Tulsa Fuel & Manufacturing Superfund Site Remedial Design and Cleanup Plans September 2014. Site Location. Located 1.3 miles south of downtown Collinsville 60 acres Bounded by: Garnett/RR to east Strip mine pit to south Acreage to west Faith Assembly Church to north. Site History. - PowerPoint PPT Presentation

Transcript of Tulsa Fuel & Manufacturing Superfund Site Remedial Design and Cleanup Plans September 2014

  • Tulsa Fuel & Manufacturing Superfund Site

    Remedial DesignandCleanup PlansSeptember 2014

  • Site LocationLocated 1.3 miles south of downtown Collinsville60 acresBounded by:Garnett/RR to eastStrip mine pit to southAcreage to westFaith Assembly Church to north

  • Site HistoryActive from 1914 1925Zinc Smelter and Lead RoasterFoundations and building footings remainPrivate Residence 1935 - 2002

  • Impacted AreasGreen-Areas that do not require cleanupPink-Areas that require cleanup to prevent unacceptable exposure through soil, sediment, and surface water

  • Site Cleanup GoalsSite remediation goals are protective of human health and the environmentImpacts above the remediation goals will be addressed along with visual waste

    Site-Specific PRGs by Medium COCSite-Specific PRGSoil, Residential (mg/kg) or (ppm)Arsenic37Cadmium75Lead500Soil, Nonresidential (mg/kg) or (ppm)Arsenic200Cadmium560Lead1,000Surface Water (g/L) or (ppb)Cadmium238Sediment (mg/kg) or (ppm)Arsenic181Cadmium813Lead500

  • Record of DecisionIssued November 2008The remedy is the consolidation and capping of soil, sediment, and waste

  • Proposed ROD AmendmentGroundwater impactsNo groundwater impactsEliminate state requirement or five foot separationTreatability StudyIndicated treatment not feasibleFuture Community ParticipationPublic comment period on proposed planPublic notice and open house

  • Remedial Design

  • Remedial DesignStormwater Management

  • Remedial Action

  • Proposed RA ScheduleUpon receipt of fundingProcurement of Contractor 60 daysPre-Construction Tasks 45 daysMobilization 6 monthsSite Restoration 4 monthsOperational and Functional 1 yearContract Closeout 30 days

  • RA ActivitiesSite MobilizationClear and GrubSoil and Sediment Erosion ControlDecontamination AreaDewatering the PondsWaste, Soil, and Sediment ConsolidationConfirmation SamplingRemove Existing Wells/Install O&M WellsSite Grading and SeedingDemobilization

  • Protective ElementsTransportation PlanAir MonitoringSite Management PlanStormwater Management

  • Operation and Maintenance

  • RA Completion

  • Community ParticipationSite documents can be found at:Collinsville Public LibraryOklahoma Department of Environmental QualityCentral Recordshttp://www.deq.state.ok.us/lpdnew/SF/TulsaFuels.htmUnited States Environmental Protection Agency

  • Questions or Comments?

    ******