TSD-Sep-2005-SPM02
-
Upload
api-3749180 -
Category
Documents
-
view
28 -
download
1
description
Transcript of TSD-Sep-2005-SPM02
![Page 1: TSD-Sep-2005-SPM02](https://reader033.fdocuments.in/reader033/viewer/2022052411/5571f21f49795947648c31ef/html5/thumbnails/1.jpg)
Nitin V Pujari TSDP-Sep-2005 - Project Management Slide 1
Wednesday, April 12, 2023
DETAILED PLANNING -
Overview & WBS
![Page 2: TSD-Sep-2005-SPM02](https://reader033.fdocuments.in/reader033/viewer/2022052411/5571f21f49795947648c31ef/html5/thumbnails/2.jpg)
Nitin V Pujari TSDP-Sep-2005 - Project Management Slide 2
Wednesday, April 12, 2023
4.1 - Detailed PlanningOverview
4.1 - Overview------------------------------------------------------------------------------------------------------------------------------------------------------------------
4.2 - The Work Breakdown Structure
5 - Size Estimates -- Lines of Code / Function Points
6 - Effort, Schedule and Cost Estimating------------------------------------------------------------------------------------------------------------------------------------------------------------------
7 - Scheduling
8 - The Software Development Plan
![Page 3: TSD-Sep-2005-SPM02](https://reader033.fdocuments.in/reader033/viewer/2022052411/5571f21f49795947648c31ef/html5/thumbnails/3.jpg)
Nitin V Pujari TSDP-Sep-2005 - Project Management Slide 3
Wednesday, April 12, 2023
Three Principles of Planning (1)
1. The precedence principle: Planning logically takes precedence over all other
managerial functions2. The effective planning principle: Plans will be effective if they are consistent with
the organization’s policy and strategy framework3. The living document principle: Plans must be maintained as living documents or
they quickly lose their value
![Page 4: TSD-Sep-2005-SPM02](https://reader033.fdocuments.in/reader033/viewer/2022052411/5571f21f49795947648c31ef/html5/thumbnails/4.jpg)
Nitin V Pujari TSDP-Sep-2005 - Project Management Slide 4
Wednesday, April 12, 2023
The GeneralManagement Process
Plan
Monitor
DoAssess
PlansNew
Knowledge
MetricsInformation
Knowledge
![Page 5: TSD-Sep-2005-SPM02](https://reader033.fdocuments.in/reader033/viewer/2022052411/5571f21f49795947648c31ef/html5/thumbnails/5.jpg)
Nitin V Pujari TSDP-Sep-2005 - Project Management Slide 5
Wednesday, April 12, 2023
Detailed Planning Process
DetailedPlanning
•Goals•Lifecycles•High level Schedule•Complexity Model•Communication Model•Process Model•SOW / Contract•Requirements•Expectations•Commitments•Risks
PEOPLEMANAGEMENT APPROVAL
TRAININGFACILITIES
CONSENSUS
•WBS (Work Breakdown Structure)
•Estimates of Size & Cost
•Detailed Schedule
•SW Development Plan
•Risks
![Page 6: TSD-Sep-2005-SPM02](https://reader033.fdocuments.in/reader033/viewer/2022052411/5571f21f49795947648c31ef/html5/thumbnails/6.jpg)
Nitin V Pujari TSDP-Sep-2005 - Project Management Slide 6
Wednesday, April 12, 2023
Understandthe Need
JOB AIDS
•Market Analysis
•Commitment
•Statement of Work
•Statement of Requirements
•Tests
•Expectations
•Process (hi level)
•Risks
MANAGEMENT INSIGHT & DECISIONS
BUSINESS PLANS AND OBJECTIVES
TRAININGFACILITIES
•Customer Needs
or
•RFP
or
•Draft SOW
or
•Product Ideas
RESEARCH
![Page 7: TSD-Sep-2005-SPM02](https://reader033.fdocuments.in/reader033/viewer/2022052411/5571f21f49795947648c31ef/html5/thumbnails/7.jpg)
Nitin V Pujari TSDP-Sep-2005 - Project Management Slide 7
Wednesday, April 12, 2023
Detailed Planning inGovernment Contract Context
Carry OutNext
Phase Previous Phase
RFPfor
NextPhase
WriteProposal
ContractorSelection
ContractNegot-iation
Note: - overlap of previous phase with proposal activities - gap between previous phase and next phaseDETAILED PLANNING USUALLY STARTS DURING PROPOSAL!(Initial planning should start even before that.)
time
Govern-ment
Cont-ractor
}}
![Page 8: TSD-Sep-2005-SPM02](https://reader033.fdocuments.in/reader033/viewer/2022052411/5571f21f49795947648c31ef/html5/thumbnails/8.jpg)
Nitin V Pujari TSDP-Sep-2005 - Project Management Slide 8
Wednesday, April 12, 2023
Objective of Detailed Planning
To describe in detail how the project will satisfy the requirements of the project
Who?
When?
How?
![Page 9: TSD-Sep-2005-SPM02](https://reader033.fdocuments.in/reader033/viewer/2022052411/5571f21f49795947648c31ef/html5/thumbnails/9.jpg)
Nitin V Pujari TSDP-Sep-2005 - Project Management Slide 9
Wednesday, April 12, 2023
Risks Associated withDetailed Planning
• Incomplete or incorrect estimates due to lack of sufficient detail or lack of sufficient information– Guesstimates instead of legwork to get accurate data
• Incomplete flow of system level constraints– Example: failure to accommodate special system
limitations, financial constraints, etc.
• Insufficient visibility into other parts of the system– Hardware
– Test Sets
– Maintenance and Support Plans
– etc.
![Page 10: TSD-Sep-2005-SPM02](https://reader033.fdocuments.in/reader033/viewer/2022052411/5571f21f49795947648c31ef/html5/thumbnails/10.jpg)
Nitin V Pujari TSDP-Sep-2005 - Project Management Slide 10
Wednesday, April 12, 2023
Facts vs. Innuendo
• Fact 1: Electric Company raises electric rates by $1 per person per month
• Fact 2: There are 10 million people living in the city
• Fact 3: There are 12 months in a year
--------------------------------------------------------------------
• Newspaper Headline:
“Electric Rates Rise by $120 million”
![Page 11: TSD-Sep-2005-SPM02](https://reader033.fdocuments.in/reader033/viewer/2022052411/5571f21f49795947648c31ef/html5/thumbnails/11.jpg)
Nitin V Pujari TSDP-Sep-2005 - Project Management Slide 11
Wednesday, April 12, 2023
Facts vs. InnuendoPart II
• Fact 1: Electric Company lowers electric rates by $1 per person per month
• Fact 2: There are 10 million people living in the city
• Fact 3: There are 30 days in an average month
--------------------------------------------------------------------
• Newspaper Headline:
“Electric Rates Cut by 3 cents -- big deal!”
![Page 12: TSD-Sep-2005-SPM02](https://reader033.fdocuments.in/reader033/viewer/2022052411/5571f21f49795947648c31ef/html5/thumbnails/12.jpg)
Nitin V Pujari TSDP-Sep-2005 - Project Management Slide 12
Wednesday, April 12, 2023
Ways to get Wrong Conclusions
• Lack of Data
• Missing Facts
• Distorted Facts
• Opinions without substantiation
• Biases
• Lack of Visibility
• etc. Truth
Bias
Opinion
Guess
![Page 13: TSD-Sep-2005-SPM02](https://reader033.fdocuments.in/reader033/viewer/2022052411/5571f21f49795947648c31ef/html5/thumbnails/13.jpg)
Nitin V Pujari TSDP-Sep-2005 - Project Management Slide 13
Wednesday, April 12, 2023
Risk Mitigation
• Review assumptions with all affected parties
• Work the details. Don’t guess if you don’t have to guess.
• Communicate with those working on other parts of the system
• Plan to replan
Replanning
Plan
actions
Planning
actions
feedback feedback for next replan
UpdatedPlan
Replanning
![Page 14: TSD-Sep-2005-SPM02](https://reader033.fdocuments.in/reader033/viewer/2022052411/5571f21f49795947648c31ef/html5/thumbnails/14.jpg)
Nitin V Pujari TSDP-Sep-2005 - Project Management Slide 14
Wednesday, April 12, 2023
The Big Picturefor Software Estimating
Where Isthe
Software?
How MuchTime is
Required?
How Bigis the
Software?
How MuchEffort is
Required?
How MuchWill itCost?
WBS Size
Effort
ScheduleIs This
Realistic?Cost
No: rethinkassumptions
or renegotiate
YesDone
![Page 15: TSD-Sep-2005-SPM02](https://reader033.fdocuments.in/reader033/viewer/2022052411/5571f21f49795947648c31ef/html5/thumbnails/15.jpg)
Nitin V Pujari TSDP-Sep-2005 - Project Management Slide 15
Wednesday, April 12, 2023
The Big Picturefor Cost Estimating
WBSSize
Effort
ScheduleCost
Yes
Where Isthe
Software?
How MuchTime is
Required?
How Bigis the
Software?
How MuchEffort is
Required?
How MuchWill itCost?
Is ThisRealistic?Done
No: rethinkassumptions
or renegotiate
![Page 16: TSD-Sep-2005-SPM02](https://reader033.fdocuments.in/reader033/viewer/2022052411/5571f21f49795947648c31ef/html5/thumbnails/16.jpg)
Nitin V Pujari TSDP-Sep-2005 - Project Management Slide 16
Wednesday, April 12, 2023
The Work Breakdown Structure (WBS)
Definition: A work breakdown structure is a hierarchical list of the work activities required to complete a project.
This includes tasks for:
- Software development
- Software development management
- Support of software development
- Any other activities required to meet customer requirements, such as creating documents, training programs, tool development or acquisition, travel, etc.
![Page 17: TSD-Sep-2005-SPM02](https://reader033.fdocuments.in/reader033/viewer/2022052411/5571f21f49795947648c31ef/html5/thumbnails/17.jpg)
Nitin V Pujari TSDP-Sep-2005 - Project Management Slide 17
Wednesday, April 12, 2023
Why Use a WBS?
The WBS is the tool you use to document all work that must be done to develop and deliver the software in a satisfactory manner
Although this information is “redundant” with the various “source” documents (SOW, requirements document, design document, etc.), it serves to consolidate information from many sources into one place and into an organized format.
![Page 18: TSD-Sep-2005-SPM02](https://reader033.fdocuments.in/reader033/viewer/2022052411/5571f21f49795947648c31ef/html5/thumbnails/18.jpg)
Nitin V Pujari TSDP-Sep-2005 - Project Management Slide 18
Wednesday, April 12, 2023
Top Level Role of WBS
SourceDocuments
(SOW, Requirements,
contract, test criteria,
etc,)HistoricalRecords(at end
of project)
WBS
CostEstimate
(proposal &/project start)
CostTracking(during
execution)
![Page 19: TSD-Sep-2005-SPM02](https://reader033.fdocuments.in/reader033/viewer/2022052411/5571f21f49795947648c31ef/html5/thumbnails/19.jpg)
Nitin V Pujari TSDP-Sep-2005 - Project Management Slide 19
Wednesday, April 12, 2023
An example of a WBSShown as a Tree
Query PopulateCreate aDatabase
Information Kiosk
UserInterface
ManageSoftware
Development
Build SISSoftware
Build TestSuite
WriteDocumentation
WriteInstallationSoftware
Software forSIS
![Page 20: TSD-Sep-2005-SPM02](https://reader033.fdocuments.in/reader033/viewer/2022052411/5571f21f49795947648c31ef/html5/thumbnails/20.jpg)
Nitin V Pujari TSDP-Sep-2005 - Project Management Slide 20
Wednesday, April 12, 2023
An example of a WBSShown as Indented Text
1.0 Software for SIS 1.1 Build SIS Software 1.1.1 Build a User Interface 1.1.2 Create a Database 1.1.3 Write Query Processing Scripts 1.1.4 Populate the Database 1.1.5 Interface with Information Kiosk 1.2 Build the Test Suite for SIS 1.2.1 etc. 1.3 Write Documentation 1.4 Write Installation Software 1.5 Manage the Above
![Page 21: TSD-Sep-2005-SPM02](https://reader033.fdocuments.in/reader033/viewer/2022052411/5571f21f49795947648c31ef/html5/thumbnails/21.jpg)
Nitin V Pujari TSDP-Sep-2005 - Project Management Slide 21
Wednesday, April 12, 2023
Example of an Additional Level of Detail in a WBS
1.0 Software for SIS 1.1 Build SIS Software 1.1.1 Build a User Interface 1.1.1.1 Analyze Requirements for User I/F 1.1.1.2 Design the User Interface 1.1.1.3 Code the User Interface 1.1.1.4 Test and Integrate the User Interface 1.1.2 etc.
![Page 22: TSD-Sep-2005-SPM02](https://reader033.fdocuments.in/reader033/viewer/2022052411/5571f21f49795947648c31ef/html5/thumbnails/22.jpg)
Nitin V Pujari TSDP-Sep-2005 - Project Management Slide 22
Wednesday, April 12, 2023
Speculation
• With object oriented and relational databases, perhaps we could come up with a new concept of a work breakdown structure that is not hierarchical
• We could then look at things any way we wanted to, such as:– by process
– by software component
– by responsibility
– etc.
![Page 23: TSD-Sep-2005-SPM02](https://reader033.fdocuments.in/reader033/viewer/2022052411/5571f21f49795947648c31ef/html5/thumbnails/23.jpg)
Nitin V Pujari TSDP-Sep-2005 - Project Management Slide 23
Wednesday, April 12, 2023
Why Do a Work Breakdown Structure? Purposes:
- To organize the work to be done
- To illustrate the work to be done
- To assure that all necessary work has been identified
- To divide the work into small, well defined tasks
- To facilitate planning, estimating and scheduling of the project
- To provide a basis for data monitoring and historical data collection
- To identify contractual tasks and deliverables
![Page 24: TSD-Sep-2005-SPM02](https://reader033.fdocuments.in/reader033/viewer/2022052411/5571f21f49795947648c31ef/html5/thumbnails/24.jpg)
Nitin V Pujari TSDP-Sep-2005 - Project Management Slide 24
Wednesday, April 12, 2023
Some Uses of a WBS
• Cost Estimating– To make sure that all tasks are estimated
– To make sure that each element of the estimate corresponds to a necessary task
– To “roll up” costs of individual elements to get total costs for sub-elements or for the system as a whole
• Cost Accounting– Work is assigned and “charged” based on specific WBS
elements
– You can then determine the actual cost of each element
• Schedule Performance– You can monitor which tasks are complete
![Page 25: TSD-Sep-2005-SPM02](https://reader033.fdocuments.in/reader033/viewer/2022052411/5571f21f49795947648c31ef/html5/thumbnails/25.jpg)
Nitin V Pujari TSDP-Sep-2005 - Project Management Slide 25
Wednesday, April 12, 2023
Additional WBS Terminology
• Activity
• Work Package
• Cost Content Summary
• WBS Dictionary
DO X
DO Y
DO Z
DO Q
STORAGE
![Page 26: TSD-Sep-2005-SPM02](https://reader033.fdocuments.in/reader033/viewer/2022052411/5571f21f49795947648c31ef/html5/thumbnails/26.jpg)
Nitin V Pujari TSDP-Sep-2005 - Project Management Slide 26
Wednesday, April 12, 2023
The Activity
Definition: an activity is a specific task to be performed.
Activities occur at all levels of the WBS.
Generally, each activity corresponds to some documented work requirement, such as a SOW paragraph
However, some activities are merely implied– Management
– Acquisition of resources
– Details of development process
– . . .
![Page 27: TSD-Sep-2005-SPM02](https://reader033.fdocuments.in/reader033/viewer/2022052411/5571f21f49795947648c31ef/html5/thumbnails/27.jpg)
Nitin V Pujari TSDP-Sep-2005 - Project Management Slide 27
Wednesday, April 12, 2023
The Work Package
Definition: the work package is a bottom-level or “atomic” activity in the WBS
This represents a task or group of tasks whose costs will be tracked and estimated together
Work Package
![Page 28: TSD-Sep-2005-SPM02](https://reader033.fdocuments.in/reader033/viewer/2022052411/5571f21f49795947648c31ef/html5/thumbnails/28.jpg)
Nitin V Pujari TSDP-Sep-2005 - Project Management Slide 28
Wednesday, April 12, 2023
Typical Work Package Properties
• Associated with a concrete event or milestone when starting and when complete
• Suitable for independent cost estimating and tracking
• Small enough to manage and large enough to be worth tracking separately
• Suitable for allocating part of the budget (people, hours, dollars, computers, etc.)
![Page 29: TSD-Sep-2005-SPM02](https://reader033.fdocuments.in/reader033/viewer/2022052411/5571f21f49795947648c31ef/html5/thumbnails/29.jpg)
Nitin V Pujari TSDP-Sep-2005 - Project Management Slide 29
Wednesday, April 12, 2023
Examples of Work Packages
• Design of a software component
• Travel to customer for interchange meetings
• Management of development for an individual software product
• Quality assurance for the software product
• Configuration management for the software product
![Page 30: TSD-Sep-2005-SPM02](https://reader033.fdocuments.in/reader033/viewer/2022052411/5571f21f49795947648c31ef/html5/thumbnails/30.jpg)
Nitin V Pujari TSDP-Sep-2005 - Project Management Slide 30
Wednesday, April 12, 2023
Alternative Work Packages for Configuration Management Tasks
• Configuration management for the software product
• Configuration management for a specific software component
• Configuration management for the design phase of the life cycle
![Page 31: TSD-Sep-2005-SPM02](https://reader033.fdocuments.in/reader033/viewer/2022052411/5571f21f49795947648c31ef/html5/thumbnails/31.jpg)
Nitin V Pujari TSDP-Sep-2005 - Project Management Slide 31
Wednesday, April 12, 2023
Guidelines for Selecting aWork Package
• Start with the Process – Associate each work package with a discrete portion of
the process [all or part]
• Consider the Design (high level)– Associate each work package with a discrete portion of
the software, such as a configuration item or major component
• Consider the Nature of the Work– Associate a work package with a given type of work or
payment
– For example, separate travel from equipment from development labor
![Page 32: TSD-Sep-2005-SPM02](https://reader033.fdocuments.in/reader033/viewer/2022052411/5571f21f49795947648c31ef/html5/thumbnails/32.jpg)
Nitin V Pujari TSDP-Sep-2005 - Project Management Slide 32
Wednesday, April 12, 2023
Cost Content Summary
Definition: a description of a work package and a rationale for its cost estimate
Example:
Cost Content Summary
Item: Travel for Customer Interchange Meetings
WBS #: 1.5.2.3 Cost: $16,800
Description: Four trips to customer for I/C meetings. Each trip will involve 3 engineers and be 2 days long
Cost Calculation: 4 * 3 * 2 * $700/day = $16,800
![Page 33: TSD-Sep-2005-SPM02](https://reader033.fdocuments.in/reader033/viewer/2022052411/5571f21f49795947648c31ef/html5/thumbnails/33.jpg)
Nitin V Pujari TSDP-Sep-2005 - Project Management Slide 33
Wednesday, April 12, 2023
WBS Dictionary
Definition: a supplement to the WBS that provides additional detail for each WBS activity
Typical contents for a given activity:– Inputs
– Outputs
– Performance Goals (if any)
– Reviews
– Exit or Completion criteria
– Detailed description (if a work package)
– Sub-activities that make up this activity
Some of the contents are determined by the process to be followed
![Page 34: TSD-Sep-2005-SPM02](https://reader033.fdocuments.in/reader033/viewer/2022052411/5571f21f49795947648c31ef/html5/thumbnails/34.jpg)
Nitin V Pujari TSDP-Sep-2005 - Project Management Slide 34
Wednesday, April 12, 2023
Example WBS Dictionary for a bottom level WBS activity(i.e., a work package)
Name: Design the File system (for compiler)WBS #: 1.1.3.2Performance Goal: 3 monthsInputs: requirements specification for file systemOutput: file system design descriptionReviews: preliminary design review, detailed design
review, plus intermediate peer reviewsExit Criteria: file system design addresses all
requirements and meets design standardsDetailed Description: using the Booch method, use
object oriented design technique to establish a design for the file system. .............
![Page 35: TSD-Sep-2005-SPM02](https://reader033.fdocuments.in/reader033/viewer/2022052411/5571f21f49795947648c31ef/html5/thumbnails/35.jpg)
Nitin V Pujari TSDP-Sep-2005 - Project Management Slide 35
Wednesday, April 12, 2023
Example WBS Dictionary for an intermediate WBS activity
Name: Develop File system (for compiler)WBS #: 1.1.3 Performance Goal: 8 month scheduleInputs: requirements specs for file systemOutput: file system codeReviews: preliminary design review, detailed design
review, test status review, formal qualification test, internal peer reviews
Exit Criteria: file system passes functional tests based on requirements
Subtasks: requirements analysis (1.1.3.1); design (1.1.3.2); code (1.1.3.3); integrate (1.1.3.4)
![Page 36: TSD-Sep-2005-SPM02](https://reader033.fdocuments.in/reader033/viewer/2022052411/5571f21f49795947648c31ef/html5/thumbnails/36.jpg)
Nitin V Pujari TSDP-Sep-2005 - Project Management Slide 36
Wednesday, April 12, 2023
Goals of a Good WBS (1)
1) Specify the ingredients of the project clearly and concisely
2) Identify the responsibilities of each task and its place within the whole
3) Identify project performance targets at every level
4) Support the comparison of actual performance with target values
5) Motivate people to meet targets
![Page 37: TSD-Sep-2005-SPM02](https://reader033.fdocuments.in/reader033/viewer/2022052411/5571f21f49795947648c31ef/html5/thumbnails/37.jpg)
Nitin V Pujari TSDP-Sep-2005 - Project Management Slide 37
Wednesday, April 12, 2023
Observations on the WBS
• Different parts of the WBS could have different levels of detail
• Later updates of the WBS could provide more detail than what is developed initially
• Avoid making too many very small work packages -- if several of them have nearly identical descriptions, see if you can combine them. (each level in the WBS multiplies by 5-10 the amount of detail that must be estimated, tracked, etc.)
• Trace the WBS to the requirements
![Page 38: TSD-Sep-2005-SPM02](https://reader033.fdocuments.in/reader033/viewer/2022052411/5571f21f49795947648c31ef/html5/thumbnails/38.jpg)
Nitin V Pujari TSDP-Sep-2005 - Project Management Slide 38
Wednesday, April 12, 2023
Construction of a WBS(high level view)
1) Develop (or refine) the WBS
2) Trace the WBS to the source documents
3) Perform (or update) cost and schedule estimates
4) Determine if WBS is consistent with cost and schedule data
5) Identify Risks
6) Repeat as necessary– To correct discrepancies
– To refine during replanning
![Page 39: TSD-Sep-2005-SPM02](https://reader033.fdocuments.in/reader033/viewer/2022052411/5571f21f49795947648c31ef/html5/thumbnails/39.jpg)
Nitin V Pujari TSDP-Sep-2005 - Project Management Slide 39
Wednesday, April 12, 2023
Develop a WBS
1) The Software Hunt -- Go through the SOW, rqmts. document, etc. and make a complete list of all items that impact the cost of doing the software
Document Paragraph Description
SOW 1.3.4 Design Software for Compiler
SOW 2.3.3 Travel for Design Reviews
...
Contract 7.13.2.a Follow ISO Standard 5432f
Rqmts. Doc. 3.4 Use data compression
...
Customer Mtg. on 3/5/95 Code all software in C++
![Page 40: TSD-Sep-2005-SPM02](https://reader033.fdocuments.in/reader033/viewer/2022052411/5571f21f49795947648c31ef/html5/thumbnails/40.jpg)
Nitin V Pujari TSDP-Sep-2005 - Project Management Slide 40
Wednesday, April 12, 2023
Source Documents
Don’t forget that there are many possible source documents
SOW - usually the best item to start with
Specifications
Concept of Operation documents
Requirements Documents of Many Kinds
Design Documents
Standards (internal and external)
Customer Conversations
Test Criteria or Expectations
![Page 41: TSD-Sep-2005-SPM02](https://reader033.fdocuments.in/reader033/viewer/2022052411/5571f21f49795947648c31ef/html5/thumbnails/41.jpg)
Nitin V Pujari TSDP-Sep-2005 - Project Management Slide 41
Wednesday, April 12, 2023
Develop a WBS
2) Determine the WBS for the company or the project (system) and how software fits in– Many organizations have a standard WBS architecture
– If your organization does not have a standard, determine what project requirements may be applicable
– For example, your project manager may have a specific approach -- number of levels, where to show certain kinds of costs, etc.
![Page 42: TSD-Sep-2005-SPM02](https://reader033.fdocuments.in/reader033/viewer/2022052411/5571f21f49795947648c31ef/html5/thumbnails/42.jpg)
Nitin V Pujari TSDP-Sep-2005 - Project Management Slide 42
Wednesday, April 12, 2023
WBS with Software Embedded in Hardware
Radar
Sig. Proc. Antenna Power S. Cabinet
Computer SoftwareAnalog
This approach can result in a large number of software elements in the WBS. A spreadsheet may be handy for tracking them all.
![Page 43: TSD-Sep-2005-SPM02](https://reader033.fdocuments.in/reader033/viewer/2022052411/5571f21f49795947648c31ef/html5/thumbnails/43.jpg)
Nitin V Pujari TSDP-Sep-2005 - Project Management Slide 43
Wednesday, April 12, 2023
WBS with Software Separate
System
Software Electrical Mechanical Mgt.
Editor etc.Compiler
This approach may tend to isolate software planning from the rest of the system, resulting in inconsistent interpretations of requirements, etc.
![Page 44: TSD-Sep-2005-SPM02](https://reader033.fdocuments.in/reader033/viewer/2022052411/5571f21f49795947648c31ef/html5/thumbnails/44.jpg)
Nitin V Pujari TSDP-Sep-2005 - Project Management Slide 44
Wednesday, April 12, 2023
Develop a WBS
3) Determine a logical structure for the software portion (s) of the WBS– many organizations have standard architectures to
facilitate collection of costs across the organization
– different software products (configuration items) may need different WBS structures
![Page 45: TSD-Sep-2005-SPM02](https://reader033.fdocuments.in/reader033/viewer/2022052411/5571f21f49795947648c31ef/html5/thumbnails/45.jpg)
Nitin V Pujari TSDP-Sep-2005 - Project Management Slide 45
Wednesday, April 12, 2023
Some “Standard” Architectures for a Software WBS
All Software All Software
Products Organizations
Components Products
Process Steps ...
All Software All Software
Process Steps Products
Products Organizations
Components ...
![Page 46: TSD-Sep-2005-SPM02](https://reader033.fdocuments.in/reader033/viewer/2022052411/5571f21f49795947648c31ef/html5/thumbnails/46.jpg)
Nitin V Pujari TSDP-Sep-2005 - Project Management Slide 46
Wednesday, April 12, 2023
Develop a WBS
4) Populate the chosen WBS structure with tasks that address the work identified in the SOW, etc. (from step 1).
5) (optional) Add a column to the data gathered in step 1 to record the corresponding WBS number, so you can have a WBS - to - source documents trace.
Doc Parag WBS# Description
SOW 1.3.4 1.1.2.2 Design Software for Compiler
SOW 2.3.3 1.7.1 Travel for Design Reviews
...
![Page 47: TSD-Sep-2005-SPM02](https://reader033.fdocuments.in/reader033/viewer/2022052411/5571f21f49795947648c31ef/html5/thumbnails/47.jpg)
Nitin V Pujari TSDP-Sep-2005 - Project Management Slide 47
Wednesday, April 12, 2023
Develop a WBS
6) (optional) Determine the cost estimating category for each element in the WBS.
Doc Parag WBS# Description Category
SOW 1.3.4 1.1.2.2 Design Software for Compiler S
. . . . . . . . . . . .
SOW 2.3.3 1.7.1 Travel for Design Reviews C
. . .
See Assignment 4 for sample cost categories
If this step is not done here, it needs to be done later, during the cost estimating process
![Page 48: TSD-Sep-2005-SPM02](https://reader033.fdocuments.in/reader033/viewer/2022052411/5571f21f49795947648c31ef/html5/thumbnails/48.jpg)
Nitin V Pujari TSDP-Sep-2005 - Project Management Slide 48
Wednesday, April 12, 2023
Notes
• There will be some items from step 1 that are scattered throughout many WBS elements (example: use a particular standard or a particular programming language)– But costs specific to that standard or language may be
separate WBS elements -- such as purchasing a compiler or carrying out a mandated review or producing a document that would not otherwise be needed
• There may be some items from step 1 that do not seem to fit the standard WBS form– Examples: warranty costs, special testing, ...
– You usually just add another element somewhere
– You may need to be creative
![Page 49: TSD-Sep-2005-SPM02](https://reader033.fdocuments.in/reader033/viewer/2022052411/5571f21f49795947648c31ef/html5/thumbnails/49.jpg)
Nitin V Pujari TSDP-Sep-2005 - Project Management Slide 49
Wednesday, April 12, 2023
Notes(continued)
• Some items in the organization’s standard WBS may not be explicitly stated in source documents– Examples: training, management, facilities, development
tools
• For these you determine whether they are needed and, if so, work with your customer or system engineer to define them in statement of work or other source documents.
• The standard WBS acts as a reminder not to forget things like these.
![Page 50: TSD-Sep-2005-SPM02](https://reader033.fdocuments.in/reader033/viewer/2022052411/5571f21f49795947648c31ef/html5/thumbnails/50.jpg)
Nitin V Pujari TSDP-Sep-2005 - Project Management Slide 50
Wednesday, April 12, 2023
Examples of WBS issues
Issue: customer requires that the design document be written in a specific format that your process does not require
Option 1: include cost of this in basic cost estimate for software development– may make your productivity rate a bit lower
Option 2: include incremental cost of producing this format as a separate WBS item– this shows the customer what it costs
– but be prepared to reduce the cost accordingly if the customer says “OK, use your own format.”
![Page 51: TSD-Sep-2005-SPM02](https://reader033.fdocuments.in/reader033/viewer/2022052411/5571f21f49795947648c31ef/html5/thumbnails/51.jpg)
Nitin V Pujari TSDP-Sep-2005 - Project Management Slide 51
Wednesday, April 12, 2023
Examples of WBS issues
Issue: configuration management is a significant overall cost, but a minor increment to individual component cost estimates
Option 1: include cost of this in basic cost estimate for each software development task– tends to create a lot of very small work packages
Option 2: include CM cost as a separate item at a higher WBS level (for example, at the level where you show project management)– tends to obscure the details of what it costs, and makes
the total look large
– invites arbitrary cuts in CM cost
![Page 52: TSD-Sep-2005-SPM02](https://reader033.fdocuments.in/reader033/viewer/2022052411/5571f21f49795947648c31ef/html5/thumbnails/52.jpg)
Nitin V Pujari TSDP-Sep-2005 - Project Management Slide 52
Wednesday, April 12, 2023
Examples of WBS issues
Issue: customer or program manager requires a WBS format or architecture that does not conform with organizational standard
Option 1: put WBS in a spreadsheet and organize both ways (separate column for each numbering system) – use “sort” command to produce WBS in either format
Option 2: negotiate to see if they will accept your standard format
![Page 53: TSD-Sep-2005-SPM02](https://reader033.fdocuments.in/reader033/viewer/2022052411/5571f21f49795947648c31ef/html5/thumbnails/53.jpg)
Nitin V Pujari TSDP-Sep-2005 - Project Management Slide 53
Wednesday, April 12, 2023
Additional (Optional) Information in WBS Trace
• Who is responsible for estimating cost
• Who is responsible for development
• What paragraph of the software development plan addresses this task
• What standards are to be applied in performing this task
• What is the final cost estimate for this WBS item (often filled in later, after cost estimating is complete)
• etc.
• etc.
![Page 54: TSD-Sep-2005-SPM02](https://reader033.fdocuments.in/reader033/viewer/2022052411/5571f21f49795947648c31ef/html5/thumbnails/54.jpg)
Nitin V Pujari TSDP-Sep-2005 - Project Management Slide 54
Wednesday, April 12, 2023
Using the WBS Trace Matrix
1) Sort by SOW paragraph and make sure each task is covered in the WBS, etc.
2) Sort by WBS number and make sure each corresponds to a legitimate activity that must be performed
3) Sort by WBS and requirements document to identify all the requirements that must be met by each activity (helps in cost estimating)
![Page 55: TSD-Sep-2005-SPM02](https://reader033.fdocuments.in/reader033/viewer/2022052411/5571f21f49795947648c31ef/html5/thumbnails/55.jpg)
Nitin V Pujari TSDP-Sep-2005 - Project Management Slide 55
Wednesday, April 12, 2023
One More Note
If a single SOW paragraph is reflected in several WBS elements (or vice versa), you can make several separate entries in the cross reference matrix.
Doc Parag WBS# Description
SOW 1.3.4 1.1.2.2 Design Software for Compiler
SOW 1.3.4 1.1.3.2 Design Software for Editor
SOW 2.3.4 1.1.3.2 Use Booch Design Method
SOW 2.3.3 1.7.1 Travel for Design Reviews
[In this example, perhaps SOW 1.3.4 says “design software”]
![Page 56: TSD-Sep-2005-SPM02](https://reader033.fdocuments.in/reader033/viewer/2022052411/5571f21f49795947648c31ef/html5/thumbnails/56.jpg)
Nitin V Pujari TSDP-Sep-2005 - Project Management Slide 56
Wednesday, April 12, 2023
Risks in Preparing a WBSPage 1 of 2
• Too Much Detail– The more detail, the higher overhead of cost
monitoring and estimating– Some government customers insist on tracking all
detail that you put in the WBS -- do you really want them tracking how many weeks you spent during design reviews?
– You may have two WBSs to get around this: a “formal” WBS at the high level and a “working” WBS at the detail level
• Work Packages are Vague– Look for concrete starting & ending events with
specific evaluation criteria– Remember that a work package must be discrete,
trackable, and measurable
![Page 57: TSD-Sep-2005-SPM02](https://reader033.fdocuments.in/reader033/viewer/2022052411/5571f21f49795947648c31ef/html5/thumbnails/57.jpg)
Nitin V Pujari TSDP-Sep-2005 - Project Management Slide 57
Wednesday, April 12, 2023
Risks in Preparing a WBSPage 2 of 2
• Excluding certain tasks– Exclusion implies 0 cost -- rarely true– When in doubt, check with others to make sure
everything is covered -- it is easy to assume someone else covered it
– If you don’t know, ask. Just because you don’t know about a required task or a software component does not mean that it costs nothing.
• Duplication– It is easy to have the same work show up in more
than one place, especially on a large project– Managers must “scrub” the WBS
![Page 58: TSD-Sep-2005-SPM02](https://reader033.fdocuments.in/reader033/viewer/2022052411/5571f21f49795947648c31ef/html5/thumbnails/58.jpg)
Nitin V Pujari TSDP-Sep-2005 - Project Management Slide 58
Wednesday, April 12, 2023
Risk Mitigation Approaches
• WBS inspection or walkthrough– Look for completeness, consistency, well defined
activities, etc.
– Let others see the WBS (you have tunnel vision and may miss something)
• Trace to source documents (and, later, to cost estimate)– Check that all requirements are included and all entries
are required
• Remember that the WBS is part of the plan -- include WBS revisions in replanning activities