Turbine&Belt

14
Site Conditions Estimate Notes Project Name Pontianak Project Location Pakenjeng Name of River - Irrigation Cisandaan System isolated stand alone / grid connection Gross Head m 46 Firm Flow 0.600 90% - 100% flow available Technical Data & Assumption Estimate Notes Design flow 0.56 Turbine type - Crossflow T14 Turbine peak efficiency % 74 Turbine efficiency at design f % 74 Turbine speed rpm 638 Maximum hydraulic losses % 2 2% - 7% Mechanical Transmission effici % 98 95% gearbox, 95% - 97% v belt, 98% flat belt Generator rating minimum kVA 210 minimum rating size Generator selected kVA 210 Generator efficiency % 93 75 - 80 small size, medium 80 - 90 < 100 kW Generator speed rpm 1500 Generator phase phase 3 Ratio of speed increaser 2.40 Transformer losses % 0 1% - 2%, 0 for no need transformer Parasitic electricity losses % 1 1% - 3% Annual downtime losses % 4 2% - 7% Annual Energy Production* Estimate Notes/Range Small hydro plant capacity kW 166.51 Small hydro plant capacity fac % 95% 40% to 95% Renewable energy available kWh 1,458,626 Renewable energy delivered kWh 1,386,278 Renewable energy delivered MWh 1386 * Based on firm flow with 90% - 100% flow available (run of river micro hydro power scheme) Firm flow Parasitic electricity losses Annual downtime losses pro-Rekayasa* Project Information m 3 /s m 3 /s power plant, it's important to ensure the power plant running through a year. Generally, micro hydro power plant is designed at the firm flow of Flow Duration Curve (FDC) or estimated as minimum of flow. Some of the energy generated by a micro-small hydro plant is used by the plant itself for auxiliary equipment (e.g. shut-off valves, by-pass gates, protection and control systems, etc.) lighting, heating, etc. For micro hydro, parasitic electricity losses are typically minimal. Parasitic electricity losses can range from 1 to 3 %. A value of 2 % is appropriate for most small hydro plants. plant will have to be shut down in order to carry out routine and emergency maintenance. This value is one of the factors used to calculate the available annual energy production of the small hydro plant. factor) and is an appropriate value for most small hydro plants. For micro-small hydro plants located in regions where increased maintenance requirements are anticipated (e.g. due to flood problems), more downtime should be anticipated and a higher value (e.g. 6 %) should be used.

description

turbin

Transcript of Turbine&Belt

Page 1: Turbine&Belt

Site Conditions Estimate NotesProject Name PontianakProject Location PakenjengName of River - Irrigation CisandaanSystem isolated stand alone / grid connection

Gross Head m 46

Firm Flow 0.600 90% - 100% flow available

Technical Data & Assumption Estimate Notes

Design flow 0.56Turbine type - Crossflow T14 Turbine peak efficiency % 74Turbine efficiency at design flow % 74Turbine speed rpm 638Maximum hydraulic losses % 2 2% - 7%

Mechanical Transmission efficiency % 98 95% gearbox, 95% - 97% v belt, 98% flat belt

Generator rating minimum kVA 210 minimum rating size

Generator selected kVA 210 Generator efficiency % 93 75 - 80 small size, medium 80 - 90 < 100 kW

Generator speed rpm 1500Generator phase phase 3Ratio of speed increaser 2.40Transformer losses % 0 1% - 2%, 0 for no need transformer

Parasitic electricity losses % 1 1% - 3%

Annual downtime losses % 4 2% - 7%

Annual Energy Production* Estimate Notes/RangeSmall hydro plant capacity kW 166.51Small hydro plant capacity factor % 95% 40% to 95%Renewable energy available kWh 1,458,626Renewable energy delivered kWh 1,386,278Renewable energy delivered MWh 1386

* Based on firm flow with 90% - 100% flow available (run of river micro hydro power scheme)

Firm flow

Parasitic electricity losses

Annual downtime losses

pro-Rekayasa* Project Information

m3/s

m3/s

The firm flow is often defined as the flow available at least 95 % of the time. For micro hydro power plant, it's important to ensure the power plant running through a year. Generally, micro hydro power plant is designed at the firm flow of Flow Duration Curve (FDC) or estimated as minimum of flow.

Some of the energy generated by a micro-small hydro plant is used by the plant itself for auxiliary equipment (e.g. shut-off valves, by-pass gates, protection and control systems, etc.) lighting, heating, etc. For micro hydro, parasitic electricity losses are typically minimal. Parasitic electricity losses can range from 1 to 3 %. A value of 2 % is appropriate for most small hydro plants.

Annual downtime losses is the estimated percentage of time that the micro-small hydro plant will have to be shut down in order to carry out routine and emergency maintenance. This value is one of the factors used to calculate the available annual energy production of the small hydro plant.

A value of 4 % represents approximately 15 days of downtime (assuming 100 % capacity factor) and is an appropriate value for most small hydro plants. For micro-small hydro plants located in regions where increased maintenance requirements are anticipated (e.g. due to flood problems), more downtime should be anticipated and a higher value (e.g. 6 %) should be used.

Page 2: Turbine&Belt

Site DataGross head m 46.00net head /design head Hnet m 45.080design flow Qt l/s 560diameter of runner Dt m 0.40

Turbine Calculation based on T14 D300 net head /design head Hnet m 45.08design flow Qt l/s 560diameter of runner Dt m 0.4unit speed (opt) n11 rpm 38

unit flow (opt) Q11opt 0.80efficiency of turbine etat opt - 74.0%

unit flow (max) Q11 max 0.94efficiency of turbine etat max - 73%Width of runner b0 mm 261shaft power output Pt opt kW 183.1

Pt max kW 212.3Turbine speed nt rpm 638

Turbine width is determinedWidth of runner mm 260.0Optimum Discharge l/s 558.6Power (turbine shaft) Ptw_opt kW 182.7Turbine speed ntw_opt rpm 638Run away speed ntw_max rpm 1148Generator/Transm. Effic. eta_g - 91%El. Output Pel kW 166.51

Turbine Efficiency Q/Qopt (%) Eff (%) Flow (l/s) Notes

115% 73% 642110% 74% 614100% 75% 559 recommended to operate until

80% 74% 447 flow available around 40% of Qopt

60% 73% 33540% 67% 22320% 50% 11212% 0% 67

pro-Rekayasa* Turbine Calculation

Hgross

m3/s

m3/s

bow

Qopt

0 100 200 300 400 500 600 7000%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

Flow (liter/second)

Eff

icin

cy

(%

)

Page 3: Turbine&Belt

Notes

0 100 200 300 400 500 600 7000%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

Flow (liter/second)

Eff

icin

cy

(%

)

Page 4: Turbine&Belt

Basic data

Descriptions Symbol value unitTurbine shaft speed n1 638 rpmTurbine Torque Tt 2735 NmGenerator shaft speed n2 1500 rpmSpeed increasing ratio 2.375Power transmitted Pt 182.70 kWTorque at generator Tg 1163 Nm

Calculation

Descriptions Symbol value unitService factor 1.15Design power for belt 210.10 kWMinimum pulley diameter 400 mmLarge pulley diameter 950 mmStandard of large pulley 1190 mmCorrection of ratio of pulley 2.98Belt speed v 40 m/sShaft centre distance e 1600 mm

Arc of contact on smaller pulley b 150Effective pull to be transmitted by belt 5287 Nload factor 1.00Force determining selection of belt FB 5287 NSpecific effective pull F'U 42 N/mmoperating tension 2.1Type Extremultus Siegling 85/80 Type 40Flat belt width 126 mmStandard of belt width 160 mmsmallest pulley width b 180 mmBelt length l 5794 mmCentrifugal force factor 0.2Elongation at fitting e 2.3 %Shaft load static FWs 14720 NShaft load dynamic FWd 13440 N

Resume of flat belt drives design :Type Extremultus Siegling 85/80 Type 40Belt length l 5794 mmStandard of belt width 160 mmDiameter of turbine pulley 1190 mmDiameter of generator pulley 400 mmPulley width b 180 mmShaft centre distance e 1600 mm

Order Specifications :

pro-Rekayasa* Belt Calculation

Pb

d2

d1'

d1

(o)FU

C2

C4

b0'

b0

C5

b0

d1

d2

EXTREMULTUS Siegling 85/80 high-efficiency flat belt GT 40, 5794 x 160 mm, endless

Page 5: Turbine&Belt

Biaya Proyek Unit Quantity Jumlah

Peralatan Elektrikal Mekanik(E&M)Turbin Crossflow T14 unit 1 Rp 125,000,000 Generator Sinkron unit 2 Rp 165,000,000 Switchgear / Sistem Kontrol unit 2 Rp 105,000,000 Ballast Load: air heater unit 2 Rp 42,000,000 Transformer 160 kVA unit 1 Rp 30,000,000 Spare parts % 5.0 Rp 21,850,000 Aksesoris % 2.5 Rp 10,925,000 Pengangkutan dan Instalasi Ls 1.0 Rp 5,000,000

Subtotal I : Rp 504,775,000

Bangunan Sipil

Persiapan, mobilisasi dan demobilisasi Rp 22,500,000 Jalan Akses Rp 4,961,250 Intake Rp 5,612,856 Bak Pengendap Rp 67,774,055 Headrace Rp - Bak Penenang Rp 37,106,012 Spillway Rp 29,673,560 Penstock Rp 122,250,417 Powerhouse Rp 168,934,507 Tailrace/Saluran pembuangan Rp 31,859,624 Finishing Rp 5,850,000

Sub Total II : Rp 496,522,281

TransmisiTiang Rp 2,700,000 Kabel Rp 13,500,000 Instalasi Kabel Rumah Pembangkit Rp 1,000,000 Lain-lain (aksesoris, tools) Rp 7,500,000

Sub Total III : Rp 24,700,000 T o t a l (I + II + III) Rp 1,025,997,281

Lain-lain

Pembebasan Tanah 590 Rp 42,000,000 Keuntungan Kontraktor % 15 Rp 160,199,592

Sub Total : Rp 202,199,592 T o t a l Rp 1,228,196,873 Pajak Pertambahan Nilai, PPn 10% Rp 122,819,687 Grand Total Rp 1,351,016,561

Dibulatkan Rp 1,541,121,400 Terbilang :(Satu milyar lima ratus empat puluh satu juta seratus dua puluh satu ribuempat ratus rupiah)

pro-Rekayasa* Rekapitulasi Rincian Biaya

m2

Page 6: Turbine&Belt

Item of works Unit Quantity Unit Price Amount

Harga Satuan E&M, Transmisi

Peralatan Elektrikal - MekanikItem Unit Quantity Harga Satuan Jumlah

Turbin kW 100 Rp 1,250,000 Rp 125,000,000 Generator kVA 150 Rp 550,000 Rp 82,500,000 Switchgear / Control system kVA 150 Rp 350,000 Rp 52,500,000 Ballast Load: air heater kW 120 Rp 175,000 Rp 21,000,000

TransmisiItem Unit Quantity Harga Satuan Jumlah

Tiang unit 3 Rp 900,000 Rp 2,700,000 Underground cable, 20 kV m 0 Rp 200,000 Rp - Overhead line ASRC m 75 Rp 180,000 Rp 13,500,000 Sambungan PLN, kWH meter Ls 1 Rp 5,000,000 Rp 5,000,000 Instalasi Ls 1 Rp 2,500,000 Rp 2,500,000

Instalasi Kabel Rumah PembangkitItem Unit Quantity Harga Satuan JumlahJumlah Sambungan houses 1 Rp 1,000,000 Rp 1,000,000

Sub Total Rp 1,000,000

Page 7: Turbine&Belt

Harga Satuan Pekerjaan Sipil

I t em Koef. Unit Harga Satuan Jumlah Total Galian Rp 27,625

unskill labour 0.625 pers Rp 25,000 Rp 15,625 tools 1 ls Rp 12,000 Rp 12,000

Urugan Rp 16,300 unskill labour 0.192 pers Rp 25,000 Rp 4,800 tools 1 ls Rp 11,500 Rp 11,500

Isian Pasir Rp 93,750 sand 1.2 m3 Rp 75,000 Rp 90,000 unskill labour 0.15 pers Rp 25,000 Rp 3,750

Pondasi batu kosong Rp 161,813 stone 1.2 m3 Rp 70,000 Rp 84,000 sand 0.4 m3 Rp 75,000 Rp 30,000 unskill labour 1.125 pers Rp 25,000 Rp 28,125 skill labour 0.5625 pers Rp 35,000 Rp 19,688

Pasangan batu 1: 2 Rp 327,025 stone 1.2 m3 Rp 70,000 Rp 84,000 PC (semen) 3.52 zak Rp 32,500 Rp 114,400 sand 0.38 m3 Rp 75,000 Rp 28,500 unskill labour 2.25 pers Rp 25,000 Rp 56,250 skill labour 1.125 pers Rp 35,000 Rp 39,375 chief labour 0.1125 pers Rp 40,000 Rp 4,500

Pasangan batu 1: 3 Rp 295,175 stone 1.2 m3 Rp 70,000 Rp 84,000 PC 2.84 zak Rp 32,500 Rp 92,300 sand 0.4 m3 Rp 75,000 Rp 30,000 unskill labour 2.25 pers Rp 20,000 Rp 45,000 skill labour 1.125 pers Rp 35,000 Rp 39,375 chief labour 0.1125 pers Rp 40,000 Rp 4,500

Pasangan batu 1:4 Rp 296,875 stone 1.2 m3 Rp 70,000 Rp 84,000 PC 2.5 zak Rp 32,500 Rp 81,250 sand 0.42 m3 Rp 75,000 Rp 31,500 unskill labour 2.25 pers Rp 25,000 Rp 56,250 skill labour 1.125 pers Rp 35,000 Rp 39,375 chief labour 0.1125 pers Rp 40,000 Rp 4,500

Plesteran + acian Rp 26,031 PC 0.2368 zak Rp 32,500 Rp 7,696 sand 0.019 m3 Rp 75,000 Rp 1,425 medium skill labour 0.286 pers Rp 30,000 Rp 8,580 Skill labour 0.214 pers Rp 35,000 Rp 7,490 Chief labour 0.021 pers Rp 40,000 Rp 840

Bronjong Rp 145,150 Stone 1.2 m3 Rp 70,000 Rp 84,000 Wire cage 3.5 kg Rp 12,000 Rp 42,000 unskill labour 0.45 pers Rp 25,000 Rp 11,250 skill labour 0.2 pers Rp 35,000 Rp 7,000 foreman 0.02 pers Rp 45,000 Rp 900

pro-Rekayasa* Analisa Biaya

per m3

Page 8: Turbine&Belt

Harga Satuan Pekerjaan Sipil

I t em Koef. Unit Harga Satuan Jumlah Total

pro-Rekayasa* Analisa Biaya

per m3

Stoplogs Rp 172,100 Wood 0.048 m3 Rp 1,200,000 Rp 57,600 Carpenter 1 pers Rp 35,000 Rp 35,000 labour 2 pers Rp 25,000 Rp 50,000 foreman 0.1 pers Rp 45,000 Rp 4,500 tools 1 ls Rp 25,000 Rp 25,000

Lantai Kerja Rp 351,370 PC 3.956 zak Rp 32,500 Rp 128,570 Sand for concrete 0.55 m3 Rp 90,000 Rp 49,500 Split/gravel 0.93 m3 Rp 95,000 Rp 88,350 tools 1 ls Rp 15,000 Rp 15,000 labour 2 pers Rp 25,000 Rp 50,000 skill labour 0.5 pers Rp 35,000 Rp 17,500 chief labour 0.05 pers Rp 40,000 Rp 2,000 foreman 0.01 pers Rp 45,000 Rp 450

Reinforce concrete K225 ###PC 7.896 zak Rp 32,500 Rp 256,620 Split/gravel 0.81 m3 Rp 95,000 Rp 76,950 Sand for concrete 0.49 m3 Rp 90,000 Rp 44,100 Labour 3 pers Rp 25,000 Rp 75,000 Skill labour 0.5 pers Rp 35,000 Rp 17,500 Chief labour 0.05 pers Rp 40,000 Rp 2,000 foreman 0.01 pers Rp 45,000 Rp 450 tools 1 ls Rp 75,000 Rp 75,000 steel bar concrete 175 kg Rp 9,000 Rp 1,575,000 wire 2 kg Rp 9,000 Rp 18,000 labour for steel concrete 6.75 pers Rp 30,000 Rp 202,500 Chief for steel concrete 2.25 pers Rp 40,000 Rp 90,000 unskill labour 6.75 pers Rp 25,000 Rp 168,750 nail 4 kg Rp 7,500 Rp 30,000 carpenter 5 pers Rp 35,000 Rp 175,000 chief of carpenter 0.5 pers Rp 40,000 Rp 20,000 unskill labour 2 pers Rp 25,000 Rp 50,000 foreman 0.1 pers Rp 45,000 Rp 4,500

Page 9: Turbine&Belt

Rincian Biaya Pekerjaan SipilI t e m Unit Volume Harga Satuan Jumlah Total

Persiapan Pekerjaan Rp 22,500,000

1 Persiapan di lokasi ls 1.00 Rp 7,500,000 Rp 7,500,000

2 Mobilisasi dan demobilisasi ls 1.00 Rp 15,000,000 Rp 15,000,000

Pekerjaan Sipil Rp 474,022,281

1 Jalan Akses

a. Pengerasan jalan m 50.00 Rp 75,000 Rp 3,750,000

b. Jembatan penyebrangan m 15.00 Rp 65,000 Rp 975,000

h. Lain-lain % 5.00 Rp 236,250

sub total Rp 4,961,250

2 Intake

a. Galian tanah 2.19 Rp 75,000 Rp 164,063

b. Urugan tanah 0.22 Rp 65,000 Rp 14,219

c. Isian Pasir Lantai Kerja 0.26 Rp 93,750 Rp 24,609

d. Pondasi, batu kosong 0.77 Rp 161,813 Rp 124,596

e. Pondasi batu kali 1 : 2 3.23 Rp 327,025 Rp 1,057,599

f. Plesteran dan acian 8.75 Rp 26,031 Rp 227,771

g. Trashrack + Stop log Ls 1.00 Rp 4,000,000 Rp 4,000,000

sub total Rp 5,612,856

3 Bak Pengendap

a. Galian tanah 287.82 Rp 75,000 Rp 21,586,500

b. Urugan tanah 28.78 Rp 65,000 Rp 1,870,830

c. Isian Pasir Lantai Kerja 4.61 Rp 93,750 Rp 432,422

d. Pondasi, batu kosong 18.45 Rp 161,813 Rp 2,985,441

e. Pondasi batu kali 1 : 2 89.52 Rp 327,025 Rp 29,274,624

f. Plesteran dan acian 254.48 Rp 26,031 Rp 6,624,239

g. Pintu Kuras unit 1.00 Rp 5,000,000 Rp 5,000,000

sub total Rp 67,774,055

4 Headrace

a. Galian tanah 0.00 Rp 75,000 Rp -

b. Urugan tanah 0.00 Rp 65,000 Rp -

c. Isian Pasir Lantai Kerja 0.00 Rp 93,750 Rp -

d. Pondasi, batu kosong 0.00 Rp 161,813 Rp -

e. Pondasi batu kali 1 : 2 0.00 Rp 327,025 Rp -

f. Plesteran dan acian 0.00 Rp 10,000 Rp -

g. unit 0.00 Rp 172,100 Rp -

h. Lain-lain % 0.00 Rp -

sub total Rp -

5 Bak Penenang

a. Galian tanah 67.40 Rp 75,000 Rp 5,055,188

b. Urugan tanah 6.74 Rp 65,000 Rp 438,116

c. Isian Pasir Lantai Kerja 0.71 Rp 93,750 Rp 66,516

d. Reinforcement Concrete 1.30 Rp 2,876,870 Rp 3,745,685

e. Pondasi, batu kosong 2.84 Rp 161,813 Rp 459,224

f. Pondasi batu kali 1:2 27.07 Rp 327,025 Rp 8,853,384

g. Plesteran dan acian 48.79 Rp 10,000 Rp 487,900

h. unit 2.00 Rp 5,000,000 Rp 10,000,000

i. Trashrack Ls 1.00 Rp 8,000,000 Rp 8,000,000

sub total Rp 37,106,012

6 Spillway

a. Galian tanah 64.00 Rp 75,000 Rp 4,800,000

b. Urugan tanah 6.40 Rp 65,000 Rp 416,000

c. Isian Pasir Lantai Kerja 3.20 Rp 93,750 Rp 300,000

d. Pondasi, batu kosong 12.80 Rp 161,813 Rp 2,071,200

e. Pondasi batu kali 1:2 62.40 Rp 327,025 Rp 20,406,360

f. Plesteran dan acian 168.00 Rp 10,000 Rp 1,680,000

sub total Rp 29,673,560

pro-Rekayasa* Analisa Biaya

m3

m3

m3

m3

m3

m2

m3

m3

m3

m3

m3

m2

m3

m3

m3

m3

m3

m2

stop log/wood (80w x 100h) cm2

m3

m3

m3

m3

m3

m3

m2

Intake Gate(500w x 500h) cm2 x 3m

m3

m3

m3

m3

m3

m2

Page 10: Turbine&Belt

Rincian Biaya Pekerjaan SipilI t e m Unit Volume Harga Satuan Jumlah Total

7 Penstock

a. Galian tanah 2.97 Rp 75,000 Rp 222,750

b. Anchor block 11.00 Rp 350,000 Rp 3,850,000

c. Lantai Kerja PC : Ps 1 : 5 0.35 Rp 351,370 Rp 122,980

d. Isian Pasir Lantai Kerja 0.45 Rp 93,750 Rp 42,188

e. Plesteran dan acian 27.00 Rp 10,000 Rp 270,000

f. Penstock Setting 19.50 Rp 15,000 Rp 292,500

g. Penstock, dia 114 cm 20.00 Rp 1,800,000 Rp 36,000,000

h. Elbow/Bend pcs 2.00 Rp 200,000 Rp 400,000

i Saddle Support 3.00 Rp 350,000 Rp 1,050,000

j Inlet Valve/Gate pcs 2.00 Rp 40,000,000 Rp 80,000,000

sub total Rp 122,250,417

8 Under ground : Power house

a. Galian tanah 19.11 Rp 75,000 Rp 1,433,396

b. Urugan tanah 3.82 Rp 65,000 Rp 248,455

c. Isian Pasir Lantai Kerja 7.20 Rp 93,750 Rp 675,000

d. Lantai Kerja PC : Ps 1 : 5 0.60 Rp 351,370 Rp 210,822

e. Reinforcement Concrete 13.36 Rp 2,876,870 Rp 38,434,983

f. Pondasi, batu kosong 26.40 Rp 161,813 Rp 4,271,850

g. Pondasi batu kali 1:2 Rp 327,025 Rp -

h. Plesteran dan acian 216.00 Rp 10,000 Rp 2,160,000

sub total Rp 47,434,507

9 Power House

a. Bangunan 81.00 Rp 1,500,000 Rp 121,500,000

sub total Rp 121,500,000

10 Finishing

a. Painting : penstock 20.00 Rp 17,500 Rp 350,000

b. Painting : power house ls 1.00 Rp 1,500,000 Rp 1,500,000

c. Penataan area sekitar ls 1.00 Rp 4,000,000 Rp 4,000,000

sub total Rp 5,850,000

11 Tailrace

a. Galian tanah 120.74 Rp 10,000 Rp 1,207,360

b. Urugan tanah 12.07 Rp 65,000 Rp 784,784

c. Isian Pasir Lantai Kerja 5.49 Rp 93,750 Rp 514,500

d. Pondasi, batu kosong 21.95 Rp 161,813 Rp 3,552,108

e. Pondasi batu kali 1:2 71.34 Rp 327,025 Rp 23,331,272

f. Plesteran dan acian 246.96 Rp 10,000 Rp 2,469,600

sub total Rp 31,859,624

T O T A L Rp 496,522,281

m3

m3

m3

m3

m2

m1

m1

m3

m3

m3

m3

m3

m3

m3

m3

m2

m2

m1

m3

m3

m3

m3

m3

m2