Tuft’s Interlocking Early Works · 7/30/2018  · - Joe Nolan (City Point Partners) 2. Early...

14
1 Tufts Interlocking May 31, 2017 31-May-17 GLX Tufts Interlocking Early Works

Transcript of Tuft’s Interlocking Early Works · 7/30/2018  · - Joe Nolan (City Point Partners) 2. Early...

Page 1: Tuft’s Interlocking Early Works · 7/30/2018  · - Joe Nolan (City Point Partners) 2. Early Works Construction Overview and Schedule - Paul Hadley (MBTA) & Randy Henke (HNTB) 3.

1Tufts InterlockingMay 31, 2017

31-May-17

GLX Tufts Interlocking Early Works

Page 2: Tuft’s Interlocking Early Works · 7/30/2018  · - Joe Nolan (City Point Partners) 2. Early Works Construction Overview and Schedule - Paul Hadley (MBTA) & Randy Henke (HNTB) 3.

2Tufts InterlockingMay 31, 2017

Medford GLX Project Neighborhood MeetingMay 31, 2017; 6:30 PM – 7:30 PM

1. Welcome/Introductions - Joe Nolan (City Point Partners)

2. Early Works Construction Overview and Schedule - Paul Hadley (MBTA) & Randy Henke (HNTB)

3. Public Outreach & Contacting the Project - Joe Nolan (City Point Partners)

4. Upcoming Public Meetings

5. Q & A

Agenda

Page 3: Tuft’s Interlocking Early Works · 7/30/2018  · - Joe Nolan (City Point Partners) 2. Early Works Construction Overview and Schedule - Paul Hadley (MBTA) & Randy Henke (HNTB) 3.

3Tufts InterlockingMay 31, 2017

Future Track AlignmentCurrent Track Alignment

Tufts Interlocking

Page 4: Tuft’s Interlocking Early Works · 7/30/2018  · - Joe Nolan (City Point Partners) 2. Early Works Construction Overview and Schedule - Paul Hadley (MBTA) & Randy Henke (HNTB) 3.

4Tufts InterlockingMay 31, 2017

Future Track AlignmentCurrent Track AlignmentSignal Location

Page 5: Tuft’s Interlocking Early Works · 7/30/2018  · - Joe Nolan (City Point Partners) 2. Early Works Construction Overview and Schedule - Paul Hadley (MBTA) & Randy Henke (HNTB) 3.

5Tufts InterlockingMay 31, 2017

Signal House & Signal

Examples of Signal Equipment

Page 6: Tuft’s Interlocking Early Works · 7/30/2018  · - Joe Nolan (City Point Partners) 2. Early Works Construction Overview and Schedule - Paul Hadley (MBTA) & Randy Henke (HNTB) 3.

6Tufts InterlockingMay 31, 2017

Buried Duct Banks

Page 7: Tuft’s Interlocking Early Works · 7/30/2018  · - Joe Nolan (City Point Partners) 2. Early Works Construction Overview and Schedule - Paul Hadley (MBTA) & Randy Henke (HNTB) 3.

7Tufts InterlockingMay 31, 2017

Proposed Permanent Condition

Page 8: Tuft’s Interlocking Early Works · 7/30/2018  · - Joe Nolan (City Point Partners) 2. Early Works Construction Overview and Schedule - Paul Hadley (MBTA) & Randy Henke (HNTB) 3.

8Tufts InterlockingMay 31, 2017

Examples of Walls

Page 9: Tuft’s Interlocking Early Works · 7/30/2018  · - Joe Nolan (City Point Partners) 2. Early Works Construction Overview and Schedule - Paul Hadley (MBTA) & Randy Henke (HNTB) 3.

9Tufts InterlockingMay 31, 2017

Potential RoutesConstruction Equipment & Materials Traffic

Page 10: Tuft’s Interlocking Early Works · 7/30/2018  · - Joe Nolan (City Point Partners) 2. Early Works Construction Overview and Schedule - Paul Hadley (MBTA) & Randy Henke (HNTB) 3.

10Tufts InterlockingMay 31, 2017

Tufts Interlocking Schedule of Work for 2017Generally construction activities will occur weekdays from approximately 7:00 AM to 5:30 PM

Mobilize and Deliver Track Material• Ongoing June 2017

Site & Conduit Work• Grading required for utilities and new alignment of Track #1, Ongoing to late May/early June 2017

Installation of support of excavation, conduit and manholes• June to August 2017

Fine grading and install ballast mat for Track #2• September 2017

Construction of South Signal House and Retaining Wall • Work begins August 2017 through the Fall and then to resume in the Spring (March 2018)

*Due to the nature of construction, schedules are subject to change

Keolis Schedule*

Page 11: Tuft’s Interlocking Early Works · 7/30/2018  · - Joe Nolan (City Point Partners) 2. Early Works Construction Overview and Schedule - Paul Hadley (MBTA) & Randy Henke (HNTB) 3.

11Tufts InterlockingMay 31, 2017

1. Federal Transit Administration (FTA) Risk Refresh 1/25/17 -1/26/17 (Actual)

2. Issue Draft Request for Proposals for DB Shortlist 3/15/17 (Actual)

3. Hold One-on-Ones 3/28/17 – 5/10/17 (Actual)

4. Issue Final RFP 5/23/17 (Actual)

5. Alternative Technical Concept (ATC) Process 5/30/17 – 8/9/17

6. FTA Finance Plan Submission 5/31/17

7. Design Build Proposals Due 9/28/17

8. Bid Opening/Select Design Build Entity 11/28/17

9. Notice to Proceed to Design Build Entity 2/9/18

10. Project Completion 12/10/21

*Due to the nature of construction, schedules are subject to change

PROJECT SCHEDULE HIGHLIGHTS

Design Build Schedule*

Page 12: Tuft’s Interlocking Early Works · 7/30/2018  · - Joe Nolan (City Point Partners) 2. Early Works Construction Overview and Schedule - Paul Hadley (MBTA) & Randy Henke (HNTB) 3.

12Tufts InterlockingMay 31, 2017

• Contact the project

o GLX Email: [email protected]

o GLX Hotline: 1-855-GLX-INFO (24/7 coverage)

• Email blasts and GLX website updates (ongoing)

• Neighborhood database

o Sign-up with contact info at this meeting

o Targeted neighborhood updates

Public Outreach During Early Works Construction

Page 13: Tuft’s Interlocking Early Works · 7/30/2018  · - Joe Nolan (City Point Partners) 2. Early Works Construction Overview and Schedule - Paul Hadley (MBTA) & Randy Henke (HNTB) 3.

13Tufts InterlockingMay 31, 2017

GLX Medford Public MeetingJune 21, 2017 6:00 to 7:30 PM

Medford City Hall Council Chambers

85 George P Hassett Dr, Medford, MA

GLX Somerville Public MeetingDate To Be DeterminedSomerville High School Auditorium

81 Highland Ave, Somerville, MA

Upcoming Meetings

Page 14: Tuft’s Interlocking Early Works · 7/30/2018  · - Joe Nolan (City Point Partners) 2. Early Works Construction Overview and Schedule - Paul Hadley (MBTA) & Randy Henke (HNTB) 3.

14Tufts InterlockingMay 31, 2017

Questions/Comments?

Medford GLX Project Neighborhood Meeting