Turning around the Tern - Devex · Conclusions : highlights & lessons learned • Highlights •...
Transcript of Turning around the Tern - Devex · Conclusions : highlights & lessons learned • Highlights •...
Turning around the Tern
Graham Richardson (TAQA)
DEVEX conference, Aberdeen
10th May 2012
Co authors
Audrey Miles (TAQA), Michael Judt (TAQA),
Laurence Bellenfant (Senergy, now BP)
Tern Alpha drilling
and production
platform, UK,
Northern North Sea
Slide 2
Outline
• History and background of Tern area – Example reservoir : Tern Main Brent
• Phase 1 Re-development ‘staircase’
• Conclusion – Highlights
– Lessons learned
– View to the future
Facilities performance
Reservoir surveillance
Re-development scoping
Activity planning
Projects execution
‘Make it safe’
‘Make it work’
‘Make it grow’
Slide 3
Location of Tern Area licences
Shetland
Islands
Tern
Kestrel
Falcon
Slide 4
Infrastructure status : December 2008
upon TAQA completion of Asset purchase
Hudson (subsea)
Non-operated
Kestrel
(subsea)
Tern Brent
Eider
platform
Gas lift
Water injection
Liquid production
Tern
Triassic
Tern facilities capacities
- Gas lift
100 mmscf/d
- Water injection
277,000 bwpd
- Liquids handling
246,000 blpd
History and Background of Tern Area
Reservoir Illustration : Tern Main Brent
• Tern was discovered in April
1975
• Brent reservoir STOIIP
approx. 600 million barrels
• Production and water
injection started in 1989
• Typical N Sea down-dip
water injection pattern
adopted
• Recovery factor to date,
approx. 45 %
• Brent Depth is
approximately 8000 –
8300 ft, OWC 8258 ft.
TVDSS
• Hydrostatically
pressured
• Porosity 17 – 27%
and permeability
0 – 2500 mD
Brent reservoir
producer &
injector locations
March 2012
A
B
C
D
E F
G
TA30 TA07S2 TA05S4
A B C D E F
G
BCU
Heather
Brent
BMNS
Rannoch
Dunlin
Cormorant 1
Cormorant 2
Palaeosol
Basement
A B C D E F
G
BMNS Seismic surface
Model: LB_2007 update
Transfer
fault zone
Tern Brent Reservoir : structural configuration
Slide 7
Tern Brent Reservoir Example log and typical properties
Formation N/G Av Porosity Av Perm mD Av Shi
Upper Ness C 0.50 0.20 87 0.75
Lower Ness 0.72 0.26 1504 0.74
Etive 0.84 0.25 1433 0.68
Rannoch B 0.79 0.23 531 0.75
Broom 0.65 0.18 84 0.46
UPPER
NESS
LOWER
NESS
ETIVE
RANNOCH
BROOM
Tern BrentProduction 1989 - 2011
0
20000
40000
60000
80000
100000
120000
140000
160000
180000
200000
Jan-89 Jan-91 Dec-92 Dec-94 Dec-96 Dec-98 Dec-00 Dec-02 Dec-04 Dec-06 Dec-08 Dec-10 Dec-12 Dec-14
Date
Pro
du
cti
on
(b
bl/d
), In
jecti
on
(b
bl/d
)
0.0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1.0
Wate
rcu
t
'Qoil_bbl/d'
'Qliq_bbl/d'
'Qi_bbl/d'
'WCT'
Slide 8
Production evolution : Tern Brent example
Stabilization of water cut with
background contribution from
Upper Ness, Rannoch, Broom
Plateau (80,000 bopd in
the case of Tern Brent)
Strong water breakthrough dominated by
Lower Ness – Etive layers
Slide 9
Facilities Performance
• Early focus on understanding facilities capacities, baseline
performance and underlying issues
• Recognition of need to improve both production and injection
efficiency
• Injection efficiency particularly important, most reservoirs reliant
on ‘water-drive’ mechanism – Injection the ‘engine’ for sustained production
• Potential was identified for injection facilities capacity increase by
dividing 4 HP pump system into 2 * HP pump system and 2 * LP
pump system
Facilities performance
Reservoir surveillance
Re-development scoping
Activity planning
Projects execution
‘Make it safe’
‘Make it work’
‘Make it grow’
Slide 10
Reservoir surveillance
• A programme of surveillance was undertaken to
improve understanding of the wells and reservoirs,
key elements of which were : – Improved well test and fluid sampling frequency
– Cased hole production logging
– Cased hole saturation logging
– Flowing gradient surveys : gas lift performance
– Reservoir pressure measurements
– Tracer programme in all Tern Brent water injection wells
(tracer example later in the presentation)
– Well mechanical and integrity status review
Facilities Performance
Reservoir Surveillance
Re-development scoping
Activity Planning
Projects Execution
‘Make it safe’
‘Make it work’
‘Make it grow’
Slide 11
Redevelopment scoping
• Using historical information and new surveillance
data as it became available, the reservoirs were
screened for re-development potential and a strategy
developed
– Tern Main Brent : infill production and injection to improve sweep in
Upper Ness, Rannoch, Broom
– Tern Triassic : reduce well spacing, implement water-flood pilot
• Platform challenge : slot constrained, 25 available slots, most being active…
– Kestrel : producer well repair
– Falcon Area : appraisal drilling
with view to ‘fast track’ development
Facilities performance
Reservoir surveillance
Re-development scoping
Activity planning
Projects execution
‘Make it safe’
‘Make it work’
‘Make it grow’
PLAT-
FORM
SUB-
SEA
Slide 12
Activity Planning
• 7 well platform infill campaign
scoped and approved, start of
ops. planned for August 2010 – Rig re-activation
– 5 Brent activities
• 1 work-over to water injection
(dedicated Upper Ness)
• 1 work-over to reinstate full gas
lift (Upper Ness horizontal prod)
• 1 infill producer (UN, Ra, Br)
• 1 water injector sidetrack
• 1 water injector integrity
workover
– 2 Triassic activities
• 1 infill producer
• 1 work-over to water inj.
Facilities performance
Reservoir surveillance
Re-development scoping
Activity planning
Projects execution
‘Make it safe’
‘Make it work’
‘Make it grow’
• Mobile drilling 2010 – Falcon twin branch appraisal
well planned for Spring 2010
Slide 13
Projects execution : achieved timeline
Facilities performance
Reservoir surveillance
Re-development scoping
Activity planning
Projects execution
‘Make it safe’
‘Make it work’
‘Make it grow’
Achieved timeline 4Q2008 1Q2009 2Q2009 3Q2009 4Q2009 1Q2010 2Q2010 3Q2010 4Q2010 1Q2011 2Q2011 3Q2011 4Q2011 1Q2012 2Q2012 3Q2012
TAQA completes Asset purchase
Tern Platform Rig Reactivation SCOPING PLANNING EXECUTION LOOK BACK
Tern Platform Campaign SCOPING PLANNING EXECUTION LOOK BACK
Falcon Appraisal Drilling SCOPING PLANNING EXECUT.
Falcon Development SCOPING PLANNING EXECUTION LOOK BACK
Water Injection Capacity Increase SCOPING PLANNING EXECUTION
Notes 1. Platform campaign extended from 7
to 8 wells, together with some modification / optimisation of later activities in the campaign vs original plan
2. Falcon appraisal : 1st branch water, 2nd branch oil, selected development subsea via Kestrel
Note 1
Note 2
Slide 14
Evolution of campaign
Activity
Sequence
Number
Original Plan
– Slot
Number
Original Plan
- Description
Actual
realised –
Slot Number
Actual
realised -
Description
1 23 Work-over to
Water Injection :
Triassic
23 As per original
plan
2 24 Work-over to
Water Injection :
Brent
24 As per original
plan
3 08 Infill producer :
Brent 08 As per original
plan
4 04 Producer Work-
over : Brent 18 Injection Work-
over : Brent
5 18 Injection Work-
over : Brent 04 Producer Work-
over : Brent
6 05 Infill producer :
Triassic 26 Infill Injector :
Brent
7 28 Injection Work-
over : Brent 30 Infill producer :
Triassic
8 n/a n/a 28 Infill producer :
Brent OP
TIM
IZA
TIO
N
OP
PO
RT
UN
ITIE
S
Tracers
unlocked
opportunity
SE
QU
EN
CIN
G
CH
AN
GE
S
Campaign optimization, activities 6 & 8
• Original development : downdip injectors and updip producers
• In 2010, tracers injected in all Brent water injectors
• 2009 seismic identified new fault and refined the fault pattern
• Southern injectors breakthrough in the Northern producers
• Mid-flank producers less well supported
• Southern injector duplication
• Identified – New injection point for
Mid Flank producers (TA26) – Bypassed oil target (TA28)
• Integrity injection work-over became oil producer activity, dry oil production >4500 b/d at start
New fault
TA28 target
TA26 target
Slide 16
Production results
Base
Decline
Change of operatorship
Note : Plot does not include Last two Tern producers, on-stream recently Activity 7 TA30 = 1,800 bopd initial
Activity 8 TA28 = 4,600 bopd initial
Conclusions : highlights & lessons learned
• Highlights
• Commercially successful drilling campaign in highly mature field
• No subsurface ‘failures’ in the development drilling
• Significant production growth
• Costs out-turn generally as per pre-project expectation (one
significant exception mentioned in lessons learned below)
• Tern platform has strong base performance
• Attractive host for subsea and 3rd party tiebacks
• Main Lessons learned
• Infill drilling campaign : challenging slot recoveries on many activities
• Infill drilling campaign : keep it simple
• last well difficult and cost overrun
• Maintaining improvement in water injection uptime has proved
challenging due to significant maintenance backlog.
Conclusions : View to the future
• Build on the information from the first platform campaign with a view
to unlock a second campaign in the 2014 timeframe
• Continue to build and drill the near field exploration portfolio with a
view to further ‘Falcon-like’ tie back opportunities
• Attract and secure 3rd party business which is value adding and
compliant with TAQA core business