TUN 1
-
Upload
p-allen-samuel-ignatius -
Category
Documents
-
view
219 -
download
5
description
Transcript of TUN 1
Report for Karwar Tunnel Noble Geo-Structs Project No. S 16029August 31, 2015
PROJECT DESCRIPTION: ...................................................................................................... 2
SCOPE OF WORK: ................................................................................................................. 3
L-SECTION OF TUNNEL: ....................................................................................................... 3
4
4
GEOLOGY OF KARWAR: ....................................................................................................... 5
GEOTECHNICAL APPRAISAL: .............................................................................................. 9
COMMENTS ON THE QUALITY OF THE ROCK: ................................................................ 12
COMPARISION OF DESIGN PARAMETERS: ..................................................................... 12
FINITE ELEMENT ANALYSIS: ............................................................................................. 14
PLAXIS ANALYSIS: .............................................................................................................. 15
ANALYSIS AND REVIEW OF DESIGN OF TEMPORARY LINER COMPONENTS: .......... 18
SUPPORT SYSTEM ANALYSIS: .......................................................................................... 18
1
Report for Karwar Tunnel Noble Geo-Structs Project No. S 16029August 31, 2015
PROS AND CONS OF PROVISION: ..................................................................................... 20
CONSTRUCTION METHODOLOGY: .................................................................................... 22
ADEQUACY OF TUNNEL SUPPORT: .................................................................................. 23
EXECUTIVE SUMMARY: ...................................................................................................... 24
APPENDIX I CORE LOGS .................................................................................................... 27
APPENDIX II .......................................................................................................................... 29
2
Report for Karwar Tunnel Noble Geo-Structs Project No. S 16029August 31, 2015
PEER REVIEW OF TUNNEL DESIGN REPORT OF NH 17 KM 93 TO KM 283.300
INTRODUCTION:
PreambleThe twin tube tunnels at Karwar are proposed under 4 laning of Goa/Karnataka Border –
Kundapur section of NH 17 Project. The proposal reduces the length of highway from 4 km
to 2 km with tunnels. The tube tunnels provide a clear minimum width of 8.5m and minimum
vertical clearance of 5.5m. The overall width is 11.5 m. The clear distance between tunnels
is 20m. The alignment is straight having longitudinal gradient of 0.5%.
PROJECT DESCRIPTION:
The details of Tunnels are tabulated below: Figures in parenthesis represent tender stage
considerations.
Table Approximate chainages and lengths of proposed Tunnel 1
Sr. No. DescriptionEast
Tube
Length
(m)
West
Tube
Length
(m)
Total
Length (m)
Starting
Chainage
km
Ending
Chainage
km
Starting
Chainage
km
Ending
Chainage
km
1 Tunnel 1107.000
(106.985)
107.223
(107.185)
223
(200)
106.990
(106.962)
107.209
(107.196)
219
(234)
442
(434)
2 Tunnel 2107.483
(107.470)
107.815
(107.820)
332
(350)
107.490
(107.465)
107.804
(107.825)
314
(360)
646
(710)
Total
Length
1088
(1144)
Table Approximate chainages and lengths of proposed tunnel 2
Sr. No. DescriptionEast
Tube
Length
(m)
West
Tube
Length
(m)
Total
Length (m)
3
Report for Karwar Tunnel Noble Geo-Structs Project No. S 16029August 31, 2015
Starting
Chainage
km
Ending
Chainage
km
Starting
Chainage
km
Ending
Chainage
km
1 Tunnel 1106.991
(106.985)
107.223
(107.185)
232
(200)
106.980
(106.962)
107.209
(107.196)
229
(234)
461
(434)
2 Tunnel 2107.483
(107.470)
107.815
(107.820)
332
(350)
107.490
(107.465)
107.804
(107.825)
314
(360)
646
(710)
Total
Length
1076
(1144)
Detailed soil investigation is conducted by M/s Soil Tech India Pvt. Ltd. taking boreholes. In
all 3 boreholes have been drilled. Broad geological details of the stretch are inferred from the
same and from the report “Design consultancy services of 4 laning Goa/Karnataka border-
Kundapur section of NH-17 from km 93.7 to km 283.300 in state of Karnataka” by
consultants M/s Aarvee associates Pvt. Ltd., Concessionaire M/s IRB West Coast Tollway
Pvt. Ltd., Independent Engineer M/s AECOM Rodic Consultants Pvt. Ltd. The design based
on above data is reviewed here.
SCOPE OF WORK:
To review tunnel design with special reference to following aspects:
Analysis and review of design of temporary liner components
Pros and cons of provisions
Construction methodology
Adequacy of Tunnel Support.
L-SECTION OF TUNNEL:
The L section depicting overburden is shown below for east and west tubes
.
4
Report for Karwar Tunnel Noble Geo-Structs Project No. S 16029August 31, 2015
L-section THROUGH: EAST TUBE
5
Report for Karwar Tunnel Noble Geo-Structs Project No. S 16029August 31, 2015
L-section THROUGH: WEST TUBE
GEOLOGY OF KARWAR:
The coastline of Karwar is arc shaped with intermittent rocky and sandy beaches (fig 1). The
main land has three major landforms namely, coastal, fluvial and denudation plains. The
coastal landforms are sandy and rocky beaches, tidal flats and estuaries. The fluvial
landforms are river Kali, flood plains of Kali River and channels. The denudation landforms
are mountains and pediplains.
6
Report for Karwar Tunnel Noble Geo-Structs Project No. S 16029August 31, 2015
Fig. 1: Geomorphology of Karwar mainland
7
Report for Karwar Tunnel Noble Geo-Structs Project No. S 16029August 31, 2015
Karwar islands are tropical with steep rock hills of about 20 – 60m height jutting out of the
sea. The coast of the islands is rocky and there are pockets of beaches in Kangigudda
slands due to accretion process (Fig 2). There are no sand-dunes. Migmatitic gneiss and
Granitoid with basaltic dykes are the rock types that constitute the hills of Karwar islands
with intermediate lateritic soils.
Fig 2: Gemorphology of Karwar islnads and their panoramic view
The littoral zone of the islands is dominated by silt followed by sand and clay; the carbon
content ranges from 0.033% to 3.7% and organic matter varies from 0.06% to 6.4%. The soil
types of the Karwar islands are alluvial and lateritic. The soil represent typical tropical
fericrete.
The shoreline of Karwar islands does not show any phenomenal change, but in the northern
portion of the mainland at the mouth of Kali river in the vicinity of Kurmagadagudda and
Shimisgudda islands and in southern coastline there are small changes in the coastline due
to erosion and accretion. Similarly Anjadeep and Shimisgudda islands having sandy
beaches show variation in the coastline. The rocky substratum of the islands and sandy
composite serve as ideal habitats for a variety of sessile and intertidal flora and fauna.
Geological InterpretationsThe area is predominantly occupied by rock types: granitic rocks, migmatites and granite
gneiss (PGC). These rocks are intruded by younger granites, dolerite and gabbro dykes.
Dykes of dolerite, gabbro are oriented N 55-800 W-S 550-800E.
Foliations’ are along N-S or N 200 W–S 200 E.
Three Lineament sets are along N 750–800W-S750-800 E, N 700E–S700W, N 300W–S 300E.
The geological map shows the rock type in Karwar to be granite.
8
Report for Karwar Tunnel Noble Geo-Structs Project No. S 16029August 31, 2015
Geological InterpretationsThe area is predominantly occupied by rock types: granitic rocks, migmatites and granite
gneiss (PGC). These rocks are intruded by younger granites, dolerite and gabbro dykes.
Dykes of dolerite, gabbro are oriented N 55-800 W-S 550-800E
Foliations’ are along N-S or N 200 W–S 200 E.
Three Lineament sets are along N 750–800W-S750-800 E, N 700E–S700W, N 300W–S 300E.
The borelogs and corelogs are shown next.
9
Report for Karwar Tunnel Noble Geo-Structs Project No. S 16029August 31, 2015
Based on geotechnical report the stratigraphy described below for Tunnel 1:
BH 1
DEPTH R.L
0
10 Soil and boulders.
12 Highly to moderately weathered granite gneiss of size medium to coarse grained and light in colour.
15.5 Moderately to slightly weathered granite gneiss with amphibolite enclave of size medium to coarse grained and light in colour
TUNNEL
32 Fresh granite gneiss of size medium to coarse grained and light in colour.
BH 2
DEPTH R.L
0
9 Soil and boulders.
10.5 Highly weathered granite gneiss of size fine grained and greyish in colour
14 Slightly weathered granite gneiss of size medium to coarse grained and light in colour
TUNNEL
15.5 Fresh granite gneiss of size medium to coarse grained and light in colour WITH AMPHIBOLITES
62 Granite gneiss of size medium to coarse grained and light in colour
BH 3
DEPTH R.L
0
2.7 Soil and boulders.
10
Report for Karwar Tunnel Noble Geo-Structs Project No. S 16029August 31, 2015
5 Weathered granite gneiss of size medium to coarse grained and
light in colour.
9.5 Fresh granite gneiss of size medium to coarse grained and light in colour
20 Fresh granite gneiss with vertical joints of size medium to coarse grained and light in colour also enclaves of amphibolites
TUNNEL
30 Fresh granite gneiss of size medium to coarse grained and light in colour.
11
Report for Karwar Tunnel Noble Geo-Structs Project No. S 16029August 31, 2015
GEOTECHNICAL APPRAISAL:
Based on the 3 boreholes test data for the tunnel
The RMR values
BH No. 1 2 3
Above crown 51 77 71
Tunnel 29 77 65
Below invert 55 77 66
The Q values
BH No. 1 2 3
Above crown 3.5 5 4.9
Tunnel .33 5 5
Below invert 4.03 5 5
The RQD values
BH No. 1 2 3
Above crown - 100 98
Tunnel - 100 76
Below invert 80 100 78
Joint sets seen in ‘Bore’ Photos
BH No. 1 2 3
Above crown 4 4 2
Tunnel 4 1 4
Below invert 4 4 2
12
Report for Karwar Tunnel Noble Geo-Structs Project No. S 16029August 31, 2015
UCS Values (MPa)
BH No. 1 2 3
Above crown 49 203 85
Tunnel 56 60 133
Below invert 123 40 133
K Values (Lugeons)
BH No. 1 2 3
Above crown 0.137 0 0.246
Tunnel 0.13 0.39 0
Below invert - 0
Table shows RMR values at Tunnel above crown and below invert. The Q values are given
in brackets.
Table RMR and Q Values
Location BH 1 BH 2 BH 3 BH 1 BH 2 BH 3
RMR Q
Above
crown
5177 71
(3) (5) (4.9)
Tunnel29 77 65
(0.33) (5) (5)
Below
invert
55 77 66(4) (5) (5)
13
Report for Karwar Tunnel Noble Geo-Structs Project No. S 16029August 31, 2015
Joint Pattern:
Joints sets seen in core box are as follows:
BH 1 at levels 16.0m, 9.0m, 8.0m
BH 2 at levels 18.0m, 13.0m, 9.0m.
BH 3 at levels 19.0m, 23.0m, 28.0m
14
Report for Karwar Tunnel Noble Geo-Structs Project No. S 16029August 31, 2015
COMMENTS ON THE QUALITY OF THE ROCK:
Comments quality of rock: The rock type is granite gneiss in all the boreholes. The
examination of RQD reveals that between RL 28 and 20 i.e. above crown the RQD values
are 70 to 100. The photos of the Borelogs confirm the above values. These values indicate
that fair to good quality as per IS code (11315 Part II).
UCS values between 28 and 20 RL are shown from BH1, BH2 and BH3 test results. These
values indicate the quality of rock as fair and good as IS code 13365 (Part I).
Permeability Values: The permeability values are less than 1 and joints are tight and gauge
filling is impervious at pressure 30m to 70m water head.
In the above crown portion the RQD varies from 70 to 100. This indicates the quality of rock
is fair and good as per IS code 11315 (Part II). The UCS values are in the range of 82 to 203
in the above crown portion. This shows the quality of rock as strong as per IS 13365 (Part I).
The RMR values shows in the above crown portion from 54 to 77. As per 13365 Part I
quality of rock as fair to good.
Q values are 5. This shows the rock is fair in nature.
RMR values: RMR values given are in the range of 54 to 77. The rock can be considered as
fair one, where as the description rock consider it as highly weathered in nature.
The design parameters selected based on statistical analysis for 90% and 50% occurrence
levels. The values selected are for these occurrence levels, is 36 MPa and 106 MPa.
The design is based on the geotechnical investigation report by Soil Tech Pvt. Ltd, Pune 6
bores in all are taken.
COMPARISION OF DESIGN PARAMETERS:
The deformation at crown is 0.06mm
The stresses observed at crown 0.261 kN/m2
Pillar shows stress level as 10.798 kN/m2
The depth of plastic zone is seen as 1.59m at crown.
Comparison of stresses observed in tunnel by PLAXIS 2D with Phase 2 software:
15
Report for Karwar Tunnel Noble Geo-Structs Project No. S 16029August 31, 2015
So analysis stands vetted
16
Report for Karwar Tunnel Noble Geo-Structs Project No. S 16029August 31, 2015
Tunnel 1
For design purpose, RMR value is considered as 60 for Tunnel, 50 for portals. GSI shall be
considered as 55 and 40 respectively for Tunnel and Portal.
The Q values are 8 – 10 tunnel portion and (1 – 3) in Portal portion, being the weakest
values. For design purpose, however, for North portal, Tunnel and South portal, Q values
shall be considered as 2, 6 and 3 respectively.
Based on the core box photos given in the geotechnical report the joints sets are
tabulated below along with graphs for BH 1, BH2 and BH3 of Tunnel 1:
17
Report for Karwar Tunnel Noble Geo-Structs Project No. S 16029August 31, 2015
Based on the Lugeon Value given in the geotechnical reports are tabulated below
along with graphs for BH 1, BH2 and BH3 of Tunnel 1:
18
Report for Karwar Tunnel Noble Geo-Structs Project No. S 16029August 31, 2015
FINITE ELEMENT ANALYSIS:
The FEA is carried out for 2 failures criteria using Phase2 software. Mohr-Coulomb and
Hoek-Brown. The k value -1 is selected for design. The method proposed is elastic analysis,
plastic analysis. Twin tunnels at a distance of 20m from each other were taken for review.
Following tables produced from “Design consultancy services of 4 laning Goa/Karnataka
border-Kundapur section of NH-17 from km 93.7 to km 283.300 in state of Karnataka”,
Tunnel 1 Design Report by consultants M/s Aarvee associates Pvt. Ltd., Concessionaire
M/s IRB West Coast Tollway Pvt. Ltd., Independent Engineer M/s AECOM Rodic
Consultants Pvt. Ltd are compared with the results obtained from PLAXIS 2D with given
material data.
PLAXIS ANALYSIS:
TUNNEL 1
Identification Granite 1 Granite 2 Granite 3
Identification number 1 2 3
Drainage type Non-porous Non-porous Non-porous
Colour
γunsat kN/m³ 28.20 28.50 28.10
γsat kN/m³ 28.20 28.50 28.10
E kN/m² 17.63E6 17.63E6 12.90E6
ν (nu) 0.2900 0.2800 0.3000
σci kN/m² 82.00E3 82.00E3 60.00E3
mi 29.00 29.00 29.00
GSI 45.00 72.00 40.00
D 0.000 0.000 0.000
ψmax ° 11.00 11.00 11.00
19
Report for Karwar Tunnel Noble Geo-Structs Project No. S 16029August 31, 2015
σψ kN/m² 0.000 0.000 0.000
Strength Rigid Rigid Rigid
Rinter 1.000 1.000 1.000
K0,x = K0,z Yes Yes Yes
K0,x 1.000 1.000 1.000
K0,z 1.000 1.000 1.000
Identification Lining
Identification number 1
Colour
Material type Elastic
Isotropic Yes
End bearing No
EA1 kN/m 5.700E6
EA2 kN/m 5.700E6
EI kN m²/m 19.00E3
d m 0.2000
w kN/m/m 4.800
ν (nu) 0.1700
20
Report for Karwar Tunnel Noble Geo-Structs Project No. S 16029August 31, 2015
Geometry of tunnel Principal effective stresses
Deformation Plasitc point
21
Report for Karwar Tunnel Noble Geo-Structs Project No. S 16029August 31, 2015
ANALYSIS AND REVIEW OF DESIGN OF TEMPORARY LINER COMPONENTS:
Sr. No.
Design Basis Impact
1 UCS values from geotechnical data are
subjected to statistical analysis. Values
that exceed 50% and 90% values are
picked up as 96 MPa and 35 MPa
respectively.
Such an approach leads to conservative
design. Incidences of such low values is a
‘localised’ event. Moreover, depth wise
UCS pattern is ignored
R eply: UCS values mentioned above are not related to BH 1.
2 UCS vs E Graph shows a negative
slope.
Such a trend is not common in rock
mechanics
Reply: The actual trend is modified by neglecting values which lead to a positive
slope. Since different models with mean and minimum values are considered for
assessing the rock mass behavior, it does not change the predicted rock mass
behavior in Phase 2 and Plaxis.
3RMR vs Q basis is not linear but ‘log’.
The axes are mismatch with realistic
values
Reply: The typographical mistake in figure 53 can be read with "Linear" as
"Logerthemic" and interchanging Q on X-axis and RMR on Y-axis.
4 Hoek and Brown and Mohr- Coulomb
failure models are selected.
Sensitively analysis shows different
response from both the methods
5 Check for variations of σ1 is affected
Hoek and Brown
Mohr-Coulomb
HB 90 is not appropriate
6Check for variations of σ3 is affected
Hoek and Brown, Mohr- CoulombHB 90 is not appropriate
22
Report for Karwar Tunnel Noble Geo-Structs Project No. S 16029August 31, 2015
Sr. No.
Design Basis Impact
Reply: Please elaborate how HB 90 is not applicable.
7 Check for variation of shear strain is
done
RMR, Q values tabulated show strange
pattern. RMR – 70, Q = 4, 14,ok
8 Maximum support pressure k = 1
Reply: Not applicable.
9 Approach used is
Reply: Approach used in Rocscience Phase 2 is already discussed in the report.
10 Grade of concrete M 25 is considered It’s ok
11 Grade of steel Fe 500 is considered It’s ok
12 Shotcrete M25 is considered It’s ok
13 F.R.C.S. M25 is considered It’s ok
14 Plastic analysis shows It’s ok
15 Hand calculation shows It’s ok
16 Earthquake calculation for Zone III. Adequate
23
Report for Karwar Tunnel Noble Geo-Structs Project No. S 16029August 31, 2015
SUPPORT SYSTEM ANALYSIS:
1This is required if rock is considered as
highly weathered
But the rock is not highly weathered as
indicted in design but it is of RMR 60.
2This is a provision for making the rock
mass homogeneous
This provision may be required in 20%
length of the tunnel not for the entire length
3Provision is indicated throughout length
of the tunnel.
The stress level indicates that only rock
bolts are adequate.
4 This enhances strength factor
Strength factor calculation show
contribution of rock bolt to be additional
provision
24
Report for Karwar Tunnel Noble Geo-Structs Project No. S 16029August 31, 2015
PROS AND CONS OF PROVISION:
Spilling:
In poor quality rock as seen in the BH-
1 spilling will assist in excavation
If the portal is shifted by 30m rock shall be fair
type and this provision is not necessary
Reply: If we shift the portal location,buildings above the tunnel will be affected and also
keeping in view of safety of D.C bungalow and highly jointed nature of rock mass and nil Q
values obtained above crown portion in the B.H 2, spiling has been provided in this stretch/
reach.
Shotcreting:
The Sealing and SFRS are provided.
In NATM method the rock strength
mobilized as well as shotcrete strength
are basis of liner design hence
required
This is bare minimum and if not provided leads
to rock falls in rock mass. However, thickness of
shotcrete has to be adequate enough to arrest
the, induced stresses.
Reply: The thickness of shotcrete is worked out as per design analysis keeping in view rock
mass nature and it is to state that the thickness provided is sufficient to take care any
induced stresses.
Steel Ribs:
Steel ribs are provided in the portal in
30m length
Considering rock quality provision for 5m length
shall be sufficient.
Reply: We have provided steel ribs for 25m length and not for 30m. Please refer tender
document Cl.4.19, which specifies 25m length at entry and exit of each tunnel will be
strengthened with RCC Portals. Accordingly it is proposed at all portal locations. Further it is
also suggested that tunnels were strengthened up to twice the tunnel diameter. Keeping in
view of the presence of DC Bungalow and mixed geology, steel ribs with pipe roofing have
been provided in between BH No's 1 & 2.
Rock Bolts:
Rock bolts are provided in the portal in
30m length, 4m long
Considering rock quality provision for 5m long
rock bolts shall be sufficient.
Reply: Rock bolts were provided in between steel ribs, to take care off any unstable wedge
failures.
25
Report for Karwar Tunnel Noble Geo-Structs Project No. S 16029August 31, 2015
Grouting:
It is considered as dry tunnel grouting
is not provided
Whereas seepage is to be arrested in rainy
season this provision in essential.
Reply: Normally on the round shaped granite hillocks, run off will be more than infiltration.
However, depending on seepage conditions through any adverse geological features
grouting needs to be done as per geologist/ designer's advice, during excavation.
Bottom strut:
For poor quality rock this is providedRMR and Q values below invert, however,
indicate not required
Reply: Rock quality below invert is very poor with Q values varying from 0.00- 0.33 as per
borehole data of BH 1 and 2. Numerical modelling has also indicated Invert heaving. As
such bottom strut is provided.
The provision of 200mm (SFRS): thick permanent lining is indicated
Liner is indicated to be provided even when in the 2nd tube excavation is in progress
This shall be required
Blasting induced cracks in SFRS are possible. Hence the permanent lining shall be deferred until all the excavation is complete, well over 70m in advancement.
Reply: Normally lining shall be taken up as per construction schedule. Safe distance
between blasting face and lined section shall be maintained as per established data for such
rock and specific blasting pattern.
SUGGESTIONS:
The rock bolts are required only in shattered zone by intersecting joints or vertical joints.
The rock mass requires reassessment of RMR during excavation and adequate support shall be provided.
Rework out the lining system as joints lineaments are entry points for rainwater which is considerably high in Karwar.
Provision of drainage system is essential.
26
Report for Karwar Tunnel Noble Geo-Structs Project No. S 16029August 31, 2015
CONSTRUCTION METHODOLOGY:
Portal:
NATM method is suggested for controlling deformation at ground. Active support system is
in the form of rock bolts, shotcrete and steel ribs. Single or double layer of spile umbrella is
suggested. Multiple heading method is suggested. For design, however top heading is
considered.
Tunnel
Chainage 106.99 km to 107.223 and chainage 106.980 to 107.209 Left tube sequence of
excavation is top heading excavation support system consisting of rock bolts and shotcrete,
followed by excavation of benching and installation of support viz rock bolts, shotcrete. This
is followed by final tunnel lining. After this same steps for right tube from chainage 106.99
km to 107.223 and chainage 106.980 to 107.209.
The above steps but with shotcrete and rock bolt thickness altered.
Seepage provision not there.
Comments:
The steel ribs in 30m length are not required and provision for 5m shall suffice.
Bolt length shall be 5m.
Full face excavation is possible with provision of temporary (initial) lining.
For collectors bungalow with the vibration control measures suggested additional measures
are not necessary.
27
Report for Karwar Tunnel Noble Geo-Structs Project No. S 16029August 31, 2015
ADEQUACY OF TUNNEL SUPPORT:
Adequacy of tunnel support is checked with respect to
Elastic Analysis
Plastic Analysis
Earthquake Analysis
And empirical relations.
The adequate modifications are suggested for taking care of the induced stress levels after the excavation in.
Precautions for collector’s Bungalow:
The cover over crown is more than 14m. As such, the effect vibrations has to be viewed in
the perspective of delay in blast energy during travel from R.L. 20 to G.L. following
precautions shall be useful.
Restricting charge per delay to not more than 4kg.
Presplitting the rock before blasting
Controlled full face blasting.
Measuring the vibration level (PPV) at collectors Bungalow and monitoring the charge levels suitably.
The rock quality is “FAIR” and appropriate initial lining is indicated
28
Report for Karwar Tunnel Noble Geo-Structs Project No. S 16029August 31, 2015
29
Report for Karwar Tunnel Noble Geo-Structs Project No. S 16029August 31, 2015
30
Report for Karwar Tunnel Noble Geo-Structs Project No. S 16029August 31, 2015
EXECUTIVE SUMMARY:
SUPPORTS SYSTEM FOR KARWAR ROAD TUNNEL1
Introduction:
Two parallel Tunnels – Tunnel No. 1 East Tube and Tunnel No. 1 West Tube are being
constructed on the Goa/Karnataka Border to Kundapur Section of NH 17. This report is for
re-assessment of the Tunnel Supporting System.
Location of Tunnels:
The Tunnels are 20 m apart and are staggered in plan as follows:
East Tube West Tube
North Portal Chainage, m 107,000 106,990
South Portal Chainage, m 107,223 107,209
Tunnel Length, m 223 219
Since the tubes are located only 20 m. and staggering is only to the extent of about 10 m.
the data revealed by exploratory boring along Common Centerline has been considered and
is alright.
Exploratory Bore Hole Data:
31
Report for Karwar Tunnel Noble Geo-Structs Project No. S 16029August 31, 2015
For design of Roof supporting system, least of the RMR Value i.e. least of RMR at tunnel
level and in zone 14 m. above crown is being considered as follows:
North Portal RMR 50 for 40 m. zone
South Portal RMR 60 for 40 m. zone
Tunnel RMR 60 for entire length
Existence of Collectors Bungalow above West Tube should not be a matter of concern.
Elevation of the bungalow is about 65 m. At that location, tunnel crown will be at an elevation
of about 19 m. Leaving a vertical gap of about 46 m. out of which hard rock will be 31 m.,
soft rock about 5 m. and top soil about 10 m. Rock has a very high RMR of 77 i.e. Good
Class. If controlled blasting is undertaken, the bungalow will not be damaged.
32
Report for Karwar Tunnel Noble Geo-Structs Project No. S 16029August 31, 2015
33
Report for Karwar Tunnel 1Noble Geo-Structs Project No. S 16029August 31, 2015
APPENDIX I CORE LOGS
Borelogs and Corelogs for Tunnel 1
34
Report for Karwar Tunnel 1Noble Geo-Structs Project No. S 16029August 31, 2015
35
Report for Karwar Tunnel 1Noble Geo-Structs Project No. S 16029August 31, 2015
36
Report for Karwar Tunnel 1Noble Geo-Structs Project No. S 16029August 31, 2015
37
Report for Karwar Tunnel 1Noble Geo-Structs Project No. S 16029August 31, 2015
38
Report for Karwar Tunnel 1Noble Geo-Structs Project No. S 16029August 31, 2015
39
Report for Karwar Tunnel 1Noble Geo-Structs Project No. S 16029August 31, 2015
40
Report for Karwar Tunnel 1Noble Geo-Structs Project No. S 16029August 31, 2015
41
Report for Karwar Tunnel 1Noble Geo-Structs Project No. S 16029August 31, 2015
42
Report for Karwar Tunnel 1Noble Geo-Structs Project No. S 16029August 31, 2015
43
Report for Karwar Tunnel 1Noble Geo-Structs Project No. S 16029August 31, 2015
44
Report for Karwar Tunnel 1Noble Geo-Structs Project No. S 16029August 31, 2015
APPENDIX II
FINITE ELEMENT ANALYSIS DATA USED FOR PHASE 2
Table 1: Selected Rock Mass Parameters for Numerical Analysis
Table 2: Properties of Rock Joints used for Numerical Analysis
45
Report for Karwar Tunnel 1Noble Geo-Structs Project No. S 16029August 31, 2015
Table 3: Computation of the ratio of Maximum principal stress to uniaxial compressive strength of intact rock
46
Report for Karwar Tunnel 1Noble Geo-Structs Project No. S 16029August 31, 2015
Table 4: Tensile strength as per Mohr-Coulomb failure criteria
Table 5: Support pressure requirements using bolts and steel ribs to resist the rock load for jointed model
Table 6: Support pressure requirements using bolts and shotcrete to resist the rock load for general model.
Shotcrete
47
Report for Karwar Tunnel 1Noble Geo-Structs Project No. S 16029August 31, 2015
Table 7: Rock mass properties for this analysis based on Hoek and Brown
Table 8: Rock mass Strength computations
Table 9: Equivalent rock mass properties
48
Report for Karwar Tunnel 1Noble Geo-Structs Project No. S 16029August 31, 2015
49
Report for Karwar Tunnel 1Noble Geo-Structs Project No. S 16029August 31, 2015
Table 10: Test results on intact rock samples of BH3 at km: 107.210
Table 11: Test results of cohesion and friction of rock mass
Table 12: Selected Rock Mass Properties for Numerical Analysis
50
Report for Karwar Tunnel 1Noble Geo-Structs Project No. S 16029August 31, 2015
.
51