Ubit Gas Lift Line Sizevalidation Report
-
Upload
ebby-onyekwe -
Category
Documents
-
view
219 -
download
0
Transcript of Ubit Gas Lift Line Sizevalidation Report
-
7/27/2019 Ubit Gas Lift Line Sizevalidation Report
1/4
UBIT GAS LIFT LINE SIZEVALIDATION REPORT
This report gives a description of the Line size validation study carried out for the UBIT
GAS LIFT pipeline/piping system. The objective of the study was to validate the
pipeline/piping sizes proposed by the CLIENT, for the lines enlisted below;
i. Proposed 4 line to connect from boarding gas lift pipeline to gas lift manifold.
ii.Proposed 4 gas lift manifold at Ubit GA
iii. Proposed 2 gas lift flowlines for each of the Six (6) new candidate wells
iv. Proposed 6 production flowline from each of the six (6) new candidate
wells
v. Proposed 6 Test manifold
vi. Proposed 10 Production manifold
vii. Existing 4 Test manifold
All lines were sized in accordance to the requirements as stipulated in API RP 14E for single
phase gas & two (2) phase streams. The pressure drop and velocity criteria were employed
in the validation of all lines. For gas lines, the velocity of the stream must not exceed 60 ft/s
to avoid noise while pressure drop should be such that the outlet pressure can meet the
pressure requirement of the downstream equipment.
Two (2) phase lines were sized on the basis of their erosional velocity which serves
as the basis for determining the minimum cross sectional area of pipeline/piping required to
transport the fluid.
Summary of Results
I. 4 Boarding Gas Lift Pipeline (GN)
The table below shows a summary of the results obtained from the validation
calculations performed for the Boarding Gas Lift Pipeline.
Flow rate Pipe Size Schedule No. Fluid Velocity Pressure Drop (psi/100ft)
9 MMSCFD 4 XXS 8.8 ft/s 0.57
15 MMSCFD 4 XXS 14.7 ft/s 1.59
The 4 pipe size met the velocity criteria for both flow rates although at a flow rate of 9
MMSCFD, a velocity of 8.8 ft/s might give rise to liquid settle out in low spots. Hence, a
4 pipe size would be adequate to handle the flow rate. The pressure drop obtained is
also less than 10% of the inlet pressure.
-
7/27/2019 Ubit Gas Lift Line Sizevalidation Report
2/4
II. 4 Gas Lift Manifold
The table below shows a summary of the results obtained from the validation
calculations performed for the Gas Lift Manifold.
Flow rate Pipe Size Schedule No. Fluid Velocity Pressure Drop (psi/100ft)
9 MMSCFD 4 XXS 11.7 ft/s 0.76
15 MMSCFD 4 XXS 19.54 ft/s 2.11
The 4 pipe size met the velocity criteria for both flow rates. Hence, a 4 pipe size would
be adequate to handle the flow rate. The pressure drop obtained is also less than 10%
of the inlet pressure which makes it adequate.
III. 2 Gas Lift Flow lines
The table below shows a summary of the results obtained from the validation
calculations performed for the Gas Lift Manifold.
Flow rate Pipe Size Schedule No. Fluid Velocity Pressure Drop (psi/100ft)2 MMSCFD 2 XXS 11.46 ft/s 1.52
The 2 pipe size met the velocity criteria for the new gas lift flow lines. Hence, a 2 pipe
size would be adequate to handle the flow rate. The pressure drop obtained is also less
than 10% of the inlet pressure which makes it adequate.
IV. 6 Production Flowline for each candidate well
The table below shows a summary of the results obtained from the validation
calculations performed for the Gas Lift Manifold.
Gas Flow
rate
Liquid
Flow
rate
Pipe
Size
Schedule
No.
Erosional
Velocity
Minimum
Area (in2)
Minimum
inside
diameter (in)
5.65
MMSCFD
6512
BLPD6 120 40.76 ft/s 14.65 4.32
The 6 production flowline gave rise to an erosional velocity of 40.76. For this erosional
velocity, a minimum pipe inside diameter of 4.32 in is required. A 6 SCH 120 piping is
adequate for the flow rate since it provides a greater inside diameter as well as sufficient
-
7/27/2019 Ubit Gas Lift Line Sizevalidation Report
3/4
pressure containment since its MAWP at operating conditions is greater than the SITP of
the well it is producing from.
V. 6 Test Header
The table below shows a summary of the results obtained from the validation
calculations performed for the Test Header.
Gas Flow
rate
Liquid
Flow
rate
Pipe
Size
Schedule
No.
Erosional
Velocity
Minimum
Area (in2)
Minimum
inside
diameter (in)5.65
MMSCFD
6512
BLPD6 120 40.76 ft/s 14.65 4.32
The 6 Test Header gave rise to an erosional velocity of 40.76. For this erosional
velocity, a minimum pipe inside diameter of 4.32 in is required. A 6 SCH 120 piping is
adequate for the flow rate since it provides a greater inside diameter as well as sufficient
pressure containment since its MAWP at operating conditions is greater than the SITP of
the well it is producing from.
VI. 10 Production Manifold
The table below shows a summary of the results obtained from the validation
calculations performed for the Gas Lift Manifold.
Gas
Flow
rate
Liquid
Flow
rate
Pipe
Size
Schedule
No.
Erosional
Velocity
Minimum
Area (in2)
Minimum
inside
diameter (in)22.56
BLPD
26006
BLPD10 120 40.81 ft/s 58.55 8.63
The 6 production flowline gave rise to an erosional velocity of 40.81. For this erosional
velocity, a minimum pipe inside diameter of 8.63 in is required. A 10 SCH 120 piping is
adequate for the flow rate since it provides a greater inside diameter as well as sufficientpressure containment since its MAWP at operating conditions is greater than the SITP of
the well it is producing from.
VII. 4 Test Header
-
7/27/2019 Ubit Gas Lift Line Sizevalidation Report
4/4
If the existing test header is to handle the single well flow of 6512 BLPD as well as 5.65
MMSCFD for 2 phase flow, it would require a minimum inside pipe diameter of 4.32 in.
Hence, if a 4 SCH 120 is required for the test header, the corresponding inside diameter
would be less than that required (4.32 in). This implies that the existing 4 test header is
inadequate to handle the 2 phase flow rates since it gives rise to a higher erosional
velocity.