Type test Notes

download Type test Notes

of 51

Transcript of Type test Notes

  • 8/10/2019 Type test Notes

    1/51

    Automation Products Laboratories

    TYPE TESTING OF PROTECTION RELAYS

    Automation Products Laboratories - St Leonards Avenue Stafford ST17 4LX EnglandTel: +44 (0)1785 223251 Fax: +44 (0)1785 212232ALSTOM GRID UK LTD. Registered Office : St Leonards Avenue Stafford ST17 4LXRegistered in England : 4955841

    1. INTRODUCTION TO TYPE TESTING OF PROTECTIVE,

    AUXILIARY & TRIPPING RELAYS.

    A relay or protective scheme may only be called upon to operate once or twice in its

    entire life. It must however be accurate and reliable. It must be completely stable

    against maloperation when subjected to any of the numerous onerous conditions

    that may occur in its normal working environment.

    Since the prime function of a protective relay is to operate correctly under abnormal

    or extreme conditions, it is essential that the relays be tested under those conditions.

    Abnormal conditions may be caused by a number of reasons. These can be

    summarised into the following categories:

    Overvoltages or overcurrent.

    Interfering noise.

    Problems with the DC or AC auxiliary supply.

    Mechanical vibration.

    Extreme environmental conditions, temperature, humidity.

    Transients caused by Voltage or Current Transformers.

    Transients caused by large transformers, or HV cables and lines when energised.

    It is also important to determine the accuracy or response of the relay within the

    specified operating range. The relay itself must not be a source of interference to

    other equipment, and although it is connected to the primary system, it must pose no

    safety hazard to personnel or plant.

  • 8/10/2019 Type test Notes

    2/51

    5/4/2012 2 Typetest_notes_2012.doc

    It is therefore necessary to carry out TYPE TESTING on newly developed relays to

    assess their performance. Type testing is quite different from ROUTINE

    PRODUCTION relay functional testing which is carried out on every relay before it

    leaves the factory.

    The International Electrotechnical Vocabularydefines type tests as:

    A test of one or more devices made to a certain design,

    to show that the design meets certain specifications.

    Before a product is developed the required performance is specified, as are the

    required performance tests, and before any tests are carried out, test plans and test

    procedures are written and agreed. At ALSTOM Grid, Stafford, the Automation

    Products Laboratories carries out the EMC, Environmental, Electrical and Safety

    Type Testing. The functional Type Testing is carried out by the R&D Department in

    China (CTC) although Automation Products Laboratories will review both the

    Functional Test Specifications and the Functional Test Results.

    As a parallel process to this, the Automation Products Laboratories are also

    responsible for gaining third party approval for the relays. The electricity suppliers

    have their own formal approval processes for protection relays and the Automation

    Products Laboratories take the responsibility of ensuring that the relays conform to

    these requirements and that the approval process is carried out correctly. In the UK

    the Energy Networks Association (ENA) is the main approval body which represents

    a group of relay users involved in the generation, transmission, distribution and

    supply of electricity. Its membership consists of mostly UK companies, although

    there are associate members from Ireland, Japan, South Africa and Finland.

    The market for protection relays is worldwide, and, it is most important that

    internationally agreed standards are used as the basis for the tests carried out.

    Hence most references in the publications are to IEC standards (International

    Electrotechnical Commission).

  • 8/10/2019 Type test Notes

    3/51

    5/4/2012 3 Typetest_notes_2012.doc

    So, what type tests are carried out? Broadly speaking they can be split into five

    groups.

    1. Functional Tests

    2. Electrical Tests

    3. Environmental Tests

    4. EMC Tests

    5. Safety Tests

    Functional tests are carried out to determine the accuracy and repeatability of each

    of the discrete functions that the product can perform. They also determine the

    effect of the interaction between each of the discrete functions within the relay, and

    also the interaction between other items of equipment that the relay may be

    interfaced with.

    The electrical tests are designed to test that the relay is not damaged by transient

    overvoltages that may be experienced on site. In addition the affect of variations on

    the relays auxiliary supply voltage are also determined.

    Environmental tests are designed to ensure that relays can operate as expected inthe environment they are installed in. Power system protection relays can be

    installed anywhere in the world, in a diversity of environments. In order to ensure

    reliability in operation, and whether they are fit for purpose, they are subjected to the

    most stringent type tests, as specified in the IEC standards.

    EMC tests are designed to ensure that the protective relay is not affected or capable

    of affecting other equipment that is located within the substation. Compliance with

    the EMC directive is a legal requirement of all products sold within Europe.

    Safety tests and reviews are designed to ensure that the product being sold is safe

    ensuring that it causes no injury to users during its normal operation. Compliance

    with the Low Voltage Directive (LVD) is a legal requirement of all products sold within

    Europe and along with the EMC Directive is essential for CE marking the product. In

    addition Underwriters Laboratories (UL) and Atmosphres Explosibles (ATEX)

    testing is carried out in conjunction with the appropriate authorities.

  • 8/10/2019 Type test Notes

    4/51

    5/4/2012 4 Typetest_notes_2012.doc

    1.1 UKAS ACCREDITATION

    The Automation Products Laboratories are accredited by the United Kingdom

    Accreditation Services (UKAS). The laboratory complies and operates to ISO/IEC

    17025 requirements to provide a quality service. The Schedule of Accreditation

    detailing the tests for which Automation Products Laboratories is accredited is shown

    on the UKAS web site; www.UKAS.org.

    All equipment used to carry out the tests, is calibrated by an accredited test house

    which includes our own Electrical Measurements Laboratory which is also UKAS

    accredited.

    Specialised tests are performed at external accredited test houses, these being:

    Mechanical testing: Vibration response and endurance, shock response and

    withstand, bump and seismic.

    Enclosure protection testing: dust and water ingress

    Electromagnetic Interference testing: Conducted and radiated emissions, conducted

    and radiated immunity.

    2. FUNCTIONAL TESTS

    2.1 ACCURACY AND REPEATABILITY OF PROTECTION FUNCTIONS

    Taken to the basic definition, functional tests consist of applying voltage, current or

    frequency variations over the complete setting range for the function under test, and

    measuring the performance in terms of accuracy and repeatability.

    They are carried out under reference laboratory conditions, usually in a temperature

    and humidity controlled environment.

  • 8/10/2019 Type test Notes

    5/51

    5/4/2012 5 Typetest_notes_2012.doc

    Consider the following simple overcurrent element.

    Element Range Step Size

    I>1 0.08 - 4.00In 0.01In

    I>2 0.08 - 32In 0.01In

    Directionality Forward/Reverse/Non-directional

    RCA -95to +95 1

    Characteristic DT/IDMT

    Definite Time Delay 0 - 100s 0.01s

    IEC IDMT Time Delay IEC Standard Inverse

    IEC Very Inverse

    IEC Extremely Inverse

    UK Long Time Inverse

    Time Multiplier Setting

    (TMS)

    0.025 - 1.2 0.025

    IEEE IDMT Time Delay IEEE Moderately Inverse

    IEEE Very Inverse

    IEEE Extremely Inverse

    US-C08 Inverse

    US-C02 Short Time Inverse

    Time Dial (TD) 0.5 15 0.1

    IEC Reset Time (DT only) 0 - 100s 0.01s

    IEEE Reset Time IDMT/DT

    IEEE DT Reset Time 0 - 100s 0.01s

    IEEE IDMT Reset Time IEEE Moderately Inverse

    IEEE Very Inverse

    IEEE Extremely Inverse

    US-C08 Inverse

    US-C02 Short Time Inverse

  • 8/10/2019 Type test Notes

    6/51

    5/4/2012 6 Typetest_notes_2012.doc

    The functions described above are the basic building blocks of any overcurrent relay,

    and, the following tests would be carried out to prove the functionality:

    Test 1:- Three phase non-directional pick up and drop off accuracy over complete

    current setting range for both stages

    Test 2:- Three phase directional pick up and drop off accuracy over complete

    RCA setting range in the forward direction, current angle sweep

    Test 3:- Three phase directional pick up and drop off accuracy over complete

    RCA setting range in the reverse direction, current angle sweep

    Test 4:- Three phase directional pick up and drop off accuracy over complete

    RCA setting range in the forward direction, voltage angle sweep

    Test 5:- Three phase directional pick up and drop off accuracy over complete

    RCA setting range in the reverse direction, voltage angle sweep

    Test 6:- Three phase polarising voltage threshold test

    Test 7:- Accuracy of DT timer over complete setting range

    Test 8:- Accuracy of IDMT curves over claimed accuracy range

    Test 9:- Accuracy of IDMT TMS/TD

    Test 10:- Effect of changing fault current on IDMT operating times

    Test 11:-Minimum Pick-Up of Starts and Trips for IDMT curves

    Test 12:- Accuracy of reset timers

    Test 13:- Effect of any blocking signals, opto inputs, VTS, Autoreclose

    Test 14:- Voltage polarisation memory

  • 8/10/2019 Type test Notes

    7/51

    5/4/2012 7 Typetest_notes_2012.doc

    So, for even the most basic function, there are numerous tests that are carried out in

    order to prove the correct implementation and operation of the function. This is a

    very time consuming process, and for a large project, involves numerous engineers

    and technicians for several months. In the case of the Px4x development, if only oneperson were to carry out all the test duties, it would take a total of 4 years to write the

    test specifications, and 30 years to carry out all of the tests. Then there would be the

    small matter of writing the type test reports!

    2.2 RATINGS/BURDENS AND THERMAL WITHSTAND TESTS

    In the case of measuring the burden and rating of the relays CTs, VTs, auxiliary

    power supply and opto inputs, as well as the maximum quantities that these

    components can withstand thermally, tests are performed to the requirementsdefined in:

    IEC 60255-1 Electrical Relays Measuring Relays and Protection Equipment

    Part 1: (Common Requirements)

    This standard specifies the general performance requirements of all electrical

    measuring relays and protection equipment used in the electrotechnical fields

    covered by the IEC, and gives recommended values for ratings, burdens, markings

    and accuracy claims.

    In the case of the burden, this is measured for the CTs, VTs, opto inputs and

    auxiliary voltage input. This involves measuring the operating voltage and/or current

    drawn by each of these components over the specified operating range.

    For ratings, this is again measured for the CTs, VTs, opto inputs and auxiliary

    voltage input. This involves applying the appropriate input quantity at increasing

    values for decreasing amounts of time. For CTs and VTs, thermocouples are

    embedded in the windings and the temperature rise when the current or voltage is

    applied is measured. This gives an indication of the point where the insulation is

    about to melt or deteriorate, although the wire itself may be able to withstand the

    applied quantity. This also determines the short time thermal withstand of the

    components. For CTs this is the maximum current they will withstand for 1s, and for

    VTs it is the maximum voltage they will withstand for 10s.

  • 8/10/2019 Type test Notes

    8/51

    5/4/2012 8 Typetest_notes_2012.doc

    Output contact ratings tests are performed to determine the ability of the relays

    output contacts to perform repeated loaded operations. These are usually off the

    shelf components, and the performance when breaking DC inductive and resistive

    loads is rarely claimed by the manufacturer, so tests have to be performed todetermine this.

    2.3 COMMUNICATIONS TESTS

    More and more, relays are being developed with highly complex communication

    capabilities to allow information exchange within intelligent protection schemes.

    Tests are performed to ensure that various communication commands sent to the

    relay result in the correct response. Tests are also performed to ensure that the

    communications do not have an adverse effect on the protection performance of therelay, for example, increasing the operating time should a system fault occur whilst

    the relay is communicating remotely with the control room.

    2.4 MEASUREMENT PERFORMANCE

    Modern relays have an extensive array of measured quantities, ranging from voltage,

    current and frequency, active, reactive and apparent power, peak, fixed and rolling

    demand values, and the sum of the broken current value used for circuit breaker

    condition monitoring. The accuracy of these measured quantities has to bedetermined.

    Some measurements are made directly by the relay, for example phase current and

    voltage magnitude. However, others are derived by the relay, for example negative

    sequence quantities, so tests have to be performed to determine the comparative

    performance between direct and derived measurements.

    2.5 INFLUENCING QUANTITIES

    Along with measuring the accuracy and repeatability of each of the protection

    functions, there is a whole suite of functional tests designed to determine the effect

    of various parameters on the protection performance. These are known as

    influencing quantities, and consist of the following.

  • 8/10/2019 Type test Notes

    9/51

    5/4/2012 9 Typetest_notes_2012.doc

    System X/R, where tests are performed with faults at various X/R values, ranging

    from 1 up to 120. This results in fault waveforms with DC offset components, and

    allows the effect on the relays operating times to be determined.

    Point on Wave, where tests are performed with faults applied over the complete

    point on wave range. Again this allows the affect on the relay operating times to

    be determined.

    Harmonics, where the effect of harmonics up to 17th, usually at 10% of the

    fundamental are determined. Relays installed in proximity to HVDC links,

    capacitive compensators, and arc furnaces will encounter distortion of the current

    and voltage waveform due to the presence of various harmonics.

    Frequency. Under normal operating conditions, the system frequency varies over

    strictly specified limits. However, generator and motor protection relays are

    required to operate over an extremely wide frequency range, and the accuracy

    has to be determined over this range. Similarly, modern relays are dual

    frequency rated to work with either 50Hz or 60Hz systems, so a comparison in the

    protection performance at these two frequencies has to be determined. In fact, in

    some cases, the functional tests are performed at 60Hz, because this is the most

    onerous condition for the relay in terms of samples per cycle, i.e. the digital signal

    processor (DSP) has to work 20% faster when the relay is configured for 60Hz,than it does for comparable performance at 50Hz.

    Auxiliary Voltage. In modern relays, the operating range of the auxiliary voltage is

    very wide, and therefore tests are performed to ensure that the relay will perform

    its functions with the same accuracy and speed over the complete operating

    voltage range. Most relay power supplies are also dual rated to work with either

    AC or DC voltage, and a comparison in functional performance is made between

    these two parameters.

    2.6 CONJUNCTIVE TESTS

    These tests derive their name from the fact that they are performed with a relay in

    conjunction with a real current transformer, and realistic power system parameters.

    The main aim of these tests is to determine:

  • 8/10/2019 Type test Notes

    10/51

    5/4/2012 10 Typetest_notes_2012.doc

    line current transformer requirements

    realistic operating times

    limits of stability for through faults

    Traditionally, these tests have been performed on a bulky heavy current plant known

    as the synthetic test plant, which used CTs, VTs, resistors and inductors to simulate

    the line. This equipment has now been replaced with the RTDS (Real Time Digital

    Simulator), which is essentially a power system simulator. (There is a separate

    presentation and notes on the RTDS).

    3. ELECTRICAL WITHSTAND TESTSThese tests are performed on unenergised relays to prove that:

    1. The insulation employed is able to withstand the likely overvoltages encountered

    in service.

    2. The creepage and clearance distance between two points is large enough to

    withstand the likely overvoltages encountered in service.

    3.1 DIELECTRIC WITHSTAND TESTS.

    The test is designed to prove the rated insulation voltage as declared by the

    manufacturer.

    ALSTOM Grid, Stafford, perform this test as a type test, and also as a standard

    routine production test on every relay produced.

    The relevant standard is:

    IEC 60255-27 Measuring Relays and Protection Equipment Part 27: ProductSafety Requirements.

    The relevant test levels used by ALSTOM Grid, Stafford are:

    2.0 kV rms 50/60Hz for 1 minute applied between all terminals to case earth, and

    then between independent circuits

  • 8/10/2019 Type test Notes

    11/51

    5/4/2012 11 Typetest_notes_2012.doc

    1.5 kV rms 50/60Hz for 1 minute applied across dedicated normally open contacts

    of tripping output relays

    1.0 kV rms 50/60Hz for 1 minute applied across normally open contacts of

    watchdog relays or changeover pairs:

    The pass criteria are that no breakdown or flashover shall occur, and the relay shall

    still perform its main functions within the claimed tolerance after the test.

    3.2 IMPULSE TEST.

    The purpose of this test is to prove the ability of the relay's insulation to withstand

    without damage overvoltages of very high amplitude and short duration, for example,

    those caused by lightning strikes. The test waveform is shown below:

    Impulse Waveform (not to scale)

    50%

    5 kV

    1.2 us 50 us

    Rise time : 1.2 us

    Fall Time : 50 us to 50 %

    Peak amplitude : 5 kV

    Pulse energy : 0.5 Joules

    Figure 1 High Voltage Impulse Test Waveform

    The impulse is applied to a de-energised relay as 3 positive and 3 negative impulses

    applied at intervals of not less than 5 seconds between:

    all circuits and the case earth

    all independent circuits

    the terminals of independent circuits except for normally open contacts

  • 8/10/2019 Type test Notes

    12/51

    5/4/2012 12 Typetest_notes_2012.doc

    The relevant standard is:

    IEC 60255-27 Measuring Relays and Protection Equipment Part 27: Product

    Safety Requirements.

    The relevant test level is:

    5kV, 1.2/50s waveform, 0.5J

    The pass criteria are that no breakdown or flashover shall occur, and the relay shall

    still perform its main functions within the claimed tolerance after the test.

    3.3 INSULATION RESISTANCE

    The purpose of this test is to measure the insulation resistance of the relay. 500Vdc

    is applied for 5s, and the current drawn measured.

    The relevant standard is:

    IEC 60255-5 - Electrical Relays Part 5: Insulation Coordination for Measuring

    Relays and Protection Equipment Requirements and Tests.

    The relevant test level is:

    100M between all circuits and the case earth, all independent circuits and

    across normally open contacts

    The pass criteria are that the insulation resistance must be greater than 100M

    between the circuits specified above.

    4. ENVIRONMENTAL TESTS

    As well as proving that the relay can carry out all the functions claimed to the

    required accuracy over the claimed operating range, it also has to be ensured that

    the relay is capable of performing these functions correctly in the environment it may

    find itself in. This involves testing each new product to extremes of temperature,

    humidity and vibration.

  • 8/10/2019 Type test Notes

    13/51

    5/4/2012 13 Typetest_notes_2012.doc

    4.1 TEMPERATURE TESTS

    Temperature tests are performed to ensure that the relay can withstand extremes in

    operating and storage temperatures, both hot and cold.

    The relevant standards are:

    IEC 60068-2-1 Environmental Testing Part 2-1: Tests Test A: Cold

    IEC 60068-2-2 - Environmental Testing Part 2-2: Tests Test B: Dry Heat

    The test conditions are:

    Storage and Transit -25C to +70C

    Operating -25C to +55C

    For the storage and transit test, the relay is placed unenergised in a temperature

    cabinet at -25C and held at this temperature for duration of 96 hours. After this time

    has elapsed, the relay is removed from the cabinet and allowed to return to the

    ambient temperature. It is then powered up, and tested to ensure that all the

    functions still operate within the claimed tolerances. The same process is repeated

    for the +70C temperature.

    The criteria for acceptance are that after the temperature testing the relay should

    carry out its main functions correctly, and that the results should be within the

    claimed tolerance.

    For the operating temperature test, the relay is placed energised in the temperature

    cabinet, and subjected to the following temperatures:

    -25C, 0C, +20C, +40C, +55C.

    At each of these temperatures the relay is allowed to stabilise until it is at the same

    temperature as the test level. It is then powered down and up again, and subjected

    to tests to determine that the functions still operate within the claimed tolerances.

  • 8/10/2019 Type test Notes

    14/51

    5/4/2012 14 Typetest_notes_2012.doc

    The criteria for acceptance in this case is that the relay must power up correctly,

    (particularly important at low temperatures), it must perform all its main functions

    within the claimed tolerance, and the LCD should be legible, (again, this is important

    at the low temperatures).

    4.2 HUMIDITY TESTS

    Closely related to the temperature test is the humidity test. This test is carried out to

    ensure that the relay will withstand and operate correctly when subjected to high

    humidity at a constant temperature over a prescribed period.

    The relevant standard is:

    IEC 60068-2-78 Environmental Testing Part 2-78: Tests Test Cab: Damp

    Heat, Steady State.

    The test conditions are:

    +40C 2C and 93% relative humidity.

    Duration 56 days.

    For these tests the relay is placed in a humidity cabinet, and energised with normal

    in-service quantities for the complete duration of the test. In practical terms this

    usually means energising the relay with currents and voltages such that it is 10%

    from the threshold for operation.

    Functional tests are performed on the relay at 21 and 56 days, whilst it is still in the

    cabinet. These tests determine if the main functions of the relay perform within the

    claimed tolerance. Throughout the duration of the test the relay is monitored to

    ensure that no unwanted operations occur.

    Once the relay is removed from the humidity cabinet, its insulation resistance is

    measured to ensure that it has not deteriorated to below the claimed level. The relay

    is then functionally tested again, and finally dismantled to check for signs of

    component corrosion and growth.

  • 8/10/2019 Type test Notes

    15/51

    5/4/2012 15 Typetest_notes_2012.doc

    In this case, the criteria for acceptance is that for the 56 day duration no unwanted

    operations shall occur including transient operation of indicating devices. After the

    test the relays insulation resistance should not have significantly reduced, and it

    should perform all of its main protection and communications functions within theclaimed tolerance. The relay should also suffer no significant corrosion or growth,

    and photographs are usually taken of each PCB and the case as a record of this.

    4.2.1 Cyclic temperature and humidity testing

    In addition to the 56-day humidity tests is the cyclic temperature with humidity test.

    This test is a short term test which physically temperature stresses the relay whilst

    subjecting it to a high ambient humidity. The test does not replace the 56 day test

    but is used for testing extension to ranges or minor modifications to prove that thedesign is unaffected.

    The relevant standard is:

    IEC 60068-2-30 Environmental Testing Part 2-1: Tests Test Db: Damp heat,

    cyclic (12h + 12h cycle).

    The test conditions are:

    +25C 3C and 95% relative humidity/ +55C 2C and 95% relative humidity.

    24 hour cycle period conforming to profile shown below.

  • 8/10/2019 Type test Notes

    16/51

    5/4/2012 16 Typetest_notes_2012.doc

    Figure 2 Cyclic temperature and humidity profile

    For these tests the relay is placed in a humidity cabinet, and energised with normal

    in-service quantities for the complete duration of the tests. In practical terms this

    usually means energising the relay with currents and voltages such that it is 10%

    from the threshold for operation. Throughout the duration of the test the relay is

    monitored to ensure that no unwanted operations occur.

    Once the relay is removed from the humidity cabinet, its insulation resistance ismeasured to ensure that it has not deteriorated to below the claimed level. The relay

    is then functionally tested again, and finally dismantled to check for signs of

    component corrosion and growth.

  • 8/10/2019 Type test Notes

    17/51

    5/4/2012 17 Typetest_notes_2012.doc

    The criteria for acceptance is that no unwanted operations shall occur including

    transient operation of indicating devices. After the test the relays insulation

    resistance should not have significantly reduced, and it should perform all of its main

    protection and communications functions within the claimed tolerance. The relayshould also suffer no significant corrosion or growth, and photographs are usually

    taken of each PCB and the case as a record of this.

    4.3 ENCLOSURE PROTECTION TESTS

    The object of this test is to prove that the casing system of the relay is protected

    against the ingress of dust, moisture, fingers, tools etc., depending upon the test

    level specified.

    The relevant standard is:

    IEC 60529 - Degrees of Protection Provided by Enclosures (IP Code)

    For MiDOS cases, (MCGG, KCGG, KBCH), the relevant level for the case is IP50,

    which means protected from the ingress of dust particles, denoted by the 5, and no

    protection against the ingress of moisture, denoted by the 0. For the MiCOM relays,

    (P*40, P*30, the relevant level is IP52, which means, protected against the ingress of

    dust particles, denoted by the 5, and protected against the ingress of dripping water

    at an angle of 15, denoted by the 2.

    For the dust test, the relay is placed in a chamber containing 2kg of powder per

    cubic metre of the chamber volume. The chamber is then sealed, and the dust

    circulated violently for a period of 8 hours, after which time the relay looks like this:

  • 8/10/2019 Type test Notes

    18/51

    5/4/2012 18 Typetest_notes_2012.doc

    Figure 3 LFZR relay on completion of the dust tests.

    The relay is then carefully dismantled and inspected to determine the degree of

    ingress of dust. The criteria for acceptance is that dust may enter and accumulate

    inside the case as long as it does not interfere with the normal operation of the relay.

    An engineering judgment is made about this considering the fact that the dust

    encountered in service may be conductive.

    For the dripping water test, the relay is subjected to 2.5mins of dripping water at a

    flow rate of 3mm/min with the relay inclined at an angle of 15 from the horizontal.

    The pass criteria in this case is that if any water has entered, it shall not:

    Be sufficient to interfere with the correct operation of the equipment or impair

    safety.

    Deposit on insulated parts where it could lead to tracking along the creepage

    distances.

    Reach live parts or windings not designed to operate when wet.

    Accumulate near the cable end or enter the cable if any.

  • 8/10/2019 Type test Notes

    19/51

    5/4/2012 19 Typetest_notes_2012.doc

    4.4 MECHANICAL TESTS

    These tests are carried out to simulate a number of mechanical conditions the

    product may have to endure during its lifetime. They fall into three distinct

    categories, each designed to simulate a different environment, and covered by a

    different standard.

    Vibration

    Shock and Bump

    Seismic

    In all cases, these tests are performed at an external test house. The relays are

    subjected to the tests in the three axes, front to back, side to side, and top to bottom.

    The relays are subjected to the mechanical tests in both the normal in service

    condition, that is with current and voltage applied so that the relay is 10% from the

    threshold of operation, and also on the tripped condition, where current and voltage

    is applied so that the relay is 10% above the threshold for operation.

    4.4.1 Vibration Tests

    Two types of vibration tests are carried out:

    Vibration Response

    Vibration Endurance

    The vibration response test is carried out with the relay energised to ensure that it is

    able to perform correctly when subjected to constant mechanical vibration caused by

    rotating machines such as generators and motors and industrial plant such as

    crushers and mills.

    The vibration endurance is performed with the relay unenergised, and is an

    accelerated life test to simulate the effect of long term vibration and also some forms

    of transportation.

  • 8/10/2019 Type test Notes

    20/51

    5/4/2012 20 Typetest_notes_2012.doc

    The relevant standard is:

    IEC 60255-21-1 Electrical Relays Part 21: Vibration, Shock, Bump and

    Seismic Tests on Measuring Relays and Protection Equipment Section One:

    Vibration Tests (Sinusoidal)

    The relevant test levels are:

    Vibration Response Class 2, 1g, 10 - 150Hz, 1 sweep, energised.

    Vibration Endurance Class 2, 2g, 10 - 150Hz, 20 sweeps, unenergised.

    For the vibration response test, the pass criteria is that the equipment shall not

    maloperate, and shall still perform its main functions within the claimed tolerance

    after the test.

    For the vibration endurance test, the pass criteria is that the equipment should not

    suffer any mechanical damage, and should still perform its main functions within the

    claimed tolerance after the test.

    4.4.2 Shock and Bump Test

    Three types of shock and bump tests are carried out:

    Shock Response

    Shock Withstand

    Bump

    The aim of these tests is to ensure that the equipment can withstand similar

    conditions both in service and in transportation. Circuit breaker mounted relays can

    be subjected to shocks when the breaker operates, panel mounted relays can

    receive impact shocks caused by ladders and doors. Relays can also undergo

    repeated bumps during transit.

  • 8/10/2019 Type test Notes

    21/51

    5/4/2012 21 Typetest_notes_2012.doc

    The shock and bump impulse waveform is shown below:

    Figure 4 Shock and Bump Impulse Waveform

    - - - - - nominal pulse.

    limits of tolerance.

    D Duration of nominal pulse.

    A Peak acceleration of nominal pulse.

    T1 minimum time during which the pulse shall be monitored for shocks and

    bumps produced using a conventional shock and bump machine.

    T2 minimum time during which the pulse shall be monitored for shocks and

    bumps produced using a vibration generator.

    The relevant standard is:

    IEC 60255-21-2 - Electrical Relays Part 21: Vibration, Shock, Bump and

    Seismic Tests on Measuring Relays and Protection Equipment Section Two:

    Shock and Bump Tests

  • 8/10/2019 Type test Notes

    22/51

    5/4/2012 22 Typetest_notes_2012.doc

    The relevant test levels are:

    Shock Response, Class 2, 10g, 11ms, 3 pulses, energised

    Shock Withstand, Class 1, 15g, 11ms, 3 pulses, unenergised

    Bump, Class 1, 10g, 16ms, 1000 pulses, unenergised

    For the shock response test, the pass criteria is that the equipment shall not

    maloperate and shall still perform its main functions within the claimed tolerance

    after the test.

    For the shock withstand and bump tests, the pass criteria is that the equipment

    should not suffer any mechanical damage, and should still perform its main functions

    within the claimed tolerance after the test.

    4.4.3 Seismic Tests

    The third type of mechanical test that is carried out is the seismic test. This is

    designed to prove that the relay can operate as intended during earthquakes. The

    test consists of a single axis sinusoidal sweep.

    The relevant standard is:

    IEC 60255-21-3 - Electrical Relays Part 21: Vibration, Shock, Bump and

    Seismic Tests on Measuring Relays and Protection Equipment Section Three:

    Seismic Tests

    The relevant test level is:

    Class 2, 1 - 35Hz, 1 sweep, energised.

  • 8/10/2019 Type test Notes

    23/51

    5/4/2012 23 Typetest_notes_2012.doc

    The sweep parameters are:

    Peak displacement below

    the cross over frequency.

    (mm).

    Peak acceleration above

    the cross over frequency

    (gn).

    Number of

    sweep cycles

    in each axis

    x (horizontal) y (vertical) X (horizontal) y (vertical)

    7.5 3.5 2.0 1.0 1

    The criteria for acceptance is that the equipment shall not maloperate, and shall still

    perform its main functions within the claimed tolerance after the test.

    5. ELECTROMAGNETIC COMPATIBILITY TESTS

    There are numerous tests that are carried out to determine the ability of relays to

    withstand the electrical environment in which they are installed. The substation

    environment is a very severe environment in terms of the electrical and

    electromagnetic interference that can arise. There are many sources of interference

    within a substation, some originating internally, others being conducted along the

    overhead lines or cables into the substation from external disturbances. The most

    common sources are:

    Switching Operations

    System Faults

    Lightning Strikes

    Conductor Flashover

    Telecommunication Operations e.g. mobile phones

    A whole suite of tests are performed to simulate these types of interference, and

    they fall under the broad category known as EMC, or Electromagnetic Compatibility

    tests.

  • 8/10/2019 Type test Notes

    24/51

    5/4/2012 24 Typetest_notes_2012.doc

    Broadly speaking, EMC can be defined as:

    The ability of equipments to co-exist in the same electromagnetic environment.

    It is not a new subject and has been tested for by the military ever since the advent

    of electronic equipment. If there is no electromagnetic compatibility in the battlefield

    then the results can be disastrous.

    For example, in 1967 there was an incident that occurred aboard the US aircraft

    carrier Forrestal whilst cruising off the coast of North Vietnam. All the planes on

    board were loaded with two 1000lb bombs each, as well as air to ground and air to

    air missiles, and were fully fuelled and ready for take-off. Somewhere on the deck,

    attached to the wing of an aircraft, was an improperly mounted shielded cable

    connector. As the radar swept around, radio frequency voltages were generated in

    the cable, which ignited a missile that shot across the deck, struck the aircraft

    opposite and blew its fuel tanks apart. Its two bombs fell on to the deck and

    exploded. Fire spread below decks, and by the time it was extinguished, 134 men

    were either dead or missing. Total damages were put at $72 million.

    Early Antilock Braking Systems (ABS) on both aircraft and automobiles were

    susceptible to EMI. Accidents occurred when the brakes functioned improperly

    because EMI disrupted the ABS control systems.

    The sirens of passing emergency vehicles caused some electric wheel chairs and

    invalid buggies to operate. This problem caused several deaths when these chairs

    and buggies moved into the path of oncoming traffic and not responding to the users

    input.

    More recently there have been some problems with the throttle jamming wide open

    on some modern cars that use fly by wire technology to control the engines throttle.

    This also has caused several deaths and although the true cause of this was never

    discovered it is widely believed that it was due to an EMC problem in the cars

    concerned. This shows that an EMC related issue can be difficult to find and hard to

    prove as it leaves no physical evidence particularly within the electronic circuits that it

    effects which is particularly the case for microprocessor circuitry.

  • 8/10/2019 Type test Notes

    25/51

    5/4/2012 25 Typetest_notes_2012.doc

    So, it is evident that EMC can cause real and serious problems, and does need to be

    taken into account when designing electronic equipment. To achieve this, in addition

    to designing for statutory compliance to the EMC and Low Voltage Directives, the

    following range of tests are carried out during our products development process.

    5.1 DC INTERRUPT

    This is a test to determine the maximum length of time that the relay can withstand

    an interruption in the auxiliary supply without de-energising e.g. switching off, and

    that time when it is exceeded and it does transiently switch off, that no maloperation

    occurs.

    It simulates the effect of a loose fuse in the battery circuit, or a short circuit in the

    common DC supply, interrupted by a fuse. Another source of DC interruption is if

    there is a power system fault and the battery is supplying both the relay and the

    circuit breaker trip coils. When the battery energises the coils to initiate the circuit

    breaker trip, the voltage may fall below the required level for operation of the relay

    and hence a DC interrupt occurs.

    The relevant test standard is:

    IEC 60255-11 Measuring Relays and Protection Equipment Part 11: Voltage

    Dips, Short Interruptions, Variations and Ripple on Auxiliary Power Supply Port.

    The relevant test level is:

    20ms interruption without de-energising

    10, 20, 30, 50, 100, 200, 300, 500, 1000 & 5000ms interruptions without

    maloperating.

    The relay is powered from a battery supply, and both short circuit and open circuit

    interruptions are carried out. Each interruption is applied 10 times, and for auxiliary

    power supplies with a large operating range, the tests are performed at minimum,

    maximum, and other voltages across this range, to ensure compliance over the

    complete range.

  • 8/10/2019 Type test Notes

    26/51

    5/4/2012 26 Typetest_notes_2012.doc

    The pass criteria for this test is that for interruptions of 20ms and less, the relay shall

    not maloperate or de-energise, i.e. it shall not respond to the d.c. interrupt. For

    interruptions greater than 20ms, the relay shall not maloperate, and power up

    correctly.

    5.2 AC RIPPLE ON DC SUPPLY

    This test determines that the relay is able to operate correctly with a superimposed

    AC voltage on the DC supply. This is caused by the station battery being charged by

    the battery charger and the relevant waveform is shown below.

    0.00

    10.00

    20.00

    30.00

    40.00

    50.00

    60.00

    188

    175

    262

    349

    436

    523

    610

    697

    784

    871

    958

    1045

    1132

    1219

    1306

    1393

    Time (ms)

    Voltage

    Figure 5 AC ripple superimposed on DC supply

    The relevant test standard is:

    IEC 60255-11 Measuring Relays and Protection Equipment Part 11: Voltage

    Dips, Short Interruptions, Variations and Ripple on Auxiliary Power Supply Port.

    The relevant test level is:

    12% ripple peak to peak on the dc auxiliary voltage.

  • 8/10/2019 Type test Notes

    27/51

    5/4/2012 27 Typetest_notes_2012.doc

    For auxiliary power supplies with a large operating range, the tests are performed at

    minimum, maximum, and other voltages across this range, to ensure compliance for

    the complete range. The interference is applied using a full wave rectifier network,

    connected in parallel with the battery supply.

    The pass criteria is that during application of the ripple, the relay shall not

    maloperate, and shall still perform its main functions within the claimed tolerance.

    5.3 DC RAMP DOWN / RAMP UP

    This test simulates a failed station battery charger, which would result in the auxiliary

    voltage to the relay slowly ramping down. The ramp up part simulates the battery

    being recharged after discharging. The relay must power up cleanly when the

    voltage is applied and not maloperate.

    The relevant test standard is:

    ALSTOM Grid Staffords Standard, (no international or national standard exists)

    The relevant test levels are:

    1min/cycle and 100min/cycle where 1 cycle is Vmax - 0 - Vmax.

    The pass criteria is that the relay must not maloperate by either issuing a trip

    command or by chattering (rapidly switching off and on) when the boundary level of

    the voltage is reached, for both the ramp down and ramp up test.

    5.4 AC DIPS AND INTERRUPTIONS

    This test is to evaluate the effects of a relay when subjected to voltage dips, short

    interruptions and voltage variations.

    The tests simulate the effect of a loose fuse or wire in the supply circuit, or a shortcircuit in the common AC supply. Another source of AC interruption is when a power

    system fault or overload occurs. When loads are switched onto the supply, the

    voltage may fall below the required level for operation of the relay and hence an AC

    dip, interruption or variation may occur.

    The relevant test standard is:

  • 8/10/2019 Type test Notes

    28/51

    5/4/2012 28 Typetest_notes_2012.doc

    IEC 61000-4-11 Electromagnetic Compatibility (EMC) Part 4-11: Testing and

    Measurement Techniques - Voltage dips, Short Interruptions and Voltage

    Variations Immunity Tests.

    The relevant test levels are:

    Minimum operating voltage 80% of lower voltage range (LVR)

    Maximum operating voltage 110% of higher voltage range (HVR)

    Voltage Dips and Interruptions:

    0% i.e. 100% Voltage dip for a duration of: 10, 20, 50, 100, 200ms & 5s

    40% i.e. 60% Voltage dip for a duration of: 10, 20, 50, 100, 200ms & 5s

    70% i.e. 30% Voltage dip for a duration of: 10, 20, 50, 100, 200ms & 5s

    Note: The above interruptions are applied for both positive and negative polarities

    at the following angles: 0, 45, 90, 135, 180, 225, 270 and 315.

    Voltage Variations: Levels of 100, 40 and 0% of the 80% of lower voltage range

    (LVR) and 110% of higher voltage range (HVR) for 1s duration. Time to reach

    new level: 2s.

    An interruption of the supply shall not exceed 1 minute

    Repetitive Start Tests to simulate a loose fuse

    The tests are carried out using an AC voltage variation generator which powers the

    relay, the tests are performed at 80% LVR AND 110% HVR with minimum, half and

    full loading i.e. number of outputs etc energised.

    The pass criteria for the above tests is for the specified variations and interruptions,

    loss of function is permitted, but the relay must self recover with no loss or corruption

    of settings or data and without operator intervention.

  • 8/10/2019 Type test Notes

    29/51

    5/4/2012 29 Typetest_notes_2012.doc

    5.5 HIGH FREQUENCY DISTURBANCE TEST

    This test simulates the types of interference caused by switching operations and

    power system faults, which cause high voltage transients. The high frequency

    disturbance test waveform has a frequency of 100kHz, 1MHz, 3MHz, 10MHz or

    30MHz. A typical 1MHz waveform is shown below.

    Figure 6 1MHz High Frequency Disturbance Waveform

    This type of interference is most likely to occur when a circuit breaker breaks load or

    fault current, or an isolator/disconnector breaks load or charging current. This type

    of voltage disturbance occurs for switching operations in any electrical circuit and the

    frequency of oscillation is given by the equation below:

    fLC

    =1

    2

    Where:

    F is the oscillating frequency

    L is the inductance in the circuit

    C is the capacitance in the circuit

  • 8/10/2019 Type test Notes

    30/51

  • 8/10/2019 Type test Notes

    31/51

    5/4/2012 31 Typetest_notes_2012.doc

    5.6 FAST TRANSIENT

    This test simulates the type of high voltage interference caused by high-speed

    disconnector operations in GIS substations, and by breakdown of the SF6 insulation

    between the conductors and the earthed enclosure. Both these types of interference

    can be inductively coupled onto the circuits connected to the relay, or be directly

    introduced via the CT and VT inputs.

    The fast transient waveform/pulse train is shown below.

    5 ns rise time, 50 ns pulse width.

    Repetition Period.

    Burst Duration (15 ms)

    Burst Period, 300 ms

    V

    V

    t

    t

    Figure 7 Fast Transient Waveform/Pulse Train.

    This waveform has a very fast rise time of around 5ns and duration above 50% of

    the crest value of around 50ns.

    The relevant test standard is:

    IEC 60255-22-4 Measuring Relays and Protection Equipment Part 22-4:

    Electrical Disturbance Tests Electrical Fast Transient/Burst Immunity Test.

    Also ANSI/IEEE C37-90.1 - IEEE Standard for Surge Withstand Capabilities(SWC) Tests for Relays and Relay Systems Associated with Electrical Power

    Apparatus.

    The relevant test level is:

    Class III, 2kV, 5kHz, common mode only.

  • 8/10/2019 Type test Notes

    32/51

    5/4/2012 32 Typetest_notes_2012.doc

    Class IV, 4kV, 2.5kHz, common mode only.

    ANSI/IEEE 4kV, 2.5kHz, common and differential mode.

    The test is to one circuit at a time, and the test duration is 1min. Tests are carried

    out on each circuit, with the relay in the following modes of operation:

    1. Current and voltage applied at 90% of setting, (relay not tripped)

    2. Current and voltage applied at 110% of setting, (relay tripped)

    3. Main protection and communications functions are tested to determine the effect

    of the interference.

    The pass criteria is that during application of the fast transient, the relay shall not

    maloperate, and shall still perform its main functions within the claimed tolerance.

    5.7 POWER FREQUENCY INTERFERENCE

    This test simulates the type of interference that is caused when there is a power

    system fault and very high levels of fault current flow in the primary conductors or the

    earth grid. This causes 50 or 60Hz interference to be induced onto control and

    communications circuits.

    The relevant test standard is:

    IEC 60255-22-7 Electrical Relays Part 22-7: Electrical Disturbance Tests for

    Measuring Relays and Protection Equipment Power Frequency Immunity Tests.

    The relevant test level is:

    300Vrms common mode, 150V rms differential mode, applied to circuits for which

    power system inputs are not connected.

    Tests are carried out on each circuit, with the relay in the following modes of

    operation:

    1. Current and voltage applied at 90% of setting, (relay not tripped)

    2. Current and voltage applied at 110% of setting, (relay tripped)

  • 8/10/2019 Type test Notes

    33/51

    5/4/2012 33 Typetest_notes_2012.doc

    3. Main protection and communications functions are tested to determine the effect

    of the interference.

    The pass criteria is that during application of the power frequency interference, the

    relay shall not maloperate, and shall still perform its main functions within the

    claimed tolerance.

    5.8 ELECTROSTATIC DISCHARGE

    This test simulates the type of high voltage interference that occurs when an

    operator touches the relays front panel after being charged to a high potential by the

    friction between dissimilar materials moving against one another.

    For example, in 2005 Frank Clewer of Warrnambool in Western Victoria, Australia

    attended a job interview wearing a nylon jacket and woollen shirt. As he walked

    through the building he left scorch marks across the carpet which subsequently

    ignited and led to everyone being evacuated. Firemen attending the scene cut the

    power supply believing the fire had been caused by a power surge. However, they

    later discovered that Mr Clewers clothes were carrying an electrical charge of 40kV!

    In this case the discharge is only ever applied to the front panel of the relay, with the

    cover both on and off. Two types of discharges are applied, air discharge and

    contact discharge. Air discharges are used on surfaces that are normally insulators,

    and contact discharges are used on surfaces that are normally conducting. Typical

    application points are shown in the diagrams below.

  • 8/10/2019 Type test Notes

    34/51

    5/4/2012 34 Typetest_notes_2012.doc

    Figure 8 Application points for the ESD tests. Front cover on.

    Figure 9 Application points for the ESD tests. Front cover removed.

    The shaded labels indicate those points which are not normally conducting and

    which will therefore be subjected to the air discharge. The unshaded areas are

    those that are normally conducting and will be subjected to the contact discharge.

  • 8/10/2019 Type test Notes

    35/51

    5/4/2012 35 Typetest_notes_2012.doc

    The relevant test standard is:

    IEC 60255-22-2 - Measuring Relays and Protection Equipment Part 22-2:

    Electrical Disturbance Tests Electrostatic Discharge Tests

    The relevant test level is:

    Cover On: Class 4, 8kV contact discharge, 15kV air discharge

    Cover Off: Class 3, 6kV contact discharge, 8kV air discharge

    In both cases above, all the lower test levels are also tested.

    The discharge current waveform is as shown below:

    Time, ns

    Cu

    rrent,%o

    fPeak

    0

    10

    20

    30

    40

    50

    60

    70

    80

    90

    100

    0 10 20 30 40 50 60 70 80 90

    Rise Time = 0.7 to 1.0 ns.Current Specified for 30 ns and 60 ns

    Figure 10 ESD Current Waveform

    The test is performed with single discharges repeated on each test point 10 times

    with positive polarity and 10 times with negative polarity at each test level, the timeinterval between successive discharges is greater than 1 second.

    Tests are carried out at each level, with the relay in the following modes of operation:

    1. Current and voltage applied at 90% of setting, (relay not tripped)

    2. Current and voltage applied at 110% of setting, (relay tripped)

  • 8/10/2019 Type test Notes

    36/51

    5/4/2012 36 Typetest_notes_2012.doc

    3. Main protection and communications functions are tested to determine the effect

    of the discharge.

    The pass criteria is that during application of the electrostatic discharge, the relay

    shall not maloperate, and shall still perform its main functions within the claimed

    tolerance.

    5.9 SURGE IMMUNITY

    This test simulates interference caused by major power system disturbances such as

    capacitor bank switching and lightning strikes on overhead lines within 5km of the

    substation.

    The open circuit voltage is a 1.2 /50s test waveshape, and the short circuit current

    is a 8/20s waveshape. The short circuit output current can be as high as 2kA and

    this test is therefore much more powerful and potentially destructive than any of the

    other interference tests.

    The relevant test standard is:

    IEC 60255-22-5 - Measuring Relays and Protection Equipment Part 22-5:

    Electrical Disturbance Tests Surge Immunity Test.

    The relevant test level is:

    Level 4, 4kV common mode, 2kV differential mode

    The pass criteria is that during application of the surge, the relay shall not

    maloperate, and shall still perform its main functions within the claimed tolerance.

    Also, it shall not suffer any damage.

    5.10 CONDUCTED AND RADIATED EMISSIONS

    These tests arise primarily from the essential protection requirements of the

    European Community (EU) directive on EMC which require manufacturers to ensure

    that any equipment to be sold in the EU must not interfere with other equipment. To

    achieve this it is necessary to measure the emissions from the equipment and

    ensure that they are below the specified limits.

  • 8/10/2019 Type test Notes

    37/51

    5/4/2012 37 Typetest_notes_2012.doc

    Conducted emissions are measured from the equipments power supply ports and

    communications ports.

    Radiated emissions measurements are to ensure that the interference radiated from

    the equipment is not at a level which could cause interference to other equipment.

    When performing these two tests, the relay is in a quiescent condition, that is not

    tripped, with currents and voltages applied at 90% of the setting values. This is

    because for the majority of its life, the relay will be in the quiescent state and the

    emission of electromagnetic interference when the relay is tripped is considered to

    be of no significance.

    The relevant test standards are:

    IEC 60255-25 - Electrical Relays Part 25: Electromagnetic Emission Tests for

    Measuring Relays and Protection Equipment

    IEC 60255-26 Measuring Relays and Protection Equipment: Part 26:

    Electromagnetic compatibility requirements

    The relevant test levels are detailed in tables 1 to 4 below:

    Table 1. Test level requirements for radiated emissions up to 1GHz

    Frequency Range (MHz) Limits of Radiated Emissions at 10m1

    Measurement Distance

    Quasi-Peak dB (V/m)

    30 to 230MHz 402

    230 to 1000MHz 47

    Notes:

    1. The limits can be changed for different measurement distances

    2. The lower limit shall apply at the transition frequency

  • 8/10/2019 Type test Notes

    38/51

    5/4/2012 38 Typetest_notes_2012.doc

    Table 2. Test level requirements for radiated emissions over 1GHz

    Frequency Range (GHz) Limits of Radiated Emissions at 3m

    Measurement Distance

    Average Limit dB

    (V/m)

    Peak Limit dB (V/m)

    1 to 3 561 76

    3 to 6 60 80

    Notes:

    1. The lower limit shall apply at the transition frequency

    The highest frequency that the radiated emissions is measured up to is determined

    by the highest frequency generated or used within the EUT as follows:

    If the highest frequency of the internal sources of the EUT is less than108MHz, the measurement shall only be made up to 1GHz

    If the highest frequency of the internal sources of the EUT is between108MHz and 500MHz, the measurement shall be made up to 2GHz

    If the highest frequency of the internal sources of the EUT is between500MHz and 1GHz, the measurement shall be made up to 5GHz

    If the highest frequency of the internal sources of the EUT is above1GHz, the measurement shall be made up to 5 times the highestfrequency or 6GHz, whichever is less

    Table 3. Test level requirements for conducted emissions on power supply inputs

    Frequency Range (MHz) Limits dB (V)

    Quasi-peak Average

    0.15 to 0.5 791 66

    1

    0.5 to 30 73 60

    Notes:

    1. The lower limit shall apply at the transition frequency

  • 8/10/2019 Type test Notes

    39/51

    5/4/2012 39 Typetest_notes_2012.doc

    Table 4. Test level requirements for conducted emissions on communications ports

    Frequency Range

    (MHz)

    Voltage limits1

    dB (V)

    Current limits1

    dB (A)

    Quasi-

    peak

    Average Quasi-peak Average

    0.15 to 0.5 97 to 872 84 to 74

    2 53 to 43

    2 40 to 30

    2

    0.5 to 30 87 74 43 30

    Notes:

    1. The current and voltage disturbance limits are derived for use with animpedance stabilization network (ISN) which represents a common mode(asymmetric mode) impedance of 150to the communications port undertest (conversion factor is 20 log10150/1 = 44dB). The choice of whether thecurrent limits or voltage limits are used for measurement depends on theavailability of test equipment at the time of testing.

    2. The limits decrease linearly with the logarithm of the frequency in the rangeof 0.15MHz to 0.5MHz

    5.11 CONDUCTED AND RADIATED IMMUNITY

    These tests are designed to ensure that the equipment is immune to levels ofinterference which it may be subjected to. The two tests conducted and radiated,

    arise from the fact that for a conductor to be an efficient antenna, it must have a

    length of at least wavelength of the electromagnetic wave it is required to conduct.

    If a relay were to be subjected to radiated interference at 150kHz, then a conductor

    of at least =300,000,000/150,000*4 = 500m long would be needed to conduct the

    interference. Even with all the cabling attached and with the longest PCB track

    length taken into account, it would be highly unlikely that the relay would be able to

    conduct radiation of this frequency, and the test therefore, would have no effect.The interference has to be physically introduced by conduction, hence the conducted

    immunity test.

  • 8/10/2019 Type test Notes

    40/51

    5/4/2012 40 Typetest_notes_2012.doc

    Note that at the radiated immunity lower frequency limit of 80MHz, a conductor

    length of approximately 1.0m is required. At this frequency radiated immunity tests

    can be performed in confidence that the relay will conduct this interference, through

    a combination of the attached cabling and the PCB tracks.

    Although the test standards state that all 6 faces of the equipment should be

    subjected to the interference, in practice this is not carried out. Applying interference

    to sides and top and bottom of the relay would have little affect as the circuitry inside

    is effectively screened by the earthed metal case. However, the front and rear of the

    relay are not completely enclosed by metal and are therefore not at all well screened,

    and can be regarded as an EMC hole. Electromagnetic interference when directed

    at the front and back of the relay can enter freely onto the PCBs inside.

    When performing these two tests, the relay is in a quiescent condition, that is not

    tripped, with currents and voltages applied at 90% of the setting values. This is

    because for the majority of its life, the relay will be in the quiescent state and the

    coincidence of an electromagnetic disturbance and a fault is considered to be

    unlikely.

    However, spot functional checks are performed at selected frequencies, where the

    relay is tested to exercise all of its main protection and control functions, to ensure

    that it will operate as expected, should it be required to do so.

    The frequencies for the spot checks are in general selected to coincide with the radio

    frequency broadcast bands and in particular, the frequencies of substation

    attendants mobile communications. This is to ensure that when working in the

    vicinity of a relay, the substation attendant should be able to operate his walkie-talkie

    without fear of causing the relay to maloperate.

    In addition, two further frequency sweeps are performed between 800MHz - 960MHz

    and 1.4GHz - 2.0GHz at 30V/m to replicate the digital radio telephone and base

    station frequencies used throughout the world.

    The relevant test standards for the radiated immunity test are:

    IEC 60255-22-3 - Measuring Relays and Protection Equipment Part 22-3:

    Electrical Disturbance Tests Radiated Electromagnetic Field Immunity.

  • 8/10/2019 Type test Notes

    41/51

    5/4/2012 41 Typetest_notes_2012.doc

    IEC 61000-4-3 Electromagnetic Compatibility (EMC. Testing and Measurement

    Techniques. Radiated, Radio-Frequency, Electromagnetic Field Immunity Test

    ANSI/IEEE C37.90.2 IEEE Standard for Withstand Capability of Relay Systems

    to Radiated Electromagnetic Interference from Transceivers

    The relevant test levels for these radiated immunity tests are:

    Class III, 10V/m, 80MHz 2.7GHz with 80% AM modulation using a 1kHz

    sinewave. Plus additional spot frequency tests at 80, 160, 380, 450, 900, 1850 &

    2150MHz.

    Digital Radio Telephone Sweep Tests,

    Level 4, 30V/m, 800MHz - 960MHz

    Level 4, 30V/m, 1.4GHz - 2.0GHz

    Both with 80% AM modulation using a 1kHz sinewave

    ANSI/IEEE, 35V/m 80MHz 1GHz with 80% AM modulation using a 1kHz

    sinewave. Plus additional spot frequency tests at 80, 160, 450 and 900MHz.

    The relevant test standard for the conducted immunity test is:

    IEC 60255-22-6 Electrical Relays Part 22-6: Electrical Disturbance Tests for

    Measuring Relays and Protection Equipment - Immunity to Conducted

    Disturbances Induced by Radio Frequency Fields.

    The relevant test level for the conducted immunity test is:

    Class III, 10Vrms, 150kHz - 80MHz.

    The pass criteria is that during application of the interference, the relay shall not

    maloperate, and shall still perform its main functions within the claimed tolerance.

  • 8/10/2019 Type test Notes

    42/51

    5/4/2012 42 Typetest_notes_2012.doc

    5.12 POWER FREQUENCY MAGNETIC FIELD

    These tests are designed to ensure that the equipment is immune to levels of

    magnetic interference which it may be subjected to. The three tests (steady state,

    pulsed and damped oscillatory magnetic field) arise from the fact that for different

    site conditions the level and waveshape is altered.

    5.12.1 Steady state magnetic field

    These tests simulate the magnetic field that would be experienced by a device

    located within close proximity of the power system. The relay is tested by immersing

    the product within a magnetic field generated by two induction coils. The relay is

    rotated such that in each axis it is subjected to the full magnetic field strength. The

    test setup is represented in the diagram below.

    EUTInduction Coil

    Ground Plane

    Induction Coil

    Figure 11 Power frequency magnetic field set-up

    The relevant test standard is:

    IEC 61000-4-8 Electromagnetic Compatibility (EMC) Part 4-8: Testing and

    Measurement Techniques Power Frequency Magnetic Field Immunity Test

  • 8/10/2019 Type test Notes

    43/51

    5/4/2012 43 Typetest_notes_2012.doc

    The relevant test level is:

    Level 5: 100A/m continuous and 1000A/m short duration

    The pass criteria is that during the application of the steady state condition, the relay

    shall not maloperate, and shall still perform its main functions within the claimed

    tolerance. During the application of the short duration test, the main protection

    function shall be exercised and verified that the operating characteristics of the relay

    are unaffected.

    5.12.2 Pulsed magnetic field

    These tests simulate the magnetic field that would be experienced by a device

    located within close proximity of the power system during a transient fault condition.

    The generator for the induction coils shall produce a 6.4/16s waveshape with the

    equipment configured as per the steady state magnetic field test.

    The relevant test standard is:

    IEC 61000-4-9 - Electromagnetic Compatibility (EMC) Part 4-9: Testing and

    Measurement Techniques Pulse Magnetic Field Immunity Test.

    The relevant test level is:

    Level 5: 1000A/m

    The pass criteria is that during the application of the magnetic field, the relay shall

    not maloperate, and shall still perform its main functions within the claimed tolerance.

    5.12.3 Damped oscillatory magnetic field

    These tests simulate the magnetic field that would be experienced by a device

    located within close proximity of the power system during a transient fault condition.

    The generator for the coil shall produce an oscillatory waveshape with a frequency of

    100kHz and 1MHz, the equipment shall be configured as per steady state magnetic

    field test.

    The relevant test standard is:

  • 8/10/2019 Type test Notes

    44/51

    5/4/2012 44 Typetest_notes_2012.doc

    IEC 61000-4-10 - Electromagnetic Compatibility (EMC) Part 4-10: Testing and

    Measurement Techniques Damped Oscillatory Magnetic Field Immunity.

    The relevant test level is:

    Level 5: 100A/m, 100kHz and 1MHz

    The pass criteria is that during the application of the magnetic field, the relay shall

    not maloperate, and shall still perform its main functions within the claimed tolerance.

    5.13 SAFETY

    All relays sold within Europe are required to comply with the European Low Voltage

    directive (LVD) 2006/95/EC. This requirement has been mandatory since January1997 in order to CE mark a product. Products manufactured before this date

    complied with the appropriate Health and Safety at Work and Consumer Protection

    legislation. Note that this legislation covers the Product Safety i.e. whether the

    product is inherently safe and does not pose any hazard to the user of the product.

    The ability to detect and protect against external events which might cause a hazard

    is dealt with under any applicable functional safety requirements.

    The essential requirement of the legislation is to show due diligence that the product

    is safe and will not cause electric shock or f ire hazard under normal conditions and in

    the presence of a single fault. The LVD requirements cover all aspects of the

    product and are not just confined to the electrical connections. The product must be

    well constructed according to good engineering practice i.e. it must not fall apart

    exposing live parts or presenting mechanical hazards. Walls must not be so flimsy

    that pressing against these reduces the insulation distances below the minimum

    requirement. The product must be adequately insulated and be suitably earthed with

    clearly labelled manufacturer mark/logo, product ratings and any safety warnings. In

    addition the product publication must contain adequate instructions and warnings

    affecting safety.

    Compliance with the Low Voltage Directive is demonstrated via self assessment with

    the information being stored in a Technical File.

  • 8/10/2019 Type test Notes

    45/51

    5/4/2012 45 Typetest_notes_2012.doc

    The key relevant test standards are:

    IEC 60255-27 Measuring relays and protection equipment. Part 27: Product safety

    Requirements.

    IEC 60664-1 - Insulation Coordination for Equipment Within Low Voltage Systems

    Part 1: Principles, requirements and tests

    UL 508 edition 17, Industrial Control Equipment

    UL 840 edition 3, Insulation Coordination Including Clearances and Creepage

    Distances for Electrical Equipment.

    IEC 60079-0, Electrical Apparatus for explosive gas atmospheres

    and other BS, EN, IEC and UL standards referenced directly or indirectly by the

    above documents.

    6. ADDITIONAL TESTING

    In addition to the Type Testing that is carried out on our products the Automation

    Products Laboratories has introduced additional testing. This testing is carried out

    after the Type Testing has been completed and prior to the products being available

    for sale to our customers. This testing is carried out by a team of Technicians who

    are effectively acting as our first customers. The testing focuses on the functional

    operation of the product in that tests are carried out to ensure that the product

    performs according to the claims made in the publications, the commissioning

    instructions are also followed to ensure that they are correct and the product

    performs as detailed in these instructions.

    Another aspect of this additional testing is what we term Break-It Testing. This

    again is carried out by our team of Technicians who carry out unusual tests on the

    products to ensure that they do not have any unforeseen problems, an example of

    such a test is:

  • 8/10/2019 Type test Notes

    46/51

    5/4/2012 46 Typetest_notes_2012.doc

    When downloading a settings file to a relay the communications cable is

    disconnected before the file has downloaded, the relay will be tested to see

    what effect this has had. The expected result is that the relay should

    disregard the new settings and continue to operate using the original settingsand the relay shall continue to work and trip as expected.

    There are many other examples of this type of testing that is carried out as Break-It

    Testing but they are far too numerous to detail here. As can be seen from the above

    example the intention is to carry out testing that is not usually part of routine Type

    Testing and is more representative to how the product will be used in service.

    The purpose of carrying out this additional and Break-It Testing is to ensure and if

    necessary improve product quality and to detect and rectify any potential problems

    with the products before they go on sale to our customers.

    7. IEC 61850 CONFORMANCE TESTING.

    7.1 OBJECTIVE

    The objective as quoted in the UCAIug (Utilities Communication Architecture

    International Users Group) Conformance Test Procedures for Server Devices is:

    Does the protocol implementation of the DUT, conform to the IEC 61850 standard

    and the PICS, MICS, PIXIT and ICD specifications as configured with SCD?

    From the quotation above what is the:

    DUT? The DUT is the Device Under Test.

    IEC 61850 standard? The set of rules that the DUT protocol implementation

    must adhere to. The standard is broken down into many parts of which the

    following IEC documents for Communication networks and systems insubstations are used as reference during Conformance Testing:

  • 8/10/2019 Type test Notes

    47/51

    5/4/2012 47 Typetest_notes_2012.doc

    IEC 61850 Title

    Part 1 Introduction and overview

    Part 2 Glossary

    Part 3 General Requirements

    Part 4 System and Project Management

    Part 5 Communication Requirements for Functions and Device Models

    Part 6 Substation Automation System Configuration Language

    Part 7-1 Basic Communication for Substation and Feeder Equipment - Principles and

    Models

    Part 7-2 Basic Communication for Substation and Feeder Equipment - Abstract

    Communication Service Interface (ACSI)

    Part 7-3 Basic Communication for Substation and Feeder Equipment Common Data

    Classes and Attributes

    Part 7-4 Basic Communication for Substation and Feeder Equipment - Compatible

    Logical Node and Data Object Addressing

    Part 8-1 Specific Communication Service Mapping (SCSM) Mapping to MMS

    Part 10 Conformance Testing

    PICS Protocol Implementation Conformance Statement, a document

    supplied with the DUT outlining what protocol services from part 7-2 are

    supported.

    MICS Model Implementation Conformance Statement, a document supplied

    with the DUT outlining what Logical Device, Node, Common Data Class and

    Attribute Definitions from parts 7-3 and 7-4 are supported and the format they

    will use in the DUT. The MICS will conform to what is available in the ICD

    file.

  • 8/10/2019 Type test Notes

    48/51

    5/4/2012 48 Typetest_notes_2012.doc

    EQUIPMENT SIMULATOR

    Ethernet switchin Hub

    SIMULATOR / PC

    ANALYZERDevice Under

    Test DUT

    Time Master

    PIXIT Protocol Implementation eXtra Information for Testing, a document

    supplied with the DUT outlining conditions considered for each Conformance

    Block supported by the DUT. The Conformance Test Engineer will reference

    this document throughout the testing as and when specified by the UCA TestProcedures to do so.

    ICD IED Configuration Description, the empty configuration file/data model

    for the DUT in SCL (Substation Configuration Description) format.

    SCD Substation Configuration Description, the configured file/data model

    for the DUT in SCL format.

    7.2 TEST ENVIRONMENT

    All tests are carried out by the Test Engineer in a laboratory faculty. Tests can be

    performed to the UCA Test Procedures as Stafford Automation Product Laboratories

    is a UCA Accredited Laboratory with ISO/IEC 17025 and ISO 9000 Quality System.

    7.3 COMPONENTS IN THE TEST ENVIRONMENT

    The test environment consists of the following components:

  • 8/10/2019 Type test Notes

    49/51

    5/4/2012 49 Typetest_notes_2012.doc

    7.4 TEST TOOLS

    We are currently conducting tests using the latest versions of the globally used

    KEMA tools. Although the diagram above specifies an external analyser and time

    master, the PC will consist of all tools necessary to conduct the Conformance Test

    including the analyser and time master. The test tools are:

    UniCA Client Simulator KEMA Tool for running mandatory/conditional test

    case as defined in the UCA Test Procedures.

    UniCA Goose Simulator KEMA Tool for running mandatory/conditional

    Goose Subscription test cases as defined in the UCA Test Procedures.

    UniCA SCL Checker KEMA Tool for the checking of the SCL File and Data

    Model to ensure that there are no conflicts when compared to what is defined

    in the standard.

    UniCA 61850 Analyser KEMA Tool allowing the Test Engineer to

    interrogate and store trace files for all test cases.

    Omicron Test Suite for Omicron CMC256plus Equipment Simulator for

    generating input/output signals.

    Time Master PC based software to time synchronise device/clients.

    SCL Configuration Tool IEC 61850 IED Configurator, of the MiCOM S1

    Studio Suite, used to configure device for test.

    7.5 TESTING

    We are currently running Conformance Tests to the latest edition of the UCA Test

    Procedures, Conformance Test Procedures for Server Devices with IEC 61850-8-1

    interface Revision 2.3.

    UCA Test Procedures requires the testing of:

    Documents

    o PICS Protocol Implementation Conformance Statement

  • 8/10/2019 Type test Notes

    50/51

    5/4/2012 50 Typetest_notes_2012.doc

    o MICS Model Implementation Conformance Statement

    o TICS Technical Issues Implementation Conformance Statement

    o PIXIT Protocol Implementation eXtra Information for Testing

    SCL Configuration Files/Data Model

    o ICD IED Configuration Description

    o SCD / CID Substation Configuration Description / Configured IED

    Description

    Test Cases for following Conformance Blocks if supported by the DUT:

    o Basic Exchange Application Association and Server

    o Data Set

    o Substitution

    o Setting Group

    o Reporting Buffered, Unbuffered and Enhanced Buffered

    o GOOSE - Publishing and Subscribing

    o Control Direct Control, SBO Control (Select-Before-Operate), Enhanced

    Direct Control and Enhanced SBO Control

    o Time and Time Synchronization

    o File Transfer

    7.6 TESTING

    When all tests have been performed and conducted according to the structured UCATest Procedures using the tools provided, an IEC 61850 Conformance Test

    Certificate is issued.

  • 8/10/2019 Type test Notes

    51/51

    The tests and certificate can only be conducted and issued respectively by a UCA

    accredited laboratory. Alstom Grid UK Stafford Laboratory is UCA accredited. A list

    of other UCA accredited Test Laboratories from the UK and abroad is listed on the

    UCA website, www.ucaiug.org.

    References

    [1] IEC 61850 Communication networks and systems in substations

    [2] Conformance Test Procedures for Server Devices with IEC 61850-8-1 interface

    Revision 2.3

    [3] www.ucaiug.org