Tunnels Poor Rock

download Tunnels Poor Rock

of 8

Transcript of Tunnels Poor Rock

  • 7/31/2019 Tunnels Poor Rock

    1/8

    DESIGN AND CONSTRUCTION OF TUNNELSIN POOR AND FAULTED ROCK MASSES

    W. Schubert

    Graz University of Technology([email protected])

    Abstract

    In weak or faulted rock and high overburden considerable displacements occur during excavation of tunnels and galleries. In mostcases the behaviour of the ground is not ductile, but governed by different failure modes. In the design stage it is important toidentify potential failure modes under the given boundary conditions to be able to select appropriate construction methods. Aparticular problem under such conditions is that the strains developing often exceed the deformability of standard linings,frequently leading to severe damages and the necessity of costly repairs. To allow for safe and economical tunnel construction,strategies have to be used, which guarantee support characteristics compatible with the strains, and at the same time utilize thesupports as much as possible. Recent developments of ductile elements used in combination with shotcrete and rock bolts areshown, and their efficiency reviewed. For the design of such supports the development of the expected displacements must bepredicted and the time dependent properties of shotcrete considered.Special tools to predict displacements and a relatively simple analysis method to design shotcrete linings with integrated yieldingelements, based on expected displacements and the transient lining properties are presented.The methods described in this paper have been successfully used in the European Alps and on other projects around the world.

    Keywords : Tunnel, weak rock, ductile supports, time dependent properties of linings.

    1. Introduction

    The huge number of tunnels constructed duringthe last decades has led to the accumulation of considerable experience. Due to improvedinvestigation and modelling methods theconstruction of tunnels under adverse conditionshas become safe and efficient. The inherentinaccuracies in the geological and geotechnicalmodels, as well as the simplifications in theanalysis tools also play a role in the success of aproject.

    Experience in tunnel construction in poor andfaulted rocks under high overburden still islimited. However, with the construction of longbasis tunnels those conditions are met quitefrequently. A serious challenge is theheterogeneity of brittle faults, as well as thelarge, anisotropic and in many cases long lastingdeformations [1]. In addition, with highoverburden the exact location and properties of fault zones usually are unknown, requiringcontinuous updating of the ground model duringconstruction, as well as an adjustment of the

    construction methods to the actual conditions.Advanced exploration and monitoring methodsare required to recognize changes in the groundquality in time, allowing for a timely adjustmentof excavation and support.

    Special attention has to be paid to anappropriate estimation of displacementmagnitudes and its timely development. The sizeof the excavation has to allow for the expecteddisplacements without impairing the clearanceprofile. When displacements are underestimated,extremely costly reshaping is required. On theother hand, the timely development of thedisplacements can play a major role in theutilization of the lining capacity in case shotcreteis used.

    Conventional supports often are not able tosustain the large imposed strains. In the past thisproblem has been addressed by leaving opengaps in shotcrete linings. More recently theintegration of ductile elements into linings hasbecome common practice on many projects.

  • 7/31/2019 Tunnels Poor Rock

    2/8

    2. Design

    Designing tunnels with low cover and uncertainground properties, one can simply increase thelining thickness or quality to obtain a reasonablefactor of safety even under adverse conditions.This is not a viable approach when expectinglarge displacements under high cover. In suchcases, much care has to be taken in the selectionof the models and the input parameters.

    2.1. Modeling methods

    Frequently the concept of the ground reactioncurve is used for the pre-design of tunnels. Thisapproach is useful for an estimate of theexpected displacements. The combination of theground reaction curve with supports isquestionable, as supports are activated by thedisplacements, and are no active support loadson the perimeter. The question of pre-relaxationprior to installation of support is discussedbelow.

    To save time, it is still common practice to use2D numerical models for the design of tunnels.One of the problems with 2D numericalsimulations is the selection of proper pre-relaxation or load reduction factors. In manycases, the equivalent support pressure prior toinstallation of support is chosen with somethinglike 0.7, leading to an overestimation of liningload and effect of the support. It has shown thatfor poor ground failure occurs already ahead of the face [2], influencing the development of

    displacements. An empirical relationshipbetween ground quality, ground stress, andtunnel size was developed by Pilgerstorfer [3].He used 3D numerical simulations to determinethe development of the displacements, and thenback calculated the equivalent support pressurewith closed form solutions. It showed that for anunfavorable ratio between stress and groundstrength the equivalent support pressure factor atthe tunnel face can reach values of 0.2 and less.

    The application of those relationships allows

    realistically evaluating the development of displacements and loading of the lining for ratheruniform ground conditions with 2D simulations.In case of a strongly heterogeneous ground, withblocks or stiffer rock mass embedded in a softmatrix, a three dimensional modeling will beunavoidable, as 2D models may providemisleading results.

    When deciding whether a 2D or 3D model isrequired, following effects have to beconsidered: Arching within fault zones can develop up to

    a certain critical length of a weak zone. Thisleads to a reduction in displacements within aweak zone, and additional loads in the betterground close to the weak ground [4].

    Stiff blocks or regions embedded in softmatrix may accumulate stresses during andafter tunnel excavation. Overloading andsubsequent brittle failure of those blocks orzones may be the result.

    An important issue is also if a continuous modelis appropriate, or joints and other rock massfeatures have to be modelled explicitly. In allcases, where the behaviour is dominated by

    shearing along joints or joint opening, discretemodels will be required. This typically applies tofoliated rock mass, with the strike of the foliationparallel or sub parallel to the tunnel axis.Displacement characteristics and magnitudeswith different relative orientations betweenfoliation and tunnel axis can differ considerably[5].

    Another issue also rarely addressed insimulations is the time dependent developmentFigure 1. Back calculated equivalent support pressure

    coefficient for certain conditions [from 3]

  • 7/31/2019 Tunnels Poor Rock

    3/8

    of strength and deformability of shotcrete. Inmost cases linings are simulated as elasticmaterial, with a step wise increase of the elasticproperties, usually from 5.000 MPa to 15.000MPa and more. Simulations under considerationof time dependent shotcrete properties showedthat the fictitious E-modulus practically neverexceeds 5.000 MPa [6]. Only when ground andlining properties are chosen with care, we canspeak of a realistic model.

    2.2. Support options

    Tunnel supports on the one hand should provideas much resistance against deformation aspossible, on the other hand should be able tosustain the large imposed strains. Variousmethods have been developed over the decadesto cope with the difficulties.

    A traditional method in mining whenexperiencing large displacements was to use U-shaped steel sets with sliding couplings incombination with wire mesh or lagging. Inparticular in cases of anisotropic deformation the

    steel sets buckle, and costly and dangerousrepairs are required. Supports had to be replacedmany times until stabilization was reached.

    The improvement of the tunneling techniqueduring the nineteen sixties, in particular theincreased use of shotcrete and rock bolts,considerably reduced the problems in poorground. Severe problems with considerabledisplacements and destruction of the shotcretelining were experienced in a fault zone at theTauerntunnel in the Austrian Alps in the earlynineteen seventies [7]. To prevent the failure of the shotcrete, open deformation slots were left in

    the lining, which closed with deformation. Incombination with a dense bolting, this conceptworked quite well. The same concept was laterused at the Arlbergtunnel [8], theKarawankentunnel [9] and Inntaltunnel [10, 11]in western Austria with quite some success.

    A serious collapse during the excavation of the Galgenbergtunnel in a very heterogeneousfault zone showed that this type of support israther vulnerable to rapidly developing loads in

    the excavation area. As a consequence of theaccident, ductile lining systems were developedwith the aim to provide as much supportresistance as possible, but on the other handguaranteeing that the linings are notoverstressed. Several systems of yieldingelements presently are on the market, some usingsteel, others using cement based materials. Acomparative study recently showed that the LSC(Lining Stress Controller) system is easiest tocontrol and has the highest efficiency [12]. Itconsists of a set of steel tubes, which are loadedaxially. Special provisions allow a rather softinitial response, accounting for the low strengthof young shotcrete. The system easily can beadjusted to the project specific requirements bycombining different numbers and types of tubes.Special software is used for the determination of the layout of the elements, considering expecteddisplacement development, time dependent

    Figure 2. Yielding elements of the type LSC integratedin a shotcrete lining at the Tauerntunnel. Photo:Vergeiner

    0,00

    0,20

    0,40

    0,60

    0,80

    1,00

    0 1 2 3 4 5 6 7 8 9 10

    time (days)

    s t r e s s

    i n t e n s

    i t y

    Figure 3. Utilization rate of the lining versus time for a 4-tubeLSC element; tunnel diameter 10 m, final radial displacementsabout 300 mm

  • 7/31/2019 Tunnels Poor Rock

    4/8

    shotcrete properties, and advance rate.

    In general in Alpine tunnels in poor and faultedground, the ductile shotcrete support issupplemented by lattice girders, and rock boltingin considerable density. The length of the boltsranges from 1/2 to 2/3 of the tunnel diameter.The density of the bolts is influenced by theground structure and the relative orientationbetween main geological features and the tunnelaxis. The density commonly is in a range of 1 to2 pieces per square meter. As a rule, the strike of

    foliation parallel or sub parallel to the tunnel axisis more unfavourable, than a strike perpendicularor in an oblique angle to the tunnel axis.

    An important factor for the performance of grouted bolts, which are subject to largedisplacements, is the rib geometry. Investigationsshowed that with wider rib spacing the efficiencyof the bolts considerably increases [13, 14].

    Figure 4 shows the results of laboratory testson bolts with different rib geometries. The boltswere pulled with a constant displacement rate,while the grout was still fresh, as is the case alsoin nature. It showed that with small rib spacingthe grout easily is sheared of, resulting in a lowcapacity of the bolt. From this example it can beseen that for tunnels under difficult conditionsalso apparently minor details can have a bigimpact on the success.

    2.3. Construction sequence

    Face stability problems in many cases areassociated with poor ground conditions.Basically two approaches exist to cope with thisproblem. One is a heavy support of the face,frequently with glass fibre bolts in case of fullface excavation. The other approach is to make asequential excavation. As the required facesupport increases exponentially with the heightof the face, in most cases the sequentialexcavation is more economical and quicker.

    3. Detailed design during construction

    The uncertainty in the geological models and thevariability of the ground quality within a faultzone require a continuous updating of the groundmodel during construction. With the updatedmodel, the final layout of excavation and supportcan be done.

    3.1. Prediction of ground quality ahead of the face

    Prediction of the ground quality ahead of theface is essential for choosing appropriateexcavation dimensions and support type andquantity.

    Probing ahead by core drillings is costly andtime consuming. Thus such methods are used inexceptional cases only. Geophysicalinvestigation ahead of the face definitely haspotential, but still is not developed to a statewhich would allow a reliable prediction.

    A very efficient method for predicting groundconditions by evaluating data from 3Ddisplacement monitoring has been developedmore than ten years ago [15,16, 17]. The basicidea behind the evaluation method is rathersimple. As long as there is no major change inthe ground volume affected by the excavation,the displacement characteristics will be similar.As soon as the stress distribution changes due tothe influence of zones of different quality, thedisplacement pattern will change. In case weak material is ahead, the displacement vector willrotate against the direction of excavation. A

    -250

    -200

    -150

    -100

    -50

    00 4 8 12 16 20 24 28 32 36

    Time [h]

    p u l

    l o u

    t f o r c e

    [ k N ]

    cs=13,7 mm

    cs=27,4 mm

    cs=54,8 mm

    Grout Type AM 500/1 Disp. Rate 0.012 mm/min-250

    -200

    -150

    -100

    -50

    00 4 8 12 16 20 24 28 32 36

    Time [h]

    p u l

    l o u

    t f o r c e

    [ k N ]

    cs=13,7 mm

    cs=27,4 mm

    cs=54,8 mm

    Grout Type AM 500/1 Disp. Rate 0.012 mm/min

    Figure 4: Results of laboratory tests on grouted boltswith different rib spacing; Displacement was imposed onthe bolt, while the grout was setting [13]

  • 7/31/2019 Tunnels Poor Rock

    5/8

    change to stronger rock mass ahead shows in arelative rotation of the displacement vector intothe direction of excavation.

    Recently systematic evaluation of site dataand numerical simulations has been used todevelop a catalogue of characteristicdisplacement trends for standard geotechnicalconditions [18]. The expert knowledge will beused to develop an automated data evaluationand interpretation tool. Typical displacementtrends for an excavation through heterogeneousground can be seen in Figure 5. Site applicationshowed that this method is relatively reliable.

    Besides there are no additional costs, as themeasurement data are available in any case. Tomake at least qualitative predictions only a fewadditional evaluations need to be made. Figure 6shows monitoring results from a tunnel inwestern Austria, where the change in thedisplacement vector orientation clearly indicatedthe change in the ground conditions well aheadof the transition.

    Naturally, no precise prediction of the extentof a zone of different properties or the exact

    quality of the ground ahead can be made. Thetool in combination with other evaluations and

    engineering judgment should be used to beprepared for changes in the ground conditions. Atimely alert can ease preparations, and thus savea lot of repair works.

    3.2. Prediction of displacements during construction

    In weak ground not only the final magnitude of the displacements is of importance, but also thedevelopment with face advance and time, as thiscontrols the lining load development.

    Guenot et al. [19] and Sulem et al. [20] pro-posed analytical functions that describe

    Figure 5. Typical development of displacement trendswhen tunnelling through heterogeneous ground [18]

    Figure 6. Plot of crown settlements (top), anddisplacement vector orientation (bottom) along a tunnelsection. The change in the displacement vectororientation indicates the change in the groundconditions.

  • 7/31/2019 Tunnels Poor Rock

    6/8

    displacements in a plane perpendicular to thetunnel axis as a function of time and the faceadvance. Barlow [21] and Sellner [22] modifiedthis approach. The displacement behaviour of therock mass and support basically is representedby four function parameters. Two parameters (T,m) are used to simulate time dependency and theother two parameters (X, C) the face advanceeffect. With curve fitting the characteristics of the displacements can be determined.Extrapolating the parameter trends, thedisplacements can be predicted even for sectionsahead of the face, using also the informationfrom the evaluation of the monitoring data asdescribed above. Add-ons to the predictionmodule allow an assessment of the effect of different linings and construction sequences.Sellner has developed a user friendly code forthe prediction of displacements (GeoFit [23]).

    The predicted displacements can also be usedto estimate the expected utilization of the liningcapacity. This for example is very valuable whenthe decision has to be made if a closed lining isstill appropriate or the integration of yielding

    elements is required. Thus one is in a position toadjust the support to the expected behavior.

    3.3. Check of System Behaviour

    Once a section has been excavated, the systembehaviour has to be monitored to see if it iswithin acceptable limits. Again here thecomparison between predicted with the actuallymeasured displacements using the sameprocedure is very important [Figure 7].Deviations from the expected behaviour can beeasily detected, also in cases of varying

    excavation rate. This is particularly important inheterogeneous ground, where deviations fromthe ideal behaviour can indicate changes in theground conditions, or beginning failures in theground or support.

    Preconditions for a successful use of monitoringdata for prediction of displacements and groundconditions ahead of the face, as well as check of the system behaviour are 3D measurements withhigh quality and consistency. A certain problem

    still is the limited availability of geotechnicalengineers, trained in the use of those tools.

    3.4. Site organization and constructionquality

    It should be stressed that tunnelling in difficultgeotechnical conditions requires perfect siteorganization and construction quality. The sitehas to be organized in a way that responsibilitiesare clear, and evaluation and interpretation of themonitoring data is done sufficiently rapid inrelation to the possible evolution of the system.Contingency measures and actions shall beplanned for cases where the system behaviourexceeds acceptable limits. This contingency plan

    Figure 7. Comparison of predicted and measureddisplacements on a tunnel with a top heading benchexcavation sequence and a temporary top heading invertwith the code GeoFit

    Figure 8. Top heading at the second tube of theTauerntunnel with four rows of ductile elementsintegrated in the shotcrete lining. Photo: Vergeiner

  • 7/31/2019 Tunnels Poor Rock

    7/8

    shall continuously be updated, as the experiencewith the system behaviour increases.

    Needless to say that difficult groundconditions besides experienced engineers fordesign and on site also require experiencedminers, who can produce the best possiblequality.

    4. Conclusion

    Tunnelling in poor ground with high overburdenis a real engineering challenge. Usualengineering approaches, like increasing thestructures` capacity or dimension does notprovide satisfactory results. Quite in contrast, thedamage and loss are even bigger, when one triesto suppress displacements under such conditions.The means economically available simply are notsufficient to cope with the energy inherent in thesystem. For an economical and safe tunnelling,the design of excavation and support has to berobust in a way that a wide variation indisplacement magnitudes and characteristics canbe covered. Ductile elements incorporated in the

    lining have shown to be effective, if the rightsystem is chosen, and the detailed adjustment isdone on site.

    The design of tunnels in poor ground and highoverburden requires more attention than forproject with average conditions. Timedependent ground and support properties,heterogeneity of the ground, and largedisplacements require a thorough and realisticmodeling.

    Tools have been developed for prediction of displacements and check of the system behavior.The application on a great number of projectshas shown the reliability of the tools, as well asthe capacity to support the site engineers in theirdecisions.

    Essential for successful tunneling in suchconditions also is the availability of qualified sitestaff, a flexible contract setup and a siteorganization which enables quick decisions.

    Considerable effort was put into the collectionand generation of expert knowledge.Appropriately used, this will assist in making

    decisions in design and construction of tunnels inpoor ground.

    References

    1. Schubert, W. & G. Riedmller. 2000.Tunnelling in Fault Zones - State of the Art inInvestigation and Construction. Felsbau 18, Nr.2: 7-15. Verlag Glckauf, Essen .

    2. Hoek, E., C. Carranca-Torres, M. Diederichs,B. Corkum, 2008. Integration of geotechnicaland structural design in tunnelling. ProceedingsUniversity of Minnesota 56 th AnnualGeotechnical Engineering conference . 1-53

    3. Pilgerstorfer, T. 2008. Prediction of displacement development using closed formsolutions. Diploma thesis, Institute of Rock Mechanics and Tunnelling, Graz University of Technology

    4. Schubert, W., K. Grossauer, E.A. Button.2004. Interpretation of Displacement MonitoringData for Tunnels in Heterogeneous Rock Mass.

    International Journal of Rock Mechanics and Mining Sciences, Vol. 41(2004), No. 3, Special Issue : 538-539. Elsevier

    5. Goricki, A., E.A. Button, W. Schubert, M.Ptsch, and R. Leitner, 2005. The Influence of Discontinuity Orientation on the Behaviour of Tunnels - Basics and Case Histories. Felsbau 23,

    Nr. 5 : 12-18, VGE

    6. Leitner, R., 2005. Numerical investigation onfailure mechanisms and function of tunnel

    support systems. Diploma thesis, Institute of Rock Mechanics and Tunnelling, GrazUniversity of Technology

    7. Pchhacker, H. 1974. ModernerTunnelvortrieb in sehr stark druckhaftemGebirge. Porr Nachrichten 57/58

    8. John, M. 1980. Construction of the Arlbergexpressway tunnel tube. Tunnels and Tunnelling

  • 7/31/2019 Tunnels Poor Rock

    8/8

    International 12 (5) , 45-50

    9. Schubert, P. and Marinko, T., 1989. Vortriebdes Karawankentunnels im tektonisch stark beanspruchten Sdabschnitt. Felsbau 7, Nr. 2 ,65-68

    10. Schubert, W. 1993. Erfahrungen bei derDurchrterung einer Grostrung imInntaltunnel. Felsbau 11 Nr.6 : 287-290. Essen ,

    VGE.

    11. Schubert, W. 1993. Importance of ShotcreteSupport in Squeezing Rock. In Kompen, R.,Opsahl, O., Berg, K. (eds), Sprayed Concrete-

    Modern use of wet mix and sprayed concrete for underground support; Proc. intern. symp.,Fagernes, Norway: 277-282. Oslo: NorwegianConcrete Association.

    12. Schubert, W. 2008. Design of DuctileTunnel Linings. Proceedings of 42nd US Rock

    Mechanics Symposium and 2nd U.S.-Canada

    Rock Mechanics Symposium (CD ), paper ID 08-146

    13. Blmel, M. 1996. Performance of groutedbolts in squeezing rock. In Barla, G. (ed.),Prediction and Performance in Rock Mechanicsand Rock Engineering; Proc. EUROCK '96 , Vol.2: 885-891. Rotterdam: A.A. Balkema.

    14. Blmel, M., H.F. Schweiger, and H. Golser,1997. Effect of rib geometry on the load bearingcapacity of grouted rock bolts. In Golser, J.,

    Hinkel, W., Schubert, W. (eds), Tunnels for People; Vol. 1: 127-132. Rotterdam: A.A.Balkema.

    15. Schubert, W. and A. Budil. 1995. TheImportance of Longitudinal Deformation inTunnel Excavation. In Fujii, T. (ed.), 8th

    International Congress on Rock Mechanics;Proc., Tokyo, Japan, 1411-1414. Rotterdam:A.A. Balkema.

    16. Steindorfer, A. 1997. Short term predictionof rock mass behaviour in tunnelling usingadvanced analysis of displacement monitoringdata. pp 111. In Riedmller, Schubert &Semprich (eds), Gruppe Geotechnik Graz, Heft1.

    17. Grossauer, K., W. Schubert. 2008. Analysisof tunnel displacements for geotechnical shortterm predictions. Geomechanik und Tunnelbau

    1, Nr. 5 . Berlin, Ernst & Sohn

    18. Grossauer, K., G. Lenz. 2007. Is it possibleto Automate the Interpretation of DisplacementMonitoring Data? Felsbau 25, Nr. 5 , 99-106.Essen: Verlag Glckauf.

    19. Guenot, A., Panet, M. & Sulem, J. 1985. ANew Aspect in Tunnel Closure Interpretation. In

    Ashwoth, E. (ed). Re-search and Engineering Applications in Rock Masses. Proc. 26th US Symposium on Rock Mechanics, Rapid City,South Dakota, 26-28 June, 1985: 445-460.

    Rotterdam: Balkema.

    20. Sulem, J. Panet, M. & Guenot, A. 1987.Closure analysis in deep tunnels. In Int. Journalof Rock Mechanics and Mining Science 24 : 145-154. Amsterdam: Elsevier.

    21. Barlow, J.P. 1986. Interpretation of TunnelConvergence Measurements. MSc Thesis, Dep.of Civil Engineering, University of Alberta,Canada.

    22. Sellner, P.J. 2000. Prediction of Displacements in Tunnelling. Ph.D. Thesis, GrazUniversity of Technology, Austria. In Schubert,

    Riedmller & Semprich (eds.). Schriftenreihe der Gruppe Geotechnik Graz , Heft 9.

    23. http://www.3-g.at/geofit