TurningUpTheHeat - Land and Groundwater · 2018-06-22 · Feasibility Results Sample 1 Sample 2...
Transcript of TurningUpTheHeat - Land and Groundwater · 2018-06-22 · Feasibility Results Sample 1 Sample 2...
Turning Up The Heat
Applica2ons of In-‐situ and Ex-‐situ Thermal Remedia2on Techniques on Contaminated Sites
Indirect Thermal Desorption Plant
Andrew Race – Engineering Manager VIC
Veolia Indirect Thermal Desorption Plant
Vacuum distillation process designed to: • Dewater and decontaminate hydrocarbon affected PIW • Recover as much as possible
Important Points • Will not remove metals apart from Hg • Operates under vacuum and inert blanketing • Indirect heating of product using thermal oil jacketing • Potentially other wastes can be treated subject to EPA approval
FEEDING UNIT THERMAL OIL HEATING UNIT
DRYER UNIT 1
DRYER UNIT 2
DISCHARGE UNIT
CONDENSER UNIT
COOLING WATER UNIT
DROPLET CATCHER
DUST FILTER VACUUM PUMP CHILLER ACTIVE CARBON
FILTER
DISCHARGE TO ATMOSPHERE
CHILLED WATER UNIT
INERT
CAT B, C NOT SUITABLE FOR
TREATMENT
CAT A NOT SUITABLE FOR
TREATMENT
TO COMPOST
TO LANDFILL
BACK TO EXISTING
TREATMENT PLANT
CAT A, B OR C DROPLET CATCHER
OIL / WATERBACK TO EXISTING TREATMENT PLANT
CLEAN OUTPUT MATERIAL
INERT REUSE OR DISPOSAL
TREATED SOLIDS
FILTER CAKE
LIQUID FLOWS
GASEOUS FLOWS
THERMAL OIL FEED/RETURN
COOLING WATER FEED/RETURN
SOLID FLOWS
WATER
FLAME IONISATION DETECTOR
INSTRUMENTATION
Process Flow Diagram
Vital Statistics
Process Temperature up to 370°C
Process Pressure 800 to 100 mbar (abs) Throughput 20,000 tonnes / annum
2.86 tonnes / hour
Inputs pH > 4.5 Grain size < 30 mm
Output Water with oil Oil with water Inert solid powder
Timeline
1/01/2008 1/06/2015
1/01/2008 -‐ 1/01/2009Pre Feasibility
1/01/2009 -‐ 1/01/2010Feasibility
1/01/2010 -‐ 1/01/2013Detailed Design
1/01/2013 -‐ 27/10/2014Construction
27/10/2014 -‐ 30/12/2014Commissioning
Feasibility Study
Feasibility Results
Sample 1 Sample 2 Sample 3 Sample 4
Totals (mg/kg) IW Cat C Cat B Input Output Input Output Input Output Input Output
TPH C6-C9 325 650 2600 0.023 0.01 14 2.64 1.136 0.486 1.378 0.2508
TPH C10-C36 5000 10000 40000 2020 164.6 166000 2400 51400 5400 32400 2656
Benzo(a)pyrene 5 5 20 19.6 0.546 5.54 0.038 0.34 0.046 0.306 0.048
Sum of PAH 50 100 400 318 5.18 1580 6.54 55.4 2.586 46.8 2.336
Di(2-ethylhexyl)phthalate 40 40 160 0.238 0.2 2.92 0.2 28.6 0.2 14.92 0.2
Detailed Design
Construction
Assembly
Assembly
Assembly
Contact
Andrew Race Engineering Manager, VIC [email protected] 0409 452 249
Presentation to ALGA Peter Mirkov – CEO
19 November 2014
Page 16
Agenda
Introduction to RENEX RENEX Project Overview Project Challenges Industry Interaction Regulatory Support and/or enforcement
Page 17
Introduction to RENEX
Project Background Victorian government mandate to eliminate high hazard waste to landfill by 2020 Contaminated soil represents the single largest source of hazardous waste sent to landfill Lack of existing treatment options for Contaminated Soils and other Prescribed Industrial Wastes Victorian Legislation focusing on Waste Management Hierarchy & Resource Recovery Although project was driven by Victorian legislation and market, treatment opportunities for wastes from across Australia exist and are expected to be utilised
Page 18
Introduction to RENEX
Who is RENEX A newly created business focusing on providing an Industrial Waste Treatment & Resource Recovery Facility (emphasis on Soils and Prescribed Industrial Wastes) Ownership
– Funds Managed by CleanTech Ventures • Victorian Clean Technology Fund • Cleantech Australia Fund
– Macquarie Bank – OPTrust – Private Investors
Page 19
RENEX Project Overview • Permanent facility for the treatment of up to 100,000 tonnes per annum of
contaminated soil and other PIWs (Other PIWs will include PCB oils, waste oils, as well as shredder floc from car recycling, tyres)
• 4 Ha site in Dandenong South
• 11,000 m2 under roof
• Storage capacity for up to 30,000 tonnes of contaminated soil
• Facility has complete mechanical pre-treatment capability – crushing, screening, metal removal - ability to receive concrete, bricks, rubble, plastic, tyvek suits, timber etc. “If it can be transported, we can accept it”.
• Modelled throughput at 10 tonnes per hour. • Materials pre-dried – full treatment capacity maintained, receive materials up to
sludge consistency (40+% moisture) • Facility is being commissioned in several major stages
Stage 1 – license to receive & store Soils & other PIWs (EPA approval 6th Nov 2013)
Stage 2 – EPA 30A approval to treat stockpiled soils – (EPA approval 3rd Nov 2014)
Stage 3 – EPA 20 Operating License – (Expect EPA approval Mar/Apr 2015)
Page 20
RENEX Project Overview
Insert RENEX site diagram
Page 21
RENEX Project Overview
What can RENEX treat? The facility can treat all organics (including volatile metals such as mercury) and at very high concentrations
– Phenols – Aromatic hydrocarbon – Petroleum hydrocarbons – Polychlorinated biphenyls (up to 6,000 mg/kg) – Chlorinated hydrocarbons – Organochlorine pesticides – All other organics – Mercury
Project Challenges
• Commenced in 2007 – over 7 years in the making
• So you want to build a Large Scale Thermal Soil & PIW Treatment Facility in Australia, here is what you need:
• Agreement from proven, global technology provider (1-3 years + $) • Identify and secure suitable land and location (1-2 years + $$$) • Local engineering exertise to produce EPA Works Approval Application (1 year + $) • Planning Permit, likely VCAT hearings (1-2 years + $$) • Project Funding, debt not an option as Banks wont talk to you, need expensive equity funding
(2 years + $$$$) • Local engineering, construction and operational capability (1 year + $$) • Build facility and transfer technology (2 years + $$$$$) • Receive largest EPA HazWaste fund of $1m 5 years after being promised (and yet still haven’t
received it all – but very grateful nonetheless)
• Above will take 7+ years and cost $70+ million
Page 22
Regulatory Support and/or enforcement
• EPA extremely supportive in technical management of project commissioning but lack of EPA enforcement commitment produces market uncertainty
• Regulations already gazetted (s.195) and hopefully will be enforced – timing issue with EPA
• Cat A and Cat B prices have reduced by 30%-40% (or more) since RENEX started receiving soil – obviously mostly driven by lowering of landfilling prices, and in some cases interstate movements. RENEX has dropped prices by similar amounts in this time. Is this sustainable? Is this good for our industry?
• Landfill can always be cheaper – but not the best environmental outcome
Page 23
Industry Interaction
• Consultants very supportive – but can create ‘conflict’ when assessing remediation options
• Ensuring that RENEX’s value proposition is communicated to a broad base within each firm
• Site owners have been very keen to look at RENEX as a potential solution – often wishing to contract directly with us
• Cartage companies have been willing to investigate RENEX as a viable solution to landfills where possible
• RENEX’s is not the solution for everything – but is a better solution than landfill
• What ‘value’ should be attributed to a solution that has a greater environmental benefit than landfill? OR What does EPA really mean by “Practically Accessible”
Page 24
Thermal Remediation Drivers for On Site Application
In-situ / Ex-situ By
Andrew Wollen, ERR Representing, GEO INC
What is Gas Thermal Remediation (GTR)? Ø Propane/Natural gas/Diesel Ø Closed heaPng system >> No VOC emissions Ø Soil and groundwater heated by thermal conducPon Ø Treatment temperatures from 50°C to >400°C Ø Treat sand, silt, CLAY, Bedrock, and Groundwater
Ø Vapor extracPon wells remove VOCs Ø VOCs treated by vapor treatment system
Steel Heater Wells
Outer tube
Inner tube
Technical Benefits of Heat
• Vapor pressure of organic materials increase
• Viscosity of separate phase liquids decrease
• Increases desorption • Diffusion rates increase • Solubility increases • Increases biodegradation • Rates of Hydrolysis increase • Thermal Oxidation
NAPL
VOLATILIZATION
Vapo
r&Pressure
DISSOLUTION
Henry’s&C
onstant
VOLATILIZATION
DISSOLUTION
DISSOLUTION
VOLATILIZATIO
N
DISSOLUTION
ADSORPTION������������
������������
Vapor&PressureADSO
RPTION
��������
GROUNDWATER
SOIL
SOIL1GAS
Thermal Conductivity varies by a factor of only 2-4 across all soil types
In-Situ GTR
Ex-Situ GTR
• 36 GTR TCHs • 36 Vapor Extraction Wells • Target Temperature: 200°C • Thermal Treatment Duration: 39 days • Treatment Goal: less than 100 mg/kg total petroleum hydrocarbons
Three Levels of Thermal Treatment
Level of Heating & Contaminant
Target Treatment
Temperature
(°C)
Heating Well
Spacing
(m)
Desiccation of Zone?
Range of Costs (all
inclusive)
($/m3)
1. VOCs: Gentle Heating (BTEX, CVOCs)
<100 4 – 6 No 40-200
2. VOCs (CVOCs, BTEX)
>100 2 – 4 Depends 60-300
3. SVOCs (PCBs, PAHs, BaP, dioxins)
200-300 1.5 – 3 Yes 150-600
Why in-situ Thermal Remediation? Challenging Goals • Rapid schedule • Low clean-up standards in
soil, GW or vapour intrusion • High probability of success • Source zone mass removal • Other options failed
Challenging Sites • Limited access - no
excavation possible • Depth of impacts precludes
excavation • Odour / noise / emissions • Transport risks/costs • Complex mix of COCs • DNAPL below the water
table • LNAPL smear zones • Fractured bedrock • Clay lithology- diffusion
limited condition
Dry Cleaner, Near Railway, Active
Form
er D
ry
Cle
aner
Former D
ry C
leaner
Equipment entry through 1m wide door
Compact Installation
Natural gas, propane, diesel, gasoline
Scalable equipment Site access
Flexibility is key Flexibility has been key for many
projects interna6onally!
• Refrigerated Cooling Compression and Condensation combined with regenerative adsorption
• Condenses VOCs into NAPL • NO UPPER LIMIT for influent
VOC concentration • NO DILUTION! • >99% Removal efficiency
Vapour Treatment C3 Technology or GAC
2014 Cleanup Project Excellence Award
Parsons Brinkerhoff / Huntsman
Thermal Conductive Heating Summary
1. Applicability: soil temperatures < 70C to > 325C 2. Access: where other approaches are constrained
3. Speed: Mobilize and commence operations in weeks not months, small footprint, & often minimal electrical installation required
4. Scalability: very small to very large projects
5. Economics: Very competitive in overall cost $/m3
6. Performance Guarantees are common
Questions?
PANEL SESSION