Tube Expansion
-
Upload
veerraju-pentakota -
Category
Documents
-
view
20 -
download
0
Transcript of Tube Expansion
-
Tube expansion
Methods and Procedures
By
C.P.Parekh
-
Tube fitting with Tube sheet
By welding only
By expansion only
By welding and expansion
-
Introduction
Tube expansion is the art of reducing tube wall by compressing the
OD of the tube against a fix container.
Tube
Tube
shee
t
Tube
Tube
shee
t
Before After
Welded
side
-
Why Tube Expansion Is Required?
To avoid...
Sludge accumulation
Secondary side IGA/SCC
crevices
Corrosion in tube sheet
Damage to the tube due to
vibration
Tube
Tube
shee
t
-
Stage of tube expansion
Prior to start of rolling, the tube to tube
sheet welds shall have successfully passed
the helium leak test. ( as per spec.no PB-P-
188, para. 3.2)
Before expansion
Cleanliness of the tube inside surface .
Primary side rolling and checking shall
completed before commencing secondary
side of rolling
-
Methods of tube expansion
1. Mechanical : A mechanical tube expander consists of an odd number
roller (usually 3 Nos.), a taper mandrel to push the roller
outward, a cage to house the roller and a collar to set the
location of the expansion.A typical Expander is shown in
fig.
-
2. Hydraulic: This is differs from other known anchoring methods in that
the tube is physically deformed simply by means of pressurized
liquid. The amount of pressurized liquid introduced is a function
of the proportion of elastic and plastic expansion occurring in
the tube and tube sheet.In this a mandrel with two O rings at
appropriate location is inserted into the tube sheet.Hydraulic
pressure applied between two O rings causes the tube in that
region to expand.
Methods of tube expansion
-
3. Explosive Forming:
This is done by detonating a carefully sized charged inside each tube causing it to deform and make contact
with the tube sheet.
4. Hydro / Mechanical:
This system makes use of mechanical expander but the self feed of mandrel is replaced by positive hydraulic
feed using a separate hydraulic circuit apart from the
electric drive used for rotation of mandrel.
Methods of tube expansion
-
Requirement for Nuclear Steam
Generator
In order to control the cold work imparted to the tube during
expansion, percentage thinning restricted between 3 and 6 %.
Apart from this , the strength of joint should qualify for a
minimum pull out strength 764 - 1530 kg and the leak tightness
has to be ensured by leak test. Leak rate shall not be more than
1 x 10^-7 cc/sec . A tube expansion cross section shown in
figure.
-
Expansion process by Pilgrim technique
Expansion is carrying out mainly in two stages process.
1. Closing of gap between hole id and tube OD.
2. Thinning against wall.
As clearance between tube OD and hole dia varies, tube ID
cannot decided until sufficient trials will be taken to determine
the limiting torque value.
When the expansion length for the product is more then the
roller length of the tube expander, more than one stage of
expansion has to performed. That type of expansion is called as
Pilgrim technique of expansion.
Cont....
-
Pilgrim expansion technique
In this technique
Overlapping of stage is automatically performed by
arrangement available in tube expander.
Special control employed in control unit.
After fixed rolling,
The restraining collar is pushed back to the second
groove position and the control switched to pilgrim
mode
controller gives desired(Can be set by timer switch)
no of anti clockwise rotation to expander.
Clock wise rotation starts for actual expansion
Once the torque limits per setting is reached , the
rotation is reversed again to anti clockwise direction.
This continues till the collar of the expander is
touches the tube sheet and switched off.
-
Pilgrim expansion technique
Advantage of this technique
Faster then other processes
Ensures better control on cold work imparted to
the tube.
Very smooth transition due to design of profile
of roller end resulting in
lesser stress level
hence better resistant to stress corrosion cracking.
Leakage can be minimized between tube and
tube sheet
-
% Thinning calculation
Percentage thinning = (Do - Di) - (d - Di w)
2S
Where,
Di w = Average tube inside diameter after rolling
Di = Average tube inside diameter before rolling
Do = Average tube OD before rolling
d = Average hole diameter
S = Do - Di
2
Percentage thinning shall be in the range of
3 - 6 %
-
Testing and Insp. on expanded joints
Check on job
Check completeness of rolling by ensuring tube ID at rolled /Expanded
portion with respect to unexpanded portion by using bore gauge or air
gauge.
1% of rolled tubes surface shall be examined by boroscope on both rolling
length.
In the reference hole % thinning at both rolled places shall be computed at
the middle of expanded region by using formula.
Removal of lubricants to be checked as peer approved cleaning procedure.
Length of rolling to be checked at random.
Check on RCBs
Visual examination of tube surfaces
Length of rolling on each tube
Pull out test for all the tubes. Pull is between 764 - 1530 kg.
% thinning between 3 - 6 %
-
Qualifying the Procedure And joint
Prepare a procedure qualification block , which has to
simulate the job condition.
Carry out the expansion as per procedures.
Take adequate trial to get the parameter by which %
thinning, Pull out test, helium leak test,visual check meet
the required values.
If the above values are meeting the requirement the process
is qualified to perform on job.
During production control is exercised in rolling quality
control block (RCBs)
-
Operator Qualification
The person who are engaged for qualifying machine is
automatically qualified for performing on the job.
For other
10 nos. tubes hole to be rolled and following is the test
required on that.
% thinning of that rolled tube within limit.
Pull out test on all tube
Out of 10 tubes 2 tube ID to be sectioning for scratch
free expansion.
-
List of non conformance
In case of RCB Tube s fails to meet the acceptance criteria
two successive tubes shall be rolled and shall meet the
acceptance criteria before proceeding on the job
If roller breaks during rolling all the previous holes rolled
using the above tool shall be inspected for any damage.
The holes, where rolling is incomplete or interrupted due
to power failure, shall be identified and rolling shall be
performed after all other holes rolling completed.
On job rolling shall be performed only after RCBs
satisfactory results on above holes.
There are few mores other than this.
-
Record of expansion
Following record to be kept for expansion of tubes
No. of tube rolled (with location R x C) for each shift,
day, operator,equipment and settings.
Correlation of RCBs with the tube locations, equipment
and operator.
Melt and heat no. of tube and block.
Report of % thinning and surface inspection of 1% tubes
in the tube sheet.
Pull out test and % thinning results of RCBs
Certificate of checking of length of expansion and
termination from secondary side .
Non conformance list
-
Tube cleaning Procedure
Cleaning operation
Pug all the tubes at 450 mm depth from tube end.
Fill 2 storage tank with DM water
In 1st tank add approved cleaning agent to make 5% w/v concentration
and stir the solution and raise temp up to 50c.
In 2nd tank also raise and maintain the temp. between 50c- 55c..
With help of CF pump put the cleaning agent in circulation and inject the
solution in tube at 8-10 kg/cm with injection lance at a depth of 450mm.
Cleaning operation shall be start from top row and finish at bottom row.
Withdraw injection lance towards tube end.
Repeat this for few times.
Check on tube end with help of filter paper / tissues by rubbing them in
ID of the tube for any oil spots.
Stop pump and allow cleaning agent to drain from tube injector.
Cont...
-
Tube cleaning Procedure
Flushing operation: Close discharge valve from cleaning tank.
Start the pump and open DM water by transverseing the injection
lance in to the tube and back.
Start from top and bottom.
Random check of pH on the flushing at the tube end with
phenolophthalene indication shall not show any pink color.
Inspection : Check all tube end for free from lubricants.
Remove all plugs and with ball test check for free passage.