Ubd Section 02 - Qhse
-
Upload
umair-tariq -
Category
Documents
-
view
232 -
download
2
Transcript of Ubd Section 02 - Qhse
7/23/2019 Ubd Section 02 - Qhse
http://slidepdf.com/reader/full/ubd-section-02-qhse 1/27
0© Weatherford International, Inc. All rights reserved.
DRILLING & WELL SERVICES
®
QHSE WEATHERFORD
UNDERBALANCED SYSTEMS
7/23/2019 Ubd Section 02 - Qhse
http://slidepdf.com/reader/full/ubd-section-02-qhse 2/27
1© Weatherford International, Inc. All rights reserved.
DRILLING & WELL SERVICES
®Hazard/Risk Evaluation
• HAZARD : a condition that exists with the potential to do harm or damage to personnel,property or equipment.
• RISK : the likelihood of the hazard causing harm or damage to personnel, property orequipment
• HAZARD CONSEQUENCE : relates to the possible impact of a particular hazard
arising, to either the safety of personnel/installation or to the success of the operation
7/23/2019 Ubd Section 02 - Qhse
http://slidepdf.com/reader/full/ubd-section-02-qhse 3/27
2© Weatherford International, Inc. All rights reserved.
DRILLING & WELL SERVICES
®Hazard/Risk Evaluation
• FREQUENCY OF OCCURANCE: probability of a particular hazard occurring.
• Very unlikely RARE to occur during an operation.
• Possible SOMETIMES likely to occur during the operation.
• Very Likely ALMOST ALWAYS OCCURS during the operation.
• CONTROL MEASURES – safety or operational measures that are either already inplace or require to be investigated in order to mitigate the risk or reduce the level ofrisk to an acceptable level.
Once the control measures have been identified & implemented, the risk should then bereassessed to ensure a low assessment. There may still be some operational riskassociated with the task referred to as Residual Risk.
7/23/2019 Ubd Section 02 - Qhse
http://slidepdf.com/reader/full/ubd-section-02-qhse 4/273© Weatherford International, Inc. All rights reserved.
DRILLING & WELL SERVICES
®Residual Risk
• Operational and HSE risks, must be reduced to as low as possible (ALARP)*
(ALARP)* - The code of “ As low as reasonably practicable” dictates that even if the risk can
be shown to be tolerable, it must be reduced until the cost of further improvement becomesgrossly disproportionate to the risk reduction achieved. This may still result in the residual riskbeing defined as medium or high as described.
7/23/2019 Ubd Section 02 - Qhse
http://slidepdf.com/reader/full/ubd-section-02-qhse 5/27
4© Weatherford International, Inc. All rights reserved.
DRILLING & WELL SERVICES
®Category of Residual Risk
• LOW Adequate measures are in place
• MEDIUM (safety) Do not proceed. Identify further control measures or an alternative
method of executing the operation such that the residual risk is reduced to LOW.
• MEDIUM (operational) Do not proceed until all additional control measures have beenidentified & implemented such that the residual risk is reduced to LOW.
• HIGH (safety) Do not proceed. Identify further control measures or an alternative methodof executing the operation such as the residual risk is reduced to LOW.
• HIGH (operational) If it is decided that the residual risk remains high followingimplementation of all control measures, the operation may continue.
7/23/2019 Ubd Section 02 - Qhse
http://slidepdf.com/reader/full/ubd-section-02-qhse 6/27
5© Weatherford International, Inc. All rights reserved.
DRILLING & WELL SERVICES
®QHSE MS Structure
7/23/2019 Ubd Section 02 - Qhse
http://slidepdf.com/reader/full/ubd-section-02-qhse 7/27
6© Weatherford International, Inc. All rights reserved.
DRILLING & WELL SERVICES
®
Quality Management SystemTop Level Global Framework
Level 1
Level 2
Level 3
Enterprise Excellence
Management System
Business Unit Quality
Management System
Business Unit
OperatingProcedures
Business
Units
ActivityOperating Procedures
Region
RegionGuidance &Procedures
QHSE/OPMS
Top Level
Expectations
Guidelines &
RecommendedPractices
7/23/2019 Ubd Section 02 - Qhse
http://slidepdf.com/reader/full/ubd-section-02-qhse 8/27
7© Weatherford International, Inc. All rights reserved.
DRILLING & WELL SERVICES
® A Comprehensive UBD QHSE System
Sound Equipment Design
– Formalized Safety Review Process
• HAZOP, HAZID, SIMOPS – Operational Procedures
• Procedural HAZOP
– Emergency Procedures & Contingencies
– Specialized Training
– Effective Site Specific HSE Plan
– Audits, Inspections
– Reviews
7/23/2019 Ubd Section 02 - Qhse
http://slidepdf.com/reader/full/ubd-section-02-qhse 9/27
8© Weatherford International, Inc. All rights reserved.
DRILLING & WELL SERVICES
®
7/23/2019 Ubd Section 02 - Qhse
http://slidepdf.com/reader/full/ubd-section-02-qhse 10/27
9© Weatherford International, Inc. All rights reserved.
DRILLING & WELL SERVICES
®Equipment Design
• A properly designed andimplemented UBD QHSEsystem is safer than
conventional drilling system
• A properly designed UBDsystem does not have todepend on personnel
properly interpreting andresponding to well controlincident
• The system is designed toproperly handle & process
flow from the well
7/23/2019 Ubd Section 02 - Qhse
http://slidepdf.com/reader/full/ubd-section-02-qhse 11/27
10© Weatherford International, Inc. All rights reserved.
DRILLING & WELL SERVICES
®
HAZOPs and HAZIDs are both systematicprocesses to Identify Hazards
• A HAZOP is designed to review process systems and operating proceduresto confirm whether they will operate as intended, without having introducedany avoidable hazards.
• A HAZID is designed to identify all potential hazards which could result fromoperation of a facility or from carrying out an activity.
• A HAZID is based on the HAZOP process but is more flexible.
7/23/2019 Ubd Section 02 - Qhse
http://slidepdf.com/reader/full/ubd-section-02-qhse 12/27
11© Weatherford International, Inc. All rights reserved.
DRILLING & WELL SERVICES
®
• Core Team Session Leader
Session recorder
Design Process Engineer
Project Operations Representative
• Additional Members Instrument Engineer
Project Engineer
Mechanical Engineer
Independent Experts (unless covered by Leader)
7/23/2019 Ubd Section 02 - Qhse
http://slidepdf.com/reader/full/ubd-section-02-qhse 13/27
12© Weatherford International, Inc. All rights reserved.
DRILLING & WELL SERVICES
®HAZOPS, HAZIDS & SIMOPS
• What are they & why do them?
• HAZOPs and HAZIDs are both systematic processes to identify hazards.
• “You cannot manage what you don’t know.” – A HAZOP is designed to review process systems and operating
procedures to confirm whether they will operate and be operable asintended, without having introduced any avoidable hazards.
– A HAZID is designed to identify all potential hazards which could resultfrom operation of a facility or from carrying out an activity.
– A HAZID is based on the HAZOP process but is more flexible.
7/23/2019 Ubd Section 02 - Qhse
http://slidepdf.com/reader/full/ubd-section-02-qhse 14/27
13© Weatherford International, Inc. All rights reserved.
DRILLING & WELL SERVICES
®HAZOPS & HAZIDS
• A group of experienced people are led through a systematic process as a means ofcarrying out a detailed review of a system or activity.
– The system or activity is broken down into simple sections (Nodes) and, byapplying a set of guidewords, the team identify potential hazards, safeguards
in place and any shortcomings.
• A summary of the overall project/facility and the design intent from the project or processengineer .
• Description on how the scope has been divided and provide a list of nodes.
• Run through the guideword list highlighting any proposed variation to normal practice.
• The node is described and marked on the drawings provided
7/23/2019 Ubd Section 02 - Qhse
http://slidepdf.com/reader/full/ubd-section-02-qhse 15/27
14© Weatherford International, Inc. All rights reserved.
DRILLING & WELL SERVICES
®HAZOPS & HAZIDS
Flow Pressure Level Temperature Erosion/Corrosion
Composition Sampling Operability Safety Critical spares
Maintenance Material
problems
Human
error
Viscosity
Primary Keywords
No/Less More Reverse Contamination Reactivity
Emulsions Foaming Procedures Change Failure
Issue Redundancy Risk Not taken Fluctuating
Secondary Keywords
7/23/2019 Ubd Section 02 - Qhse
http://slidepdf.com/reader/full/ubd-section-02-qhse 16/27
15© Weatherford International, Inc. All rights reserved.
DRILLING & WELL SERVICES
®HAZOPS & HAZIDS
GUIDEWORD POSSIBLE CAUSES
REVERSE FLOW Defective check valve, incorrect differential pressure, two-way flow, emergency venting, incorrectoperation, in-line spare equipment etc
MORE LEVEL “level” applied to vessels instead of flow
Outlet isolated or blocked, inflow greater than outflow, control failure, faulty level measurement, foametc
LESS LEVEL Inlet flow stops, leak, outflow greater than inflow, control failure, faulty level measurement, agitatorwhip etc
FLUCTUATING LEVEL Control system operation, foam, agitator whip etc
MORE PRESSURE Surge problems, leakage from interconnected HP system, gas breakthrough (inadequate venting),isolation procedures for relief valves defective, thermal overpressure, positive displacement pumps,failed open PCVs, design pressures, specification of pipes, vessels, fittings instruments, blockagedownstream etc
LESS PRESSURE Generation of vacuum condition, condensation, gas dissolving in liquid, restricted pump/compressorsuction line, undetected leakage, vessel drainage, blockage of gas blanket gas reducing valve etc
FLUCTUATING PRESSURE water hammer, pump/compressor control systems, vibration
7/23/2019 Ubd Section 02 - Qhse
http://slidepdf.com/reader/full/ubd-section-02-qhse 17/27
16© Weatherford International, Inc. All rights reserved.
DRILLING & WELL SERVICES
®HAZOPS & HAZIDS
DEVIATION CAUSE CONSEQUENCE SAFEGUARDS ACTION
FlowNo/Less
pump failure Yard test [1] Review preventative maintenanceschedule for all system components[2] Provide procedure to clean-out hosesduring rig moves
FlowNo/Less
Shut valves CompetencyProceduresMaintenanceetc
FlowMore Human error Overload separatorErode linesLiquid carry-over to flare
Calculate maximum that well can deliveragainst separator capacity to ensure thatany impact of human error is minimizedby system design
Composition
Issue
Failure of membrane
monitoring system
Higher O2 limit in well Provide O2 sample tubes to reconfirm O2
generation levels
CompositionIssue
Emulsions Affects well test results Production can acceptemulsions if produced
7/23/2019 Ubd Section 02 - Qhse
http://slidepdf.com/reader/full/ubd-section-02-qhse 18/27
17© Weatherford International, Inc. All rights reserved.
DRILLING & WELL SERVICES
®HAZOPS & HAZIDS
• Review of P&IDs and cause and effects at:
approved for manufacture
revision after inter-discipline checks
and before manufacture starts
• For vendor equipment – once the drawings are available
• In the final stages of preparing a procedure
• Management of change
7/23/2019 Ubd Section 02 - Qhse
http://slidepdf.com/reader/full/ubd-section-02-qhse 19/27
18© Weatherford International, Inc. All rights reserved.
DRILLING & WELL SERVICES
®HAZOPS & HAZIDS
HAZIDS – Example – UBD Project
• Usage of crude as drilling fluid• Compressed gas in the drill string and surface pipe work
• Intentional loss of primary well control barriers (i.e. mud column)
• H2S
• CO2
7/23/2019 Ubd Section 02 - Qhse
http://slidepdf.com/reader/full/ubd-section-02-qhse 20/27
19© Weatherford International, Inc. All rights reserved.
DRILLING & WELL SERVICES
®Hazards Associated with UBD
• Positive Surface Pressure (Live Well Risk)
Reliance on mechanical barriers
High Fluid Return VelocitiesSurface equipment erosion
Make Up of the Injected Gas
Down hole fire/corrosionLive Formation Fluids at Surface
Fire—H2S
Wellbore Stability Problems
Hole collapse, mud weight required for support
7/23/2019 Ubd Section 02 - Qhse
http://slidepdf.com/reader/full/ubd-section-02-qhse 21/27
20© Weatherford International, Inc. All rights reserved.
DRILLING & WELL SERVICES
®SIMOPS
XXXXX UBDConcurrent
Operations
Rig-upUBDSurfacepackage
Rigup/downTank farm
Commissioning
Drill toShoe
Drill-ingUBD
Well Shut-in (for wellcontrol)
Crane/ForkliftOperationsTruck Oman
TruckCrude
GPSCuttings
Decommission UBDSurfacePackage
Rig-down
Completion
Rig-up UBD Surface package Yes N/A Yes N/A No Yes Yes N/A N/A N/A N/A
Rig up/down tank farm Yes Yes Yes No No Yes No Yes N/A Yes Yes
Commissioning N/A Yes Yes N/A No Yes Yes N/A N/A N/A N/A
Drill to Shoe Yes Yes Yes N/A N/A Yes Yes N/A N/A N/A N/A
Drilling UBD N/A No N/A N/A N/A Yes Yes No N/A N/A N/A
Well Shut-in (for well control) No No No N/A N/A No No No No No No
Crane/Forklift Operations Yes Yes Yes Yes Yes No Yes Yes Yes Yes Yes
Truck - Crude Yes No Yes Yes Yes No Yes N/A Yes Yes Yes
GPS Cuttings N/A Yes N/A N/A No No Yes N/A No Yes Yes
Decommission UBD SurfacePackage
N/A N/A N/A N/A N/A No Yes Yes No N/A Yes
Rig Down N/A Yes N/A N/A N/A No Yes Yes Yes N/A Yes
Completion N/A Yes N/A N/A N/A No Yes Yes Yes Yes Yes
7/23/2019 Ubd Section 02 - Qhse
http://slidepdf.com/reader/full/ubd-section-02-qhse 22/27
21© Weatherford International, Inc. All rights reserved.
DRILLING & WELL SERVICES
®Operational Procedures
UBD PROCEDURES (HAZOPED)
• Procedures on all critical operations are documented and HAZOPed
• No deviation to procedures is tolerated in UBD
• Management of change process is frequently used to facilitate anyproposed changes to procedures or systems at site
• Management of change form to be used for permanent changes
7/23/2019 Ubd Section 02 - Qhse
http://slidepdf.com/reader/full/ubd-section-02-qhse 23/27
22© Weatherford International, Inc. All rights reserved.
DRILLING & WELL SERVICES
®Training
• All personnel from the Package Supervisor or Engineer down to Assistant
Operators are fully trained in the operation of all items of UBS equipment
deployed for the projects.
• Where training or advance courses are required our own staff as well as the
operators can benefit from participation.
• UBD Well Control Simulator is installed in the Regional Office
• Communication is the most important for UB solutions and full radio sets are
utilized.
7/23/2019 Ubd Section 02 - Qhse
http://slidepdf.com/reader/full/ubd-section-02-qhse 24/27
23© Weatherford International, Inc. All rights reserved.
DRILLING & WELL SERVICES
®Training
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34
R R r R r R R R R R r R R r R r R r r r r r r r r r r r r r R R R R R R R R R R R R r R R R r R R R R R R R R R R R R R R R R
R R R R R R R R R R R R R R R R R R R R R R R R R R R R R R R R R RR R R R R R R R R R R R R R R R R R R R R R R R R R R R RR R R R R R R R R R R R R R R R R R R R R R R R R R R R R
R R R R r R R R R r r r r r r R R R R r R R R R r r r r r r
R R R R R R R R R R R R r R R R R R R R R R R R R R R R R R R RR R R R R R r R R R R R r R r R r r r r r r r r r
R R R R R r r r R r R r R r r r r r r r
r r R R R R R R R r R r R r R R r r r r r r r R R R R R R r R R R R R R r R R r R R R R R R R R R R R RR R R R R R R R R R R R R R R R R R R R R
R R r R r R R r r r r r R R r R R R R R R R R R R R R R R R
Technical Sales
UBS Site Engineer
* for immediate implentation - all WFT and external training resources are available for scheduling (comprehensive Workforce Development Program under development); R = REQUIRED, r = recommended
Job Function
Manager, Product Line
Shift Supervisor, Compression
Manager, Project
Shift Supervisor, Separation
Operator, Separation
F
i r s t A i d
O
f f s h o r e S u r v i v a l ( a s r e q u i r e
d )
Operator, Compression
Engineer, CCE
S
a f e t y i n t h e W o r k p l a c e
Supervisor, Well Site
Engineer, Project UBS
P
r o j e c t M a n a g e m e n t
H
y d r o g e n S u l f i d e S a f e t y
F
l o w M o d e l i n g - A d v a n c e d
W
C S o n l i n e P r i m a r y C e m e n t i n g
W
C S o n l i n e H o r i z o n t a l D r i l l i n g ( V o l 1 - 2 )
W
C S o n l i n e O i l w e l l D r i l l i n g ( V
o l 1 - 1 0 )
W
C S o n l i n e O i l a n d G a s R e s
e r v o i r s
W
C S o n l i n e H 2 S P r o d u c t i o n O p e r a t i o n s
W
C S o n l i n e K i c k D e t e c t i o n
W
C S o n l i n e B a s i c O i l f i e l d C a l c u l a t i o n s ( V o l 1 - 2 )
Operation Mgr/Superintendant
Technician, RCH / RotBOP
Technician, DAQ / Systems
Weatherford Underbalanced Services Phase-1* Training Matrix
W
e l l C o n t r o l - I W C F o r W e
l l C A P - a c c r e d i t e d
U
n d e r b a l a n c e d D r i l l i n g - B
a s i c
F
l o w M o d e l i n g - B a s i c
U
n d e r b a l a n c e d D r i l l i n g - A
d v a n c e d
W
F T H e a l t h ,
S a f e t y a n d E n v i r o n m e n t a l
W
F T T e a m D e v e l o p m e n t W
o r k s h o p
W
F T F u n d a m e n t a l C o m p l e t i o n P r a c t i c e s
W
F T A m b a s s a d o r ( ' C h a r m S
c h o o l ' )
C
o n f i n e d S p a c e S a f e t y
T
R U E f o r D r i l l i n g ( p r o j e c t - s p e c i f i c )
O
S H A 5 0 1
S
T O P
W
F T W e a t h e r f o r d O v e r v i e
w / I n d u c t i o n
Provisional at this stage
F
o r k l i f t ( a s r e q u i r e d )
W
C S o n l i n e W i r e l i n e O p e r a t i o n s ( V o l 1 - 5 )
H
A Z I D / H A Z O P P r o c e s s e s
C
O S H H / H A Z M A T
L
e a d e r s h i p
W
F T B a s i c T r a i n i n g f o r S u
p e r v i s o r s
W
C S o n l i n e B i t H y d r a u l i c s
W
F T B l o w o u t P r e v e n t o r a n d M a n i f o l d s
7/23/2019 Ubd Section 02 - Qhse
http://slidepdf.com/reader/full/ubd-section-02-qhse 25/27
24© Weatherford International, Inc. All rights reserved.
DRILLING & WELL SERVICES
®HSE Plan
A u d i t i n g
P o l i c y
O r g a n i s i n g
P l an n i n g a n dI m p l e m e n t i n g
M e a s u r i n g
P e r f o r m a n c e
R e v i e w i n g
P e r f o r m a n c e
7/23/2019 Ubd Section 02 - Qhse
http://slidepdf.com/reader/full/ubd-section-02-qhse 26/27
25© Weatherford International, Inc. All rights reserved.
DRILLING & WELL SERVICES
®HSE Plan Contents
• Leadership and Commitment
• Policy & Strategic Objectives
• Organization, Responsibilities, Resources, Standards & Documentation
• Hazards & Effects Management Process
• Planning & Procedures
• Implementation, Monitoring & Corrective Action
• Audit & Review
7/23/2019 Ubd Section 02 - Qhse
http://slidepdf.com/reader/full/ubd-section-02-qhse 27/27
26© Weatherford International, Inc. All rights reserved.
DRILLING & WELL SERVICES
®HSE Monthly Review Report
CONTENTS
1. Minutes of Last Month Contract QHSE & Operations Review Meeting
2. Schedule for the next Contract QHSE & Operations Review Meeting
3. HSE Performance & Statistics
• LTI Free Days LTIF Vs Man-hours
• Identified Hazards Vs Incidents (current month)
• Identified Hazards Vs Incidents (Project to Date)
• HSE Communication (Management Meetings, Meetings, TBT, JSAs)
• HSE Training Status
4. Operations
• Drilling Time Performance
• Rig Days UBD Vs Rig Days on Well
• Rig Down – Rig Up Performance
• WFT NPT-Total NPT Performance