reader035/viewer/2022062620/551b36e1550346dd1a8b5145/html5/thumbnails/20.jpg)
The End
![Page 21: UCN Beamline Shielding, Target & Remote-Handling UCN CDR (Sept/2010) L.Lee.](https://reader035.fdocuments.in/reader035/viewer/2022062620/551b36e1550346dd1a8b5145/html5/thumbnails/21.jpg)
Shielding Costs
ORIGINAL (“With PIF”) UCN Layout NEW (“No PIF”) UCN Layout
Shielding Budgets
Original cost estimate (total) $1820 k (from CFI proposal)
Vendor Quotes:Concrete $1251 kSteel (radioactive) $ 360 k (66%)Steel (new) $ 480 k (33%)Staging/Installation $ 20 kTotal $2111 k
Latest UCN Layout: Concrete $ 834 kSteel (radioactive) $ 240 k (66%)Steel (new) $ 320 k (33%)Staging/Installation $ 20 kTotal $1414 k
![Page 22: UCN Beamline Shielding, Target & Remote-Handling UCN CDR (Sept/2010) L.Lee.](https://reader035.fdocuments.in/reader035/viewer/2022062620/551b36e1550346dd1a8b5145/html5/thumbnails/22.jpg)
UCN Shielding – Layer 2 (Base Layers)
![Page 23: UCN Beamline Shielding, Target & Remote-Handling UCN CDR (Sept/2010) L.Lee.](https://reader035.fdocuments.in/reader035/viewer/2022062620/551b36e1550346dd1a8b5145/html5/thumbnails/23.jpg)
![Page 24: UCN Beamline Shielding, Target & Remote-Handling UCN CDR (Sept/2010) L.Lee.](https://reader035.fdocuments.in/reader035/viewer/2022062620/551b36e1550346dd1a8b5145/html5/thumbnails/24.jpg)
Water-cooling vs Helium-cooling
Water Cooling Helium Cooling
Good cooling efficiency Low cooling efficiency high flow velocities req.
“Conventional” technology Greater Technical & Regulatory (ASME) complexity
Activation of water Low ActivationLeaks Contamination Risks Low Contamination RisksBoiling of Coolant
Two Water-cooled targets (1AT1 & 1AT2) in operation “near-by”Water-cooling infrastructure already available
![Page 25: UCN Beamline Shielding, Target & Remote-Handling UCN CDR (Sept/2010) L.Lee.](https://reader035.fdocuments.in/reader035/viewer/2022062620/551b36e1550346dd1a8b5145/html5/thumbnails/25.jpg)
Spallation Target
Calculations from Safety (A.Trudel) indicates target activity level after 10 years of irradiation will still be a factor of ~5 below the A2 transport limit
A stopping target of tungsten bombarded with 100 uA of 500 MeV protons. Blue arrows correspond to 1, 5 & 10 years of irradiation. Shown below the arrow is the total activity as a fraction of the A2 transport limit. The inventory of activity in the target at ten years is at approximately one fifth of the A2 transport limit for Type A packages.