Ubd Section 02 - Qhse

27
7/23/2019 Ubd Section 02 - Qhse http://slidepdf.com/reader/full/ubd-section-02-qhse 1/27 0 © Weatherford International, Inc. All rights reserved. DRILLING & WELL SERVICES ® QHSE WEATHERFORD UNDERBALANCED SYSTEMS

Transcript of Ubd Section 02 - Qhse

Page 1: Ubd Section 02 - Qhse

7/23/2019 Ubd Section 02 - Qhse

http://slidepdf.com/reader/full/ubd-section-02-qhse 1/27

0© Weatherford International, Inc. All rights reserved.

DRILLING & WELL SERVICES

®

QHSE WEATHERFORD

UNDERBALANCED SYSTEMS

Page 2: Ubd Section 02 - Qhse

7/23/2019 Ubd Section 02 - Qhse

http://slidepdf.com/reader/full/ubd-section-02-qhse 2/27

1© Weatherford International, Inc. All rights reserved.

DRILLING & WELL SERVICES

®Hazard/Risk Evaluation

• HAZARD : a condition that exists with the potential to do harm or damage to personnel,property or equipment.

• RISK : the likelihood of the hazard causing harm or damage to personnel, property orequipment

• HAZARD CONSEQUENCE : relates to the possible impact of a particular hazard

arising, to either the safety of personnel/installation or to the success of the operation

Page 3: Ubd Section 02 - Qhse

7/23/2019 Ubd Section 02 - Qhse

http://slidepdf.com/reader/full/ubd-section-02-qhse 3/27

2© Weatherford International, Inc. All rights reserved.

DRILLING & WELL SERVICES

®Hazard/Risk Evaluation

• FREQUENCY OF OCCURANCE: probability of a particular hazard occurring.

• Very unlikely RARE to occur during an operation.

• Possible SOMETIMES likely to occur during the operation.

• Very Likely  ALMOST ALWAYS OCCURS during the operation.

• CONTROL MEASURES – safety or operational measures that are either already inplace or require to be investigated in order to mitigate the risk or reduce the level ofrisk to an acceptable level.

Once the control measures have been identified & implemented, the risk should then bereassessed to ensure a low assessment. There may still be some operational riskassociated with the task referred to as Residual Risk.

Page 4: Ubd Section 02 - Qhse

7/23/2019 Ubd Section 02 - Qhse

http://slidepdf.com/reader/full/ubd-section-02-qhse 4/273© Weatherford International, Inc. All rights reserved.

DRILLING & WELL SERVICES

®Residual Risk

• Operational and HSE risks, must be reduced to as low as possible (ALARP)*

(ALARP)* - The code of “ As low as reasonably practicable” dictates that even if the risk can

be shown to be tolerable, it must be reduced until the cost of further improvement becomesgrossly disproportionate to the risk reduction achieved. This may still result in the residual riskbeing defined as medium or high as described.

Page 5: Ubd Section 02 - Qhse

7/23/2019 Ubd Section 02 - Qhse

http://slidepdf.com/reader/full/ubd-section-02-qhse 5/27

4© Weatherford International, Inc. All rights reserved.

DRILLING & WELL SERVICES

®Category of Residual Risk

• LOW Adequate measures are in place

• MEDIUM (safety) Do not proceed. Identify further control measures or an alternative

method of executing the operation such that the residual risk is reduced to LOW.

• MEDIUM (operational) Do not proceed until all additional control measures have beenidentified & implemented such that the residual risk is reduced to LOW.

• HIGH (safety) Do not proceed. Identify further control measures or an alternative methodof executing the operation such as the residual risk is reduced to LOW.

• HIGH (operational) If it is decided that the residual risk remains high followingimplementation of all control measures, the operation may continue.

Page 6: Ubd Section 02 - Qhse

7/23/2019 Ubd Section 02 - Qhse

http://slidepdf.com/reader/full/ubd-section-02-qhse 6/27

5© Weatherford International, Inc. All rights reserved.

DRILLING & WELL SERVICES

®QHSE MS Structure

Page 7: Ubd Section 02 - Qhse

7/23/2019 Ubd Section 02 - Qhse

http://slidepdf.com/reader/full/ubd-section-02-qhse 7/27

6© Weatherford International, Inc. All rights reserved.

DRILLING & WELL SERVICES

®

Quality Management SystemTop Level Global Framework

Level 1

Level 2

Level 3

Enterprise Excellence

Management System

Business Unit Quality

Management System

Business Unit

OperatingProcedures

Business

Units

 ActivityOperating Procedures

Region

RegionGuidance &Procedures

QHSE/OPMS

Top Level

Expectations

Guidelines &

RecommendedPractices

Page 8: Ubd Section 02 - Qhse

7/23/2019 Ubd Section 02 - Qhse

http://slidepdf.com/reader/full/ubd-section-02-qhse 8/27

7© Weatherford International, Inc. All rights reserved.

DRILLING & WELL SERVICES

® A Comprehensive UBD QHSE System

Sound Equipment Design

 –  Formalized Safety Review Process

• HAZOP, HAZID, SIMOPS –  Operational Procedures

• Procedural HAZOP

 –  Emergency Procedures & Contingencies

 –  Specialized Training

 –  Effective Site Specific HSE Plan

 –  Audits, Inspections

 –  Reviews

Page 9: Ubd Section 02 - Qhse

7/23/2019 Ubd Section 02 - Qhse

http://slidepdf.com/reader/full/ubd-section-02-qhse 9/27

8© Weatherford International, Inc. All rights reserved.

DRILLING & WELL SERVICES

®

Page 10: Ubd Section 02 - Qhse

7/23/2019 Ubd Section 02 - Qhse

http://slidepdf.com/reader/full/ubd-section-02-qhse 10/27

9© Weatherford International, Inc. All rights reserved.

DRILLING & WELL SERVICES

®Equipment Design

•  A properly designed andimplemented UBD QHSEsystem is safer than

conventional drilling system

•  A properly designed UBDsystem does not have todepend on personnel

properly interpreting andresponding to well controlincident

• The system is designed toproperly handle & process

flow from the well

Page 11: Ubd Section 02 - Qhse

7/23/2019 Ubd Section 02 - Qhse

http://slidepdf.com/reader/full/ubd-section-02-qhse 11/27

10© Weatherford International, Inc. All rights reserved.

DRILLING & WELL SERVICES

®

HAZOPs and HAZIDs are both systematicprocesses to Identify Hazards

•  A HAZOP is designed to review process systems and operating proceduresto confirm whether they will operate as intended, without having introducedany avoidable hazards.

•  A HAZID is designed to identify all potential hazards which could result fromoperation of a facility or from carrying out an activity.

•  A HAZID is based on the HAZOP process but is more flexible.

Page 12: Ubd Section 02 - Qhse

7/23/2019 Ubd Section 02 - Qhse

http://slidepdf.com/reader/full/ubd-section-02-qhse 12/27

11© Weatherford International, Inc. All rights reserved.

DRILLING & WELL SERVICES

®

• Core Team Session Leader

Session recorder

Design Process Engineer

Project Operations Representative

•  Additional Members Instrument Engineer

Project Engineer

Mechanical Engineer

Independent Experts (unless covered by Leader)

Page 13: Ubd Section 02 - Qhse

7/23/2019 Ubd Section 02 - Qhse

http://slidepdf.com/reader/full/ubd-section-02-qhse 13/27

12© Weatherford International, Inc. All rights reserved.

DRILLING & WELL SERVICES

®HAZOPS, HAZIDS & SIMOPS

• What are they & why do them?

• HAZOPs and HAZIDs are both systematic processes to identify hazards.

• “You cannot manage what you don’t know.” –   A HAZOP is designed to review process systems and operating

procedures to confirm whether they will operate and be operable asintended, without having introduced any avoidable hazards.

 –   A HAZID is designed to identify all potential hazards which could resultfrom operation of a facility or from carrying out an activity.

 –   A HAZID is based on the HAZOP process but is more flexible.

Page 14: Ubd Section 02 - Qhse

7/23/2019 Ubd Section 02 - Qhse

http://slidepdf.com/reader/full/ubd-section-02-qhse 14/27

13© Weatherford International, Inc. All rights reserved.

DRILLING & WELL SERVICES

®HAZOPS & HAZIDS

•  A group of experienced people are led through a systematic process as a means ofcarrying out a detailed review of a system or activity.

 –  The system or activity is broken down into simple sections (Nodes) and, byapplying a set of guidewords, the team identify potential hazards, safeguards

in place and any shortcomings.

•  A summary of the overall project/facility and the design intent from the project or processengineer .

• Description on how the scope has been divided and provide a list of nodes.

• Run through the guideword list highlighting any proposed variation to normal practice.

• The node is described and marked on the drawings provided

Page 15: Ubd Section 02 - Qhse

7/23/2019 Ubd Section 02 - Qhse

http://slidepdf.com/reader/full/ubd-section-02-qhse 15/27

14© Weatherford International, Inc. All rights reserved.

DRILLING & WELL SERVICES

®HAZOPS & HAZIDS

Flow Pressure Level Temperature Erosion/Corrosion

Composition Sampling Operability Safety Critical spares

Maintenance Material

problems

Human

error 

Viscosity

Primary Keywords

No/Less More Reverse Contamination Reactivity

Emulsions Foaming Procedures Change Failure

Issue Redundancy Risk Not taken Fluctuating

Secondary Keywords

Page 16: Ubd Section 02 - Qhse

7/23/2019 Ubd Section 02 - Qhse

http://slidepdf.com/reader/full/ubd-section-02-qhse 16/27

15© Weatherford International, Inc. All rights reserved.

DRILLING & WELL SERVICES

®HAZOPS & HAZIDS

GUIDEWORD POSSIBLE CAUSES

REVERSE FLOW Defective check valve, incorrect differential pressure, two-way flow, emergency venting, incorrectoperation, in-line spare equipment etc

MORE LEVEL “level” applied to vessels instead of flow

Outlet isolated or blocked, inflow greater than outflow, control failure, faulty level measurement, foametc

LESS LEVEL Inlet flow stops, leak, outflow greater than inflow, control failure, faulty level measurement, agitatorwhip etc

FLUCTUATING LEVEL Control system operation, foam, agitator whip etc

MORE PRESSURE Surge problems, leakage from interconnected HP system, gas breakthrough (inadequate venting),isolation procedures for relief valves defective, thermal overpressure, positive displacement pumps,failed open PCVs, design pressures, specification of pipes, vessels, fittings instruments, blockagedownstream etc

LESS PRESSURE Generation of vacuum condition, condensation, gas dissolving in liquid, restricted pump/compressorsuction line, undetected leakage, vessel drainage, blockage of gas blanket gas reducing valve etc

FLUCTUATING PRESSURE water hammer, pump/compressor control systems, vibration

Page 17: Ubd Section 02 - Qhse

7/23/2019 Ubd Section 02 - Qhse

http://slidepdf.com/reader/full/ubd-section-02-qhse 17/27

16© Weatherford International, Inc. All rights reserved.

DRILLING & WELL SERVICES

®HAZOPS & HAZIDS

DEVIATION CAUSE CONSEQUENCE SAFEGUARDS ACTION

FlowNo/Less

pump failure Yard test [1] Review preventative maintenanceschedule for all system components[2] Provide procedure to clean-out hosesduring rig moves

FlowNo/Less

Shut valves CompetencyProceduresMaintenanceetc

FlowMore Human error Overload separatorErode linesLiquid carry-over to flare

Calculate maximum that well can deliveragainst separator capacity to ensure thatany impact of human error is minimizedby system design

Composition

Issue

Failure of membrane

monitoring system

Higher O2 limit in well Provide O2 sample tubes to reconfirm O2

generation levels

CompositionIssue

Emulsions Affects well test results Production can acceptemulsions if produced

Page 18: Ubd Section 02 - Qhse

7/23/2019 Ubd Section 02 - Qhse

http://slidepdf.com/reader/full/ubd-section-02-qhse 18/27

17© Weatherford International, Inc. All rights reserved.

DRILLING & WELL SERVICES

®HAZOPS & HAZIDS

• Review of P&IDs and cause and effects at:

approved for manufacture

revision after inter-discipline checks

and before manufacture starts

• For vendor equipment – once the drawings are available

• In the final stages of preparing a procedure

• Management of change

Page 19: Ubd Section 02 - Qhse

7/23/2019 Ubd Section 02 - Qhse

http://slidepdf.com/reader/full/ubd-section-02-qhse 19/27

18© Weatherford International, Inc. All rights reserved.

DRILLING & WELL SERVICES

®HAZOPS & HAZIDS

HAZIDS – Example – UBD Project

• Usage of crude as drilling fluid• Compressed gas in the drill string and surface pipe work

• Intentional loss of primary well control barriers (i.e. mud column)

• H2S

• CO2

Page 20: Ubd Section 02 - Qhse

7/23/2019 Ubd Section 02 - Qhse

http://slidepdf.com/reader/full/ubd-section-02-qhse 20/27

19© Weatherford International, Inc. All rights reserved.

DRILLING & WELL SERVICES

®Hazards Associated with UBD

• Positive Surface Pressure (Live Well Risk)

Reliance on mechanical barriers

High Fluid Return VelocitiesSurface equipment erosion

Make Up of the Injected Gas

Down hole fire/corrosionLive Formation Fluids at Surface

Fire—H2S

Wellbore Stability Problems

Hole collapse, mud weight required for support

Page 21: Ubd Section 02 - Qhse

7/23/2019 Ubd Section 02 - Qhse

http://slidepdf.com/reader/full/ubd-section-02-qhse 21/27

20© Weatherford International, Inc. All rights reserved.

DRILLING & WELL SERVICES

®SIMOPS

XXXXX UBDConcurrent

Operations

Rig-upUBDSurfacepackage

Rigup/downTank farm

Commissioning

Drill toShoe

Drill-ingUBD

Well Shut-in (for wellcontrol)

Crane/ForkliftOperationsTruck Oman

TruckCrude

GPSCuttings

Decommission UBDSurfacePackage

Rig-down

Completion

Rig-up UBD Surface package Yes N/A Yes N/A No Yes Yes N/A N/A N/A N/A

Rig up/down tank farm Yes Yes Yes No No Yes No Yes N/A Yes Yes

Commissioning N/A Yes Yes N/A No Yes Yes N/A N/A N/A N/A

Drill to Shoe Yes Yes Yes N/A N/A Yes Yes N/A N/A N/A N/A

Drilling UBD N/A No N/A N/A N/A Yes Yes No N/A N/A N/A

Well Shut-in (for well control) No No No N/A N/A No No No No No No

Crane/Forklift Operations Yes Yes Yes Yes Yes No Yes Yes Yes Yes Yes

Truck - Crude Yes No Yes Yes Yes No Yes N/A Yes Yes Yes

GPS Cuttings N/A Yes N/A N/A No No Yes N/A No Yes Yes

Decommission UBD SurfacePackage

N/A N/A N/A N/A N/A No Yes Yes No N/A Yes

Rig Down N/A Yes N/A N/A N/A No Yes Yes Yes N/A Yes

Completion N/A Yes N/A N/A N/A No Yes Yes Yes Yes Yes

Page 22: Ubd Section 02 - Qhse

7/23/2019 Ubd Section 02 - Qhse

http://slidepdf.com/reader/full/ubd-section-02-qhse 22/27

21© Weatherford International, Inc. All rights reserved.

DRILLING & WELL SERVICES

®Operational Procedures

UBD PROCEDURES (HAZOPED)

• Procedures on all critical operations are documented and HAZOPed

• No deviation to procedures is tolerated in UBD

• Management of change process is frequently used to facilitate anyproposed changes to procedures or systems at site

• Management of change form to be used for permanent changes

Page 23: Ubd Section 02 - Qhse

7/23/2019 Ubd Section 02 - Qhse

http://slidepdf.com/reader/full/ubd-section-02-qhse 23/27

22© Weatherford International, Inc. All rights reserved.

DRILLING & WELL SERVICES

®Training

•  All personnel from the Package Supervisor or Engineer down to Assistant

Operators are fully trained in the operation of all items of UBS equipment

deployed for the projects.

• Where training or advance courses are required our own staff as well as the

operators can benefit from participation.

• UBD Well Control Simulator is installed in the Regional Office

• Communication is the most important for UB solutions and full radio sets are

utilized.

Page 24: Ubd Section 02 - Qhse

7/23/2019 Ubd Section 02 - Qhse

http://slidepdf.com/reader/full/ubd-section-02-qhse 24/27

23© Weatherford International, Inc. All rights reserved.

DRILLING & WELL SERVICES

®Training

1   2   3   4   5   6   7   8   9   10  11  12  13  14  15  16  17  18  19  20  21  22  23  24  25  26  27  28  29  30  31  32  33  34

R   R   r    R   r    R   R   R   R   R   r    R   R   r    R   r    R   r    r    r    r    r    r    r    r    r    r    r    r    r R   R   R   R   R   R   R   R   R   R   R   R   r    R   R   R   r    R   R   R   R   R   R   R   R   R   R   R   R   R   R   R   R

R   R   R   R   R   R   R   R   R   R   R   R   R   R   R   R   R   R   R   R   R   R   R   R   R   R   R   R   R   R   R   R   R   RR   R   R   R   R   R   R   R   R   R   R   R   R   R   R   R   R   R   R   R   R   R   R   R   R   R   R   R   RR   R   R   R   R   R   R   R   R   R   R   R   R   R   R   R   R   R   R   R   R   R   R   R   R   R   R   R   R

R   R   R   R   r    R   R   R   R   r    r    r    r    r    r R   R   R   R   r    R   R   R   R   r    r    r    r    r    r 

R   R   R   R   R   R   R   R   R   R   R   R   r    R   R   R   R   R   R   R   R   R   R   R   R   R   R   R   R   R   R   RR   R   R   R   R   R   r    R   R   R   R   R   r    R   r    R   r    r    r    r    r    r    r    r    r 

R   R   R   R   R   r    r    r    R   r    R   r    R   r    r    r    r    r    r    r 

r    r    R   R   R   R   R   R   R   r    R   r    R   r    R   R   r    r    r    r    r    r    r R   R   R   R   R   R   r    R   R   R   R   R   R   r    R   R   r    R   R   R   R   R   R   R   R   R   R   R   RR   R   R   R   R   R   R   R   R   R   R   R   R   R   R   R   R   R   R   R   R

R   R   r    R   r    R   R   r    r    r    r    r    R   R   r    R   R   R   R   R   R   R   R   R   R   R   R   R   R   R

Technical Sales

UBS Site Engineer

* for immediate implentation - all WFT and external training resources are available for scheduling (comprehensive Workforce Development Program under development); R = REQUIRED, r = recommended

Job Function

Manager, Product Line

Shift Supervisor, Compression

Manager, Project

Shift Supervisor, Separation

Operator, Separation

           F

   i  r  s   t   A   i   d

           O

   f   f  s   h  o  r  e   S  u  r  v   i  v  a   l           (  a  s  r  e  q  u   i  r  e

   d   )

Operator, Compression

Engineer, CCE

           S

  a   f  e   t  y   i  n   t   h  e   W  o  r   k  p   l  a  c  e

Supervisor, Well Site

Engineer, Project UBS

           P

  r  o   j  e  c   t   M  a  n  a  g  e  m  e  n   t

           H

  y   d  r  o  g  e  n   S  u   l   f   i   d  e   S  a   f  e   t  y

           F

   l  o  w   M  o   d  e   l   i  n  g  -   A   d  v  a  n  c  e   d

           W

   C   S          o  n   l   i  n  e           P  r   i  m  a  r  y   C  e  m  e  n   t   i  n  g

           W

   C   S          o  n   l   i  n  e           H  o  r   i  z  o  n   t  a   l   D  r   i   l   l   i  n  g           (   V  o   l   1  -   2   )

           W

   C   S          o  n   l   i  n  e           O   i   l  w  e   l   l   D  r   i   l   l   i  n  g           (   V

  o   l   1  -   1   0   )

           W

   C   S          o  n   l   i  n  e           O   i   l  a  n   d   G  a  s   R  e  s

  e  r  v  o   i  r  s

           W

   C   S          o  n   l   i  n  e           H           2           S   P  r  o   d  u  c   t   i  o  n   O  p  e  r  a   t   i  o  n  s

           W

   C   S          o  n   l   i  n  e           K   i  c   k   D  e   t  e  c   t   i  o  n

           W

   C   S          o  n   l   i  n  e           B  a  s   i  c   O   i   l   f   i  e   l   d   C  a   l  c  u   l  a   t   i  o  n  s           (   V  o   l   1  -   2   )

Operation Mgr/Superintendant

Technician, RCH / RotBOP

Technician, DAQ / Systems

Weatherford Underbalanced Services Phase-1* Training Matrix

           W

  e   l   l   C  o  n   t  r  o   l  -   I   W   C   F  o  r   W  e

   l   l   C   A   P  -  a  c  c  r  e   d   i   t  e   d

           U

  n   d  e  r   b  a   l  a  n  c  e   d   D  r   i   l   l   i  n  g  -   B

  a  s   i  c

           F

   l  o  w   M  o   d  e   l   i  n  g  -   B  a  s   i  c

           U

  n   d  e  r   b  a   l  a  n  c  e   d   D  r   i   l   l   i  n  g  -   A

   d  v  a  n  c  e   d

           W

   F   T   H  e  a   l   t   h ,

   S  a   f  e   t  y  a  n   d   E  n  v   i  r  o  n  m  e  n   t  a   l

           W

   F   T   T  e  a  m   D  e  v  e   l  o  p  m  e  n   t   W

  o  r   k  s   h  o  p

           W

   F   T   F  u  n   d  a  m  e  n   t  a   l   C  o  m  p   l  e   t   i  o  n   P  r  a  c   t   i  c  e  s

           W

   F   T   A  m   b  a  s  s  a   d  o  r           (   '   C   h  a  r  m    S

  c   h  o  o   l   '   )

           C

  o  n   f   i  n  e   d   S  p  a  c  e   S  a   f  e   t  y

           T

   R   U   E   f  o  r   D  r   i   l   l   i  n  g           (  p  r  o   j  e  c   t  -  s  p  e  c   i   f   i  c   )

           O

   S   H   A   5   0   1

           S

   T   O   P

           W

   F   T   W  e  a   t   h  e  r   f  o  r   d   O  v  e  r  v   i  e

  w   /   I  n   d  u  c   t   i  o  n

Provisional at this stage

           F

  o  r   k   l   i   f   t           (  a  s  r  e  q  u   i  r  e   d   )

           W

   C   S          o  n   l   i  n  e           W   i  r  e   l   i  n  e   O  p  e  r  a   t   i  o  n  s           (   V  o   l   1  -   5   )

           H

   A   Z   I   D   /   H   A   Z   O   P   P  r  o  c  e  s  s  e  s

           C

   O   S   H   H   /   H   A   Z   M   A   T

           L

  e  a   d  e  r  s   h   i  p

           W

   F   T   B  a  s   i  c   T  r  a   i  n   i  n  g   f  o  r   S  u

  p  e  r  v   i  s  o  r  s

           W

   C   S          o  n   l   i  n  e           B   i   t   H  y   d  r  a  u   l   i  c  s

           W

   F   T   B   l  o  w  o  u   t   P  r  e  v  e  n   t  o  r  a  n   d   M  a  n   i   f  o   l   d  s

Page 25: Ubd Section 02 - Qhse

7/23/2019 Ubd Section 02 - Qhse

http://slidepdf.com/reader/full/ubd-section-02-qhse 25/27

24© Weatherford International, Inc. All rights reserved.

DRILLING & WELL SERVICES

®HSE Plan 

 A u d i t i n g

P o l i c y

O r g a n i s i n g

P l an n i n g a n dI m p l e m e n t i n g

M e a s u r i n g

P e r f o r m a n c e

R e v i e w i n g

P e r f o r m a n c e

Page 26: Ubd Section 02 - Qhse

7/23/2019 Ubd Section 02 - Qhse

http://slidepdf.com/reader/full/ubd-section-02-qhse 26/27

25© Weatherford International, Inc. All rights reserved.

DRILLING & WELL SERVICES

®HSE Plan Contents

• Leadership and Commitment

• Policy & Strategic Objectives

• Organization, Responsibilities, Resources, Standards & Documentation

• Hazards & Effects Management Process

• Planning & Procedures

• Implementation, Monitoring & Corrective Action

•  Audit & Review

Page 27: Ubd Section 02 - Qhse

7/23/2019 Ubd Section 02 - Qhse

http://slidepdf.com/reader/full/ubd-section-02-qhse 27/27

26© Weatherford International, Inc. All rights reserved.

DRILLING & WELL SERVICES

®HSE Monthly Review Report

CONTENTS

1. Minutes of Last Month Contract QHSE & Operations Review Meeting

2. Schedule for the next Contract QHSE & Operations Review Meeting

3. HSE Performance & Statistics

• LTI Free Days LTIF Vs Man-hours

• Identified Hazards Vs Incidents (current month)

• Identified Hazards Vs Incidents (Project to Date)

• HSE Communication (Management Meetings, Meetings, TBT, JSAs)

• HSE Training Status

4. Operations

• Drilling Time Performance

• Rig Days UBD Vs Rig Days on Well

• Rig Down – Rig Up Performance

• WFT NPT-Total NPT Performance